E2 

LOG ‐ LAGOON 40
Date of PO  Expected delivery date (start  Actual 
S No: Product Name Brand BUILDING NAME Qty Unit Lead Time Supplier MRF No Approved Date PO No: Status MTS Status
issued date) Delivery Date

Electrical

1 FLOOD LIGHT WITH ARM LEDVANCE Fence  1500 PCS 4‐6 Week ILF/FAIR LIGHT

2 FEEDER PANEL ALFANAR Fence  5 PCS 8 Week ALFANAR

3 4Cx6mm2 CU/XLPE/PVC+1Cx4mm2 CU/PVC Bahra/Riyadh Fence  8000 MTR 4‐6 Week Electric House

4 4x120mm2 CU/XLPE/SWA/PVC +1CX70mm2 Bahra/Riyadh Fence  1000 MTR 4‐6 Week Electric House

5 4x240mm2 CU/XLPE/SWA/PVC +1CX70mm2 Bahra/Riyadh Fence  500 MTR 4‐6 Week Electric House