PROJECT : Aruga Mactan Sales Lounge and Model Unit

LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 002 Request Date: October 16, 2019 Trade:

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of excavation of footing F-1 Grid Line 2/Af Tower A
10/16/2019
2 Inspection of excavation at COF-1 Grid Line 1/Ac-Ad Tower A

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga Mactan Sales Lounge and Model Unit
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 003 Request Date: October 16, 2019 Trade:

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of gravel bed for COF-2 Grid Line 1/Ae-Af Tower A
2 Inspection of gravel bed for COF-1 Grid Line 1/Ac-Ad Tower A 10/16/2019

3 Inspection of gravel bed at F-1 Grid Line 2/Af Tower A

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga Mactan Sales Lounge and Model Unit
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 004 Request Date: October 16, 2019 Trade:

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of rebar installation for COF-2 Grid Line 1/Ae-Af Tower A
2 Inspection of rebar installation for COF-1 Grid Line 1/Ac-Ad Tower A
10/18/2019
3 Inspection of rebar installation for F-1 Grid Line 2/ Af Tower A
4 Inspection of column starter bar at grid line 1/ Ac-Af, RC-1 and RC-2 Tower A

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga Mactan Sales Lounge and Model Unit
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 005 Request Date: October 20, 2019 Trade:

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of column starter bar at grid line 2/Af RC-4 Tower A 10/20/2019

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga Mactan Sales Lounge and Model Unit
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 006 Request Date: October 26, 2019 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Excavation for footing, MF-2 at 3-4/ Ae-Af. Tower A
2 Inspection of Gravel bedding for footing, MF-2 at 3-4/ Ae-Af. Tower A 10/28/2019

3 Inspection of Elevation and Thickness of footing MF-2 at 3-4/ Ae-Af. Tower A

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga Mactan Sales Lounge and Model Unit
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 009 Request Date: November 14, 2019 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of rebar for FTB-1 and FTB-2 along GL Af/1-3 and 1/Ad-Ae Tower A 14-Nov-19

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga Mactan Sales Lounge and Model Unit
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0010 Request Date: November 21, 2019 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection of Excavation for MF-1 and Isolated footing F-5, F-4 and F-6 at Back 21-Nov-19
1 parking Tower A
Inspection of Gravel bed for MF-1 and Isolated footing F-5, F-4 and F-6 at Back 21-Nov-19
2 parking Tower B & C
3 Inspection 0f Excavation for Retaining Wall..See attached Tower B & C 21-Nov-19

Requested by: Noted by:

Rex Calma Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0013 Request Date: February 20, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Excavation for RW-3 /RWF-3, UTWF-1 and UTWF-2 of Domestic Tower A 20-Feb-20
Water Tank

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0015 Request Date: February 28, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Rebars and Formworks on RWF-3, UWTWF-1, UWTWF-2 Tower A 28-Feb-20

2 Inspection of Rebars and Formworks on RWF-1 Tower B 28-Feb-20

3 Inspection of Rebars and Formworks on RWF-2 Tower C 28-Feb-20

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0016 Request Date: March 04, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Formworks on Footing F - 2, F - 3 and F - 5. Located at GL 6 - Tower B and Tower 07-Mar-20
14''/Bb/Cb. C

Inspection of Colum Starter Bars on Footing F - 2, F - 3 and F - 5. Located at GL 6 - Tower B and Tower
2 07-Mar-20
14''/Bb/Cb. C

Inspection of Footing Rebars on Footing F - 2, F - 3 and F - 5. Located at GL 6 - Tower B and Tower


3 07-Mar-20
14''/Bb/Cb. C

Inspection of Excavation on Footing F - 2, F - 3 and F - 5. Located at GL 6 - Tower B and Tower


4 07-Mar-20
14''/Bb/Cb. C

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0017 Request Date: March 04, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Excavation on MF - 3, located at GL 5 - 6/Ac - Af Zone A 07-Mar-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0017 Request Date: March 09, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Formworks on MF - 3, located at GL 5 - 6/Ac - Af Zone A 12-Mar-20

2 Inspection of Rebars on MF - 3, located at GL 5 - 6/Ac - Af Zone A 12-Mar-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:


