Dhanbad-Sonnagar-ROB-06 Classic Schedule Layout 31-Aug-22 10:21

# Activity ID Activity Name Original Start Finish Total August 2022 September 2022 OctoberNovember
2022 2022
Duration Float

1 DFCC-ROB-06 Dhanbad-Sonnagar-ROB-06 248 16-Aug-22 A 24-Apr-23 0

2 DFCC-ROB-06-1000 Preliminary Site Survey and submission of 30 16-Aug-22 A 16-Sep-22 0 30


Preliminary Site Survey and submission of Concept P
Concept Plans indicating different options
for ROB alignment Structure Team, Highway Team
3 DFCC-ROB-06-1010 Approval of concept plan from Indian 30 01-Sep-22 01-Oct-22 0 30
Approval of concept plan from Indian Ra
Railway as well as State Govt. Authority
Highway Team
4 DFCC-ROB-06-1020 Geotechnical Investigation for GAD and 30 01-Oct-22 31-Oct-22 0 30
Geotechnical
Submission of final Report
Client
5 DFCC-ROB-06-1030 Topographical Survey 30 01-Oct-22 31-Oct-22 0 30
Topographica
ELITE
6 DFCC-ROB-06-1040 Submission of GAD 15 31-Oct-22 15-Nov-22 0
Structure Team
7 DFCC-ROB-06-1050 Approval of GAD from IR as well as from 45 15-Nov-22 30-Dec-22 0
state authority .

8 DFCC-ROB-06-1060 Praparation of 20A proposal 20 30-Dec-22 19-Jan-23 0

9 DFCC-ROB-06-1070 Submission of Detailed Design for 45 07-Jan-23 21-Feb-23 0


sub-structure

10 DFCC-ROB-06-1080 Submission of Detailed Design for 15 21-Feb-23 08-Mar-23 0


super-structure

11 DFCC-ROB-06-1090 Approval of design and proof checked by 30 08-Mar-23 07-Apr-23 0


NIT/IIT

12 DFCC-ROB-06-1100 Preparation of launching scheme and 15 07-Apr-23 22-Apr-23 0


Drawing and approval of Competent
Authority
13 DFCC-ROB-06-1110 Submission of BOQ, Tender Document 15 09-Apr-23 24-Apr-23 0

14 DFCC-ROB-06-1120 Completion of ROB-06-Design 0 24-Apr-23 0

Actual Work Critical Remaining Work Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Dhanbad-Sonnagar-ROB-06 Classic Schedule Layout 31-Aug-22 10:21
November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023

24-Apr-23, DFCC-ROB-06 Dhanbad-Sonnagar-ROB-06

bmission of Concept Plans indicating different options for ROB alignment

ept plan from Indian Railway as well as State Govt. Authority

Geotechnical Investigation for GAD and Submission of final Report

Topographical Survey

15
Submission of GAD
Structure Team
45
Approval of GAD from IR as well as from state authority .
Structure Team
20
Praparation of 20A proposal
Structure Team
45
Submission of Detailed Design for sub-structure
Structure Team
15
Submission of Detailed Design for super-structure
Structure Team
30
Approval of design and proof checked by NIT/IIT
Client, IIT and NIT
15
Preparation of launching scheme and Drawing and approval of Competent Autho
ELITE
15
Submission of BOQ, Tender Document
ELITE

Completion of ROB-06-Design,

Actual Work Critical Remaining Work Page 2 of 2 TASK filter: All Activities