SOLAR PROJECT PLAN

PROJECT TITLE START DATE


PROJECT
300 MW SOLAR PROJECT 01/02 DURATION
PROJECT MANAGER END DATE in days

03/26 312

WBS DURATION in
TASK NAME STATUS ASSIGNED TO START DATE END DATE COMMENTS
NO. days

1 PROJECT CONCEPTION AND INITIATION In Progress 03/01 07/23 145

1.1 –– Project Concept Not Started 03/01 03/07 7

1.1.1 –– Project Charter Revisions Not Started 03/08 03/14 7

1.2 – Research Not Started 03/16 03/30 15

1.3 – Getting Approval Not Started 04/01 04/30 30

1.4 – EIA/IEE of the project Not Started 05/10 07/23 75

1.5 – Guidelines preparation of Project Not Started 05/10 07/08 60

1.6 – Preparation of Project Budget/BoQ Not Started 05/10 06/08 30

2 PROJECT DEFINITION AND PLANNING Not Started 03/01 04/30 61

2.1 – Scope & Goal Setting Not Started 03/01 03/07 7

2.2 – Budget Not Started 03/08 03/14 7

2.3 – Communication Plan Not Started 03/16 03/30 15

2.4 – Risk Management Not Started 04/01 04/30 30

3 PROJECT LAUNCH & EXECUTION Not Started 04/08 11/08 215

3.1 – Status & Tracking Not Started 04/08 04/17 10

3.2 – Detailed Survey of Civil Works Not Started 04/17 05/01 15

3.2.1 –– Final Design & Approval Not Started 05/06 06/04 30

3.2.2 –– Execution of Civil Works Not Started 05/28 10/24 150

3.3 – Installation of Solar Panal & Grid Not Started 08/26 11/08 75

4 PROJECT PERFORMANCE TEST & HAND OVER Not Started 11/18 03/06 110

4.1 – Tessing of Power & Installation in Grid Not Started 11/18 12/17 30

4.2 – Quality Deliverables & Rectifications Not Started 12/20 01/03 15

4.3 – Hand Over of Project Not Started 01/04 01/07 4

4.4 – Liability Period Not Started 01/07 03/06 60


12/30 01/04 01/09 01/14 01/19 01/24 01/29 02/03 02/08 02/13 02/18 02/23 02/28 03/04 03/09 03/14

PROJECT CONCEPTION AND INITIATION

–– Project Concept

–– Project Charter Revisions

– Research

– Getting Approval

– EIA/IEE of the project

– Guidelines preparation of Project

– Preparation of Project Budget/BoQ

PROJECT DEFINITION AND PLANNING

– Scope & Goal Setting

– Budget

– Communication Plan

– Risk Management

PROJECT LAUNCH & EXECUTION

– Status & Tracking

– Detailed Survey of Civil Works

–– Final Design & Approval

–– Execution of Civil Works

– Installation of Solar Panal & Grid

PROJECT PERFORMANCE TEST & HAND OVER

– Tessing of Power & Installation in Grid

– Quality Deliverables & Rectifications

– Hand Over of Project

– Liability Period