Professional Documents
Culture Documents
Excerpt Mihirs Handbook of Chemical Process Engineering
Excerpt Mihirs Handbook of Chemical Process Engineering
PROCESS ENGINEERING
BY MIHIR PATEL
SAMPLE DOCUMENT
Copyright @ 2018. The Handbook of Chemical Process Engineering. All rights reserved.
No part of this publication may be reproduced or distributed in any form or by any means,
electronic, mechanical, photocopying, recording, or otherwise or stored in a database or retrieval
system without prior written permission of author. The program listings may be entered, stored and
executed in a computer system, but they may not be reproduced for publication.
ISBN # 978-93-5279-698-4
1 | Page
PREFACE - ABOUT THE AUTHOR
Mihir M. Patel
www.chemicalprocessengineering.com
The author, Mr. Mihir M. Patel, is a Chemical Engineer with a Master’s degree from USA in 1987.
He is a practicing chemical engineer with many years of experience in process and process safety
engineering. Additionally, he is a Project Management Professional (PMP ®) from PMI, USA, which
gives him a unique overall project perspective in addition to process perspective.
He has worked all around the globe, in small as well as mega greenfield and brownfield projects.
The projects have been oil & gas, petrochemicals, polymerization as well as chemical plants. The
processes have been continuous as well as batch.
He has worked in premium companies in design as well as in operations field.
He wrote this book with a vision to aid all level of chemical engineers to carry out chemical
process engineering in a very practical, efficient and simplified way. It took him nearly 2.5
years to perfect this handbook and launched in the beginning of 2018. Which is a composite
compilation of all the key aspects of chemical engineering. Within less than 2 years, it has
become popular globally, with readers being immensely benefited by it.
2 | Page
DEDICATED TO
Firstly: To My Heavenly Father, Almighty God, who gave me the idea, wisdom and perseverance to
take-up and complete this book.
Secondly: To my dear wife Niyati, who has patiently stood by me and encouraged me during the two
and half years it took to complete this book, even when I worked on weekends / holidays, as well as
encouraged me in success of the book thereafter, and who has always been with me at all times,
good and bad.
Setting up of a Greenfield Chemical Plant is essentially a complex process and a chemical engineer
(quite often called a process engineer) has to wear different hats while visualizing and implementing
any chemical plant from “Concept to Commissioning”, in a time bound manner. Whereas theoretical
understanding of concepts is very important, it is equally critical to have an easy access to the vast
pool of Chemical Engineering knowledge in the form of handy design tools, documents and formats
which help the process engineer to overcome the challenges of time and cost constraints of a
project. “Mihir’s Handbook of Chemical Process Engineering” endeavors to do just that. The author
with his vast experience as a “Process” as well as a “Project” Engineer in the chemical industry, has
brilliantly compiled the various practical aspects of process design and project management in this
Handbook.
The Handbook does excellent justice to the most common Unit Operations encountered in the
Chemical and Petroleum Industry. Besides covering the important theoretical aspects from a more
practical viewpoint in various chapters in Volumes I & II, one must note that the Volume III,
Chapters 40 to 44 place a very important tool in the hands of the Process / Project engineer by
vividly covering the important Process Engineering Calculation Templates, Checklists, Datasheets,
Technical Bid Evaluation Formats and Typical P&IDs.
Overall, this is an excellent reference book for Process / Project Engineers of all ages involved in
Chemical Process Engineering. I wish Mihir all the success for the launch of this handbook and
complement him for his tireless efforts in compiling and publishing such a useful reference book for
chemical process engineers.
Manoj Shah
Presently: Consultant Chemical Plants and Technologies.
Previously: Retired as Executive Director (Technical) at IBI Chematur Engineering & Consultancy
Ltd., Mumbai, India
Background of Manoj Shah: He is a Chemical Engineer with a Master’s degree in Chemical Engineering
from USA. He has 40+ years of experience in the Chemical industry, having carried out engineering
on many projects, greenfield as well as brownfield in the international market.
3 | Page
CUSTOMER REVIEWS
This kind of book I was looking from many years Saish Todankar
(India)
One stop solution for all process engineers Syed Fayaz Ahmed
(Saudi Arabia)
It’s one of the best book I have ever seen Ketul Shah
(India)
4 | Page
SAMPLE FROM THE BOOK
Table of Contents
SAMPLE DOCUMENT ........................................................................................................................................ 1
PREFACE - ABOUT THE AUTHOR..................................................................................................................... 2
DEDICATED TO ................................................................................................................................................. 3
FOREWORD by Manoj Shah ............................................................................................................................... 3
CUSTOMER REVIEWS ...................................................................................................................................... 4
SAMPLE FROM THE BOOK ............................................................................................................................... 5
CHAPTER 3: PUMPS ......................................................................................................................................... 7
Important Details on Pump Selection – Types, Usages, Series vs Parallel Operation.......................................... 7
3.5 Overall Pump Options: ............................................................................................................................ 7
3.6.8 Stream Specific Gravity (Multiple Fluids)............................................................................................. 12
3.6.18 Parallel vs. Series Centrifugal Pump Operation ................................................................................. 14
CHAPTER 6: HEAT EXCHANGERS .................................................................................................................. 22
Selection of Shell & Tube Heat Exchangers – TEMA Types, Comparisons & Usage Applications ..................... 22
6.4.1 TEMA Types...................................................................................................................................... 22
CHAPTER 7: TANKS ........................................................................................................................................ 29
Methodology of Pressure Settings on Storage Tanks & Tank PDS Preparation ................................................ 29
Case Scenario: .......................................................................................................................................... 29
7.4.13 Process Datasheet Preparation: ....................................................................................................... 33
CHAPTER 16: UTILITIES SYSTEM DESIGN ..................................................................................................... 35
How to Design Utilities – Liquid Fuels, Compressed Air/Dryers & Boilers ......................................................... 35