Patrick Junther Sazon Hennessy Lopio
STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0019 Request Date: March 10, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Column Starter Bars at MF - 3. GL 5 - 6/Ac - Af. Zone A 13-Mar-20

2 Inspection of Shear wall Starter Bars at MF - 3. GL 5 - 6/Ac - Af. Zone A 13-Mar-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0020 Request Date: March 17, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of Column RC - 6 Starter Bars at MF - 4. GL 7/Bc Zone B 20-Mar-20

2 Inspection of Column RC - 6 Starter Bars at MF - 4. GL 8/Bc Zone B 20-Mar-20

3 Inspection of Column RC - 7 Starter Bars at MF - 4. GL 7/Bd Zone B 20-Mar-20

4 Inspection of Column RC - 7 Starter Bars at MF - 4. GL 8/Bd Zone B 20-Mar-20

5 Inspection of Column RC - 8 Starter Bars at MF - 4. GL 9/Bc Zone B 20-Mar-20

6 Inspection of Column RC - 9 Starter Bars at MF - 4. GL 9/Bd Zone B 20-Mar-20

7 Inspection of Excavation at MF - 4. GL 7 - 9/Bc - Bd. Zone B 20-Mar-20

8 Inspection of Formworks at MF - 4. GL 7 - 9/Bc - Bd. Zone B 20-Mar-20

9 Inspection of Footing Rebars at MF - 4. GL 7 - 9/Bc - Bd. Zone B 20-Mar-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:


Patrick Junther Sazon Hennessy Lopio
STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0021 Request Date: March 18, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Excavation of MF - 6 at G.L. 10 - 11/Bc - Bf Zone B 21-Mar-20

2 Inspection for vertical rebars of RW - 3 at G.L. 1 - 4/Ac Zone A 21-Mar-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0022 Request Date: April 02, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Excavation of COF - 4 at G.L. 12/Cc - Cd Zone C 05-Apr-20

2 Inspection for Excavation of COF - 4 at G.L. 13/Cc - Cd Zone C 05-Apr-20

3 Inspection for Excavation of MF - 7 at G.L. 14 - 14'/Cc - Cd Zone C 05-Apr-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0023 Request Date: April 13, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for bottom bars of COF - 4 at G.L. 12/Cc - Cd Zone C 16-Apr-20

2 Inspection for bottom bars of COF - 5 at G.L. 13/Cc - Cd Zone C 16-Apr-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0024 Request Date: April 14, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for bottom bars of MF-7 at G.L. 14-14''/Cc-Cd Zone C 17-Apr-20
2 Inspection for starter bars of RC-10 at G.L 12/Cc Zone C 17-Apr-20
3 Inspection for starter bars RC-11 at G.L 12/Cd Zone C 17-Apr-20
4 Inspection for starter bars RC-12 at G.L 13/Cc Zone C 17-Apr-20
5 Inspection for starter bars RC-13 at G.L 13/Cd Zone C 17-Apr-20

Requested by: Noted by:

Alexis Mercado Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0025 Request Date: April 21, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Top bars of COF-4 at G.L 12 / Cc-Cd Zone C 24-Apr-20
2 Inspection for Top bars of COF-5 at G.L. 13 / Cc-Cd Zone C 24-Apr-20
3 Inspection for excavation of MF-5 at G.L. 7-8 / Ce-Cf Zone B 24-Apr-20
4 Inspection for formworks of MF-5 at G.L. 7-8 / Ce-Cf Zone B 24-Apr-20

