Professional Documents
Culture Documents
Some Case Digests For Law On Obligations
Some Case Digests For Law On Obligations
There is no basis for demanding the penal clause since the obligation
has been extinguished. Here there has been a waiver of the penal
clause as it was not demanded before the full obligation was fully paid
and extinguished.
Now, besides the Real Estate Mortgages, the penal clause which is
also an accessory obligation must also be deemed extinguished
considering that the principal obligation was considered extinguished,
and the penal clause being an accessory obligation cannot exist
without a principal obligation.
Nowhere in this case did it appear that SSS demanded from Moonwalk
the payment of its monthly amortizations. Neither did it show that
petitioner demanded the payment of the stipulated penalty upon the
failure of Moonwalk to meet its monthly amortization. What the
complaint itself showed was that SSS tried to enforce the obligation
sometime in September, 1977 by foreclosing the real estate
mortgages executed by Moonwalk in favor of SSS. But this
foreclosure did not push through upon Moonwalk’s requests and
promises to pay in full. The next demand for payment happened on
October 1,
1979 when SSS issued a Statement of Account to Moonwalk And in
accordance with said statement, Moonwalk paid its loan in full.
What is clear, therefore, is that Moonwalk was never in default
because SSS never compelled performance.
2. RCBC vs. CA
TITLE RIZAL COMMERCIAL BANKING CORPORATION, petitioner, vs. COURT
OF APPEALS and FELIPE LUSTRE, respondents
Article 1170 of the Civil Code states that those who in the
performance of their obligations are guilty of delay are liable for
damages. The delay in the performance of the obligation, however,
must be either malicious or negligent.
Thus, assuming that private respondent was guilty of delay in
the payment of the value of the unsigned check, private respondent
cannot be held liable for damages. There is no imputation, much less
evidence, that private respondent acted with malice or negligence in
failing to sign the check. Indeed, we agree with the Court of Appeals’
finding that such omission was mere “inadvertence” on the part of
private respondent. Toyota salesperson Jorge Geronimo testified that
he even verified whether private respondent had signed all the
checks and in fact returned three or four unsigned checks to him for
signing: x x x Even when the checks were delivered to petitioner, it
did not object to the unsigned.
CONCLUSION WHEREFORE, subject to these modifications, the decision of the
Court of Appeals is AFFIRMED. SO ORDERED.
3. Barzaga vs. CA
Solar Harvest cannot demand for the refund of its payment, which in
essence is actually a claim for rescission.
An upgrading is for the better condition and, definitely for the benefit
of the passenger.—Neither was the transfer of the Vazquezes effected
for some evil or devious purpose. As testified to by Mr. Robson, the
First Class Section is better than the Business Class Section in terms
of comfort, quality of food, and service from the cabin crew; thus, the
difference in fare between the First Class and Business Class at that
time was $250. Needless to state, an upgrading is for the better
condition and, definitely, for the benefit of the passenger.
CONCLUSION WHEREFORE, the instant petition is hereby partly
GRANTED. The Decision of the Court of Appeals of 24 July 2001 in CA-
G.R. CV No. 63339 is hereby MODIFIED, and as modified, the awards
for moral damages and attorney’s fees are set aside and deleted, and
the award for nominal damages is reduced to P5,000.
RULING No. The Court agrees with the CA that under the factual milieu of the
present case, MERALCO failed to exercise the utmost degree of care
and diligence required of it, pursuant to Articles 1170 & 1173 of the
Civil Code. It was not enough for MERALCO to merely rely on the
Decision of the MTC without ascertaining whether it had become final
and executory. Verily, only upon finality of the said Decision can it be
said with conclusiveness that respondents have no right or proper
interest over the subject property, thus, are not entitled to the
services of MERALCO
PONENTE ROMERO, J.
RTC ruled in favor of Areola. The court declared that the respondent
acted in bad faith in unilaterally cancelling the insurance policy. Had
the insured met an accident at the time, the insurance company
would have disclaimed any liability because Areola could not have
been considered insured. Thus, there was breach of contract entitling
petitioner to damages prayed for.
ISSUE(S) 1. W/N the erroneous act of cancelling subject insurance policy entitle
petitioner-insured to payment of damages?
2. W/N the subsequent act of reinstating the wrongfully cancelled
insurance policy by respondent insurance company, in an effort to
rectify such error, obliterate whatever liability for damages it may
have to bear, thus absolving it therefrom?
PONENTE BELLOSILLO, J.
