Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

Maison samira Matouk

(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

Maison Samira Matouk


Design Consultant
Pooleng Architecture & Engineering

Main Contractor
Tianjin Qinglong Construction Engineering CO.LTD

Rev. Description Date Prepared By Reviewed By

0 Issued for Tianjin Qinglong Pooleng Architecture


28.03.2023
approval Construction Engineering Engineering

Page 1 of 7
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

1.0 Scope

The scope of this method statement is to detail the method of Connection installation of Underground
drainage piping with stub out underground piping.

2.0 Material & Equipment

2.1 UPVC underground drainage pipes with fittings BS 4514 & BS 5255
2.2 PPE safety
2.3 Plumber’s Toolbox
2.4 Hacksaw
2.5 Bristle brush
2.6 Measuring Tape
2.7 Scaffolding
2.8 UPVC sealant

3.0 Applicable Location

Retail Maison Samira Matoouk (RU 2035)

4.0 Method

4.1 Storage

4.1.1 When offloading pipes shall be lowered to the ground either manually or with
mechanical aid like crane depending on the quantity of the pipe and should not be
dropped to the ground. Refer – Manufacturer’s instruction for transport, handling and
storage.

4.1.2 Pipes shall be given adequate support at all times and shall be stacked on a flat surface
free from any sharp objects.

Page 2 of 7
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

4.1.3 Timber supports of a least 3” wide shall be placed beneath the pipes with spacing not
greater than 1.8 mtr. Closer supports will be required for sizes below 160 mm.

4.1.4 Pipes and fittings shall not be stored under direct sunlight.

4.1.5 Socketed pipes shall be stacked in layers with sockets placed at alternate ends of the
stack and with the sockets protruding to avoid unstable stacks and the possibility of
imparting a permanent set to the pipes.

4.1.6 Larger pipe sizes of thicker class shall always be placed at the bottom.

4.2 Installation

4.2.1 Pipes are brought to the work place manually from the store to the area.

4.2.2 Ensure that the mating areas of spigot and socket are thoroughly clean and square.

4.2.2 Set the rubber ring into groove.

4.2.3 Assess the full socket depth by simple measurement and mark spigot accordingly.

4.2.4 Apply lubricant to the spigot side and to the inside of the joint on rubber.

4.2.5 Accurate axial alignment of the spigot and socket prior to joining is important, hand
feed spigot into rubber joint until resistance from the inner sealing section is felt.

4.2.7 Complete the joint by applying leverage to the following socket and using a timer block
to prevent damage.

4.2.8 Connect installation underground drainage pipe with stub out underground piping by
joint.
4.2.9 Testing and commissioning after connection underground drainage piping by leakage
test after connection.

Page 3 of 7
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

Important Notice

a) If pipes are cut on site, make sure that the new spigots are cut square with a fine toothed
saw and are chamfered to half pipe thickness with a coarse file before jointing.

b) All pipes and fittings delivered to site for the work should be stored in an approved
manner to avoid deterioration due to accidental damage and atmospheric condition.

c) Before final erection, all pipes should be free of dust, scale rust or other form of
corrosion.

d) All pipes will be laid to a uniform slope as indicated on the drawing on a prepared
trench bed.

e) Before laying, all pipes and fittings should be checked for defects and jointing spaces
cleaned properly.

f) Socketed pipes to be laid with sockets uphill. Scoop out compact bed locally at pipe
sockets where socket pipes are used. Adjust pipes to line and level with the help of 1
mtr. Long spirit level and if required the surveyor’s help can be obtained. Ensure pipe
bottoms rest uniformly on the bedding.

g) To avoid possible damage or deformation of the pipe, its support by the ground in which
it is laid should be made as uniform as possible and must be free from large stones,
sharp edged flints or other hard objects.

4.3 Back-Filling

4.3.1 Before commencing to place any side fill material; any levelling pegs or temporary
packing shall be removed.

4.3.2 Filling around the pipes shall be done with the same bedding material to a minimum
height of 100mm and a maximum of 300mm and be thoroughly compacted.

4.3.3 Plastic identification tape shall be installed during back filling operations. The tape
shall be centered on the pipeline with lettering facing upwards.

Page 4 of 7
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

5.0 Safety

5.1 All safety precautions shall be followed as per established project safety procedures.

5.2 Warning sign shall be placed at required location.

5.3 Fire blanket to be kept at the required location.

5.4 Fire extinguisher to be placed at the work spot.

5.5 Hot work permit to be obtained from the concerned safety officer.

6.0 Records

6.1 Work Inspection request (WIR).

6.2 Installation checklist duly signed by M/s Tianjin Qinglong Construction Engineering CO. LTD
and M/s Pooleng Architecture Engineering.