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0026 Request Date: May 04, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection of starter bars of RC-12 at G.L. 14/Cc Zone C 07-May-20
2 Inspection of starter bars of RC-13 at G.L. 14/Cd Zone C 07-May-20
3 Inspection for starter bars of RSW-4 at G.L. 14'-14"/Cc-Cd Zone c 07-May-20
4 Inspection of top bars of MF-7 Zone c 07-May-20
5 Inspection of bottom bars of MF-5 Zone B 07-May-20
6 Inspection of starter bars of RC-6 at G.L. 7/Bf Zone B 07-May-20
7 Inspection of starter bars of RC-6 at G.L. 8/Bf Zone B 07-May-20
8 Inspection of starter bars of RC-7 at G.L. 7/Be Zone B 07-May-20
9 Inspection of starter bars of RC-7 at G.L. 7/Be Zone B 07-May-20
10 Inspection of starter bars of RC-8 at G.L. 9/Be Zone B 07-May-20
11 Inspection of starter bars of RC-9 at G.L. 9/Bf Zone B 07-May-20
12 Inspection of formworks of RWF-4 at G.L. Bi and Ci Zone B and C 07-May-20
13 Inspection of rebars of RWF-4 at G.L. Bi and Ci Zone B and C 07-May-20

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0027 Request Date: May 19, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for top bars of MF-5 Zone B 22-May-20
2 Inspection for Formworks and Rebars of RWF-4 at G.L. 6 Zone B 22-May-20
3 Inspection for Formworks and Rebars of RWF-4 at G.L. 14" Zone C 22-May-20
4 Inspection for formworks of RW-1 and RW-2 at G.L. 6-14' Zone B and C 22-May-20

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0028 Request Date: May 21, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars of columns and shear wall at Zone A Zone A 24-May-20
2 Inspection for formworks of columns and Shear wall at Zone A Zone A 24-May-20
3 Inspection for rebars and formworks of F-5, and F-6 at G.L 7-8/Bg-Bh Zone B 24-May-20
4 Inspection for Formworks and rebars of RWF-14"/Ca-Cc Zone B and C 24-May-20

5 Inspection for formworks and rebars of FTB-1 at G.L. 6-10'/Bb and 10'- Zone B and C 24-May-20
14'/Cb

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0029 Request Date: June 09, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for bottom bars of MF-6 Zone C 12-Jun-20
2 Inspection for top bars of MF-6 Zone C 12-Jun-20
3 Inspection for starter bars of Columns and shear walls at MF-6 Zone C 12-Jun-20
4 Inspection for rebars and formworks of F-5 at G.L. 9/Bh Zone B 12-Jun-20
5 Inspection for formworks of f-5 at G.L. 11-12/Cg'-Ch Zone C 12-Jun-20
6 inspection for rebars of RW-10 at G.L. 12-14"/Cc Zone C 12-Jun-20
7 Inspection for formworks of Columns at MF-4 and MF-5

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0030 Request Date: July 09, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Bottom bars of MF-8 Zone C 12-Jul-20
2 Inspection for Topb Bars of MF-8 Zone C 12-Jul-20
3 Inspection for starter bars of Columns at MF-8 Zone C 12-Jul-20
Inspection for formworks and rebars of Isolated footings at G.L. 11-14' /
4 Cg and 9 / Bg Zone B 12-Jul-20

5 Inspection for Forworks of RW-4 Zone C 12-Jul-20

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0031 Request Date: August 05, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Excavation of MF-8 ZONE C 08-Aug-20
2 Inspection for rebars and formworks of FTB's at back parking area ZONE B & C 08-Aug-20

3 Inspection for rebars and formworks of FTB's connecting MF-4,5,6,7,8,COF-4, and ZONE B & C 08-Aug-20
COF-5

4 Inspection for Rebars and formworks of Columns at COF-4, 5, MF-7, and MF-8 ZONE C 08-Aug-20

08-Aug-20

Requested by: Noted by:

Arjay Mandap Homer Calicdan


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0032 Request Date: August 15, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection for formworks and rebars of columns, shear walls, and Retaining walls
1 Zone B 18-Aug-20
at MF-3
2 inspection for formwrks and rebars of RSW-4 Zone C 18-Aug-20

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0033 Request Date: August 15, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 inspection for formworks and rebars of RSW-3, & RSW-6 Zone B 18-Aug-20

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0034 Request Date: August 31, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Rebars and formworks of Columns at MF-4, and MF-5 Zone B 03-Sep-20

2 Inspection for Rebars and Formworks of Columns, Shear wall, and Retaining wall Zone B 03-Sep-20
at MF-3

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0035 Request Date: September 03, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars and formworks of FTB-1 at G.L. 4-5/Ad-Af Zone A 06-Sep-20

