Professional Documents
Culture Documents
Primavera P6 Professional Advanced Rel 19: Eduardo Vera
Primavera P6 Professional Advanced Rel 19: Eduardo Vera
Advanced Rel 19
Eduardo Vera
AMBIT Enterprise Solutions S.L.
evera@ambitec.es
D91348GC10
Edition 1.0
• Linear
– Resource assignment work is automatically spread
evenly, or linearly, over the duration of an activity.
• Non-linear
– Work is not distributed evenly.
5-day activity
Plumber Linear 8h 8h 8h 8h 8h
Resource Resource M T W T F M T W T F
Curve
Carpenter Back-loaded 4h 4h 6h 6h 6h 10h 10h 10h 12h 12h
Bucket Planning
Leveling Resources
Activity B
16
Resource
Allocation
Rose Danner 8
Resource
8h/d Max Units/Time limit line
0
June 1-5 June 8-12 June 15-19 June 22-26 June 29 - July 6-10
July 3
Activity B
16
Resource
Allocation
8
Rose Danner Resource
8h/d Max Units/Time limit line
0
June 1-5 June 8-12 June 15-19 June 22-26 June 29 - July 6-10
July 3
A F
C E
Duration Types
Examples:
2 days X 8 hrs/day = 16 hours
3 days X 4 hrs/day = 12 hours
5 days X 16 hrs/day = 80 hours
Related equations:
– Actual Units + Remaining Units = At Completion Units
– Budgeted Units – At Completion Units = Variance (in Units)
Fixed
Duration Units
Units/Time
10 d 8 h/d 80 h
Fixed Fixed
Units
Duration Units/Time
10 d 8 h/d 80 h
Change 8 h/d 40 h
5d
Duration
Change 10 d 40 h
4 h/d
Units/Time
Change
10 d 12 h/d 120 h
Units
Fixed
Units/Time Fixed Units
Duration
10 d 8 h/d 80 h
Change
5d 16 h/d 80 h
Duration
Change
10 d 4 h/d 40 h
Units/Time
Change
10 d 12 h/d 120 h
Units
Earned Value
Project Plan:
10-day project to build 10 desks for $1,000
• $1,000 total value
• 1 desk per day
• $100 per desk
In our example:
$300 (EV) – $500 (PV) = – $200 (SV)
In our example:
$300 (EV) – $600 (AC) = – $300 (CV)
In our example:
300/500 = .6
In our example:
300/600 = .5
Key
SV Schedule Variance
CV Cost Variance
ETC Estimate to Complete
BAC Budget at Completion
EAC Estimate at Completion
VAC Variance at Completion
Advanced Scheduling
Black bars =
Critical path
Can activities that are not on the critical path affect project
duration?
1. Yes
2. No
FLOAT
Black bars =
Critical path
Gray bars =
Near critical
White bars =
Less critical
FLOAT
Retained Logic
Preserves original
relationship
between activities.
Progress Override
Disregards original
relationship
between activities.
5 day workweek
7 day workweek