NATURE/ PETITION for review on certiorari of a decision of the Court of
KEYWORDS/ Appeals/ Payments by a Third Person/ First Division
DIVISION
FACTS On April 1987, petitioner Jacinto M. Tanguilig under the name J.M.T.
Engineering and General Merchandising proposed to respondent
Vicente Herce, Jr. to construct a windmill system for the latter, for a
consideration of P60,000.00 with a one-year guaranty.
Respondent denied the claim saying that he had already paid this
amount to the San Pedro General Merchandising Inc. (SPGMI) which
constructed the deep well to which the windmill system was to be
connected. According to respondent, since the deep well formed part
of the system the payment he tendered to SPGMI should be credited
to his account by petitioner.
The trial court held that the construction of the deep well was not part
of the windmill project as evidenced clearly by the letter proposals
submitted by petitioner to respondent and with respect to the repair
of the windmill, there is no clear and convincing proof that the
windmill system fell down due to the defect of the construction.
The petitioner filed for a motion for reconsideration but was denied,
hence this petition.
ISSUE(S) 3. W/N the agreement to construct the windmill system included the
installation of a deep well?
4. W/N petitioner is under obligation to reconstruct the windmill after
it collapsed?
PONENTE PARAS, J.
Upon the issues being joined, a pre-trial was conducted, during which,
the parties agreed to refer the technical issues involved in the case
to Commissioner Andres O. Hizon, who was appointed by the trial
court. Thus, the issues were divided into technical issues, which were
referred to the Commissioner and non-technical issues, which were
tried by the Court.
Plaintiff moved twice for the demolition of the building for it may
topple down in case of a strong earthquake, which were opposed by
the defendants but was later authorized by the Commissioner at the
expense of the plaintiff. But, other strong earthquakes caused further
damage to the property, so the actual demolition was undertaken by
the buyer of the damaged building.
Hizon submitted his report with the findings that while the damage
sustained by the PBA building was caused by the earthquake, they
were also caused by the (1) defects in the plans and specifications
prepared by the architects, (2) deviations from said plans and
specifications by United and (3) failure of United to observe the
requisite workmanship in construction of the building and of the
contractors and architects to exercise the requisite degree of
supervision in the construction of the said building.
RULING(S) 1. No. To exempt the obligor from liability under Art. 1174 of the Civil
Code, for a breach of an obligation due to an “act of God,’ the
following must concur: (a) the cause of the breach of the obligation
must be independent of the will of the debtor; (b) the event must
be either unforeseeable or unavoidable; (c) the event must be
such as to render it impossible for the debtor to fulfill his obligation
in a normal manner; and (d) the debtor must be free from any
participation in, or aggravation of the injury to the creditor.
The negligence of the defendant and the third-party defendants
petitioners was established beyond dispute both in the lower court
and in the IAC. United was found to have made substantial
deviations from the plans and specifications, and to have failed to
observe the requisite workmanship in the construction as well as
to exercise the requisite degree of supervision; while the third-
party defendants were found to have inadequacies or defects in
the plans and specifications prepared by them. As correctly
assessed by both courts, the defects in the construction and in the
plans and specifications were the proximate causes that rendered
the PBA building unable to withstand the earthquake. For this
reason the defendant and third-party defendants cannot claim
exemption from liability.
In any event, the relevant and logical observations of the trial
court as affirmed by IAC that “while it is not possible to state with
certainty that the building would not have collapsed were those
defects not present, the fact remains that several buildings in the
same area withstood the earthquake to which the building of the
plaintiff was similarly subjected,” cannot be ignored.
Relative thereto, the ruling of the Supreme Court in Tucker v.
Milan, reads: “One who negligently creates a dangerous condition
cannot escape liability for the natural and probable consequences
thereof, although the act of a third person, or an act of God for
which he is not responsible, intervenes to precipitate the loss.” As
already discussed, the destruction was not purely an act of God.
Truth to tell hundreds of ancient buildings in the vicinity were
hardly affected by the earthquake. Only one thing spells out the
fatal difference; gross negligence and evident bad faith, without
which the damage would not have occurred.
FACTS In the early afternoon of August 17, 1960, barge L-1892, owned by
the Luzon Stevedoring Corporation (Luzon) was being towed down
the Pasig river by tugboats “Bangus” and “Barbero”1 also belonging
to the same corporation, when the barge rammed against one of the
wooden piles of the Nagtahan bailey bridge, smashing the posts and
causing the bridge to list. The river, at the time, was swollen and the
current swift, on account of the heavy downpour of Manila and the
surrounding provinces.