2 Zone B 06-Sep-20
Inspection for Rebars and Formworks of RWF-4 at G.L. 14"/Cd-Cf

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0036 Request Date: September 08, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars and formworks of RWF-4 at G.L. 14"/Cc-Cg Zone c 11-Sep-20

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0037 Request Date: September 14, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars of beams and girders at G.L. 5-10/Bc-Bf (Zone B) Zone c 17-Sep-20
2 inspection for formworks of beams and girders at G.L. 5-10/Bc-Bf (Zone B) Zone c 17-Sep-20
3 Inspection for formworks of slab at G.L. 5-10/Bc-Bf (Zone B) Zone c 17-Sep-20

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0038 Request Date: September 22, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars (Bottom and Top) Slabs at G.L. 5-10/Bc-Bf (Zone B) Zone B 22-Sep-20
2 Inspection for rebars (Ties) on Columns at G.L. 5-10/Bc-Bf (Zone B) Zone B 22-Sep-20

3 Zone B 22-Sep-20
Inspection for Formworks on Slabs, Beams and Girdersat G.L. 5-10/Bc-Bf (Zone B)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0039 Request Date: September 30, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars of beams and girders at Zone C Zone C 03-Oct-20
2 Inspection for rebars of slab at Zone C Zone c 03-Oct-20

3 Inspection fo formworks of Retaning walls, shearwalls, columns, beams, girders, Zone C 03-Oct-20
and slab at Zone C
4 inspection for coordinates and elevation of beams, slab, and columns at Zone C Zone C 03-Oct-20

5 Inspection for formworks and rebars of FTB-3 at G.L. 10-14'/Cc Zone B & C 03-Oct-20

Requested by: Noted by:

Arjay Mandap Erickson Rivera


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0040 Request Date: October 07, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebras of RSW and Columns at Zone B Zone B 07-Oct-20

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0041 Request Date: October 20, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Rebar inspection for Girders, Beams, and Slab at Zone A (GF) Zone A 20-Oct-20
2 Formworks inspection for Girders, Beams, and Slab at Zone A (GF) Zone A 20-Oct-20

3 Zone C 20-Oct-20
Rebar and formworks Inspection for Columns, and Shear Walls at Zone C (LGF-GF)

Requested by: Noted by:

Arjay Mandap Erickson Rivera


Structural Coordinator - OMC Project Manager

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0042 Request Date: November 10, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Formworks of Slab, Beams, & Girders, at GF Zone B Zone B 13-Nov-20

2 Zone B 13-Nov-20
Inspection for Rebars of Slab, Beams, & Girders, at GF Zone B

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0043 Request Date: November 16, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for rebars of Columns at Zone A (GF-2F) Zone A 19-Nov-20

2 Zone B 13-Nov-20
Inspection for formworks of Columns at Zone A (GF-2F)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0044 Request Date: November 25, 2020 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Formworks inspection for Slab, Beams, and Girders at GF Zone C Zone C 28-Nov-20

2 Rebars inspection for Slab, Beams, and Girders at GF Zone C Zone C 28-Nov-20

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0045 Request Date: January 18, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Rebar and formworks inspection for Column at G.L. 11/Cc-Cf, & 12-14'/Cd-Cf Zone C 18-Jan-21

2 Rebar and formworks inspection for RSW-2 Zone B 18-Jan-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Patrick Junther Sazon Hennessy Lopio


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0046 Request Date: January 25, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Beams, and slab formworks inspection for Zone A (2nd Floor) Zone A 25-Jan-21

2 Beams, and slab rebar inspection for Zone A (2nd Floor) Zone A 25-Jan-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0047 Request Date: February 05, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection for Formworks and rebars of Columns at G.L. 12-14/Cc Zone C 05-Feb-21

2 Beams, and slab rebar inspection for Zone B (2nd Floor) Zone B 05-Feb-21

3 Zone B 05-Feb-21
Beams, and Slab Formworks inspection for Zone B (2nd Floor)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0048 Request Date: February 22, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
formworks and rebar inspection for Beams, and slab at G.L. 10-
1 14"/Cc-Cf (2nd Floor) Zone C 22-Feb-21

