Ben Rinnes Activity Risk Assessment Worksheet: Activity ARA 224 Date: 22/12/07 Assessment Team: S Patterson, J Muniz
Ben Rinnes Activity Risk Assessment Worksheet: Activity ARA 224 Date: 22/12/07 Assessment Team: S Patterson, J Muniz
Probability
Probability
No. Step Potential Incident. might be for Recovery Party in place
harmed
Severity
Severity
Risk Risk
1 Remove/Install Main Falling Hatch, Falling tools Plant L L L Safety Harnesses to be worn when YES L L L
Hatch Cover on Skid Flow lines working around open hatch. Erect
deck People barriers. Use of radios for
communication Between D/Floor &
Check lifting equipment and
Certification. Use specialist-lifting
device. No personnel working in
well bay below when installing
hatch. Skid deck
2 Install High Pressure Failure of lifting equipment Plant L L L Rotary Barrier to be installed. YES L L L
Riser and Riser Valves Master Bushings removed Flow lines Production Op in attendance at well
from Rotary Table People bay. Heavy lift Tannoy/Permit
Flow lines Depressurised, only if risk
of impact, liaise with C/room.
Wellhead Barrier off around Well.
Check lifting equipment before use
(DP to Riser flange x/over). Check
certification.
3 Remove/Install 13 5/8” Failure of Equipment Plant L L L Ensure plates installed over skid YES L L L
BOP’s Falling Tools. People deck. ‘R’ clips to be installed on
Failure of Airlines hoses Ensure Permit endorsed For
work period. Barrier off BOP Deck.
Make PA announcement concerning
heavy lift operations