BBC Holland Page 1

Calculation of CraneStabilty if in use Crane both *


* one, two or both

fixed values:
Weight of Jib (mJ) : 19.70 t
Length of Jib (LJib) : 23.70 m
Distance Centre of Gravity Jib to Middle of Cranefoundation (ySJ) : 10.00 m
Height of Jib craneforeward above ceel if a = 0° (zJib) : 19.10 m
Height of Jib craneaft above ceel if a = 0° (zJib) : 19.10 m
Distance cranefoundation to CL (ycranefoundation) : -5.70 m
SWL (max) per crane *: 60.00 t *60t/53,8°; 35t/24,9°
Length of crossbar or Distance of Hooks *: 12.00 m *variable
Distance of cranes : 32.90 m

variable values:
Luffing angle of jib (a) : 53.80 ° Outreach of jib: -9.31 m
Slewing Angle of jib CL (b) / (Port [-] / Stb [+] * loading or discharging : -41.71 ° Distance between hooks : 12.00 m
Weight of collo (mL) loading * 120.00 t required beta-value if both
Set value to zero! => 0.00 m cranes are in service: 41.71 °
Set value to zero! => 0.00 m

Calculation of total transversal moments

Jib : -155 mt

Collo : -1802 mt

Total moment : -1956 mt

Calculation of change of VCG caused by

rising of jib : 318 mt

Collo
Crane No. 1 : 2293 mt
Crane No. 2 : 2293 mt

Total moment : 4905 mt


BBC Holland Page 2

density of water r = 1.025 t/m³

0.746570
Item weight VCG VM TCG TM ib⋅ρ
[t] [m] [mt] [m] [mt] [mt]
Values from Stab.Prog. 3,440.29 4.699 16,166 0.093 320 132
DVM because of hatch cover discharged ashore -147.00 9.80 -1,441
distribution of weight
collo on Crane No. 1 60.00 38.22 2,293 -15.01 -901
collo on Crane No. 2 60.00 38.22 2,293 -15.01 -901
Jib of crane No. 1 159 -77
Jib of crane No. 2 159 -77
action to improve stab.
Wingtank No. 7 PS -120.00 3.26 -391 -6.22 746.4 0
Wingtank No. 7 SS 120.00 4.08 490 6.22 746.4 0
Wingtank No. 8 PS 0 -6.21 0 0
Wingtank No. 8 SS 0 6.21 0 0
Deplacement new 3,413.29 19,729 -144 132

RESULTS:
from hydrostatic VCG = 5.780 m List F = -3.70 °
tables! DGM = 0.039 m
VCG' = 5.819 m
KM = 6.470 m value trim -1.00m
GM' = 0.651 m minimum reqiured is 0,58m !

Loading with two cranes from ballast condition a maximum load (m = 120t)

Situation: Load is hoisted from the berth with max outreach by min. luffing angle of jibs

Prior Condition:
- Tween Deck in one stack as far as possible on Stb-side in Lower Hold,
MV "XYZ" Page 1 MV "XYZ"
Calculation of CraneStabilty if in use Crane both *
* one, two or both

fixed values: Item


Weight of Jib (mJ) : 12.57 t
Length of Jib (LJib) : 18.26 m Values from Stab.Prog.
Distance Centre of Gravity Jib to Middle of Cranefoundation (ySJ) : 9.17 m Hatchcover open
Height of Jib craneforeward above ceel if a = 0° (zJib) : 16.80 m Hatchcover discharged or shifted
Height of Jib craneaft above ceel if a = 0° (zJib) : 16.80 m
Distance cranefoundation to CL (ycranefoundation) : -5.70 m distribution of weight
SWL (max) per crane *: 100.00 t *60t/81,3°-62,2°; 35t/85°-36,7°; 30t/85°-20° collo on Crane No. 1
Length of crossbar or Distance of Hooks *: 12.00 m *variable collo on Crane No. 2
Distance of cranes : 28.30 m Jib of crane No. 1
Jib of crane No. 2
action to improve stab.
Ballast from Heeling Tank Port
variable values: to Heeling Tank Starbooard
Luffing angle of jib (a) : 60.00 ° Outreach of jib: 1.59 m
Slewing Angle of jib CL (b) / (Port [-] / Stb [+]
* loading or discharging : 10.00 ° Distance between hooks : 10.32 m
Weight of collo (mL) discharging * 24.00 t required beta-value if both Deplacement new
TCG collo (Port [-] / Stb [+] Set value => 0.00 m cranes are in service: 26.79 °
VCG collo Set value => 6.00 m

Calculation of total transversal moments from hydrostatic


tables!
Jib : 10 mt

Collo : -99 mt

Total moment : -89 mt

Calculation of change of VCG caused by

rising of jib : 100 mt

Collo
Crane No. 1 : 639 mt
Crane No. 2 : 639 mt

Total moment : 1377 mt


Page 2

density of water r = 1.025 t/m³

weight VCG VM TCG TM ib⋅ρ


[t] [m] [mt] [m] [mt] [mt]
5,338.60 4.630 24,718 -0.020 -107 231
700
0 0
0 0

24.00 26.61 639 0.00 0


24.00 26.61 639 0.00 0
100 10
100 10

0 0
0 0
0 0 0
0 0 0
5,386.60 26,895 -87 231

RESULTS:
VCG = 4.993 m List F = -1.87 °
DGM = 0.043 m
VCG' = 5.036 m
KM = 5.530 m
GM' = 0.494 m minimum reqiured is 0,58m !