CFI held the defendant liable for the damage caused by its employees
and ordering it to pay to plaintiff the actual cost of the repair of the
Nagtahan bailey bridge which amounted to P192,561.72, with legal
interest thereon from the date of the filing of the complaint.
ISSUE(S) 6. W/N the collision of appellant's barge with the supports or piers of
the Nagtahan bridge was in law caused by fortuitous event or force
majeure?
RULING(S) 5. No. Considering that the Nagtahan bridge was an immovable and
stationary object and uncontrovertedly provided with adequate
openings for the passage of water craft, including barges like those
of appellant's, it is undeniable that the unusual event that the
barge, exclusively controlled by appellant, rammed the bridge
supports raises a presumption of negligence on the part of
appellant or its employees manning the barge or the tugs that
towed it. In the ordinary course of events, such a thing does not
happen if proper care is used. In Anglo American Jurisprudence,
the inference arises by what is known as the “res ipsa loquitur”
rule.
Caso fortuito or force majeure (which in law are identical in so far
as they exempt an obligor from liability) by definition are
extraordinary events not foreseeable or avoidable, “events that
could not be foreseen, or which, though foreseen, were inevitable”
(Art. 1174, Civil Code). It is, therefore, not enough that the event
could not have been foreseen or anticipated, as is commonly
believed, but it must be one impossible to foresee or to avoid. The
mere difficulty to foresee the happening is not impossibility to
foresee the same: “un hecho no constituye caso fortuito por la sola
circunstancia de que su existencia haga mas dificil o mas onerosa
la accion diligente del presento ofensor.” The very measures
adopted by appellant prove that the possibility of danger was not
only foreseeable, but actually foreseen, and was not caso fortuito.
Otherwise stated, the appellant, Luzon Stevedoring Corporation,
knowing and appreciating the perils posed by the swollen stream
and its swift current, voluntarily entered into a situation involving
obvious danger; it therefore assured the risk, and cannot shed
responsibility merely because the precautions it adopted turned
out to be insufficient.
13. Far East Bank & Trust Co. vs. CA, 241 SCRA 671
TITLE FAR EAST BANK AND TRUST COMPANY, petitioner, vs. THE
HONORABLE COURT OF APPEALS, LUIS A. LUNA and CLARITA S.
LUNA, respondents.
PONENTE VITUG, J.
FACTS In October 1986, private respondent Luis A. Luna applied for, and
was accorded, a FAREASTCARD issued by petitioner Far East Bank
and Trust Company ("FEBTC") at its Pasig Branch. Upon his request,
the bank also issued a supplemental card to private respondent
Clarita S. Luna.
In August 1988, Clarita lost her credit card. Clarita submitted an
affidavit of loss.
On appeal, the Court of Appeals (CA) affirmed the decision of the trial
court. Its motion for reconsideration having been denied by CA,
FEBTC went to the Supreme Court with this petition for review.
CONCLUSION WHEREFORE, the petition for review is given due course. The
appealed decision is MODIFIED by deleting the award of moral and
exemplary damages to private respondents; in its stead, petitioner is
ordered to pay private respondent Luis A. Luna an amount of
P5,000.00 by way of nominal damages. In all other respects, the
appealed decision is AFFIRMED. No costs.
PONENTE YNARES-SANTIAGO, J.
NATURE/ PETITION for review on certiorari of the decision and resolution of the
KEYWORDS/ Court of Appeals/Third Party/Third Division
DIVISION
The trial court rendered a decision in favor of petitioner. FEU and its
President were ordered to pay jointly and severally Saludaga for
damages, while Galaxy and its President were ordered to indemnify
jointly and severally FEU.
15. Fil Estate Properties Inc. vs. Sps. Ronquillo, 713 SCRA 91
TITLE FIL-ESTATE PROPERTIES, INC. and FIL-ESTATE NETWORK, INC.,
petitioners, vs. SPOUSES CONRADO and MARIA VICTORIA
RONQUILLO, respondents.
PONENTE PEREZ, J.
FACTS Petitioner Fil-Estate Properties, Inc. is the owner and developer of the
Central Park Place Tower while co-petitioner Fil-Estate Network, Inc.
is its authorized marketing agent. Respondent Spouses Conrado and
Maria Victoria Ronquillo purchased from petitioners an 82-sq. m.
condominium unit at Central Park Place Tower in Mandaluyong for a
pre-selling contract price of P5,174,000.00.
