FOC ROLL-OUT SAN FERNANDO PROJECT


ESTIMATED TIME FRAME OF CONSTRUCTION
CABLE LAYING OF FIBER OPTIC CABLE - ESTIMATED LENGTH = 18,000 m
No. of days
ITEM DAYS DURATION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
1 Permitting 5
2 Pole Dressing 9
3 Cable Pulling 18
4 Tensioning / Fixing 18
5 Splicing & Termination 5
6 Testing 5
7 Acceptance 2
Total no. of days 51

Note: No. of days completion may vary due to circumstances uncontrolled by MIESCOR & RADIUS

Prepared by:

Jennie Lyn C. Soberano


Project Manager