Professional Documents
Culture Documents
Method Statement Submittal (V1.0) : Aug 28, 2021, ID #698 Report Details
Method Statement Submittal (V1.0) : Aug 28, 2021, ID #698 Report Details
Dubai, Dubai
REPORT DETAILS
Description MS-022 - RCC Band beam, PCC Blinding, Sacrificial block work along the shoring and inside pile cap & Risk Assement
Submitted by DC PNCA PG
Status Submitted
Subcontractor : Others :
1 MS-SS-CIVIL-022 Method Statement For RCC Band beam, PCC Blinding, Sacrificial block work along 00 B
the shoring and inside pile cap & Risk Assement
Consultant's Comments
Structural
Provision of expansion joint (sleeved or groove cuts ) shall be reviewed with the contractor based on site feasibility.
Initially conduct a pull out tests to determine the ultimate load (Nu) from the chemical anchoring into the panels.
Scaffolding design for block wall construction shall be designed as per applicable safety guidelines.
Filling of sand behind the block wall shall be before concreting. Separate statement with amount of moisture shall be updated.
Other comments.
Comply to all safety regulations as stipulated by DDA, Dubai municipality and all other relevant authorities.
Risk assessment is not included, shall be thoroughly reviewed with joint meeting with Contractor and HSE of main contractor.
Attachments : YES NO
Nos.
✔
A- Approved B- Approved As Noted C- Not Approved (Resubmit) D- Rejected
FS/CO/07/01
TST(7OPR01) Project Submittals
Dubai, Dubai
DOCUMENTS (1)
1. SCOPE
• This method statement is applicable for installation of block masonry works along the
shoring & inside the pile caps that are intended in “The Sobha Tower” on sheik Zayed road,
Dubai, in accordance to project specifications/ contract documents with reference to
approved IFC, shop drawings etc..
• The purpose of the procedure is to ensure that all the personnel involved in this activity are
fully aware of the safe method to be employed/procedure to be adopted to ensure that
documentation is generated to record and verify that work executed in acceptable manner in
compliance with project specification requirement.
2. REFERENCE:
Specific safety measures have to followed as applicable, and all the safety measures are
covered separately in the Project Safety Plan
4. DEFINITIONS
Page 1 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
5. RESPONSIBILITIES
Description Responsibility
Page 2 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
Ensure that the site is securely protected against unauthorized access by the provision
of adequate barriers lighting and signs.
Ensure excavation and pile head breaking is approved by consultant.
Ensure FDD test carried out and approved by consultant
Ensure necessary clearance is obtained by surveyor
Ensure necessary stamps if applicable are closed prior to start the activity
Setting out
All Survey equipment shall be calibrated, and certificates shall be available at site.
Permanent Benchmark shall be established at site and the approval shall be obtained
from the Engineer / surveyor.
Setting out level and thickness of blinding concrete AND blinding concrete including
RCC band beam along the shoring shall be marked and verified by surveyor as per the
latest approved drawings.
Necessary clearance from surveyor shall be obtained prior to start the work
Page 3 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
Execution
Install side forms along the shoring line as per the survey points for the area to receive
blinding concrete and band beam.
RCC Band beam 400 X 200mm shall be provided and cast above blinding concrete of
100mm thick leaving starter bars for stiffener columns at 4 mt c/c (please refer to
attached sketch) & starter bars for 3 layers of hollow blocks i.e. T12@800mm prior to
casting of band beam along the shoring.
Below the block work RCC band beam and blinding shall be casted
RCC band beam shall have 6 T12 and ties/ shear reinforcement of T10 at 150mm c/c
For the rest of the area where only blinding concrete, establish level dabs at 2 mt
center to center using cement mortar 1:6 or blinding concrete.
Pour blinding concrete /PCC either by chute, pump or using bucket, between the dabs
and level using straight edge to form a band.
Cross check the top level of blinding concrete using dumpy/ laser level at regular intervals.
Finish the concrete smooth either by manual or power floating as per specification
within the applicable tolerance
Ensure continuous curing for at least 7 days
Page 4 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
Protect the concrete from trafficking until the concrete has set and hardened
Saw cut shall be carried out after the concrete is set to ensure no crack appears in the
blinding concrete
Ref:ST-SCL-CIVIL-FD-SD-101.00 REV.00
6.2 SACRIFICIAL BLOCK MASONRY WORK to RAFT FOUNDATION and PILE CAPS
Page 5 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
The entire working area for the block work activity will be thoroughly cleaned and will
make it free from concrete materials, debris and other unwanted material.
