External Works (Road and Associated Service Document No: AHAR/MST/SFZ/MEP 02 Rev 0
Networks) Date: 22 July 2018
The detail responsibilities of above mentioned personnel’s are mentioned in the approved
Project Quality Plan.
The Criteria for fixing the subcontractor will be mainly as per the requirement of Project. The
Sub Contractors will be analysed according to their previous work experience of the similar
nature, their Company profile, their ability to execute the work as per the project specification
and up to the satisfaction of the Client. More weightage will be given to the Subcontractors
who are registered with the SME.
9.0 Procedure
9.1 Receiving materials:
While receiving the materials, the following is to be ensured:
The material received is as per approved MAS. (Design conforming to BS EN 1295-
1:1998.)
The quantities are correct as per the purchase order and delivery note.
9.3 Pre-Installation:
9.3.1 Trench Preparation and Bedding
Centerline marking and excavation dimensions shall be done as per the Approved
drawing including clearance from the face of any structure and within necessary working
space.
Adequate signage shall be placed near the excavation.
Trench inspection shall be carried out as Per approved Excavation MST&ITP
The trench bottom shall be carefully examined for the presence of hard objects, rocky
projections or large tree roots and shall be trimmed to an even finish.
Depth of bedding shall be as per approved drawing.
It shall be ensured that the Bedding material is free from large stones and granular
material or crushed stone or sand(to be satisfied standard specification requirements)
Side fill will be done minimum 100mm or pipe diameter whichever is greater.
Initial filling material shall be granular, Crushed gravel or sand, thickness shall be as per
drawing.
Refer to the below sketch in page 7 of this method statement for bedding details only.
1-Granular material well compacted under and around the pipe or crushed aggregate 3 to 8mm.
2-Material selected from trench excavation well compacted to 95% of MDD.
3-Mass concrete.
Internal Inspection NO
Rectify
Cleared?
YES
Raise IR for Engineer’s inspection
NO
YES Rectify
Clearance to Civil for upper bedding
and Backfilling
FIG-2
9.4.2 Welding
No.
S.No. Description Elec. Power Requirement per No.
Required
A Extrusion welding AMP Watts Phase
1 Hand Held extruder 17 3935 Single 2
2 Hot Air Gun 9 2000 Single 2
3 Jigsaw-2.6A, 570W 2.7 550 Single 2
4 Reciprocating Saw 5.0A 1010 Single 1
5 Drilling Machine Single 1
6 Angle grinder 3.8 800 Single 1
The Weholite pipes to be joined by welding shall be placed at a distance of 1mtr apart
measured from pipe edge faces.
Fig -4
Fig -5
9.5 Testing
a) Pre- Testing
Inspection shall be carried out as per the sequence referred in Inspection Test plan for
External Storm water system Installation and Testing –PE WEHOLITE Pipe during
construction & before backfilling.
b) Air Testing
Air testing shall be done as per clause no 8.2.3.9 of OMAN standard specification volume no
3.
As soon as practicable after a length of pipe has been completed, it shall be subjected to an
air test to BS EN 1610
Length of pipe shall be plugged and sealed and air pumped into the pipe by approved
method.
We shall allow 5 minutes for stabilization of air temperature and adjust pressure to 100 mm,
the section will not be considered satisfactory if the air air pressure fails from 100 mm to 75
mm head of water in 5 minutes or less
Failure to pass the air test is not conclusive and if no leakage can be traced by externally
application of soapy water to all sealing areas.
9.6 Backfilling
After inspection clearance of Air test, approved bedding and filling material will be filled
(Surrounding) as per bedding detail at page 7 of this method statement.
On completion of the above, the upper bedding material will be water sprayed and
manually compacted. Mechanical compactors will not be used at this stage.
Approved backfilling material shall then be filled on top of upper bedding.
The backfilled material shall then be water sprayed and compacted using plate
compactors or equivalent.
Plate compactor can be used only minimum 450mm above the crown level of the pipe.
12.0 Appendices:
Appendix 1 - Inspection and Testing Plan
Appendix 2 - Checklist
Appendix 3 - Risk Assessment
Appendix 4 - Drawings