Professional Documents
Culture Documents
Geotechnical Applications-Univ Birmingham-CEM3D1
Geotechnical Applications-Univ Birmingham-CEM3D1
Geotechnical Applications-Univ Birmingham-CEM3D1
SCHOOL OF ENGINEERING
Bored Piles
1. No casing is needed in stiff clay. In sands and silts casing shoe should be kept
below the bottom of the hole. Excavating below the casing show may cause over-
break and water-filled cavities outside the casing. On removing the casing these
bodies of water are released into the wet concrete causing washing out of cement
paste (See Figure 5.1d).
2. Inflow of water through the base of the hole may loosen the ground and reduce
shaft resistance. Use drilling mud to overcome this.
3. Boulders are difficult to remove with small diameter piling equipment. Substitute
a few large diameter piles with larger equipment capable of dealing with boulders.
4. The base of the bore must be thoroughly cleaned out before concreting. Under-
reams should be inspected to see that material has not fallen from the sides.
5. Concreting through water in the base of a bore causes segregation of the concrete.
If water is more than a few centimetres deep, it must be removed. A tremie pipe
should be used in wet bores.
6. Bored piles should be concreted immediately after excavation to avoid softening
of the soil.
7. Concrete should be high slump and self-compacting.
8. Very few cases of deterioration of bored pile concrete have been recorded.
Increase the cover to the reinforcement in very aggressive conditions.
9. Concrete should not be allowed to impact on the sides of the holes or on the
reinforcement cage (See Figure 5.1a) in order to avoid segregation, and concreting
should be continued once started. Delays between lifts cause weak zones.
10. Casing withdrawal may lift the concrete and leave gaps in the shaft, dented or
dirty casing should not be used (See Figure 5.1b).
11. Allow for the slump of the concrete when pulling out the casing. The concrete
level should be generously topped up during casing removal, otherwise the pile
1. Cracking caused by bad curing or handling stresses may lead to later corrosion of
reinforcement. Transverse cracks less than about 0.3mm wide are usually
acceptable except in very aggressive conditions.
2. The ends of sectional piles should be square within 1 in 300. Out-of-square ends
may cause eccentric driving forces.
1. Pile sections should be properly aligned when welding, and welds should be
strong enough to resist driving forces.
2. Buckling is seldom critical, even in very soft soils. Light sections may bend
during handling.
Pile driving
1. Drive to set, not to length, otherwise severe head damage may result.
2. Piles can be damaged by heavy driving intended to penetrate hard layers. Check
by driving a test pile.
3. Use a hammer of mass at least equal to the mass of the pile, and applying low
drops. This causes less head damage than a light hammer with high drops. With a
heavy hammer more of the driving energy is effective in moving the pile.
4. Boulders may deflect and buckle or break piles.
5. In difficult cases predrilling may be used, but this reduces the side friction on the
pile shaft.
6. Pile driving may cause a local increase in pore water pressure. If driving stops for
some reason, rapid dissipation of pore pressure may increase the side resistance so
much that the pile cannot be moved when driving restarts.
7. Driving low-displacement piles in soft carbonate rocks e.g. chalk can create a skin
of liquefied material around the pile that reduces the side friction. Piles may have
to be lengthened to achieve the required set.
8. Pile driving in saturated silts may cause negative pore water pressure and a ‘false’
set. It may be necessary to drive piles at intervals of a few days with rests in
between.
1. Heave may lift piles already driven, leading to loss of bearing capacity or tension
failure. Heave is worst in clay soils, and it may be reduced by using low-
displacement piles, by pre-boring, or by substituting bored piles. Little heave
occurs in sands and gravels because the volume of the pile is accommodated by
compression. Heave extends for some distance around a driven pile, and it may
damage sensitive structures or buried services.
2. Lateral soil movement can damage retaining walls and river banks. Raised pore
water pressure may re-activate landslips.
Noise from pile driving – Pile driving is noisy. Noise shields can be used.
Vibration – Vibration is difficult to measure, and its effect on structures are very hard
to predict. Surveying of existing buildings should be carried out before driving begins.
