Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Construction of Submersible Bridge across Davar Nalla Near Devi Mandir On Parwariya -Raisen

Road Distt. Raisen


S.NO SOR NO. ITEM UNIT QTY RATE AMOUNT
A Foundation
1 12.32/80 Exploratory boring
a) Upto 1 m below bed level Rm 3 2722 8,166
b) Beyond 1 m depth upto 5 m Rm 12 2847 34,164
c) Beyond 5 m depth Rm 15 2970 44,550
2 12.1/77 Excavation for structures
1 Ordinary Soil
a) Upto 3m depth cum 2831.04 61 172,693
b) 3m to 6m depth cum 957.72 70 67,040
3 12.2/77.1 Add extra if dewatering
1 Ordinary Soil
a) Upto 3m depth cum 534 30.5 16,287
b) 3m to 6m depth cum 957.72 35 33,520
5 12.3/77 PCC M15 in foundation cum 36.68 4349 159,521
6 12.6/77 PCC M15 RAFT cum 294.87 4617 1,361,415
12.6/77 RCC M30 Wall cum 235.04 5419 1,273,682
7 12.30/8 HYSD MT 24.08 81349 1,958,884
8 15.1/94 Boulder laying cum 376.5 2211 832,442

B SUB-STRUCTURE
9 13.1/82 RCC M30
a) Height upto 5 m cum 269.7 6335 1,708,550
b) height 5m to 10 m cum 130.38 6500 847,470
10 13.2/83 HYSD MT 40 81530 3,261,200
11 13.9/83 WeepHoles M 19.2 185 3,552
12 13.10/8 Back filling behind abut. cum 524.45 665 348,759
13.11/83 Filter Media cum 14.94 750 11,205

C SUPER-STRUCTURE
13 14.1/68 RCC M30 cum 13.8 6113 84,359
14 14.4/89 HYSD MT 0.69 82810 57,139
15 14.13/9 PCC M15 below approach slab cum 8.86 4664 41,323
16 14.14/9 M30 below approach slab cum 25.2 9683 244,012
17 14.6/89 Wearing coat M30 cum 22.5 11685 262,913
18 14.19/9 Filler joint RM 554.4 457 253,361
19 14.29/9 Railing RM 80 1564 125,120
20 14.28/92 Marble plates Each 2 1521 3,042
D APPROACH
21 2.2 C&G Hect 0.105 22918 2,406
22 3.3 Excavation in Soil Cum 625 55 34,375
23 3.13/20 Embankment construction Cum 5147 155 797,785
24 4.12/25 CRM Cum 329.16 1157 380,838
25 6.1/36 DLC Cum 161.98 2767 448,199
27 6.4/36 PQC sqm 371.25 6103 2,265,739
29 4.13/25 Shoulders Cum 869.4 223 193,876
30 6.8/37 Tor steel MT 2.175 68297 148,546
31 6.15/39 NP4 300 MM Cable duct RM 30 713 21,390

E Protection work
32 12.1/77 Excavation for structure cum 283.5 61 17,294
33 12.3/77 M15 IN foundation cum 42.53 4349 184,963
34 12.6/77 Pcc M15 cum 291.6 4617 1,346,317
35 12.3/80 HYSD MT 2.92 81349 237,539
34 15.5/94 Filler material cum 51.75 750 38,813
35 15.4/64 Concrete blocks M 103.5 4947 512,015

F CROSS DRAINAGE
37 12.1/77 Excavation of foundation cum 380.7 61 23,223
38 9.1/56 M15 IN foundation cum 132.69 4195 556,635
39 9.2/62 NP4 1200 DIA SINGLE ROW M 30 9544 286,320
40 9.3/62 NP4 1200 DIA DOUBLE ROW M 15 19242 288,630
41 9.8/62 Pcc M15 cum 127.58 4617 589,037

TOTAL AMOUNT 21,588,306

You might also like