Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

SONU BUILDERS PRIVATE LIMITED

Checklist for Bathroom Waterproofing Works

Project: _______________________________________________________________

Reference Drawing No. __________________ Date:________________________

Flat / Unit No. ________________________________Toilet No. __________________

S.
Description S NS N.A Remarks
No.
Completion of 12 – 15mm thk. Ratio of Internal plaster:
internal plaster (with integral
waterproofing compound) of walls
leaving margin of 1m from FFL
1      
(The proportion of Integral
waterproofing compound shall be as
per the technical specification & as
per the item description of BOQ)
Chasing on wall for the concealed  
2 plumbing line as per the approved      
shop drawing of plumbing
3 Cleaning of RCC bare sunk slab        

4 Brick bond joint filling        

Bare slab ponding for minimum of 24 Date & Time:


5      
Hrs.
Bare slab testing with identification of  
6 water dripping, water seepage & any      
other water leakage
Grouting at the identified defect &  
7      
coving treatment
Re-testing after 24 Hrs. of grouting & Date & Time:
8      
24 Hrs. of ponding testing
Opening to be made in wall for the  
9      
drainage out lets
Application of First coat of Coating height to be mentioned
10      
waterproofing chemical
Application of Second coat of  
11      
waterproofing chemical
Application of Third coat of  
12 waterproofing chemical (if required /      
specified)
Application of protective coat over  
13      
the waterproofing chemical coat
Temporary sealing of the drainage  
14      
out let
Ponding testing for minimum of 72 Date & Time:
Hrs. or as per the technical
15      
specification of the proprietary
contractor (whichever is higher)
16 Ponding testing       Date & Time:

17 Leakage / Seepage observed        

If Yes; repairing is done as per the  


18      
process & shall be test as per above
Plumbing concealed & Drainage  
19      
lines in toilet are laid & tested
Sealing of conceal line by cement  
20      
sand mortar admixed with integral

Check List No. Rev. No. R0 Effective Date : 01/04/2023


Page 1 of 2
SONU BUILDERS PRIVATE LIMITED
Checklist for Bathroom Waterproofing Works

waterproofing chemical
Sunk filling by Brick bat coba (brick Date & Time
21 bat shall be done as per the item      
description of BOQ) to the slope
Brick bats ponding & testing for  
22      
minimum of 72 Hrs. of ponding
23 Testing / checking for leakage       Date & Time

If Yes; repairing is done as per the  


24      
process & shall be test as per above
If NO; top of brick bat shall be  
25 finished with IPS with slope towards      
the drain point
Curing & ponding testing of 72 Hrs.  
26      
for final clearance

NOTE:
1 The drain pipes shall be completely embedded inside the brick bat & top finishing
2 If specified the escape pipe shall be preferably kept on top of base coat

Contractor’s Representative Project Engineer Project Manager

(Name and Signature) (Name and Signature) (Name and Signature)


Note: S - Satisfactory; NS - Not Satisfactory ; N.A - Not Applicable

Check List No. Rev. No. R0 Effective Date : 01/04/2023


Page 2 of 2

You might also like