Petitioners also sought relief from the Court of Appeals (CA) but their
petition was denied for lack of merit as well as their motion for
reconsideration. CA pointed out that petitioners failed to prove that
the Asian financial crisis constitutes a fortuitous event.
ISSUE(S) 13. W/N the Asian financial crisis constitutes a fortuitous event
which would justify delay in the performance of the petitioners'
contractual obligation?
14. W/N the respondents are entitled to rescission?
RULING(S) 12. No. Notably, the issues had already been settled by the Court in
the case of Fil-Estate Properties, Inc. v. Spouses Go, where the
Court stated that the Asian financial crisis is not an instance of caso
fortuito. Bearing the same factual milieu as the instant case
involves the same company, Fil-Estate, albeit about a different
condominium property. The company likewise reneged on its
obligation to respondents therein by failing to develop the
condominium project despite substantial payment of the contract
price. Fil-Estate advanced the same argument that the 1997 Asian
financial crisis is a fortuitous event which justifies the delay of the
construction project.
First off, the Court classified the issue as a question of fact which
may not be raised in a petition for review considering that there
was no variance in the factual findings of the HLURB, the Office of
the President and the Court of Appeals.
Second, the Court cited the previous rulings of Asian Construction
and Development Corporation v. Philippine Commercial
International Bank and Mondragon Leisure and Resorts Corporation
v. Court of Appeals holding that the 1997 Asian financial crisis did
not constitute a valid justification to renege on obligations. The
Court expounded: Also, we cannot generalize that the Asian
financial crisis in 1997 was unforeseeable and beyond the control
of a business corporation. It is unfortunate that petitioner
apparently met with considerable difficulty e.g., increase cost of
materials and labor, even before the scheduled commencement of
its real estate project as early as 1995. However, a real estate
enterprise engaged in the pre-selling of condominium units is
concededly a master in projections on commodities and currency
movements and business risks. The fluctuating movement of the
Philippine peso in the foreign exchange market is an everyday
occurrence, and fluctuations in currency exchange rates happen
every day, thus, not an instance of caso fortuito.
13. Yes. The non-performance of petitioners’ obligation entitles
respondents to rescission under Art. 1191 of the New Civil Code
which states: Art. 1191. The power to rescind obligations is implied
in reciprocal ones, in case one of the obligors should not comply
with what is incumbent upon him. The injured party may choose
between the fulfilment and the rescission of the obligation, with
payment of damages in either case. He may also seek rescission,
even after he has chosen fulfilment, if the latter should become
impossible.
More in point is Sec. 23 of PD No. 957, the rule governing the sale
of condominiums, which provides: Sec. 23. Non-Forfeiture of
Payments.—No instalment payment made by a buyer in a
subdivision or condominium project for the lot or unit he contracted
to buy shall be forfeited in favor of the owner or developer when
the buyer, after due notice to the owner or developer, desists from
further payment due to the failure of the owner or developer to
develop the subdivision or condominium project according to the
approved plans and within the time limit for complying with the
same. Such buyer may, at his option, be reimbursed the total
amount paid including amortization interests but excluding
delinquency interests, with interest thereon at the legal rate.
16. Metro Concast Steel Corp. vs. Allied Bank Corp., 711 SCRA 479
TITLE METRO CONCAST STEEL CORPORATION, SPOUSES JOSE S. DYCHIAO
AND TIU OH YAN, SPOUSES GUILLERMO AND MERCEDES DYCHIAO,
AND SPOUSES VICENTE AND FILOMENA DYCHIAO, petitioners, vs.
ALLIED BANK CORPORATION, respondent.
PONENTE PERLAS-BERNABE, J.
NATURE/ PETITION for review on certiorari of the decision and resolution of the
KEYWORDS/ Court of Appeals/Fortuitous Events/Second Division
DIVISION
FACTS On various dates and for different amounts, Metro Concast engaged
in the business of manufacturing steel, through its officers, obtained
several loans from Allied Bank. These loan transactions were covered
by a promissory note and separate letters of credit/trust receipts.
They also alleged that the economic reverses suffered by the Philippine
economy in 1998 as well as the devaluation of the peso against the
US dollar contributed greatly to the downfall of the steel industry,
directly affecting the business of Metro Concast and eventually leading
to its cessation.