16.2.2 Liquid Fuel ....................................................................................................................................... 35
16.3 Compressed Air system ...................................................................................................................... 39
Dryers ........................................................................................................................................................ 42
16.5.9 Specification of Boilers ..................................................................................................................... 47
CHAPTER 24: SPECIAL PROCESS ITEMS ...................................................................................................... 50
How to Select & Specify Special Process Items with Important Details on Flame Arresters, Spray Nozzles,
Liquid Filtration, Strainers............................................................................................................................... 50
24.1 Flame Arresters: .................................................................................................................................... 50
24.2 Spray nozzles: .................................................................................................................................... 54
24.7 Liquid Filtration: .................................................................................................................................. 52
24.9.2 Basket type strainers: ....................................................................................................................... 54
24.9.4 Pressure Drop Calculation ................................................................................................................ 56
CHAPTER 26: TYPES OF PROJECTS .............................................................................................................. 57
How to Select Project Types / Stages with Examples for a Process Engineer ................................................... 57
26.1 PROJECT STAGES:........................................................................................................................... 57
CHAPTER 29:................................................................................................................................................... 60
PROCESS DESIGN DOCUMENTATION ........................................................................................................... 60
5 | Page
How to Prepare & Specify Process Design Documents. Details on Equipment List, Block Flow Diagram
(BFD), Process Flow Diagram (PFD) and Utility Flow Diagram (UFD), Process Safe Guarding Flow Diagram
(PSFD).......................................................................................................................................................... 60
29.5 TITLE OF DOCUMENT: Equipment List .............................................................................................. 60
29.6 TITLE OF DOCUMENT: BLOCK FLOW DIAGRAM (BFD).................................................................... 62
29.7 TITLE OF DOCUMENT: PROCESS FLOW DIAGRAMS (PFD) and UTILITY FLOW DIAGRAM (UFD) .. 63
29.12 TITLE OF DOCUMENT: PROCESS SAFEGUARDING FLOW DIAGRAMS (PSFD) ............................ 66
CHAPTER 30: TECHNICAL BID VALUATIONS ................................................................................................. 69
How to Prepare Technical Bid Evaluation of Screw Compressor ...................................................................... 69
30.7 Technical Evaluation Guidelines for Screw Compressors ..................................................................... 69
Handbook Details ....................................................................................................................................... 74
6 | Page
CHAPTER 3: PUMPS
7 | Page
Pump Capacity, gpm
8 | Page
The major types of pumps available are listed in the following table.
Centrifugal: Reciprocating:
4. Turbine
Special: Rotary:
1. Jet 1. Gear
4. Inertia 4. Vane
9 | Page
Comparison between centrifugal and positive displacement type is provided
below in table 3.2.
10 | P a g e
Many applications can be handled by a horizontal or vertical centrifugal
pump. The following should be considered.
A selection table showing the physical range of head and capacity suitable for
the various types of pump is provided below.
Minimum Maximum
Low Capacity
General Use
Reciprocating Power 4.5 (20) 227 (1,000) Over 305 (1,000)
11 | P a g e
2 – Stage 2.7 (10) 1820 (8,000) Over 210 (700)
High Capacity
12 | P a g e
gravity of the heaviest liquid that the pump is expected to handle.
What this diagram implies is that e.g. if same centrifugal pump of say 20 mlc
head is used to pump water (sp. gr of 1.0) and also mercury (sp. gr of 13.6),
then ignoring effect of viscosity for this example and considering atmospheric
suction, the discharge pressure of water will be 2 barg while of mercury will be
27.2 barg. Thus, in case of pumping mercury, if pump has been procured
originally only for water, then either motor will trip due to overload or pump
casing may bust if it is of lower design pressure.
13 | P a g e
3.6.18 Parallel vs. Series Centrifugal Pump Operation
Pumps with different pump curves should generally not operate in parallel.
When this cannot be avoided, the pump with the lower shut-off head must be
protected against operating at flows below the allowable minimum flow.
14 | P a g e
Fig 3.30: Two identical centrifugal pumps in parallel operation
15 | P a g e
In order to meet a requirement for flow capacity higher than normal on an
infrequent basis, it may be preferable to have the primary pump and its spare
operate in parallel, instead of designing each pump for the full above-normal
flow rate.
1. The required service capacity may exceed the utility energy supply
available for a single driver or driver type e.g. many companies have low
voltage (LV) to high voltage (HV) power supply cutoff at 160 KW motor
size. Thus multiple parallel pumps may be installed to make each motor
LV.
2. Desire for operating flexibility in power supply or type could result in
multiple pumps with different driver types e.g. one motor driven with
other steam turbine driven.
3. The use of multiple pumps may allow investment savings. For example,
three 50%- pumps may require lower a total investment than two pumps
sized for 100% for the service capacity. (This would be possible but
unusual.)
17 | P a g e
operation at reduced conditions during maintenance, inspection or repair of
either pump.
A problem that can occur with pumps in parallel is shown in fig 3.31. Two
pumps are never exactly alike. If two pumps are installed in parallel, one
pump may take more than half of the total flow and the other pump less than
half. The pump with the lower flow rate may be operating below its minimum
acceptable flow rate. As the fig shows, the head produced by the two pumps
will be identical because they are connected to the same process. If the head
produced by pump B is lower than head produced by pump A, the situation
shown in the fig will occur. Pump B will decrease its flow rate until it can
produce the same head as pump A.
This situation is most dangerous when one pump is driven by a motor and the
other pump by a turbine. It is impossible to set the two speeds exactly equal,
and the difference in speed will cause a difference in head produced.
If two pumps are nominally identical and both driven by motors, the two head
curves can be assumed to be within 3% of each other. If so, one can make the
worst assumption, that is, the head of pump B is 3% lower than the head of
pump A. Then, using the system operating conditions, plot the flow through
both pumps. Make sure that the lowest flow rate is not below the pump
minimum allowable flow rate.
