PL-MEP-002 Installation & Testing of Underground Drainage Piping
PL-MEP-002 Installation & Testing of Underground Drainage Piping
(RU2035&RU2035a)
Main Contractor
Tianjin Qinglong Construction Engineering CO.LTD
Page 1 of 7
Maison samira Matouk
(RU2035&RU2035a)
1.0 Scope
The scope of this method statement is to detail the method of Connection installation of Underground
drainage piping with stub out underground piping.
2.1 UPVC underground drainage pipes with fittings BS 4514 & BS 5255
2.2 PPE safety
2.3 Plumber’s Toolbox
2.4 Hacksaw
2.5 Bristle brush
2.6 Measuring Tape
2.7 Scaffolding
2.8 UPVC sealant
4.0 Method
4.1 Storage
4.1.1 When offloading pipes shall be lowered to the ground either manually or with
mechanical aid like crane depending on the quantity of the pipe and should not be
dropped to the ground. Refer – Manufacturer’s instruction for transport, handling and
storage.
4.1.2 Pipes shall be given adequate support at all times and shall be stacked on a flat surface
free from any sharp objects.
Page 2 of 7
Maison samira Matouk
(RU2035&RU2035a)
4.1.3 Timber supports of a least 3” wide shall be placed beneath the pipes with spacing not
greater than 1.8 mtr. Closer supports will be required for sizes below 160 mm.
4.1.4 Pipes and fittings shall not be stored under direct sunlight.
4.1.5 Socketed pipes shall be stacked in layers with sockets placed at alternate ends of the
stack and with the sockets protruding to avoid unstable stacks and the possibility of
imparting a permanent set to the pipes.
4.1.6 Larger pipe sizes of thicker class shall always be placed at the bottom.
4.2 Installation
4.2.1 Pipes are brought to the work place manually from the store to the area.
4.2.2 Ensure that the mating areas of spigot and socket are thoroughly clean and square.
4.2.3 Assess the full socket depth by simple measurement and mark spigot accordingly.
4.2.4 Apply lubricant to the spigot side and to the inside of the joint on rubber.
4.2.5 Accurate axial alignment of the spigot and socket prior to joining is important, hand
feed spigot into rubber joint until resistance from the inner sealing section is felt.
4.2.7 Complete the joint by applying leverage to the following socket and using a timer block
to prevent damage.
4.2.8 Connect installation underground drainage pipe with stub out underground piping by
joint.
4.2.9 Testing and commissioning after connection underground drainage piping by leakage
test after connection.
Page 3 of 7
Maison samira Matouk
(RU2035&RU2035a)
Important Notice
a) If pipes are cut on site, make sure that the new spigots are cut square with a fine toothed
saw and are chamfered to half pipe thickness with a coarse file before jointing.
b) All pipes and fittings delivered to site for the work should be stored in an approved
manner to avoid deterioration due to accidental damage and atmospheric condition.
c) Before final erection, all pipes should be free of dust, scale rust or other form of
corrosion.
d) All pipes will be laid to a uniform slope as indicated on the drawing on a prepared
trench bed.
e) Before laying, all pipes and fittings should be checked for defects and jointing spaces
cleaned properly.
f) Socketed pipes to be laid with sockets uphill. Scoop out compact bed locally at pipe
sockets where socket pipes are used. Adjust pipes to line and level with the help of 1
mtr. Long spirit level and if required the surveyor’s help can be obtained. Ensure pipe
bottoms rest uniformly on the bedding.
g) To avoid possible damage or deformation of the pipe, its support by the ground in which
it is laid should be made as uniform as possible and must be free from large stones,
sharp edged flints or other hard objects.
4.3 Back-Filling
4.3.1 Before commencing to place any side fill material; any levelling pegs or temporary
packing shall be removed.
4.3.2 Filling around the pipes shall be done with the same bedding material to a minimum
height of 100mm and a maximum of 300mm and be thoroughly compacted.
4.3.3 Plastic identification tape shall be installed during back filling operations. The tape
shall be centered on the pipeline with lettering facing upwards.
Page 4 of 7
Maison samira Matouk
(RU2035&RU2035a)
5.0 Safety
5.1 All safety precautions shall be followed as per established project safety procedures.
5.5 Hot work permit to be obtained from the concerned safety officer.
6.0 Records
6.2 Installation checklist duly signed by M/s Tianjin Qinglong Construction Engineering CO. LTD
and M/s Pooleng Architecture Engineering.
7.0 Attachments
Page 5 of 7
Maison samira Matouk
(RU2035&RU2035a)
Yes No Yes No
01 Check to be sure that the contractor has the √ √
final approved plans signed by the Engineer
02 Check to be sure that the contractor has all √ √
the required submittals and shop drawings,
and these have been satisfactorily reviewed
by Consultant
03 Check the materials to be installed for √ √
conformance with approved submittals and
shop drawings.
04 Check each pipe length for cracks or √ √
imperfections
05 Ensure the pipe ends are clean √ √
06 Check the material complies with material √ √
submittal
07 Sizes of pipes & fittings are as per approved √ √
shop drawings
08 Location and routing of pipes are as per √ √
approved shop drawings
Page 6 of 7
Maison samira Matouk
(RU2035&RU2035a)
Page 7 of 7
Maison Samira Matoouk (RU2035)
Falling from height 1. Only light work, off short duration and work
in which the operative can maintain secure
hand and foot hold can be undertaken form
a ladder
Operatives/ Supervisor
Use of Ladder Med 2. Never try to overreach with any ladders
5 Staff/ 3 4 12 1 4 4 Low Site Eng.
ium 3. Check the ladder is of suitable quality for
Foreman,
industrial use and is in good condition
4. Maintain a minimum of 3 points of contact
with stepladders at all times
(feet/thighs/hands)
Maison Samira Matoouk (RU2035)
1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that
risks have well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these
potential high risks.