Removing Socket From Wall Between

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

Maison samira Matouk

(RU2035&RU2035a)

Consultant Pooleng Architecture Tianjin Qinglong


& Engineering Client :-Samira Matoouk Main
construction
Contract
or Engineering CO. Ltd

Method Statement No.


Method Statement Title
PL-MSS-MEP-004
Removing GI boxes and wires from Wall between RU2035 & Ru2035a
Rev. No. & Date:
‘0’ – 10.03.2023

Maison Samira Matouk


Design Consultant
Pooleng Architecture & Engineering

Main Contractor
Tianjin Qinglong Construction Engineering CO.LTD

Rev. Description Date Prepared By Reviewed By

0 Issued for Tianjin Qinglong Pooleng Architecture


10.03.2023
approval Construction Engineering Engineering

Page 1 of 6
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Tianjin Qinglong


& Engineering Client :-Samira Matoouk Main
construction
Contract
or Engineering CO. Ltd

Method Statement No.


Method Statement Title
PL-MSS-MEP-004
Removing GI boxes and wires from Wall between RU2035 & Ru2035a
Rev. No. & Date:
‘0’ – 10.03.2023

1.0 Scope

The scope of this method statement is to detail the method of Removing Socket from Wall between
RU2035 & RU2035a

2.0 Material & Equipment

2.1 Cutting Tools


2.2 Hydraulic Crimping Tools
2.3 Manual Crimping Tools
2.4 Measuring Equipment
2.5 Megger
2.6 Hand Gloves, Fall Protection and PPE Safety

3.0 Applicable Location

Retail Maison Samira Matoouk (RU 2035)

4.0 Method

4.1 Storage

4.1.1 Lay down area at site to be coordinated and arrangements to be made for mobilization
of material.

4.1.2 Prior to commencement of work, Engineers & supervisor will inspect all work before
removing socket.
4.1.3 Only required materials to be shifted to site and stored temporarily and ensure extra
materials are not dumped to site and congest the working area.
4.1.4 Once work is completed, extra materials and tools to be return back to stores, work are
to be kept clean.

Page 2 of 6
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Tianjin Qinglong


& Engineering Client :-Samira Matoouk Main
construction
Contract
or Engineering CO. Ltd

Method Statement No.


Method Statement Title
PL-MSS-MEP-004
Removing GI boxes and wires from Wall between RU2035 & Ru2035a
Rev. No. & Date:
‘0’ – 10.03.2023

4.2 procedures

4.2.1 Before Starting removing the wiring for the above mentioned activities, we have to
check the connection of wiring and all area is dry from water or any rubbish inside
conduits.

4.2.2 At the wall we checking the wire from starting to the socket itself.

4.2.2 We need to make power off during removing the socket to avoid any hazard.

4.2.3 Checking inlet and outlet for this circuit to be ensure that no effect on the structural
loop.

4.2.4 After that closing this Loop by properly way to avoid any damage or hazarding happen
in the future.

4.2.5 Removing GI boxes and wiring after finishing closing structural Loop.

5.0 Inspection

5.1 Removing GI boxes and wiring from wall between RU2035 & RU2035a.

6.0 Safety

6.1 Safety precautions shall be followed in line with established project safety plan.

6.2 People shall use PPE such as safety harnesses, safety shoes, helmets, etc.

6.3 Safety Officer shall check and ensure that all safety precautions are taken before starting the
work in the shafts and heights.

6.4 Safety Officer shall check and ensure that all scaffoldings used are having duly signed tags.

Page 3 of 6
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Tianjin Qinglong


& Engineering Client :-Samira Matoouk Main
construction
Contract
or Engineering CO. Ltd

Method Statement No.


Method Statement Title
PL-MSS-MEP-004
Removing GI boxes and wires from Wall between RU2035 & Ru2035a
Rev. No. & Date:
‘0’ – 10.03.2023

7.0 Records

7.1 Work Inspection request (WIR)

7.2 Installation checklist duly signed by M/s Tianjin Qinglong Construction Engineering
CO. LTD and M/s Pooleng Architecture Engineering.

8.0 Attachments

8.1 Check List

8.2 Risk Assessment

Page 4 of 6
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Tianjin Qinglong


& Engineering Client :-Samira Matoouk Main
construction
Contract
or Engineering CO. Ltd

Method Statement No.


Method Statement Title
PL-MSS-MEP-004
Removing GI boxes and wires from Wall between RU2035 & Ru2035a
Rev. No. & Date:
‘0’ – 10.03.2023

8.1 Check List

Item To be checked Checked By


S.
N Main Contractor Consultant
Items to be checked Remark
Ye N Ye N
s o s o
01 Removing wiring with properly way as per
approved shop drawings
02 Removing socket from the wall as per
approved shop drawings
03 No damage on structural Loop
04 No damage after removing wiring structural
05 No Damage after removing GI boxes

Page 5 of 6
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Tianjin Qinglong


& Engineering Client :-Samira Matoouk Main
construction
Contract
or Engineering CO. Ltd

Method Statement No.


Method Statement Title
PL-MSS-MEP-004
Removing GI boxes and wires from Wall between RU2035 & Ru2035a
Rev. No. & Date:
‘0’ – 10.03.2023

8.2 RISK ASSESSMENT

Page 6 of 6