PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM

Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 2/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

DOCUMENT INFORMATION

The following required information is minimum requirement which need to be updated


each time the document is changed.

Creation by : Mr. Nguyen Cong Son

Review Frequency : When new revision issue

File Name : TF1_2Q92_100019_C_Inspection and Testing


Procedure with Plan for Painting

List of Qualified Approvers : Project Manager

Locations of Controlled Copies :


 Master Document ☐CV ☐CO ☐CM ☐CE ☐DC
☐EE ☐EM ☐ES ☐FT ☐FF
☐HR ☐IE ☐IF ☐IT ☐MP
☐MR ☐MS ☐PE ☐PL ☐PC
☐PM ☒QM
 Copied Document ☒CV ☒CO ☒CM ☒CE ☒DC
☒EE ☒EM ☒ES ☒FT ☒FF
(E-file) ☒HR ☒IE ☒IF ☒IT ☒MP
☒MR ☒MS ☒PE ☒PL ☒PC
☒PM ☒QM

Management of Changes : ☐ Internal (MOC No.)


: ☐ External (Project Correspondence No.)
: ☒ New Issue

Related Documents Document Number Document Title


SP-009 Painting Specification
CON-014 Instruction for Painting work
TF1-2D92-100079 Painting Procedure

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 3/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

REVISION LOG
Date Revised Detail
Rev.
(dd/mm/yyyy) Item Page Article Description

A 28/05/2019 All All All Issue for Review


B 11/09/2019 All All All Issue for Review
C 12/02/2020 6 5 Revised as per LSP’s comment
Added Paint Material Inspection
C 12/02/2020 10 1.2
as per LSP’s comment
C 12/02/2020 12 2.7 Revised as per LSP’s comment
C 12/02/2020 13 3.1 Revised as per LSP’s comment

C 12/02/2020 14 3.5; 3.7 Revised as per LSP’s comment


3.8; 3.9;
C 12/02/2020 15 Revised as per LSP’s comment
4.1

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 4/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

Index
1. Purpose ..................................................................................................................... 5
2. Scope ........................................................................................................................ 5
3. References ................................................................................................................ 5
3.1. Codes and Standards ....................................................................................... 5
3.2. Project specifications and Procedures........................................................... 5
4. Abbreviation ............................................................................................................. 5
5. Definitions................................................................................................................. 6
6. Inspection and Testing Procedure .......................................................................... 6
6.1. Material/Tools & Equipment Inspection ......................................................... 6
6.2. Surface Preparation inspection ...................................................................... 7
6.3. Paint application inspection............................................................................ 8
6.4. Final Inspection ................................................................................................ 8
7. Subcontractor Responsibility ................................................................................ 9
8. Inspection and Testing with plan ........................................................................... 9

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 5/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

1. Purpose
This inspection and test plan establishes the work process, inspection and test are to
be executed, documented and required by PPC and LSP.
In addition, this procedure aids the quality control personnel in the performance of
their work, the plan identifies the various steps of inspections to be performed during
the surface preparation and painting works.
2. Scope
This document is applicable for the inspection and testing relating to the surface
preparation and painting works of the following shop fabrication and field erection for
steel structure, tanks, vessels, piping and equipment.
3. References
3.1. Codes and Standards
ISO : International Organization for Standardization

ASTM : American Society for Testing and Material

SSPC : The Society for Protective Coatings

3.2. Project specifications and Procedures


SP-009 : Painting Specification
CON-014 : Instruction for Painting Work
SP-017 : Factory/Shop Inspection and Testing
TF1-2D92-100079 : Painting Procedure
TF1-2D92-100016 : Inspection Tool/Equipment Calibration Procedure
TF1-2Q92-000009 : Non-conformance Control Procedure
4. Abbreviation
LSP : Long Son Petrochemicals Co. Ltd
PPC : The Consortium of POSCO Engineering & Construction and

PVC-MS

PEC : POSCO Engineering & Construction Co., Ltd

PVC-MS : Petroleum Equipment Assembly and Metal Structure


Joint Stock Company

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 6/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

DFT : Dry Film Thickness

WFT : Wet Film Thickness

MSDS : Material Safety Data Sheet

TDS : Technical Data Sheet

IRN : Inspection Release Note

FIN : Field Inspection Notice

5. Definitions
H Hold point, FIN is required. During hold point inspection, the witness will be
performed. PPC/Subcontractor shall not proceed with the work until presence
of the inspector or written consent of LSP’s inspector. LSP have the right to
access fabrication area at all time

W Witness, Inspection activities performed by PPC/Subcontractor and witnessed


by LSP’s inspector. FIN is required. If the LSP’s inspector is not present,
PPC/Subcontractor may perform the inspection/tests as scheduled unless
otherwise requested. LSP have the right to access fabrication area at all time.