Hence, in order to settle their debts with Allied Bank, they offered the
sale of Metro Concast’s remaining assets to Allied Bank, which the
latter, however, refused. Instead, Allied Bank advised them to sell the
equipment and apply the proceeds of the sale to their outstanding
obligations. Accordingly, petitioners offered the equipment for sale,
but since there were no takers, the equipment was reduced into ferro
scrap or scrap metal over the years.
RTC, dismissed the complaint, holding that the causes of action sued
upon had been paid or otherwise extinguished, since Allied Bank was
duly represented by its agent, Atty. Saw, in all the negotiations and
transactions with Peakstar, then it stands to reason that the MoA
between Metro Concast and Peakstar was binding upon said bank.
Allied Bank appealed to the CA, which reversed the RTC's decision
ratiocinating that there was no legal basis in fact and in law to declare
that when Bankwise reneged its guarantee under the [MoA], herein
[petitioners] should be deemed to be discharged from their obligations
lawfully incurred in favor of [Allied Bank].
ISSUE(S) 15. W/N the loan obligations incurred by the petitioners under the
subject promissory note and various trust receipts have already
been extinguished?
RULING(S) 14. No. Art. 1231 of the Civil Code states that obligations are
extinguished either by payment or performance, the loss of the
thing due, the condonation or remission of the debt, the confusion
or merger of the rights of creditor and debtor, compensation or
novation.
Anent petitioners’ reliance on force majeure, suffice it to state that
Peakstar’s breach of its obligations to Metro Concast arising from
the MoA cannot be classified as a fortuitous event under
jurisprudential formulation. As discussed in Sicam v. Jorge:
Fortuitous events by definition are extraordinary events not
foreseeable or avoidable. It is therefore, not enough that the event
should not have been foreseen or anticipated, as is commonly
believed but it must be one impossible to foresee or to avoid. The
mere difficulty to foresee the happening is not impossibility to
foresee the same. To constitute a fortuitous event, the following
elements must concur: (a) the cause of the unforeseen and
unexpected occurrence or of the failure of the debtor to comply
with obligations must be independent of human will; (b) it must be
impossible to foresee the event that constitutes the caso fortuito
or, if it can be foreseen, it must be impossible to avoid; (c) the
occurrence must be such as to render it impossible for the debtor
to fulfil obligations in a normal manner; and, (d) the obligor must
be free from any participation in the aggravation of the injury or
loss.
While it may be argued that Peakstar’s breach of the MoA was
unforeseen by petitioners, the same is clearly not “impossible” to
foresee or even an event which is “independent of human will.”
Neither has it been shown that said occurrence rendered it
impossible for petitioners to pay their loan obligations to Allied Bank
and thus, negates the former’s force majeure theory altogether.
The fact of the matter is that petitioners’ loan obligations to Allied
Bank remain subsisting for the basic reason that the former has not
been able to prove that the same had already been paid or, in any
way, extinguished.
PONENTE MORELAND, J.
NATURE An appeal from a judgment of the Court of First
Instance of Zamboanga
ISSUE/S Whether or not the obligation in question has a fixed duration of the
period for the payment?
RULING No. The obligation in question seems to leave the duration of the period
for the payment to the will of the debtor as this case falls within the
provisions of article 1128 of the Civil Code where it is apparent from the
nature of the obligation and the circumstances of the case that there
was an intention to grant to the debtor a time for payment and such
time has been left to the will of the debtor, the obligation is not due and
payable until an action has been commenced by the creditor against the
debtor for the purpose of having the court fix the date on and after which
the obligation is payable and, in pursuance of said action, such date has
been fixed.
An action for the purpose of having the court set the date of maturity of
an obligation of the character above described must be brought within
ten years from the time when the Code of Civil Procedure went into
effect under section 38 of said Code. However, in the present case, the
action to recover upon such an obligation, before a time for payment
has been set by the court pursuant to an action for the purpose, is
premature and must be dismissed upon the proper representations.
18. Jimmy Co v CA
TITLE JIMMY CO, doing business under the name & style
DRAGON METAL MANUFACTURING, petitioner,
vs.
COURT OF APPEALS and BROADWAY MOTOR SALES
CORPORATION, respondents.
PONENTE MARTINEZ, J.
ISSUE/S Whether or not a repair shop can be held liable for the
loss of a customer’s vehicle while the same is in its custody
for the repair or other job services?
