Concrete Pipe Cleaning

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

BSA

Stationary pumping
Pipe Line Layout

AKM 533
Pipeline layout

blv 09/00 AKM 533 FN 12


12
Pipeline – Horizontal layout

blv 09/00 AKM 533 FN 13


13
Pipeline – Downward pumping

• Use minimum of 20 meter. horizontal


line before the start of downward line to
ensure steady flow state of concrete
before entering downward line. P ump
T hrust Block
• Horizontal pipeline must be cast in a
Air Vent
thrust block to reduce the shocks
transmitted.
• Use thrust block or outside bracket
elbow at the bottom of downward line.
• Provide firm supporting to line going
downward. If possible provide standby
descending line which will be useful in
case of blockage of one line.
• Provide air vent/ bleeder valve at 90º
bend going down. This vent allows
air(displaced by concrete) to escape
out & also admits air to prevent a
siphoning effect.

blv 09/00 AKM 533 FN 14


14
Pipeline laying

Use camel hump/loop as shown in picture which will help to hold more concrete in
vertical delivery line & also will prevent the freefall & segregation of concrete in
descending line.

• Provide necessary thrust blocks for the pipeline to absorb the shocks developed while
pumping
• The immediate piping after pump must take U turn which ensures minimum shocks in
the pipeline
• Provide rigid & firm support to complete pipeline
• Ensure that the horizontal piping after the pump is at least 1/8th of total vertical pipeline.
This helps in maintaining minimum back pressure due to concrete in vertical pipeline.

blv 09/00 AKM 533 FN 15


15
Delivery Lines

blv 09/00 AKM 533 FN 18


18
Pipeline fixing systems

Pipeline support (horizontal) Pipeline support @heights

Bend support (vertical)


Scaffold support

Bend support (horizontal)

blv 09/00 AKM 533 FN 19


19
Problems in pipelines

Narrowing of the diameter as a result of encrustation

Cause :

• Leaking pipelines
• Concrete with a high fines
content
• High pressures

Consequences :

• Increased pressure requirement


• Formation of a blockage

blv 09/00 AKM 533 FN 20


20
Laying delivery lines

Securing the delivery line


• Firm anchoring to the structure or the supporting ground
• At least 1 fixing point per pipe
• Absolute linearity
• Secured against axial slippage
• Web plate of beam in direction
of forces from pumping

blv 09/00 AKM 533 FN 21


21
Causes of blockages

Coarse particles become Water bleeds out


• Segregation and bleeding during
wedged
breaks in pumping
• Leaking couplings or kinked lines
in the coupling
• Insufficient cleaning of the delivery
line
• Accumulation of aggregate in the
concrete at the end of the
discharge
High frictional resistance

Conveying direction

blv 09/00 AKM 533 FN 22


22
Quality matters

blv 09/00 AKM 533 FN 23


23
Cleaning

3 possibilities:
• From the top downwards using compressed air
• From the top downwards using water
• From the bottom upwards using water

Cleaning material available


in different degree of
hardness

Calculate the concrete quantity in the line approximately 1.25 m³ per 100m at a
diameter of 125

blv 09/00 AKM 533 FN 26


26
Cleaning

Cleaning from the top downwards using compressed air

Apply the compressed air in short


bursts only and wait until the
concrete ceases to move.

Follow the course of the sponge


ball by knocking on the line

blv 09/00 AKM 533 FN 27


27
Cleaning

Cleaning from the top downwards using compressed air


• The force of gravity aids washing out
• Force the sponge ball back using a compressor
• Air cleaning must be carried out very carefully and is
dangerous. Do not clean hoses.
• Take care as the sponge balls are ejected from
the end of the line

Use a catch basket

blv 09/00 AKM 533 FN 28


28
Cleaning

blv 09/00 AKM 533 FN 33


33
Cleaning

blv 09/00 AKM 533 FN 34


34
High pressure water cleaning

blv 09/00 AKM 533 FN 35


35
Drain off leavings

blv 09/00 AKM 533 FN 36


36
Cleaning

And don‘t forget to clean the pump itself !

blv 09/00 AKM 533 FN 38


38
Delivery lines

Pipe couplings

• Pressures of up to 250 bar


• Absolute tightness
• For permanently installed lines

• Pressures of up to 85 bar
• For booms
• For swivelling connections
• 2° play in couplings allowed

blv 09/00 AKM 533 FN 42


42
Different coupling designs

Wedge coupling

Threaded coupling

Toggle coupling

blv 09/00 AKM 533 FN 43


43
THANK YOU FOR
YOUR ATTENTION !

blv 09/00 AKM 533 FN 47