2 Formworks and rebar inspection for RSW - 4 (GF-2F) Zone C 22-Feb-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0049 Request Date: March 04, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
formworks and rebar inspection for Beams, Balconies, Canopy and slab at 1-5'/Ac-
1 Af Zone A 04-Mar-21

2 Formworks and rebar inspection for RSW - 1/Stair - 1 (2F-3F) Zone A 04-Mar-21

3 Front Parking 04-Mar-21


Formworks inspection for coluimns at Front parking (LGF-GF)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0050 Request Date: March 09, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Formworks and rebar inspection for beams, and slab at Zone B (3F) Zone B 09-Mar-21

2 Formworks and rebar inspection for columns, and shearwalls, at Zone B (2F-3F) Zone B 09-Mar-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0051 Request Date: March 18, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Formworks inspection for RW-1 at G.L. 12-14"/Ca, 14"/Ca-Cc Zone C 18-Mar-21

2 Rebar Inspection for RW-1 at G.L. 12-14"/Ca, 14"/Ca-Cc Zone C 18-Mar-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0051 Request Date: March 23, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Formworks inspection for Slab, Girders, and Beams at G.L. 10-11/Bc-Bf Zone B 23-Mar-21

2 Rebar Inspection Slab, Girders, and Beams at G.L. 10-11/Bc-Bf Zone B 23-Mar-21

3 Formworks Inspection for RSW-3, and RSW-6 (2F-3F) Zone B 23-Mar-21

4 Rebar Inspection for RSW-3, and RSW-6 (2F-3F) Zone B 23-Mar-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0053 Request Date: March 29, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Formworks inspection for Columns, Slab, Girders, and Beams at G.L. 1-5'/Ac-
1 Af Zone A 29-Mar-21

2 Rebar Inspection for Columns, Slab, Girders, and Beams at G.L. 1-5'/Ac- Zone A 29-Mar-21
Af

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0054 Request Date: April 06, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection for Formworks of Columns, Beams, girders, and Slab at G.L. 6-8/Bf-Bi
1 (Basement -LGF) Zone B 06-Apr-21

2 Inspection for Rebar of Columns, Beams, girders, and Slab at G.L. 6-8/Bf- Zone B 06-Apr-21
Bi (Basement - LGF)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0055 Request Date: April 12, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspectio for Formworks of Columns, Beams, Girders, and slab at
1 G.L. 5-10/Bc-Bf (3F-5F) Zone B 12-Apr-21

2 Inspectio for Rebars of Columns, Beams, Girders, and slab at Zone B 12-Apr-21
G.L. 5-10/Bc-Bf (3F-5F)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0056 Request Date: April 13, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection for Formworks of Columns, Beams, Girders, and slab at
1 G.L. 8-12/Bf-Bg (Zone B Basement - LGF) Zone B 13-Apr-21

2 Inspection for Rebars of Columns, Beams, Girders, and slab at Zone B 13-Apr-21
G.L. 8-12/Bf-Bg (Zone B Basement - LGF)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0057 Request Date: April 23, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection for Columns, Beams, Girdes, and slab Rebars at
1 G.L. 11-14" Zone C (2F-3F) Zone C 23-Apr-21

2 Inspection for Columns, Beams, Girdes, and slab Formworks at Zone C 23-Apr-21
G.L. 11-14" Zone C (2F-3F)

3 Inspection for Columns setting out at G.L. 11-14" Zone C (2F-3F) Zone C 23-Apr-21
4 Inspection for walls setting out at G.L. 11-14" Zone C (2F-3F) Zone C 23-Apr-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0058 Request Date: April 29, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection for columns, Beams, Girders, and Slab Rebar at G.L. 8-13/Bg-Bi
1 (Basement-LGF) Zone B 29-Apr-21

2 Inspection for columns, Beams, Girders, and Slab Formworks at G.L. 8-13/Bg-Bi Zone B 29-Apr-21
(Basement-LGF)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0060 Request Date: May 04, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection for Columns, Slab, Beams, RSW-3, and RSW-6 Formworks at G.L. 10-
1 11/Cc-Cf (3F-5F) Zone B 07-May-21