7.0 Attachments

7.1 Check List

7.2 Risk Assessment

Page 5 of 7
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

8.1 Check List

Item To be checked Checked By


S.N Main Contractor Consultant
Items to be checked Remark

Yes No Yes No
01 Check to be sure that the contractor has the √ √
final approved plans signed by the Engineer
02 Check to be sure that the contractor has all √ √
the required submittals and shop drawings,
and these have been satisfactorily reviewed
by Consultant
03 Check the materials to be installed for √ √
conformance with approved submittals and
shop drawings.
04 Check each pipe length for cracks or √ √
imperfections
05 Ensure the pipe ends are clean √ √
06 Check the material complies with material √ √
submittal
07 Sizes of pipes & fittings are as per approved √ √
shop drawings
08 Location and routing of pipes are as per √ √
approved shop drawings

Page 6 of 7
Maison samira Matouk
(RU2035&RU2035a)

Consultant Pooleng Architecture Main


Tianjin Qinglong
& Engineering Client :-Samira Matoouk construction
Contract
or Engineering CO. Ltd

Method Statement Title Method Statement No.


Connection Installation of Underground drainage piping with stub out PL-MSS-MEP-002
underground piping Rev. No. & Date:
‘0’ – 28.03.2023

8.2 RISK ASSESSMENT

Page 7 of 7
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 28/03/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Delivery/ collection drivers shall be subject to


Plant and Traffic Tianjin quinlong Construction Engineering
movement induction/Training with regards to traffic
management.
 Run over by 2. Ensure exclusion zone is set up around the
vehicles/plants preparation work area and all plant
movement and checked by supervisor
 Hit by reversing
3. Always use the pedestrian access provided
equipment
4. Traffic light batons shall be provided for banks
Delivering,  Overhead
man at night
unloading and obstructions
Operatives 5. All plant to have a fully trained banks man Site Eng.
storing of PVC  Vehicle break
1 Staff/visitors Med present all times. Supervisor,
Pipe and fittings down 3 4 12 1 4 4 Low
ium 6. No plant to reverse without banks man. Foreman,
using pickup and  Property damage
7. Ensure access route are sufficient and safe to
unloading by  Collision with use.
manual handling other vehicles
8. Do not take rest in or under vehicles
 Personal injury 9. Proper barricade and safety signboard
 Fatality provided on open excavation
Accident due to 10. All vehicles must be fitted with reverse alarm
poor lighting and / Flashing light.
visibility (operation 11. The work place and all access to be well
at night illuminated.
12. Enforce Speed limit
13. Ensure all vehicles entering the site is properly
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 28/03/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Eliminate the need for manual handling by


using mechanical aid.
2. Reduce the weight of a load to limit force
exertion
3. If unsure of the load weight, check with
1. Musculoskeletal supervisor. Supervisor,
Operatives 4. Ensure proper manual handling procedure
Manual Handling disorders Med Foreman,
2 involved in 5. Ensure adherence with sufficient and Low
2. Hand injuries 3 4 12 ium 1 4 4 Site Eng.
work appropriate PPE.
3. cut & bruises
6. Limit load carrying to 20kg per person
7. Supervisor must make sure while manual
handling load individual task and environment
to be considered to reduce the risk of manual
handling.
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Ensure accesses are kept clear at all times.


2. Housekeeping to be carried out regularly
throughout the day when required
3. Supervisor to ensure operatives are stacking
material neatly and stacks are stable and in a
Operatives safe condition
 Slips, Trips and fall Supervisor,
Staff/storekeepe 4. Provide adequate lighting especially during
 Poor house Med Foreman,
3 Material storing r 3 4 12 night hours 1 4 4 Low
keeping ium Site Eng.
5. Appropriate space is allowed around storage
areas for employees to move around safely
without the risk being trapped between
stacked materials.
6. Maintain good housekeeping.
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. STARRT card briefing must before start the


activity
2. Ensure the PTW in place.
3. Ensure proper working platform with
complete fall protection
4. Ensure Full body harness and 100% Tie off
Work at height 5. Ensure the scaffold platform is properly
erected with "Safe to use" tag.
6. Ensure castor wheels are locked
7. Hand tools must be secured/tethered
Installation of  Fall form height
Operatives/Staf 8. Work materials strictly not allowed to be
drainage Pipe
f/ stored on platform except for working tools Supervisors
(PVC) with  Falling objects Med
4 Visitors 3 4 12 9. Ensure avoid over reaching and climb on 1 4 4 Low Foreman,
accessories ium
Others handrail. Site Eng.
fittings using  Over loading
10. Ensure unauthorised person not allowed to
mobile Tower
modify the scaffolding and if needed to any
 Protruding objects
changes then must be modified by trained
and certified scaffolder.
 Access & egress 11. Ensure safe access to the working platform
12. Scaffold access must be free from obstruction
13. Ensure sufficient illumination in work area
14. Ensure while fittings the GI clamp and
brackets operatives must safely use drill
machine to avoid finger injury.
15. Ensure that working near fragile surface
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

special care of body and eye protection with


necessary PPE.
16. Must clean the debris after completion the
job and maintain good housekeeping.