S Witness, but spot check basis, FIN is required. Initial operation will be
witnessed and subsequent operation will be witnessed at discretion of the
LSP’s inspector considering the results of previous inspection unless otherwise
sampling percentage is specified. LSP have the right to access fabrication area
at all time.

M Monitor, PPC and LSP’s Inspector will have all the right to enter fabrication
areas of Subcontractor at his convenient time for the monitoring of surface
preparation and painting activities. Subcontractor is responsible for supporting
his expectations. LSP have the right to access fabrication area at all time.

R Review of inspection records and/or specified document.

P Certificate/document to be provided or prepared by Subcontractor/Vendor

6. Inspection and Testing Procedure

6.1. Material/Tools & Equipment Inspection

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 7/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

Visual Inspection on Delivered Materials


Abrasive material: Blasting abrasives shall be placed on a wooden block or other
stock methods in a dry and covered area.
Paint material: Painting materials and coating systems shall be approved by PPC
and LSP.
Storage shall be done in dry, clean and well ventilated areas, and shall be done
under supervision of Paint Manufacturer’s representative
The equipment/tools shall be in good conditions and valid calibration certificate.

6.2. Surface Preparation inspection


Prior to the surface preparation, surface contamination such as oil, grease and
any similar matter shall be removed by degreasing with suitable degreaser or
solvent cleaning in according to SSPC-SP1
Visual inspection for all material to be blasted with free of oil, grease & debris, free
of weld spatter & shape edges, all sharp edges shall be ground to give a radius of
2 mm.
Equipment/compressed air shall be checked frequently by blotter test as per
ASTM D4285.
No blasting operation on steel surfaces shall be done in the following conditions
on the working area:
- Surface temperatures is less than 3 °C above the dew point
- Relative humidity is greater than 85%
- There is a possibility that the blasted surface will be subject to wetting
before the first coat or primer coat can be applied.
To achieve the required anchor profile, abrasive particle size shall follow the
surface preparation commentary of the SSPC, ISO manual as necessary to
comply with SSPC-SP 10/ Sa 2.5.
Inspection and Testing on surface before application paint:
- Check of abrasive types
- Visual imperfections on welds, cut edges, steel surface

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 8/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

- Verify surface cleanliness to be blasted


- Check surface preparation grade and surface profile (SSPC SP10, 30-
80 µm)

6.3. Paint application inspection


The primer coat or first coat of paint shall be applied within 5 hours after of surface
preparation finished before any rusting occurs (if rust forms after cleaning, the
surface shall be re-cleaned before painting).
No painting operation shall be done in the following weather conditions in the
working area:
- Rain, snow, fog or mist. Weather is forecasted to become adverse
before the paint has been dried.
- Dust effects adversely due to high wind.
- Ambient temperature is 5 °C or below.
- Relative humidity is 85% or more.
Inspection and Testing on the surface before applying paint:
- Weather conditions
- Check of paint name
- Mixing and Thinning
- Stripe coat (at the corner, weld seam, difficult areas…)
- Apply paint and WFT check relevant for each coat
- DFT and build up DFT (including repair and touch up)
- MEK test (for Inorganic Zinc Silicate primer) before apply 2nd coat
- Visual inspection and handover to next stage

6.4. Final Inspection


Individual coats and completed coating shall be visually inspected for free from
coating defects such as sagging, pinholes, blisters and other types of coating
application defects.

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 Inspection and Testing Procedure with Plan for EPC Project No. LSA22018
Page 9/16
Doc.No. : TF1-2Q92-100019 Rev.C Painting EPC Doc No. : - Rev.C

7. Subcontractor Responsibility
Unless otherwise specified in this procedure, the surface preparation and painting
at Shop and Field shall be performed in accordance with applicable codes,
standards, and LSP project specifications.
QC personnel of Subcontractor/ Vendor are responsible for implementation of all
items in inspection and testing plan and procedure. Their duties will also support
conducting the witness/hold point inspection by PPC and LSP’s inspector.
QC personnel of Subcontractor shall carefully follow the surface preparation and
painting activities at Shop and Field to be painted for the Steel structure, tanks,
vessels, piping and equipment, and shall make sure that it complies in all the
details with the design, construction procedure, inspection and testing
requirements.
Subcontractor shall be responsible to perform all inspections and tests to verify
the quality of surface preparation and painting in accordance with the applicable
specifications. Where necessary, PPC and LSP will witness the inspections and
tests to confirm that items meet the requirements of the project specifications.