18 | P a g e
Fig 3.31: Pumps in parallel
Note that NPSH is generally a key design consideration for the first pump only
since the first pump acts as a booster for the 2nd pump in series.
Fig 3.32: Performance curve for two dissimilar centrifugal pumps in series
19 | P a g e
Pumps may be designed to operate in series arrangement for any of the
following reasons:
For series operation, the head-capacity curve is obtained by adding the two
heads at any given capacity.
20 | P a g e
It is important that adequate suction pressure be available to all pumps,
especially to the first pump in series operation. If the first pump in a series
system is deprived of adequate NPSH, its capacity will be reduced until NPSHR
equals NPSHA. Then the capacity through all the pumps in series will be
reduced, resulting in a significant overall flow loss.
The design pressure for piping and equipment, including the pumps
themselves, should be carefully examined in a series-flow operation especially
if the pumping system can be deadheaded.
The engineer should be aware that reliability is reduced for the series-flow
service since operation is now dependent on not just one pump but each
pump in the series.
Two pumps in series will generate much more discharge pressure than one
pump alone. In some cases, this pressure might be greater than the design
pressure of the downstream piping or other equipment. This condition must
be checked before proceeding with an installation of two or more pumps in
series. It is important to check the design pressure at the condition called
“pump shutoff pressure.” Shutoff pressure is obtained when the downstream
control valve is closed and the pumps operate at zero capacity and maximum
head. The shutoff pressure is equal to the pressure in the suction vessel plus
the shutoff delta P of both pumps combined. See Fig 3.34 and the example
table beneath it. For this example, the normal operating discharge pressure is
satisfactory because it is less than the design pressure. However, at shutoff,
the discharge pressure downstream of the second pump would be greater than
the equipment design pressure. This situation is not allowed. One remedy is
to install a safety valve at the discharge of the second pump as shown.
21 | P a g e
CHAPTER 6: HEAT EXCHANGERS
Shown in Fig 6.17 are the TEMA standard designates which are five types of
channels (A, B, C or N, and D), seven types of shells (E, F, G, H, J, K and X),
and eight rear end head types (L, M, N, P, S, T, U and W). The rear end head
type determines whether or not the tube bundle is removable from the shell.
22 | P a g e
23 | P a g e
(i) Straight Tube, Fixed tubesheet, Type BEM, AEM, NEN, Etc.
This TEMA type is the simplest design and is constructed without packed or
gasketed joints on the shell side. The tubesheet is welded to the shell and
the heads are bolted to the tubesheet. On the NEN heat exchanger, the shell
and the head is welded to the tubesheet. Typically, a cover plate design is
provided to facilitate tube cleaning. This TEMA category, especially the NEN,
is the lowest cost TEMA design per square foot of heat transfer surface.
Advantages
Applications
This design allows for the removal, inspection and cleaning of the shell
circuit and shell interior. Special floating tubesheet prevents intermixing of
fluids. In most cases, straight tube design is more economical than U-tube
designs.
Advantages
24 | P a g e
• The tube bundle can be repaired or replaced without disturbing shell
pipe
• Less costly than TEMA type BEP or BES which has internal floating head
• Maximum surface for a given shell diameter for removable bundle
design
• Tubes can be cleaned in AEW models without removing piping.
Limitations
• Fluids in both the shell and tube circuits must be nonvolatile, non-
toxic
• Tube side passes limited to single or two pass design
• All tubes are attached to two tube sheets. Tubes cannot expand
independently so that large thermal shock applications should be
avoided
• Packing materials produce limits on design pressure and temperature
Applications
(iii) Removable Bundle, Outside Packed Head, Type BEP, AEP, etc
This design allows for the easy removal, inspection and cleaning of the shell
circuit and shell interior without removing the floating head cover. Special
floating tubesheet prevents intermixing of fluids. In most cases, straight
tube removable design is more costly than U-tube designs.
Advantages
Limitations
Applications
(iv) Removable Bundle, Internal Split Ring Floating Head, Type AES, BES,
etc.
Ideal for applications requiring frequent tube bundle removal for inspection
and cleaning. Uses straight-tube design suitable for large differential
temperatures between the shell and tube fluids. More forgiving to thermal
shock than AEW or BEW designs. Suitable for cooling volatile or toxic
fluids.
Advantages
Limitations
Shell cover, split ring and floating head cover must be removed to remove
26 | P a g e
the tube bundle, results in higher maintenance cost than pull-through
More costly per square foot of surface than fixed tube sheet or U-tube
designs
Applications
Ideal for applications requiring frequent tube bundle removal for inspection
and cleaning as the floating head is bolted directly to the floating tubesheet.
This prevents having to remove the floating head in order to pull the tube
bundle.
Advantages
Limitations
For a given set of conditions, this TEMA style is the most expensive
design
Less surface per given shell and tube diameter than other removable
designs
Applications
27 | P a g e
thermal expansion capability. Because each tube can expand and contract
independently, this design is suitable for larger thermal shock applications.
While the AEM and AEW are the least expensive, U-tube bundles are still an
economical TEMA design.
Advantages
Limitations
Applications
28 | P a g e
CHAPTER 7: TANKS
Methodology of Pressure Settings on Storage
Tanks & Tank PDS Preparation
Case Scenario:
A fixed roof tank storing flammable material is having inert gas blanketing.
The outlet of nitrogen blanket is taken to a LP flare system. Below is the
sequence of pressure set point engineering (refer figure 7.37 below also):
1. First, calculate the inbreathing and outbreathing flow rates based on API
2000.
2. Next based on the flowrate of out-breathing to LP flare and the back
pressure of flare, calculate the pressure drop in the flare header, to arrive
at the pressure required at outlet of out-breathing control valve. Let us
say the friction drop in LP header is 150 mm WC (mm water column), &
pressure at valve outlet is 400 mm WCg.
3. Next step is to provide certain pressure drop across the out breathing
control valve. This pressure drop should be at least 1/3rd of friction drop
in outlet line to flare, for good controllability. In this example, we provide
50 mm WC across valve.