Falling from height 1. Only light work, off short duration and work
in which the operative can maintain secure
hand and foot hold can be undertaken form
a ladder
Operatives/ Supervisor
Use of Ladder Med 2. Never try to overreach with any ladders
5 Staff/ 3 4 12 1 4 4 Low Site Eng.
ium 3. Check the ladder is of suitable quality for
Foreman,
industrial use and is in good condition
4. Maintain a minimum of 3 points of contact
with stepladders at all times
(feet/thighs/hands)
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

Working on Uneven 5. If possible avoid the use of stepladders at a


ground working height of 2 meters and more.
6. Check the ladder legs (and stays) are fully
deployed or locked (depending on type) to
maintain maximum base dimensions and the
step ladder is orientated to provide
maximum stability.
7. Stepladders/ladders has to be used on
Falling objects leveled ground/firm base
8. Ensure that during using ladder from the top
2 step is blocked to avoid climb on that.
9. The ladder securely fixed to prevent slipping
outwards or sideways or securely footed at
all times.
10. Person must hold the ladder while another
operative working on it
11. 8) Materials should not be placed above the
thread of ladders/step ladders
12. Do not carry any materials in one hand while
climbing or getting down from ladder
13. Ensure the area under the ladder is
barricaded especially if it is being used in a
public area.
14. Ensure the ladder is electrical insulated
podium type if working in live services.
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Ensure that all chemical substances have a


COSHH assessment
2. Refer SDS prior to any handling of hazardous
substances and ensure SDS is easily accessible
at site while working with chemicals.
3. Ensure chemicals are properly stacked.
4. Ensure all chemical containers are properly
 Spillage/ soil
labeled.
contamination
5. Spill kits to be available at site.
6. Ensure operatives use the correct PPE
 Burns
7. Competent person to oversee the storage,
 Contact with skin
use and disposal of hazardous materials. Supervisors
Operatives Med
6 Use of Glue 3 4 12 8. Ensure that correct welfare/first aid facilities 1 4 4 Low Foreman,
 Acute/Chronic using solvent ium
Solvent, are available in the area i.e. washing SiteEng.
adverse heath
(Hazardous facility/eye wash.
effect.
Substance) 9. Proper and adequate PPE to be used always
 Fire 10. Ensure all chemical containers are properly
labeled.
11. Adjust work schedules so that workers are not
overexposed to a hazardous chemical.
12. Wear respiratory protection
13. Ensure proper and adequate PPE to be used
always.
14. Ensure smoking only in designated area
15. Ensure appropriate Firefighting equipment’s
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

are in place and easily accessible

1. All portable electrical equipment must be PAT


tested and color coded. Make sure the test
dates are visible on the equipment.
 Damaged
2. Ensure all disk shall be appropriate and expiry
Sockets & cable
date is over.
insulation.
3. Ensure all power tools are in good condition
 Electrocution
and appropriately maintained
 Electric shock
4. PTW to be obtained, prior to commencing the
 Short circuit &
Use of power task
Burns Supervisor
tools such as Operatives and Med 5. Damaged industrial sockets and power cables
7  Trip/Fall 3 4 12 1 4 4 Low Foreman
Grinder/Cutter & staff ium must be removed.
 Noise Site Eng.
Drill machine, 6. Ensure the electrical cable is not damaged
 Hearing loss
 Vibration and has not been repaired with insulating
 Dust tape or unsuitable connectors.
7. Ensure cables from power tools shall be
organized so as not to present a tripping
hazard
8. Only trained competent operatives to operate
the power tools.
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

9. Ensure proper and regular maintenance of


equipment that takes account of noise
10. Ensure proper hearing protection always.
11. Make sure people use the right tool for the
job and are trained to use it correctly
12. Ensure defective tools that require
maintenance is reported for repair or
replacement.
13. Instruct workers to keep their hands warm
and dry, and to not grip a vibrating tool too
tightly.
14. Ensuring proper job rotation and limiting time
operatives working with power tools and
hand tools.
15. Use dust mask
16. Ensure proper earth leakage protection is
provided.
17. All power tools must be 110V to be ensured.
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Risk assessment must brief to the