The area for the block work construction shall be checked for any structural defects and if any it
shall be repaired and necessary approval obtained prior to start the works
The surveyor will provide setting out for block work as per the approved drawing and will mark
all the support posts
The setting out dimensions shall be taken from grid lines as indicated in the drawing
Set out line of block walls as per the dimensions of pile cap on the blinding concrete
If surface of the blinding where block masonry work to be started, if it is found smooth it will
be chipped lightly to make it rough.
The first layer of block shall be laid in a full bed of mortar (either site mixed or approved ready
mix either wet or dry) as per setting out and adjust the level and line
Along the length of the wall provide stiffener columns at 4 meter c/c as per attached
sketch before starting block wall Ref. ST-SCL-CIVIL-FD-SD-101.00 REV00
Build block walls in stretcher course with ready mix mortar leaving toothed joint at
stiffener columns.
Bottom 3 course shall be hollow block with vertical reinforcement of T12 @800mm c/c
& to be filled by lean concrete
Upon completion of 3 course hollow blocks, solid blocks to proceed till top as per the
required height mentioned in the drawing
Provide 2no. 8mm dia. Bars as dowels in alternate course of block walls inserted into
the stiffener column.
Complete block work up to the required height.
Provide coping beam at 1.8mt. and at 3.8mt. height The beam shall have reinforcement
of 4T12, and stirrups T8 at 150c/c. Ensure stiffener column reinforcement is terminated
properly into the coping beam.
Provide shuttering for stiffener column and coping beam and pour approved grade of
concrete (C45/20).
Remove shuttering and Repair defects if any using cement-sand mortar 1:4.
Smoothen concrete projections/ protrusions if any using grinder.
Ensure curing as per specification
For podium area pile caps one side solid blocks work will provide on the shoring side.
Wherever H beam is coming in between band beam, stiffener column please provide
filler board to separate
As far as practicable, after installing pile cap reinforcement, carryout back filling around
block walls in layers as per specification of back filling.
Care shall be taken to avoid excessive vibration/ compaction, especially near the surface
of block wall.
Page 6 of 10
Page 7 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
Complete backfilling to at least 300 mm from top of block wall wherever possible.
If at all for any reason, back filling cannot be carried out around the block walls before
concreting the pile cap, temporary supports shall be installed to maintain the stability of
block walls during concreting.
Number and spacing of supports shall be calculated as mentioned below (6.8) and
provided accordingly.
The supports shall be checked thoroughly before concreting.
where
p = Lateral pressure, (kPa)
ρ = Density of concrete, kg/m3
g = Gravitational constant, 9.81 N/kg
h = Depth of fluid or plastic concrete from top of placement to point of consideration in
form, (mts, consider total height of free-standing block work)
After calculating the lateral pressure, multiply it with the area under consideration to get
the total load.
Number of supports required = Total load / Capacity of each Prop
Spacing of supports = Length / Number of supports
Distribute supports uniformly along the entire length of block wall (refer typical sketch for
general arrangement of supports.
Ensure the supports are anchored properly as per manufacturer’s recommendations.
Page 8 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
7. MANPOWER REQUIREMENT
QA/QC Engineer
Site Engineer
Safety Officer
Surveyor
Foreman
Mason
Helpers
8. MATERIAL REQUIREMENT
Blocks
Rebar
Mortar
Air compressor
Handheld blower
Markers
Measuring tape
Straight edge
Other tools and equipment as mentioned in the referenced method statements.
Page 9 of 10
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
Calibrated survey equipment like total station, Laser level or auto level
Mobile/ tower crane.
Air compressor
Handheld blower
Truck-Mounted concrete pump
Test reports for the blocks submitted along with delivery (MIR)
PPE
Works carried out with necessary permits
Workplace shall be clean after completion of daily works
Tools & equipment’s tested only used
PQP
PSP
Calibration certificate
Approved material submittal
This method statement shall be read in conjunction with the below referenced documents
14. DISTRIBUTION
This method statement shall be shared with the following for implementation
Page 10 of
Method Statement for RCC Doc no.: MS-SS-CIVIL-22
Band beam,pcc
SOBHA GOLD FZ. LLC blinding,sacrificial block
work along the shoring & Revision: 00
inside pile cap
Project Manager
Construction Manager
Project Engineer
Site engineer
HSE Engineer
QC Engineer
Approved
Not applicable
Not applicable
19. ATTACHMENT
Page 11 of