4. Once the inlet pressure to out breathing control valve is established, this
is the top setpoint of pressure in the tank pressure controlling range. In
example thus, top operating pressure is 450 mm WCg. At this point, the
control valve is fully open.
5. The high pressure alarm on tank needs to be set above this pressure of
point (4). Thus, high pressure alarm will be 500 mm WCg.
6. The breather valve positive pressure will be above the high pressure
alarm setpoint. Thus, this will be 550 mm WCg. Note that breather valve
will have 10% accumulation, thus, it will be fully open at 605 mm WCg.
7. The emergency vent valve setpoint will accordingly be above the breather
valve positive set pressure. The setpoint of emergency valve is also the
design pressure of tank on positive side. In our example, emergency valve
will be set at 650 mm WCg. This is also the design pressure of tank. One
can however keep design pressure little above emergency valve set point
also. Both are acceptable.
29 | P a g e
8. Now, one needs to provide an operating range for tank operation. Thus,
the outbreathing control valve will be fully closed at 350 mm WCg inlet
pressure.
9. There is a dead band normally provided between the closing of inlet
control valve and opening of outlet control valve. In our example, this will
be between 200 mm WCg and 350 mm WCg.
10. Thus, inlet control valve will start to open at 200 mm WCg. It will be fully
open at 100 mm WCg.
11. Still if pressure in tank drops, the low pressure alarm will come in at 50
mm WCg.
12. The inbreathing set point of PVRV will be set at (-22 mm WCg) and with
10% accumulation it will be full open at (-25 mm WCg).
13. Thus tank design pressure can be set at (-25 mm WCg).
30 | P a g e
The above diagram shows establishing of key pressures for an atmospheric
storage tank. The Pressure/Vacuum (PV) Valve is really two valves in one. One
is for pressure, and the other is for vacuum. The principle of operation is the
same. As the pressure on the pressure side of a PV valve rises, the force due to
pressure reduces the seating force of the pallet and it starts to leak. Leakage,
however, is relatively insignificant until the set point is reached, at which
point the flow increases dramatically and follows the flow curves given by the
manufacturer.
Beyond the set point, PV valves do not “pop” open, but slowly lift as the
overpressure (the
actual upstream pressure above the value of the setpoint) increases.
Emergency vent valves are simply large PV valves capable of venting greater
than normal venting loads caused by emergency conditions.
31 | P a g e
Fig 7.38: Typical Inert Gas Blanketed Tank with a vent to flare
2
9
32 | P a g e
7.4.13 Process Datasheet Preparation:
a) Tanks:
As a general rule, the cheapest tank will have a height: diameter ratio of 1,
although standard tank dimensions should be used wherever shop built tanks
are used as this will help reduce cost.
b) Drums / Bullets:
Normal Length / Diameter (L/D) ratio is 2:1 to 5:1 for horizontal bullets with >
3:1 often being the most economic in low-pressure applications. As pressure
increases, the economic L/D tends to increase. The higher range of L/D’s is
advantageous for horizontal separators and settlers. Also, refer to chapter 9 on
“Separators” for more information on L/D.
Minimum drum size should be 610 mm (24”) inside diameter (ID). Small drums
can
sometimes be fabricated more economically using 24 or 30” outside diameter pipe.
33 | P a g e
occur where using standard plate sizes in 610 mm (2 ft) increments are a
better fit, or in very high pressure and/or alloy services they may suggest
tighter dimensions down to 75 mm (3”) or even 25 mm (1”) increments in order to
reduce cost. The Process Engineer should adjust the elevations on the vessel
sketch he has provided, once overall dimensions are finalized, with all levels
referenced to the bottom of the shell.
34 | P a g e
CHAPTER 16: UTILITIES SYSTEM
DESIGN
How to Design Utilities – Liquid Fuels,
Compressed Air/Dryers & Boilers
16.2.2 Liquid Fuel
16.2.2.1 Introduction
Fuel oil systems are provided to ensure a constant regulated supply of oil to
burners of steam boilers and process furnaces. The system includes a fuel oil
pump and heater set which discharges oil at a constant pressure and at the
required condition of temperature and viscosity so that atomisation and
efficient combustion are possible.
Dependent on the grade of Fuel oil and process demand, the source may be
from process make within the complex, subsidized by import to meet the total
complex demand or imported via road, rail or marine off-loading facilities.
Where gas is available for fuel and there is a preference for it, Fuel oil make
may be exported via road, rail or marine off-loading facilities.
1. Carbon residue,
2. Asphaltenes,
3. Elemental ash analysis,
4. Burning profile, and
5. Distillation curve.
Refer table 16.2.3 below for fuel oil analysis for commercial grades.
36 | P a g e
Table 16.2.4: Typical characteristics of various liquid fuel types
37 | P a g e
Table 16.2.5: Comparison of properties of fuel oil amongst various countries
38 | P a g e
16.3 Compressed Air system
16.3.1 Introduction
Instrument Air systems provide a constant flow of dry compressed air at the
pertinent conditions to maintain the following services:
Process Air
Motive Air (to run air motor driven equipment e.g. air operated double
diaphragm pumps (AODD))
The capacity of the system is to be based upon the total requirements of all
connected loads, assuming all instruments operate simultaneously at
maximum air consumption. The capacity of the Instrument Air system cannot
be accurately assessed until the process control diagrams are complete and a
provisional count of the instrumentation is possible.
39 | P a g e
When accurate manufacturer’s data is not available, the following
assumptions are acceptable in calculating the Instrument Air requirements,
based on all instrument operating simultaneously:
[Nm3/h] [scfm]
Old type control valve with fully pneumatic system (includes 2.98 1.75
leakage rate of app. 0.3 Nm3/h)
Modern type control valve, electronically controlled with only the 1.50 0.88
actuator using Instrument Air (includes leakage rate of app. 0.3
Nm3/h)
On-Off Isolation Valve (includes leakage rate of app. 0.3 Nm3/h) – 5.53 3.25
only fraction of on-off valves needs to be considered operating
simultaneously for normal consumption, say 10%
Analyzer (oxygen, chromatograph) 8.50 5
Miscellaneous (compressor pulse jet, on-line / off-line washing, dry As required As required
gas seal panel, anti surge valve etc.)
