Professional Documents
Culture Documents
Analysis of Overheads Description Amount (ETB)
Analysis of Overheads Description Amount (ETB)
Stores
4 Stores (1 @main camp, 2 @Advance camps & 1
@ Quarry site)
Averge Area of each Store 100 m2
Total area 400 m2
Cost per m2 8000 Br/m2
Total 3,200,000.00 Br
Advance camps
Two camps each 50 m2
Cost per m2 5000 Br/m2
Total 500,000.00 Br
Guarantees
Estimated Direct Cost 753,136,825.42 Br.
Estimated Direct Cost including VAT 903,764,190.50 Br.
Amount of Performance Guarantee 234,978,689.53 Br.
Estimated Amount of premium @ 1.5% 3,524,680.34 Br.
Insurances
Estimated Direct Cost 753,136,825.42 Br.
Estimated Direct Cost including VAT 903,764,190.50 Br.
Amount of Works to be insured 1,351,127,464.80 Br.
Estimated Amount of CAR premium @ 0.25% 3,377,818.66 Br.
Rate/hr or
Item No. Description Quantity /unit No. days amount
1 Supply of bottled water for Employer rep. 200 15.00 30 90,000.00
2 Supply of gas 10 1100 11,000.00
5 Messing facilities LS 10,000.00
6 Attendance LS 15,000.00
7 Photograph LS 500.00
8 Assistance LS 5,000.00
Cleaning Materials LS 15,836.00
9 Emergence equipments LS 2,000.00
Total 149,336.00
Total Cost of Contractor's Srevices of Site Facilities 6,272,112.00
No. of
Equipment Units No. Trips Equipment*
Dozer D8R (305 hp) 7 7 Hand Tamper 1
Dozer D7R (230 hp) 3 3 Generator 5
Grader 14 H 4 4 Driller 1
Grader 140 H 1 1 Jack Hammer 4
Track Type Loader 2 2 Sand Washing Machine 1
Wheel Loader 10 10 Air Compressor 2
Track Type Excavator 222 HP 12 12 Concrete mixer 750/500 lts 5
Track Type Excavator with rock breaker 3 3 Concrete mixer 300lt lts 5
Backhoe Excavator - 128 HP 2 2 Concrete vibrator 10
Vibratory Compactor 10 10 Concrete vibrator (small) 5
Gravel Paver 1 1 Bar bend. & Cutting 3
Concrete Plant 1 3 Painting Machine 2
Crushing plant 1 3 Dumper 2
Pneumatic tyred roller 2 1 Asphalt Distributer 1
Sheep's foot roller, 14Ton 1 1 Centrifugal W/Pump 5
Mobile Crane 2 2 Water Tanker 30
Asphalt Plant (120 ton/hr) 1 4
Asphalt Kittle 1 1
Power Broom 1 1 ** To be Mobilized using the Dump Trucks
Aspalt Paver 1 1
Wagon Drill 2 2
Aggregate Spreader 1 1
Stationary Asphalt Heater 1 1
Pick up 4 WD 30
Total Equipment Mobilization Cost 2,345,634.56 Station wagon 4 WD 4
Estimated Mobilization for Engineer's Facilities 500,000.00 Truck with trailer 20t. 2
Total Mobilization Cost 2,845,634.56 Dump Truck 9m3 5
Water Truck 13,000 Lit. 15
Sub Total 56
Cost per Trip 2,289.60
Estimated Total Demobilization Cost 2,134,225.92 Mobilization Cost 128,217.60