RULING YES. It is not a defense for a repair shop of motor vehicles to escape
liability simply because the damage or loss of a thing lawfully placed in
its possession was due to car napping. Car napping per se cannot be
considered as a fortuitous event. The fact that a thing was unlawfully
and forcefully taken from another’s rightful possession, as in cases of
car napping, does not automatically give rise to a fortuitous event. To
be considered as such, car napping entails more than the mere forceful
taking of another’s property. It must be proved and established that the
event was an act of God or was done solely by third parties and that
neither the claimant nor the person alleged to be negligent has any
participation.
TITLE ROBERTO C. SICAM and AGENCIA de R.C. SICAM, INC., petitioners, vs.
LULU V. JORGE and CESAR JORGE, respondents.
PONENTE AUSTRIA-MARTINEZ, J.
ISSUE/S Whether or not the CA correctly adjudged petitioner Sicam together with
petitioner’s corporation, liable for the loss of the pawned jewelry
through robbery which is a fortuitous event that exempts the victim
from liability for the said loss?
The burden of proving that the loss was due to a fortuitous event rests
on him who invokes it. And, in order for a fortuitous event to exempt
one from liability, it is necessary that one has committed no negligence
or misconduct that may have occasioned the loss. It has been held that
an act of God cannot be invoked to protect a person who has failed to
take steps to forestall the possible adverse consequences of such a loss.
One’s negligence may have concurred with an act of God in producing
damage and injury to another; nonetheless, showing that the
immediate or proximate cause of the damage or injury was a fortuitous
event would not exempt one from liability. When the effect is found to
be partly the result of a person’s participation—whether by active
intervention, neglect or failure to act— the whole occurrence is
humanized and removed from the rules applicable to acts of God.
Robbery per se, just like carnapping, is not a fortuitous event. It does
not foreclose the possibility of negligence on the part of herein
petitioners. In Co v. Court of Appeals, 291 SCRA 111 (1998), the Court
held: It is not a defense for a repair shop of motor vehicles to escape
liability simply because the damage or loss of a thing lawfully placed in
its possession was due to carnapping. Carnapping per se cannot be
considered as a fortuitous event.” Just like in Co, petitioners merely
presented the police report of the Parañaque Police Station on the
robbery committed based on the report of petitioners’ employees which
is not sufficient to establish robbery. Such report also does not prove
that petitioners were not at fault.
Article 2123 of the Civil Code provides that with regard to pawnshops
and other establishments which are engaged in making loans secured
by pledges, the special laws and regulations concerning them shall
be observed, and subsidiarily, the provisions on pledge, mortgage and
antichresis. The provision on pledge, particularly Article 2099 of the Civil
Code, provides that the creditor shall take care of the thing pledged with
the diligence of a good father of a family. This means that petitioners
must take care of the pawns the way a prudent person would as to his
own property.
20. Austria v CA
G.R. No.
PONENTE CRUZ, J.
ISSUE/S Whether or not the Commission on Audit acted with grave abuse of
discretion in denying him relief and in holding him negligent for the loss
of the stolen money?
RULING YES. It seems that the petitioner was moved only by the best of motives
when he encashed the checks on July 1, 1983, so his co-employees in
Ternate could collect their salaries and wages the following day. For such
an attitude, Hernandez should be commended rather than faulted. As for
Hernandez’s choice between Marilao, Bulacan, and Ternate, Cavite, one
could easily agree that the former was the safer destination, being nearer,
and in view of the comparative hazards in the trips to the two places. It is
true that the petitioner miscalculated, but the Court feels he should not
be blamed for that. The decision he made seemed logical at the time and
was one that could be expected of a reasonable and prudent person. And
if, as it happened, the two robbers attacked him in broad daylight in the
jeep while it was on a busy highway, and in the presence of other
passengers, it cannot be said that all this was the result of his imprudence
and negligence. This was undoubtedly a fortuitous event covered by the
said provisions, something that could not have been reasonably foreseen
although it could have happened, and did. We find, in sum, that under the
circumstances as above narrated, the petitioner is entitled to be relieved
from accountability for the money forcibly taken from him in the afternoon
of July 1, 1983. To impose such liability upon him would be to read the
law too sternly when it should be softened by the proven facts.
CONCLUSION ACCORDINGLY, the petition is GRANTED, without any pronouncement as
to costs. It is so ordered.
22. Yobido v CA
PONENTE ROMERO, J.
FACTS 1. On April 26, 1988, spouses Tito and Leny Tumboy and their minor
children named Ardee and Jasmin, boarded at Mangagoy, Surigao
del Sur, a Yobido Liner bus bound for Davao City.