8. Inspection and Testing with plan

The inspection and testing with the plan for the surface preparation and coating
activities during carrying out the painting work and testing at Shop and Field shall
be performed as the following the table below:

Confidential: This document is confidential and must not be copied or reproduced except with the express permission
of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 10/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

1. Material/Tool & Equipment Inspections


Abrasive shall be free of oil, dust, dirt
and other foreign matter.
Abrasive size shall be suitable for
- TF1-2D92-100079 Material
1.1 R S H P Abrasive Material producing the specified anchor profile
- SP-009 Certificate
For stainless steel surface, non -
metallic abrasive (e.g. Aluminum
oxide, garnet) shall be used.
Only paints and painting materials
approved by LSP shall be used. Paint
container shall be supplied in good
condition in sealed and labeled
- TF1-2D92-100079 container. The containers shall be Material
1.2 H H H P Paint Material
- SP-009 labeled or marked as follows as a Certificate
minimum:
- Manufacturer's Name,
- Type of paint and related thinner:
- Color of paint and related thinner:

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 11/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

- Weight: gross net


- Shelf life:
Paint material - Visually inspect Paint manufacturer recommendation
1.3 M S H - storage during storage for storage conditions at site.
Records of paint Batch numbers with dates of receipt
1.4 R R H P MSDS,TDS
materials shall be kept.
Equipment and
Ensure all Instruments and
Instruments Check Calibration
1.5 R S H P equipment is calibrated and valid due
and Calibration Record
date.

2. Surface Preparation
Prior to surface - TF1-2D92-100079
2.1 M S H - Release note for painting work
preparation - SP-009
Free of oil, grease & debris
Verify surface
Free of weld spatter & sharp
2.2 M S H - cleanliness to be - ISO 8501-1
edges. All sharp edges shall be
blasted
ground to facilitate for painting quality.

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 12/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

Check equipment / Free of oil or water


2.3 M S H - - ASTM D4285
compressed air

Visible imperfections Visually inspect


2.4 M S H - Visually inspect
on welds, cut edges
& steel surfaces

Check of abrasive
2.5 M S H - - Comply as per specification
types
Surface temperatures is at least 3°C
- TF1-2D92-100079 above the dew point
2.6 M S H - Weather conditions
- SP-009 Relative humidity less than 85%
Paint manufacturer recommendation.
- Surface preparation - Visual inspection,
grade ISO 8501-1
2.7 S S H P According to each coating system
- Surface profile - Comparator, or Painting
Comply as per specification surface

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 13/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

testex tape, ISO preparation grade. report


8503-1, 8503-5 (Spot checks)

- SP-009

3. Painting Application
Surface temperatures is at least
3 °C above the dew point.
- TF1-2D92-100079
3.1 M S H - Weather conditions Relative humidity is below 85% or as
- SP-009
per Paint manufacturer
recommendation.
Visually inspect
According to manufacturer’s
3.2 M S H - Mixing and thinning during coating MSDS, TDS
recommendations
application

Prior to spray application, stripe


Stripe coat for each - TF1-2D92-100079
coated with edges, complex
3.3 M S H - coat in the coating - SP-009
structural features, areas difficult for
system
spray

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 14/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

WFT gauge shall be used to ensure


that the measurement is
Check wet film
- TF1-2D92-100079 representative of the calculated wet
3.4 M S H P thickness relevant Painting
- SP-009 film before significant solvent
grade report
evaporation occurs and expected
DFT will be achieved.
Dry film thickness - TF1-2D92-100079
after each coating Not less than minimum dry film
3.5 S S H P - SP-009 Painting
application thickness.
- SSPC PA2 report
Curing test for
inorganic zinc
3.6 M S H - - ASTM D4752 Rating resistance 4 to 5 is acceptable
silicate primer before
apply 2nd coat

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 15/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

Coats of paint shall be uniformly


Visual inspection for
applied without sags, runs, pots,
3.7 S S H - coating defect after 100%of all surfaces
damage, contamination and
each coat application after each coat
irregularities.

- TF1-2D92-100079
Power or Hand Tool: St 3.
Repair and Touch-up - SP-009
3.8 S S H - Sound DFT
painting - TF1-2D92-100080

- ISO 4624 Spot check Painting


3.9 S W H P Production testing - ASTM D3359
X-Cut and Pull off report

4. Final Inspection

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam

PACKAGE A2
Long Son Petrochemicals Co., Ltd
TANK FARM AND INTERCONNECTING PIPELINES

Contract No. : LSP-CA-147 EPC Project No. LSA22018


Inspection and Testing Procedure with Plan for Painting Page 16/16
Doc.No. : TF1-2Q92-100019 Rev.C EPC Doc No. : - Rev.C

Inspection Party
Subcon/ Inspection/Test Procedure & Verified
LSP PPC Inspection/Test Criteria Remarks
Items Standard documents
Vendor

Final inspection for


the coated items
prior to the next
Free from coating defects Painting
4.1 W W H P activities such as
insulation application report
or handover to next
stage

Notes: Parties in the inspection involvement indicate as the followings:

1- Subcontractor/Vendor

2- Paint manufacturer’s Technical Service Representative

3- PPC

4- LSP

Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.

You might also like