Extension of Time Claim For Building Project
Extension of Time Claim For Building Project
Extension of Time Claim For Building Project
Zefne Primary
Hospital Remaining
Works Construction
Claim No. 3 Project
Contents
1 PROJECT PARTICULARITIES..........................................................................................2
1.1 Introduction About the Project.....................................................................................2
1.2 The Parties.....................................................................................................................2
1.3 Basic Contract Information............................................................................................3
Annex:
Appendix A : Impacted As-Planned Analysis
1 PROJECT PARTICULARITIES
1.1 Introduction about the Project
On the 21st of January 2021 Lexus General Construction entered into a contract agreement
with S/N/N/P/R/S Health Bureau for the construction of Zefne Primary Hospital Remaining
Works Construction Project. Work on the project commenced on 29 th of April 2021 G.C..
The original date for completion of the project is 21st of October 2022 with a contract period
of 540 Calendar Days.
3 Basis of Claim
3.1 The contract contains the following provisions
3.2 The contractor is thus entitled to extension of the projection completion date due to the
above enumerated employer risk events.
4.1.1 The causes of delay referred to in this section are delays which entitle the
contractor to an extension of time due to the delay to the project progress
acceptably computed using the Impacted-as-Planned delay analysis (IAP)
technique caused by such delay events.
4.2.1 Delay in the engineering determination of the site boundary peak location up to
September 22 2022 which prevented the commencement of all project tasks under
Site Work as clearly indicated in the approved master schedule. This Employer
Delay Event entitles The Contractor to extension of project completion time as per
General Conditions of Contract 73.1(ለ) and 74.1(ሀ)
4.2.2 Delay in the engineering determination of the elevation of the arterial road that
passes adjacent to the entrance of Zefne Hospital. This Employer Delay Event in
turn prevented the commencement of all tasks under the site work summary as
indicated in the approved master schedule until September 22 2022. This
Employer Delay Event entitles The Contractor to extension of project completion
time as per General Conditions of Contract 73.1(ለ) and 74.1(ሀ)
6 Conclusion
6.1 In conclusion the claim submitted herein contains the Contractor’s request for an
extension of Time for Completion up until July 29 2023 ( i.e 178 calendar days after
February 1st 2023)