2 Inspection for Columns, Slab, Beams, RSW-3, and RSW-6 Rebars at G.L. 10-11/Cc- Zone B 07-May-21
Cf (3F-5F)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0060 Request Date: May 10, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 formworks inspection for columns at G.L. 8-12/Bg (LGF-GF) Zone C 10-May-21

2 formworks inspection for RW-4 at 14"/Cg, 7-8/Bi (LGF-GF) Zone C 10-May-21

3 Rebars inspection for columns at G.L. 8-12/Bg (first lift from footing) Zone C 10-May-21
4 Rebars inspection for RW-4 at 14"/Cg, 7-8/Bi (first lift from footing) Zone C 10-May-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0062 Request Date: May 13, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for Formworks at Zone C G.L. 10-14'' (3F-5F) Zone C 14-May-21

2 Inspection request for Rebar at Zone C G.L. 10-14'' (3F-5F) Zone C 14-May-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0063 Request Date: May 19, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for Formworks at Zone C G.L. 12-14"/Cf-Ci (Basement-LGF) Zone C 20-May-21

2 Inspection request for Rebars at Zone C G.L. 12-14"/Cf-Ci (Basement-LGF) Zone C 20-May-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0064 Request Date: May 27, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for rebars at Zone A G.L. 1-5/Ac-Af (5F-6F) Zone A 28-May-21

2 Inspection request for formworks at Zone A G.L. 1-5/Ac-Af (5F-6F) Zone A 28-May-21

3 Inspection request for columns rebars at G.L. 13-14'/Cg-Ch (LGF-GF) Zone C 28-May-21

4 Inspection request for columns formworks at G.L. 13-14'/Cg-Ch (LGF-GF) Zone C 28-May-21

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0065 Request Date: June 29, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for Columns, and Shearwalls rebars and formworks (5F-6F) Zone B

2 Inspection request for Slab, Beams, and Girders rebar and Zone B
formworks (5F-6F)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0066 Request Date: June 29, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for Columns, and Shear walls rebars and formworks (5F-6F) Zone C

2 Inspection request for Slab, Beams, and Girders rebar and Zone C
formworks (5F-6F)

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0067 Request Date: July 05, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection request for Slab, beams, gitders, & retaining wall Formworks at Zone B
1 GF G.L. 6-8/Bf-Bi Zone B

2 Inspection request for Slab, beams, gitders, & retaining wall Rebars at Zone B GF Zone B
G.L. 6-8/Bf-Bi

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0068 Request Date: July 13, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
Inspection Request for Slab, Beams, Girders Columns, and RSW-1 Rebars at 7F G.L.
1 1-5/ Ac-Af Zone A

2 Inspection request for Slab, Beams, Girders, Columns, and RSW-1 at 7F G.L. Zone A
1-5/Ac-Af

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0068 Request Date: July 13, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for RW-4 formworks at LGF-GF Back parking G.L. 9-13/Bi Zone B

2 Inspection request for RW-4 rebars at LGF-GF Back parking G.L. 9-13/Bi Zone B

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)


PROJECT : Aruga by Rockwell - Residential Tower Phase 1
LOCATION : Punta Engaño, Lapu-Lapu City

INSPECTION REQUEST FORM


Reference No. : IR No.- 0070 Request Date: July 24, 2021 Trade: Structural

Requested
Item No. Item Description Location Remarks
Date Time
1 Inspection request for Slab, beams, and girders formworks at GF G.L. 8-11/Cf-Ci Zone B

2 Inspection request for Slab, beams, and girders rebars at GF G.L. 8-11/Cf-Ci Zone B

Requested by: Noted by:

Arjay Mandap Rex Calma


Structural Coordinator - OMC Project in Charge

Item No. Results of Inspection (RLC)

Item No. Remarks/Comments/Recommendations (RLC)

Witnessed by: Approved/Dissapproved by:

Reynaldo Haboc Jr. Patrick Junther Sazon


STRUCTURAL INSPECTOR - RLC STRUCTURAL COORDINATOR - RLC

Form S-022 Revision no. 001 (Sept. 2018)