operatives.
2. Ensure permit obtained for pressure
test.
3. All pressure tests must be conducted
with due regard for the safety of life and
Pressure Testing property.
4. Precautions should be taken to see that
people not directly engaged in the
Hydro test testing operations remain out of the test
High-pressure leak area during the test period.
of water All operatives Site eng
8 Failure of hydraulic involved in 4 4 16 High 5. During pressure testing events, distinct 1 4 4 Low Supervisor
test pump work warning signs, such as DANGER – HIGH Foreman
Electric shock PRESSURE TESTING IN PROGRESS must
Electrocution be posted at the test work area with
exclusion zone .
6. Check that all high points have a tap or
vent to facilitate removal of air during
filling and that these are all closed.
7. Blank, plug or seal any open ends and
close all valves at the limits of the test
section of the piping.
8. Start to fill the piping and then ‘walk’ the
route of the piping under test,
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

continuously visually checking for leaks


and by listening for the sound of
escaping air
9. Release air from all the high points
systematically through the system to
completely fill it with water
10. Check that the test gauge is functioning
correctly has been calibrated and has the
correct range of the test pump.
11. Check that a suitable hose is available for
draining the system
12. Before attempting test, Supervisor will
review the test specifications and
procedures with the Test Inspector and
any other relevant personnel to be
certain that all equipment is adequate,
and duties are organized and understood
13. All the electric live service must be
temporary isolate to avoid electric shock
and electrocution
14. STARRT talk must conduct by supervisor
15. PPE must in use with face shield
16. Ensure proper grounding and earthling.
17. After completion of the pressure test,
release the water and disconnect all the
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

temporary connections and close both


ends
18. Exclusion zone must be removing and
remove the danger signage after
completion of pressure test.
Maison Samira Matoouk (RU2035)

Rev. No. Rev. Date


00 17/02/2023
Risk Assessment Record
Activity: Connection Installation of Underground drainage Piping with stub out underground piping

Base Risk Ranking Residual Risk Ranking


CONTROL MEASURES
IDENTIFIED (Without Controls) (With Controls) Person
No ACTIVITY People Involved
HAZARDS/RISKS Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Hand tools should be visually inspected for


 Improper defects, prior to use.
selection of hand 2. Never use damaged, blunt or broken tools to
tools. avoid injury.
 Damaged and 3. Select right tools for right Job Site engg
Defective Hand 4. Ensure no Homemade or makeshift tools to Supervisor
Use of Hand
tools. be used at site Foreman
Operatives/Staff Med
9 tools  Hand injuries 3 3 9 5. Remove from service any tool that shows 1 3 3 Low
ium
 Pinch point signs of damage or defect
 Ergonomics 6. Ensure Hand tools are Stored in accordance
 Repetitive strain with the manufacturer’s instructions.
injury 7. Ensure hands are not in direct line of fire
while working with hand tools
8. Ensure appropriate PPE at all times.
RISK ASSESSMENT & CONTROL GUIDELINES

1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that
risks have well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these
potential high risks.

1.2. Risk Assessment


Risk is the probability of an event occurring in a given set of circumstances. The ‘event’ is an exposure to hazard. The
hazard is the potential to cause harm. The risk assessment is the technique of evaluating not just the likelihood of an
event occurring, but also the outcome will be in terms of injury, loss, damage or harm.
1.3. Risk Assessment Process
The process of carrying out a risk assessment should be as follows.
1. Identify the hazards.
2. Identify who might be harmed and how.
3. Evaluate the risk and implement the control measures.
4. Record the significant findings.
5. Review the assessment and update if necessary.

1.4. Examination of the Hazards and Risk Associated


 Competent staff must be used in examining the risk associated with the identified hazard.
 Competent staff should examine following aspect to determine the risk involved:
o Examine the existing control measures in place.
o Identify employees at risk.
o Likelihood of risk.
o Severity
o Risk level and their tolerability.

1.5. Evaluating the risk:


Once the necessary information has been obtained on the hazards encountered by work activities, next stage is to
access the risks.
1.5.1. Risk Rating Score
Risk rating score is a combination of two factors.
 The severity of the risk that could injure persons or cause damage to plant.
 The likelihood of the risk that it could happen (Probability).

RISK RATING = LIKELIHOOD X SEVERITY


NOTE: Each activity has to be assessed for the risk value for determining the level of Severity and likelihood are mentioned in
the table below.
No Injury Minor Moderate Major Catastrophic
(1) Injury (2) Injury (3) Injury (4) (5)
1 2 3 4 5
Rarely (1)
Unlikely (2) 2 4 6 8 10
LIKELIHOOD
Possible (3) 3 6 9 12 15
Likely (4) 4 8 12 16 20
Almost
5 10 15 20 25
Certain (5)
RISK LEVEL:
Low Medium High

You might also like