2. Along Picop Road in Km. 17, Sta. Maria, Agusan del Sur, the left
front tire of the bus exploded. The bus fell into a ravine around three
(3) feet from the road and struck a tree. The incident resulted in the
death of 28-year-old Tito Tumboy and physical injuries to other
passengers.
3. On November 21, 1988, a complaint for breach of contract of
carriage, damages and attorney’s fees was filed by Leny and her
children against Alberta Yobido, the owner of the bus, and Cresencio
Yobido, its driver, before the Regional Trial Court of Davao City.
4. At the pre-trial conference, the parties agreed to a stipulation of
facts. No amicable settlement having been arrived at by the parties,
trial on the merits ensued.
5. On August 29, 1991, the lower court rendered a decision dismissing
the action for lack of merit. On the issue of whether or not the tire
blowout was a caso fortuito, it found that “the falling of the bus to
the cliff was a result of no other outside factor than the tire blow-
out.”
6. Dissatisfied, the plaintiffs appealed to the Court of Appeals. They
ascribed to the lower court the following errors: (a) finding that the
tire blowout was a caso fortuito; (b) failing to hold that the
defendants did not exercise utmost and/or extraordinary diligence
required of carriers under Article 1755 of the Civil Code, and (c)
deciding the case contrary to the ruling in Juntilla v. Fontanar,5 and
Necesito v. Paras.
7. On August 23, 1993, the Court of Appeals rendered the Decision
reversing that of the lower court.
8. The defendants filed a motion for reconsideration of said decision
which was denied on November 4, 1993 by the Court of Appeals.
9. Hence, the instant petition and pray that this Court review the facts
of the case.
Under the circumstances of this case, the explosion of the new tire may
not be considered a fortuitous event. There are human factors involved in
the situation. The fact that the tire was new did not imply that it was
entirely free from manufacturing defects or that it was properly mounted
on the vehicle. Neither may the fact that the tire bought and used in the
vehicle is of a brand name noted for quality, resulting in the conclusion
that it could not explode within five days’ use. Be that as it may, it is
settled that an accident caused either by defects in the automobile or
through the negligence of its driver is not a caso fortuito that would
exempt the carrier from liability for damages.
NATURE PETITION to review the decision of the Court of First Instance of Cebu.
FACTS 1. The plaintiff was a passenger of the public utility jeepney bearing
Plate No. PUJ-71-7 on the course of the trip from Danao City to Cebu
City.
2. The jeepney was driven by defendant Berfol Camoro. It was
registered under the franchise of defendant Clemente Fontanar but
was actually owned by defendant Fernando Banson.
3. When the jeepney reached Mandaue City, the right rear tire
exploded causing the vehicle to turn turtle. In the process, the
plaintiff who was sitting at the front seat was thrown out of the
vehicle.
4. Upon landing on the ground, the plaintiff momentarily lost
consciousness. When he came to his senses, he found that he had
a lacerated wound on his right palm. Aside from this, he suffered
injuries on his left arm, right thigh and on his back.
5. Because of his shock and injuries, he went back to Danao City but
on the way, he discovered that his ‘Omega’ wrist watch was lost.
6. Upon his arrival in Danao City, he immediately entered the Danao
City Hospital to attend to his injuries, and also requested his father-
in-law to proceed immediately to the place of the accident and look
for the watch.
7. In spite of the efforts of his father-in-law, the wrist watch, which he
bought for P852.70 could no longer be found.
8. Petitioner Roberto Juntilla filed Civil Case No. R-17378 for breach of
contract with damages before the City Court of Cebu City, Branch I
against Clemente Fontanar, Fernando Banzon and Berfol Camoro.
9. The respondents filed their answer, alleging inter alia that the
accident that caused losses to the petitioner was beyond the control
of the respondents taking into account that the tire that exploded
was newly bought and was only slightly used at the time it blew up.
10. After trial, Judge Romulo R. Senining of the City Court of Cebu
rendered judgment in favor of the petitioner and against the
respondents.
11. The respondents appealed to the Court of First Instance of
Cebu, Branch XIV. Judge Leonardo B. Cañares reversed the
judgment of the City Court of Cebu upon a finding that the accident
in question was due to a fortuitous event.
12. A motion for reconsideration was denied by the Court of First
Instance.
13. Hence, this petition.
ISSUE/S Whether or not the Honorable Court of First Instance of Cebu committed
grave abuse of discretion in failing to take cognizance of the fact that
defendants and/or their employee tailed to exercise ‘utmost and/or
extraordinary diligence’ required of common carriers contemplated under
Art. 1755 of the Civil Code of the Philippines?