Margin to be added %
Margin for air dryer regeneration losses during operation (this + 10% to 25%
depends on vendor design for air dryers)
Note 1: In case GI pipes are used for instrument air as is usual practice, then
connectors are union joints since GI pipes cannot be welded. Here, this
margin is appropriate. However, if instrument air piping is SS 304 with
flanges, then this margin can be ignored)
40 | P a g e
operations: Service Air, Furnace Decoking and maintenance workshop
demands. The largest demand for Plant Air in a production plant is for furnace
steam / air decoking (normally 2,500 NM3/hr), which may vary considerably
with the type of plant size and number of furnaces.
Note that, sometimes, decoke air has its own compressor and in such cases
the consumption would not be considered part of Plant Air.
Table 16.3.3 shows demands and operating conditions for pneumatic tools
and construction equipment. Note that these are peak values and that average
loads are often 10-35% of the peak values quoted.
41 | P a g e
Drilling Machines (7/8”-1 1/4”) 6.3 to 14 1000 to 1600 4.9 to 5.9
Dryers
The most common measurement of compressed air water content is dew point.
Dew point is the temperature where air is saturated with water and moisture
will begin to condense. In other words, it’s the point where dew begins to form.
Dew point is always stated as a temperature. Simply put, dew point is the
temperature where condensation begins.
For this reason, the phrase “pressure dew point (PDP)” is commonly used. This
term usually refers to the dew point of the compressed air at full line pressure.
Conversely the phrase “atmospheric dew point” refers to what the dew point
would be if fully depressurized to atmospheric conditions.
Fig 16.3.1 provides conversion chart of pressure to atmospheric dew point for
compressed air at various pressures. To obtain the dew point temperature
expected if the gas were expanded to a lower pressure proceed as follows:
42 | P a g e
2. Read horizontally to intersection of curve corresponding to the operating
pressure at which the gas was dried.
4. From that point read horizontally to scale on right hand side of chart to
obtain dew point temperature at the expanded lower pressure.
5. If dew point temperatures of atmospheric pressure are desired, after step
(ii) above, read vertically downward to scale at bottom of chart, which will
provide “Dew Point at Atmospheric Pressure”.
Two 100% air dryer packages are normally installed (duty and stand by).
4
1
43 | P a g e
44 | P a g e
Dryer types and details of each are provided below:
Compressed Air Dryers are mainly used in industries for various applications
in pneumatic tools, pneumatic instruments and pneumatic machines and in a
variety of production processes. The consequences of using wet air are rust
and scale deposits in steel pipes, increased resistance in flow, malfunctioning
of process control instruments, corrosion and damage to electromagnetic
valves and pneumatic system, peeling and blistering effect on spray painted
surface, etc. Thus it will affect the quality of product and lead to excessive
maintenance cost.
The sketch below shows a typical Compressed air system to remove these
damaging impurities and get Clean and Dry air. When compressed to 7
Kg/cm2g, the temperature of discharge air reaches around 140 oC. The after
cooler and Separator installed after the compressor will cool the air, and
remove @90% of moisture and oil. For instance, when the compressor takes in
100 NM3/h of ambient air at 40oC and 50% relative humidity, at 7 Kg/cm 2g,
the after cooler will condense an average of 30 liters of water in 24 hours. If
the outlet air temperature from the after cooler is 40 oC, it still contains 8000
ppm moisture. At 45oC, compressed air contains 10,500 ppm, at 50oC, 13,500
ppm moisture which is removed by Air Dryer. Therefore, lower the
temperature of air at dryer inlet, smaller would be the size of Air Drying Unit.
Internally heat reactivated type Air Dryers (fig 16.3.2) are used when one
needs compressed air of very low Dew point of (-) 60 C or (-) 80 C. In this
o o
Electrical heaters are provided in a central finned Stainless steel pipe in both
drying vessels. Heating cycle is for @ 2 hours and in this time hot purge air
increases desiccant temperature to around 100 C. At this temperature
o
regeneration is complete (due to dry air purge). Dew point achieved is @ (-)
40 C.
o
If still lower Dew point is required, air purging rate is slightly increased to 5%
for (-) 60 C and to 7.5% for (-) 80 C Dew point. A Pre-filter with automatic drain
o o
valve is provided to remove any physical moisture from compressed air before
entering Air dryer. An after filter is also provided in the Dryer outlet to arrest
any desiccant dust particles, up to 1 micron size.
Salient Features:
Longer life of operation
Requires less attention of operator
Once installed can be operated automatically
Heaters and valves are operated automatically
Internal heaters provide max efficiency resulting in lower power
requirement.
Easy maintenance
46 | P a g e
Atmospheric (-)40oC to (-)80oC
Dew Point
Operating 2 to 50 kg/ cm2g
Pressure
Table 16.3.6: Details of Internally Heat Reactivated Type Air Dryers
Required total capacity should be provided by use of at least 3 boilers, but all
boilers should be considered to be operating at partial load to supply normal
steam requirements. The above is recommended for redundancy purposes
only.
All boilers should preferably be considered to be water tube type except small
package units of low pressure which may be of fire tube construction.
Boilers should be of the outdoor installation type except that semi outdoor
type should be used in cold climates.
(ii) Boilers
The boiler specification should cover all aspects of the expected operating
cycle of the boiler. It is important that any special operating aspects such as
daily start-up or rapid load swings are covered in the specification of the
boiler, which should include the following:
47 | P a g e
Layout constraints and access problems
Any unusual site features such as earthquake or wind problems
Applicable emissions regulations
Codes and standards required for the country, plus site safety rules
Delivery and commissioning requirements
Auxiliary equipment required and types of drive
Control system and data management needs
Guarantees and warranties
Any essential bid comparison basis such as utility values, capital
charges, etc.