BUCE
SCHOOL OF ENGINEERING
PILE TESTING
LOAD TESTS – Essentially tests of the soil and a check on the pile design as well as
workmanship
(i) Maintain Load Test (MLT). The load is increased in stages to some multiple
of the working load. The time-settlement curve is recorded for each stage of
loading and unloading. The load at each stage is held until the rate of
settlement has decreased to less than 0.25mm/hour. The test is suitable for
checking pile head deflection. It can be used for calculating Qult if CRPT is
carried out at the end of test until failure.
(ii) Constant Rate of Penetration Test (CRPT). The load is progressively increased
to cause the pile to penetrate the soil at a constant rate until failure occurs.
Penetration rates are 0.75mm/min for piles in clay and 1.55mm/min for piles
in granular soils. It is essentially a test to determine Qult and hence applies
only to preliminary test piles. This test is not suitable for checking the
TEST PILES
(i) Trial or preliminary piles: one or more piles specially constructed for testing
before the contract to check: a. Design assumptions b. Ability of the contractor
to construct.
(ii) Contract piles: about 1% of total number, chosen at random. Cyclic loading to
1.25 or 1.50Pw.
In most pile test, failure is usually defined as deflection up to 10% pile base diameter.
Hence, the ultimate load may not be easily found. The Chin’s method is a comon
empirical method used to obtain a value of the ultimate load Qult and hence find a
value of the working load Pw.
Many curves such as hyperbolic curve and exponential curve exhibit the above
aw
properties but for ease of application, the hyperbolic curve P = is used where a
b+w
and b are positive constants. Applying the conditions listed above, we have:
aw 0
(a) When the deflection w is zero, the load P = = = 0 and the slope of the
b+w b
dP a aw a
load-displacement curve i.e. = − = is positive if a/b is
dw b + w (b + w) 2
b
positive.
aw2
(b) When the deflection increases i.e. w > 0, for w2 > w1 > 0 P2 = and
b + w2
dP dP a aw2 a aw1
− = − − +
dw w= w2 dw w= w1 b + w2 (b + w2 ) 2
b + w1 (b + w1 )2
a (w1 − w2 ) aw (b + w2 ) − aw2 (b + w1 )
2 2
= + 1
(b + w2 )(b + w1 ) (b + w1 )2 (b + w2 )2
a (w1 − w2 )(b + w2 )(b + w1 ) + aw1 (b + w2 ) − aw2 (b + w1 )
2 2
=
(b + w1 )2 (b + w2 )2
Qult w
Therefore the load-deflection equation is P = . Re-arranging, we have
b+w
w w w b
P(b + w) = Qult w or w = Qult − b or = + which is in the form of
P P Qult Qult
y=mx+c. So if the settlement w (or ∆ as given in the figure) at each loading stage P is
divided by the load P at that state and plotted against w/P (or ∆/P as given in the
figure). The inverse slope of the lines gives the ultimate load. For an end-bearing pile,
the plot is a single line. A combined friction and end-bearing pile produces two
straight lines which intersect. The ultimate load can then be divided by a factor of
safety to give a value for the working load.
SCHOOL OF ENGINEERING
4. Piles in Clay
Base capacity
The long term end-bearing capacity of a pile in clay will be considerably larger than
the undrained capacity. However, the settlement required to mobilise the drained
capacity would be far too large to be tolerated by most structures. In addition, the pile
must have sufficient immediate load-carrying capacity to prevent short term failure.
For these reasons, it is customary to calculate the base capacity of piles in clay in
terms of the undrained shear strength of the clay cu and a bearing factor Nc:
qb = cu N c (4.1)
Questions:
1. When is undrained capacity the appropriate strength parameter to be used?
2. How is the undrained capacity parameter obtained?
3. Consider how eqn (4.1) can be derived from the equation for ultimate bearing
capacity of circular footing qult = 0.3γBN γ + 1.3cN c + σ vo (N q − 1) (4.3)
4. Consider how Nc=9 can be found from the Bearing capacity chart of clay
(Skempton 1951).
5. If the undrained shear strength is obtained from field test, how should the value be
chosen the scattered values obtained according to current common British
practice? According to Eurocode 7? Find a distribution of undrained shear
strength with depth from the ground investigation notes.
Skin friction
Most piles in clay develop a high proportion of their overall capacity along the shaft.
