Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Net Present Value

Cost  NPV: Total benefits less costs

Management  NPV = present value of cash inflow minus the initial


investment

Project selection tools


 BCR.
 ROI
Definitions  IRR
 NPV
 Value analysis or value engineering is used to
reduce cost while improving quality and Benefit Cost Ratio (BCR)
performance
 The concept of factoring overall “after-the-project”  BCR < 1 then cost are greater than benefits
costs such as maintenance and service is called life  BCR > 1 then benefits are greater than costs
cycle costing  BCR = 1 then benefits equals cost
 BCR is also called Profitability Index

Budget estimates
 Total costs as compared with the increased revenue
 Order of magnitude completed during initiating that will accrue over the life of the project
 Budget completed during planning deliverable is called Return of Investment
 Definite completed during late planning (cost  Time to recover costs is called: payback period
baseline)  The cost of giving up one project over another is
Opportunity cost
 Measures the investment’s return on project
Estimating Methods profitability: Internal rate of return (IRR)

 Expert judgment is an analogous estimating. Gives Project A recovered its costs in 5 years which is considered its
the PM an idea of what the project will cost payback period. Project A’s cost was $3.0M and is expected
 Team creates the estimate from WBS giving more to bring $50M revenue during its lifetime.
accurate estimates: Bottom up estimating A PM decides to select a $7,000 contract over a $4,000
 Since bottom up estimate is done based on the contract, his opportunity cost was $4,000
WBS defined by the team, it gains buy-in Project A cost $2.5M and is expected to bring in $30M
 Mathematical model bases on unit price: revenue during its lifetime. The ROI is expected to be $27.5M
parametric estimating
 Two types of parametric estimating: regression Cost types
analysis and learning curve
 Costs that vary depending upon the activity being
done on the project: variable cost
Present Value  Costs that remains constant independent of the
activity on the project: fixed cost
 What is the present value (value today) if we  Costs that result from work on a specific project and
expect to make $25,000, two years from now, if cannot be shared with other projects: direct costs
the annual interest rate is 15%?  Costs incurred for the benefit of more than one
Fórmula: PV= FV(1+R)n project: indirect costs also called overhead cost
PV = 25000(1+.15) 2 Assigning twice the resources but only improving the output
PV = $33,062.50 by 10% is an example of the law of diminishing returns
Cost
Management

You might also like