(Note: At the end of this section are provided guidelines for process engineer to
prepare specifications and evaluate vendor bids. Vol II Chapter 30 also
provides technical bid evaluation for boilers).
1. Steam pressure
2. Steam temperature and control range
3. Steam flow: Peak, Minimum, Load patterns
4. Feed water temperature and quality
5. Standby capacity and number of units
6. Fuels and their properties
7. Ash properties
8. Firing method preferences
9. Environmental emission limitations: sulfur dioxide (SO2), nitrogen oxides
(NOx), particulate, other compounds
10. Site space and access limitations 11. Auxiliaries
11. Operator requirements
12. Evaluation basis
48 | P a g e
(b) Steam Flow or Evaporation or Boiler Output
Maximum continuous rating (MCR) is the ability of the boiler to generate and
supply the declared amount of steam continuously and effortlessly without
any kind of shortfall or side effects (such as overheating or slagging or
overloading) on the main boiler or auxiliaries.
Peak rating is the evaporation that can be sustained by the boiler for a
specified period of, for example, 2 or 4 h in a day, to meet an increased need
in either the process or the power plant. The concept of peak rating does not
apply to HRSGs.
Peak duty is always met at a fractionally reduced efficiency, as the final exit
temperature of the gas from the unit would be more than that at an MCR
condition (as the fuel flow is higher), leading to higher stack losses.
Usually, the peak duty does not exceed 110% MCR and 4 h in a day, and it is
mostly met by making use of the design and test block margins of the boiler
and the auxiliaries without having to oversize the equipment.
49 | P a g e
CHAPTER 24: SPECIAL PROCESS
ITEMS
How to Select & Specify Special Process Items
with Important Details on Flame Arresters,
Spray Nozzles, Liquid Filtration, Strainers
Explosive mixtures can burn in various ways. The following, among other
things, can influence the combustion process: the chemical composition of the
mixture, possible pressure waves, pre-compression, the geometric shape of the
combustion chamber, and the flame propagation speed.
50 | P a g e
international standards:
51 | P a g e
52 | P a g e
Fig 24.1.2: Pre-volume deflagration
53 | P a g e
Fig 24.1.4: Stabilised burning
Spray nozzles can be categorized based on the energy input used to cause
atomization, the breakup of the fluid into drops. Spray nozzles can have one
or more outlets; a multiple outlet nozzle is known as a compound nozzle.
By creating a large droplet surface area, sprays are used to generate the high
rates of heat and mass transfer that is necessary in spray drying, liquid waste
incineration, and spray quenching applications. Spray nozzles are applied in a
wide variety of process applications with a wide range of criticality. An
example is the quenching of hot gases where high performance, high
reliability, and robustness are required. Another usage of nozzles is manual
pressure washing of equipment. Similarly, Desuperheating of superheated
steam by spraying water into the superheated steam as well as chemical
injections into main streams are other usages of spray nozzles.
Single-fluid or hydraulic spray nozzles utilize the kinetic energy of the liquid to
break it up into droplets. This most widely used type of spray nozzle is more
energy efficient at producing surface area than most other types. As the fluid
pressure increases, the flow through the nozzle increases, and the drop size
decreases. Many configurations of single fluid nozzles are used depending on
the spray characteristics desired.
The simplest single fluid nozzle is a plain orifice nozzle as shown in the fig
24.2.1. This nozzle often produces little if any atomization, but directs the
stream of liquid. If the pressure drop is high, at least 25 bars (2,500 kPa), the
material is often finely atomized, as in a diesel injector. At lower pressures,
this type of nozzle is often used for tank cleaning, either as a fixed position
compound spray nozzle or as a rotary nozzle.
5
0
55 | P a g e
Fig 24.2.1: Plain orifice spray nozzle
The shaped orifice (fig 24.2.2) uses a hemispherical shaped inlet and a ‘V’ notched
outlet to cause the flow to spread out on the axis of the ‘V’ notch. A flat fan spray
results which is useful for many spray applications, such as spray painting.
The impingement surface can be formed in a spiral (fig 24.2.4) to yield a spiral
shaped sheet approximating a full cone spray pattern or a hollow-cone spray
pattern.
51 | P a g e
The spiral design generally produces a smaller drop size than pressure swirl
type nozzle design, for a given pressure and flow rate. This design is clog
resistant due to the large free passage.
52 | P a g e
scale. Ultra filtration is a separation technique of choice because labile
streams of biopolymers (proteins, nucleic acids & carbohydrates) can be
processed economically, even on a large scale, without the use of high
temperatures, solvents, etc.
– what is the sizing requirement to carry the process flow rate and contain
the solids removed?
For coarse filtration, the basket or strainer filter type is selected, and consists
of a pressure vessel type housing with a perforated internal member that
separates the coarse solids from the process liquid. The internal element is
made of perforated metal or is a coarse wire- woven basket. Refer point 24.9
53 | P a g e
for details on basket filters.
The oldest filter type is the plate-and frame filter press. These filters rely on
the type of media used, which is generally the filter sheet or pad for depth
filtration not requiring a precoat. The chamber between the filter plates
becomes filled by the removed solids until full.
54 | P a g e
Fig 24.9.3: Simplex basket strainer
Liquid Services
For liquid services to core exchangers use permanent basket line strainers
(slant top style). The perforated basket shall be lined with mesh stainless steel
wire liner if there is any potential for the presence of particulates in a fluid
system, otherwise 40 mesh is adequate. Body materials and flange ratings will
depend on the exchanger design conditions. The volume or dimensions of the
basket shall be specified as follows:
Volume = (1) Volume of mill scale formed on the inside wall of the upstream
pipe back to the source vessel or drum.