Whereas the ratio of end-bearing to skin friction may be typically 50 to 100 for piles
in sand, the corresponding range is 10 to 20 for piles in clay. Therefore, considerably
The value of α depends on the type of clay, the method of installation and the pile
material. The appropriate value of α is obtained from results of load tests. Values of α
can range from around 0.3 to around 1.0. (Question: Can the value of α be bigger than
unity?)
Driven piles:
1. The clay around the pile is displaced both vertically and horizontally. Upward
displacement results in heaving of the ground and can cause reduction in the
bearing capacity of adjacent piles.
2. The clay in the disturbed zone around the pile is completely remoulded during
driving. (Question: What kind of soil properties do remoulded clay have in terms
of c’ and φ’?)
3. The excess pore water pressures set up by the driving stresses dissipates within a
few months as the disturbed zone is relatively narrow. Thus the skin friction at the
end of the dissipation is normally appropriate in design.
The adhesion factor α for driven piles (See Figure 4.1) is generally correlated to
cu
i.e. the ratio of the undrained shear strength to the existing vertical effective
σ v'
overburden pressure (Randolph and Wroth, 1982).
value), π/4 is shape factor for a rigid circular base and f(z) is a depth factor which
is roughly 0.85. Using the assumption that the undrained Young’s modulus varies
linearly with the undrained shear strength we have (at the base of the pile):
Eu = Mcub (4.7) where M is a constant. Using eqn (4.2), we have qbult = 9cub
Mqbult
(4.8), therefore Eu = (4.9). With νu=0.5 assumed for saturated undrained
9
clay having no volumetric change during deformation, equation (4.6) becomes:
9q b D π
wb =
Mqbult 4
( ) w
1 − 0.5 2 0.85 (4.10a) or b =
4.5qb
D Mqbult
(4.10b). Taking value of M
wb q
between 250 to 400 we have = 0.01 to 0.02 b (4.11).
D q bult
Design Steps:
1. Calculate Qs and Qb from assumed d, D and L values. Using eqn (4.5b)
Qs = ∑ αcu ∆As and eqn (4.2) Qb = 9cub Ab calculate the shaft and end bearing
resistance.
wb q
3. Calculate base settlement wb from eqn (4.11) above: = 0.01 to 0.02 b
D q bult
d
4. Assume that w=wb. If wb ≥ , design may be satisfactory subject to allowable
200
d
settlement and cost. If wb < , go back to step (1) and adjust dimensions as the
200
settlement is smaller than expected. (Question: How should the dimensions be
adjusted?)
5. Estimate the compression of concrete
pile shaft. The mean concrete stress is
P
σ = where P is the mean load in
A
the concrete (see Figure 4.5) and A
the cross-sectional area. Therefore
Qs
Pw −
σ = 2 .
πd 2
4
wconc σ
Using the uniaxial equation for strain we have = with the Young’s
L E conc
modulus of concrete Econc being approximately 20GPa.
6. The settlement of the pile head is therefore approximately equal to wb+wconc.
Questions:
• How accurately can we determine the load capacity of a pile?
• Which of the following offer the most uncertainty in the calculation of pile
behaviour: 1. Loading 2. Soil properties 3. Calculation method 4. Workmanship?
BUCE
End bearing
The ultimate bearing capacity at base level is expressed
as: qb' = σ vb' N q (3.1)
Side Friction
The average value of skin friction over the length of pile embedded in sand can be
expressed as τ s = σ h' tan δ = Kσ v' tan δ (3.3)
where
δ is the angle of friction between pile and sand with δ less than or equal to φ’ and is
usually taken as 0.75φ’ for concrete and 20o for steel
K is the earth pressure coefficient
σ’v is the average effective overburden pressure along the embedded length
σ’h is the horizontal effective stress acting around the pile shaft after installation and
depends on the type of pile and how it is installed.
Suggested K values
Pile Type Loose sand Dense sand
Large-displacement driven piles 1.0 2.0
Low-displacement driven piles 0.5 1.0
Bored Piles Ko Ko
The total shaft resistance can be calculated by multiplying the skin friction by the
perimeter area of the pile: Qs = τ s As (3.4). If there is a change in the property of sand
along the length of the pile, a summation Qs = ∑ τ s ∆As (3.5) or an integral can be
The equations above indicate that both the skin friction and base capacity increase
with depth. This is not the case and there are limiting values for both. Maximum
values for unit skin friction and base capacity of 110kPa and 1,100kPa have been
quoted. (Question: Why is there limiting values for unit skin friction and base
capacity? How does progressive failure happen)
BUCE
Qb = qb Ab (2.3)
where qb is the ultimate bearing capacity at base level and Ab is the base area.
