Submitted by: Marquez, Geraldine C. Submitted to: Arch.

Gerick Domingo
Section: ARCH51S2 Course: AR591A

Assignment 5.1 Bill of Quantities, Quantity Take-Off, and Detailed Unit Pricing

TIME COST CRASH COST


ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY
A 7 6 22,750.00 19,500.00 3,250.00
B 9 6 29,250.00 19,500.00 9,750.00
C 6 4 19,500.00 13,000.00 6,500.00
D 24 4 78,000.00 13,000.00 65,000.00 PATH DURATION
E 24 2 78,000.00 6,500.00 71,500.00 A-B-E-H-L-N-O 79 DAYS
F 5 4 16,250.00 13,000.00 3,250.00 A-C-E-H-L-N-O 76 DAYS
G 16 2 52,000.00 6,500.00 45,500.00 A-C-F-I-L-N-O 56 DAYS
H 16 3 52,000.00 9,750.00 42,250.00 A-D-G-I-L-N-O 85 DAYS
I 15 2 48,750.00 6,500.00 42,250.00 A-D-G-J-M-N-O 81 DAYS
J 12 3 39,000.00 9,750.00 29,250.00 A-D-J-K-M-N-O 72 DAYS
K 7 2 22,750.00 6,500.00 16,250.00
L 6 2 19,500.00 6,500.00 13,000.00
M 5 3 16,250.00 9,750.00 6,500.00
N 15 4 48,750.00 13,000.00 35,750.00
O 2 2 6,500.00 6,500.00 -
TOTAL 169 DAYS 549,250.00 PHP

A-B-E-H-L-N-O 7+9+24+16+6+15+2 = 79 Days A-C-E-H-L-N-O 7+6+24+16+6+15+2 = 76 Days


TIME COST CRASH COST TIME COST CRASH COST
ACTIVITY ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY NORMAL CRASH NORMAL CRASH PER DAY
A 7 6 22,750 19,500 3,250 A 7 6 22,750 19,500 3,250
B 9 8 29,250 26,000 3,250 C 6 5 19,500 16,250 3,250
E 24 23 78,000 74,750 3,250 E 24 23 78,000 74,750 3,250
H 16 15 52,000 48,750 3,250 H 16 15 52,000 48,750 3,250
L 6 5 19,500 16,250 3,250 L 6 5 19,500 16,250 3,250
N 15 14 48,750 45,500 3,250 N 15 14 48,750 45,500 3,250
O 2 1 6,500 3,250 3,250 O 2 1 6,500 3,250 3,250

A-C-F-I-L-N-O 7+6+5+15+6+15+2 = 56 Days A-D-G-I-L-N-O 7+24+16+6+6+15+2 = 85 Days


TIME COST CRASH COST TIME COST CRASH COST
ACTIVITY ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY NORMAL CRASH NORMAL CRASH PER DAY
A 7 6 22,750 19,500 3,250 A 7 6 22,750 19,500 3,250
C 6 5 19,500 16,250 3,250 D 24 23 78,000 74,750 3,250
F 5 4 16,250 13,000 3,250 G 16 15 52,000 48,750 3,250
I 15 14 48,750 45,500 3,250 I 6 5 19,500 16,250 3,250
L 6 5 19,500 16,250 3,250 L 6 5 19,500 16,250 3,250
N 15 14 48,750 45,500 3,250 N 15 14 48,750 45,500 3,250
O 2 1 6,500 3,250 3,250 O 2 1 6,500 3,250 3,250

A-D-G-J-M-N-O 7+6+5+15+6+15+2 = 81 Days A-D-J-K-M-N-O 7+24+12+7+5+15+2 = 72 Days


TIME COST CRASH COST TIME COST CRASH COST
ACTIVITY ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY NORMAL CRASH NORMAL CRASH PER DAY
A 7 6 22,750 19,500 3,250 A 7 6 22,750 19,500 3,250
C 6 5 19,500 16,250 3,250 D 24 23 78,000 74,750 3,250
F 5 4 16,250 13,000 3,250 J 12 11 39,000 35,750 3,250
I 15 14 48,750 45,500 3,250 K 7 6 22,750 19,500 3,250
L 6 5 19,500 16,250 3,250 M 5 4 16,250 13,000 3,250
N 15 14 48,750 45,500 3,250 N 15 14 48,750 45,500 3,250
O 2 1 6,500 3,250 3,250 O 2 1 6,500 3,250 3,250

PATH DURATION NORMAL PROJECT COST 549,250.00


A-B-E-H-L-N-O 7+7+3+4+3+5+3 = 32 Days CRASH A 3D - 2D = 1 Dx 3,250 3,250
A-C-E-H-L-N-O 7+5+3+4+3+5+3 = 30 Days CRASH B 4D - 3D = 1 Dx 3,250 3,250
A-C-F-I-L-N-O 7+5+5+3+3+5+3 = 31 Days CRASH L 3D - 2D = 1 Dx 3,250 3,250
A-D-G-I-L-N-O 7+4+3+3+3+5+3 = 28 Days CRASH O 3D - 2D = 1 Dx 3,250 3,250
A-D-G-J-M-N-O 7+5+5+3+3+5+3 = 30 Days TOTAL 562,250.00
A-D-J-K-M-N-O 7+4+4+3+4+5+3 = 30 Days