(2) Volume allowance of mill scale, dirt, and debris expected in the source
vessel.
55 | P a g e
Table 24.9.1: Volume of mill scale (ft3)
This calculated volume shall be specified to be below the path of fluid flow.
Also, note that to obtain proper volume of the basket, the length may become
prohibitive. For these cases, increase the body size leaving the inlet and outlet
flange line sizes to obtain a more desirable basket geometry.
Vapor Services:
Use the identical procedure as for liquids, but, source vessel allowance may be
neglected. (These services are typically from tower or vessel overheads where
debris/scale settles out at the bottom of the vessel.)
56 | P a g e
CHAPTER 26: TYPES OF PROJECTS
How to Select Project Types / Stages with
Examples for a Process Engineer
26.1 PROJECT STAGES:
A process engineer should be aware of the various stages (table 26.1) that a
project can undergo.
It is not necessary for all projects to pass through each and every of below
mentioned stages.
First, it will proceed with ACCESS stage where it may undergo the study
with its own staff or employ a specialist third party to carry out the
project feasibility and confirmation of alignment with its business
strategy. It will also obtain the full picture of various licensors providing
technologies for each chemical, their pro-cons in technology, as well as
the potential buyer’s database.
Secondly, once it is satisfied with viability of project, it will go one step
further into SELECT phase (also called Pre-FEED stage), where having
selected the suitable technologies for each chemical, it will most likely,
engage a specialist third party, to refine the engineering to include not
only licensed units but also the offsites and utilities (O&U) definition
which should lead to a rough order of magnitude (ROM) costing of project
57 | P a g e
(+/- 30% costing approximately) as well as the profitability of project and
return on investment. During the ROM costing, budgetary quotes are
obtained for many major equipment and suitable judgmental factors are
taken for many items like cabling, piping, instrumentation, insulation,
overheads based on equipment costs. This stage will facilitate it to plan
the budget / resources it would require to put up such a project, having
in hand most probably the report approved by the board of directors as a
gated exercise.
Having been satisfied with SELECT phase project report, the company
will proceed to next stage i.e. DEFINE stage (also called FEED).
In DEFINE stage, each unit licensor are engaged to provide their basic
engineering design packages (BEDP) and an engineering company is hired, to
carry out FEED engineering (Front End Engineering Design) of complete
project incorporating information from BEDP of each licensed unit and its own
engineering effort in offsites and utilities (O&U).
List of FEED deliverables is listed in Volume II, chapter 28 for all disciplines
involved in engineering. In FEED, actual quotations are obtained for most
equipment including electrical / instrumentation equipment (like panels),
material take-offs (MTOs) generated for piping, insulation, instrumentation,
cables, civil materials, safety equipment/systems, etc. and quotations
obtained for these. Similarly, quotations are obtained from erection
contractors for all disciplines. Costs are also obtained for site related
infrastructure like temporary DG set, temporary porta cabins at site, labor
camps, etc.
Many a times, in FEED, the company insists on the engineering firm to identify the
LLI’s (long lead items- e.g. incinerator which can have delivery of 12 months),
obtain detailed quotes from vendors and have TBE (technical bid evaluation)
ready for such LLI’s so that at start of EXECUTE phase, order can be placed on
such LLIs to ensure actual project implementation can be completed fast.
58 | P a g e
Sr No. STAGES OF DEFINITION of STAGE
PROJECT
I ASSESS Determine project feasibility and alignment with business strategy
stakeholders.
59 | P a g e
CHAPTER 29: PROCESS DESIGN
DOCUMENTATION
How to Prepare & Specify Process Design
Documents. Details on Equipment List,
Block Flow Diagram (BFD), Process Flow
Diagram (PFD) and Utility Flow Diagram
(UFD), Process Safe Guarding Flow
Diagram (PSFD)
1. Simulation report
2. Block flow diagram
3. Process Flow Diagrams
4. Basis of Design (BOD)
60 | P a g e
CONTENTS OF DOCUMENT: It includes all major mechanical items in the
plant. It is prepared unit-wise for each plant which means all equipment in a
particular unit are listed together.
Equipment list is one of the most effective tools extensively used and referred
to during basic as well as detailed engineering phase of the project. It is used
for generating field erection data sheets for process equipment.
Equipment list is made and controlled by process engineer and used by other
engineering disciplines also.
Block flow diagrams & Process flow diagrams form an input for generating
equipment list.
In case of package units, all equipment included within the package unit are
numbered and included in equipment list with an indication of requirement of
E-Motor for each item to enable a fairly correct estimation of size of MCC with
respect to number of feeders.
Type: Centrifugal
61 | P a g e
F: Flow in m³/h
Heat Exchangers:
For package units, duty parameters are given. For example; for boilers,
capacity in TPH and pressure in kg/cm²g is given. Technical details of
equipment within package unit are furnished only after order placement.
Design Pressure
Design Temperature
Drive: Requirement of E-Motor, steam turbine, gas turbine or Electrical
Heater
Material of Construction: Broad material of construction for major parts
of equipment is specified, for example;
Pumps & Blowers – MOC for Casing & Impeller
Heat Exchangers – MOC for shell side, MOC for tube side
Test Pressure and Medium: For hydro test or pneumatic test
Source of Supply: Whether the equipment is indigenous (I), foreign (F) or
part of package unit (P) is indicated here.
Group Responsibility: Different equipment is handled by different
disciplines and are responsible for procurement/inquiry. In order to
identify the responsible department, following codes are entered:
62 | P a g e
PURPOSE OF DOCUMENT: BFD is prepared in initial stage of process
engineering. The purpose of block diagram in basic engineering package is to
show at one place the material balance in kg/h or m³/h of all process streams
entering and leaving each unit in the overall process. This communicates the
overall scope of project to the rest of team.