(Question: If the pile is bearing close to the interface of two different soil layers,
should the property of the upper or the lower layer be used for its calculation?)
The relative magnitude of shaft and base capacities will depend on the geometry of
the pile and soil profile. Hence piles are sometimes referred to as ‘end bearing’ piles
or ‘friction or floating’ piles. In cohesive soils, the shaft capacity is quite high while
in frictionless soils the base capacity is usually more important. (Question: Why do
‘floating piles’ seem to float?)
For end bearing capacity is larger than shaft friction, the stiffness is small at working
load (See Figure 2.5).
Factor of safety
The working load for all pile types is the sum of the base resistance and the shaft
friction divided by a suitable factor of safety. A factor of 2.5 is usually used.
Qs + Qb
Pw = (2.4)
2.5
When a pile test is carried out, the factor of safety is sometimes reduced to two i.e.
Qs + Qb
Pw = (2.5)
2
Qb = 9Qs (2.7d)
For Qb > 9Qs , eqn (2.6) should be used. And vice versa, eqn (2.4) should be used.
Question: What is the purpose of the factor of safety? How is the value of the factor
of safety chosen?
BUCE
Advantages
(a) Pile can be seen complete before driving
(b) Unaffected by groundwater
(c) Resistance to chemical attack (Question: why not?)
(d) High bending strength
Disadvantages
(a) Length adjustment on site is difficult
(b) Cannot penetrate obstructions e.g. hard layers, bouldery soil
(c) Noise and vibration during driving
(d) Heave caused by soil displacement may life piles already driven or cause
deflection of other piles or structures
(e) Toe enlargement impossible
(f) Cannot be driven with low headroom
3. LOW-DISPLACEMENT PILES
Advantages
(a) Much reduced ground heave
(b) Ease of penetrating thin hard layers
(c) High bending strength
(d) Extensions can be easily welded on
4. BORED PILES
Advantages
(a) Length adjustment easy on site
(b) Opportunity to inspect and test the excavated soil or to carry out in-situ
tests in the borehole (Question: Is it safe to go down and inspect?)
(c) Large high-capacity piles can be constructed
(d) Ground obstructions can be penetrated – at a cost
(e) Noise and vibration are much less than with driven piles
(f) No ground heave
(g) Construction possible in low headroom
(h) Enlarged bases can be formed with large-diameter types
Disadvantages
(a) Construction is difficult in water-bearing ground. (Question: why?)
(b) Serious construction faults can be caused when casing is withdrawn
(c) Enlarged bases cannot be formed in cohesionless soils (Question: why?)
(d) In-situ concrete may be liable to chemical attack
(e) Loss of ground and settlement damage to adjacent structures can occur
when a group of piles is formed
BUCE
SCHOOL OF ENGINEERING
PILE GROUPS
(a) Sand: Qg is considered in relation to n Qult. Qg > n Qult for a driven pile group in
loose to medium dense sand due to compaction and < n Qult for very dense sand due
to dilation.
(b) Clays: A pile group could fail as a series of failures of single piles or as an overall
block failure of the group and the surrounding soil. Both Qg values should be
checked for the lowest:
B l
Nc = 5(1+0.2 )f where f = 1 + ≤ 1.5 .
L 12 B
Example
Ab = B2 = 4.42 = 19.36 m2
n n
wk = w Σ (p j α j ) + w Pk or w k = w Σ α kj p j if α kk = 1
j=1 j=1
j≠ k
The first term in the first equation represents the influence of other piles on
pile k and the second term represents the settlement of pile k alone. These two
contributions can be combined in the form of the second equation.
w = settlement of single pile under unit load
Pj = load on pile j
or (b) Equal settlement of all piles; solve for wG and Pk (= rigid cap)
wB = w PB + w [ PA (0.42+0.42+0.35+0.35) + PB (0.42)]
∴ 0.42 PA - 0.65 PB = 0
4 PA + 2 PB = 3000
∴ PA = 566.9 kN ; PB = 366.3 kN
PA = PB = 3000/6 = 500 kN