RULING YES. The said Court erred when it absolved the carrier from any liability
upon a finding that the tire blow out is a fortuitous event. In the case at
bar, there are specific acts of negligence on the part of the respondents.
While it may be true that the tire that blew-up was still good because the
grooves of the tire were still visible, this fact alone does not make the
explosion of the tire a fortuitous event. No evidence was presented to
show that the accident was due to adverse road conditions or that
precautions were taken by the jeepney driver to compensate for any
conditions liable to cause accidents.
In Lasam v. Smith (45 Phil. 657), we laid down the following essential
characteristics of caso fortuito: “x x x ‘In a legal sense and, consequently,
also in relation to contracts, a caso fortuito presents the following essential
characteristics: (1) The cause of the unforeseen and unexpected
occurrence, or of the failure of the debtor to comply with his obligation,
must be independent of the human will. (2) It must be impossible to
foresee the event which constitutes the caso fortuito, or if it can be
foreseen, it must be impossible to avoid. (3) The occurrence must be such
as to render it impossible for the debtor to fulfill his obligation in a normal
manner. And (4) the obligor (debtor) must be free from any participation
in the aggravation of the injury resulting to the creditor.’ (5 Encyclopedia
Juridica Española,309.)”
In the case at bar, the cause of the unforeseen and unexpected occurrence
was not independent of the human will. The accident was caused either
through the negligence of the driver or because of mechanical defects in
the tire. Common carriers should teach their drivers not to overload their
vehicles, not to exceed safe and legal speed limits, and to know the correct
measures to take when a tire blows up thus insuring the safety of
passengers at all times. It is sufficient to reiterate that the source of a
common carrier’s legal liability is the contract of carriage, and by entering
into the said contract, it binds itself to carry the passengers safely as far
as human care and foresight can provide, using the utmost diligence of a
very cautious person, with a due regard for all the circumstances. The
records show that this obligation was not met by the respondents.
It should be noted that the City Court of Cebu found that the petitioner
had a lacerated wound on his right palm aside from injuries on his left
arm, right thigh and on his back, and that on his way back to Danao City,
he discovered that his “Omega” wrist watch was lost. These are findings
of facts of the City Court of Cebu which we find no reason to disturb. More
so when we consider the fact that the Court of First Instance of Cebu
impliedly concurred in these matters when it confined itself to the question
of whether or not the tire blow out was a fortuitous event.
CONCLUSION WHEREFORE, the decision of the Court of First Instance of Cebu, Branch
IV appealed from is hereby REVERSED and SET ASIDE, and the decision
of the City Court of Cebu, Branch I is REINSTATED, with the modification
that the damages shall earn interest at 12% per annum and the attorney’s
fees are increased to SIX HUNDRED PESOS (P600.00). Damages shall earn
interests from January 27, 1975. SO ORDERED.
PONENTE CORONA, J.
ISSUE/S Whether or not the court of appeals erred in applying the doctrine of “res
ipsa loquitur” in the present case?
RULING NO. Res ipsa loquitur is a Latin phrase which literally means “the thing or
the transaction speaks for itself.” It relates to the fact of an injury
that sets out an inference to the cause thereof or establishes the plaintiff’s
prima facie case. The doctrine rests on inference and not on presumption.
The facts of the occurrence warrant the supposition of negligence and they
furnish circumstantial evidence of negligence when direct evidence is
lacking. The doctrine is based on the theory that the defendant either
knows the cause of the accident or has the best opportunity of ascertaining
it and the plaintiff, having no knowledge thereof, is compelled to allege
negligence in general terms. In such instance, the plaintiff relies on proof
of the happening of the accident alone to establish negligence.
CONCLUSION WHEREFORE, the petition is hereby DENIED and the decision of the Court
of Appeals affirmed in toto. Costs against petitioners. SO ORDERED.
PONENTE QUISUMBING, J.
ISSUE/S Whether or not the Honorable Court of Appeals erred in holding that the
Asian Financial Crisis is not a fortuitous event that would excuse the
delivery by petitioner of the subject condominium unit to respondents?
CONCLUSION WHEREFORE, the petition is DENIED for lack of merit. Petitioner is hereby
ordered (1) to reimburse respondents P3,439,000.07 at 6% interest
starting August 4, 1999 until full payment, and (2) to pay respondents
P100,000.00 attorney’s fees. Costs against petitioner. SO ORDERED.