INPUTS REQUIRED:
For the preparation of block flow diagram, the following documents are
required:
Understanding of process
Preliminary overall General Arrangement (GA) drawing
Each unit is shown as one rectangular block and all incoming and outgoing
process streams as lines with arrows. The units are also shown as per the
location as per overall GA drawing.
By the above representation of unit as a block, the total process plant can be
covered under one block diagram. In one block diagram, all plants in a
complex can also be represented.
While selecting a capacity for utility package, block diagrams are generally
prepared along with concept notes.
Design basis
Simulation Report
Thermo-physical property data
Stream No.
Composition
Operating pressure & temperature
Density
Volumetric / mass flow rates
Viscosity
Utilities like steam, cooling water, pressurized air, etc. are shown by a
line with the short code for medium
64 | P a g e
The heat balance is given in units as per Design Basis units of
measurement
The utility consumption is given on each consumer as volume or mass
stream
Additional temperature and pressure data is given as required
Pressures is given in gauge pressure
Flow sheets are organized to show correct relative elevations of
equipment and also in relation to other flow sheets
iii) The PFD and the material balance is the basis for the following
engineering activities:
iv) Separate process flow diagrams are generated to take care of:
vii) It is also a practice to give the heat & material balance portion in a
separate A4 size sheet for large unit PFDs.
65 | P a g e
B) UTILITY FLOW DIAGRAMS:
Utility flow diagrams are prepared for each utility showing each consumer as a
rectangular block. These are generated mainly for all process plant
consumers.
INPUTS REQUIRED:
(i) BFD
(ii) PFD
CONTENTS OF DOCUMENT:
i) Safeguarding elements:
– Relief valves will be shown along with relief destination e.g. HP or LP flare.
66 | P a g e
Control valves and by-passes will be shown along with action on air
failure (i.e. spring action fail open/close or stay put).
Notes should be shown as necessary to state which if any of
downstream relief systems are affected by the capacity (i.e. CV) of the
control valve and restriction orifices where applicable.
Details of penultimate safeguards (i.e. alarms of high and low) do not need to
be shown on PSFDs.
Process Safeguarding Flow Diagrams (PSFD) should be prepared only for new
process units and repeat modified units where the changes affect the safety
integrity of the system.
PSFDs are based on the initial issue of the relevant PFD. The PSFDs are
intended to assist and guide the development of the P&IDs with regard to
identifying safety protective devices including emergency shutdown valves,
relief valves and depressuring facilities.
PSFDs should be issued before the issue of P&IDs to ensure that the required
information is transposed on to the P&IDs.
67 | P a g e
Fig 29.4: PSFD of a LPG bullet storage facility
68 | P a g e
CHAPTER 30: TECHNICAL BID
VALUATIONS
How to Prepare Technical Bid Evaluation of
Screw Compressor
30.7 Technical Evaluation Guidelines for Screw
Compressors
Standard:
Generally, screw compressors are specified and manufactured as per
manufacturer standard for compressed air service.
Gas screw compressors are manufactured as per API 619 for compressor and
API 614 for oil system.
Dry type are also available for process services and for compressed air service.
69 | P a g e
2. Control method of achieving minimum turndown should be provided
by vendor.
Duty and area provided for economizer are consistent with respect to
in/out conditions
Operating conditions with respect to pressures and temperature of the
economizer for shell and tube side
Ensure that oil removal boot is provided in economizer shell side
4. Consumption figures:
Refer compressor chart and cross check the power requirement for model
selected.
Minimum turndown and power consumption at part load conditions to
be checked.
5. Oil Circuit:
Oil circuit for compressor should be checked carefully and following points
must be checked:
6. Motor Selection:
Vendor shall be asked to indicate power requirement when suction gas density
is maximum.
Selected motor should have minimum 15% margin over gauranteed power
requirement and over power requirement for maximum suction gas density
condition whichever is higher.
7. Review the reference list for quoted model and ensure that said model
has already been installed elsewhere and it is working satisfactorily for
more than two years.
9. For oil lubricated compressors, oil used for machine should not be
reactive towards gas handled by machine.
******************************************************* *******************************************
72 | P a g e
Index (Full Version)
Vol Chapter Title No. of
No. Pages
I – Preface, Foreword and Overall Table of Contents 6
I 1 Introduction 5
I 2 General 138
I 3 Pumps 181
I 4 Compressors 149
I 5 Fans and Blowers 59
I 6 Heat Exchangers 93
I 7 Pressure vessels, Tanks and Bullets 58
I 8 Fractionators and Absorbers 396
I 9 Separators 92
I 10 Fired Heaters 142
I 11 Incinerators 68
I 12 Agitated Vessels 86
I 13 Safety Relief Systems 255
I 14 Line Sizing, Hydraulics 76
I 15 Vacuum systems 90
I 16 Utilities 469
I 17 Dryers 48
I 18 Motors 16
I 19 Evaporators 62
I 20 Pneumatic Conveying 78
I 21 Crystallisers 32
I 22 Steam and Gas Turbines 84
I 23 Leaching and Extraction 77
I 24 Special Process Items 191
I 25 Additional Process Calculations 50
73 | P a g e
II 26 Project Types 13
II 27 Engineering Disciplines and Sequence of 60
Engineering
II 28 Overall Engineering Documentation for all 13
Disciplines in a Project
II 29 Process Design Documentation 25
6
II 30 TBE Guidelines 44
II 31 Safety Studies 15
II 32 Automation and Control 13
8
II 33 Material of Construction 90
II 34 Cost, Time & Resource Estimation 10
II 35 Inspection and Testing 11
II 36 Precommissioning, Commissioning and 58
Guarantee Run
II 37 Specialised Studies 55
II 38 Heat Exchanger Optimization 15
6
II 39 Philosophies 28
Handbook Details
No. of Chapters/eBooks 44
No. of Pages 4000
74 | P a g e
Figures 2265
Tables 440
Calculation Templates 40
Datasheets 93
TBE Blank Formats 12
Checklists 25
www.chemicalprocessengineering.com
75 | P a g e