PORT ACCESS ELEVATED HIGHWAY PROJECT

SECTION 1 FROM STA.0+000 TO STA.5+270


Contract No: RDA/ADB/OCB/PAEH/CW/01
EMPLOYER :
Weather
ROAD DEVELOPMENT AUTHORITY

ENGINEER:
Sedalia Associates, Inc. Joint Venture With Roughton International Ltd And Mg Consultants Date: 31-Aug-2022
(Pvt.) Limited
CONTRACTOR:
Day Not Holiday
CCECC-HPRB-HNRBI JV
DAILY WORK SCHEDULE PLAN
Work Time
No: Category Section Work Description Officer In Charge Contact No: Inspection Time Planned Work Ending time
07:30-18:30 18:30-07:30
1 P52L-U10 Concreting Mr. Hirantha (077) 760 5064 ● ● 18:30 till 19:00
2 P43R-U03 Concreting Mr. Hirantha (077) 760 5064 ● ● 21:30 till 19:00
3 P53R-U01 Concreting Mr. Hirantha (077) 760 5064 ● ● 0:00 till 5:00
4 P104L-U01 Concreting Mr. Hirantha (077) 760 5064 ● ● 2:30 till 5:00

P44R-U06, P44L-U05, P46L-U12, P53R-U01, P53R-U15, P53L-


5 U12, P108R-U03, P43L-U05, P43R-U04, P108L-U01, P40L-U01, Rebar work Mr. Hirantha (077) 760 5064 ● ● till 19:30
Beam Yard P40R-U01, P108M-U01,, P104L-U01

P46L-U11, P104L-U01, P108L-U01, P40L-U01, P40R-U01,


6 Form work preparation Mr. Hirantha (077) 760 5064 ● ● till 19:30
P108M-U01, P53R-U01, P53R-U13, P43R-U03

7 P55L-D0,P55R-D0,P55L-U0 Final stressing Mr. Hirantha (077) 760 5064 ● ● till 19:30
8 P56L-U14, P56R-U14 Grouting Mr. Hirantha (077) 760 5064 ● ● till 19:30
9 Pier 49 sewer line construction work. Mr. Akesha (072) 389 4949 ● ● till 20:00
10 Pier 68, 75 trial pit Mr. Akesha (072) 389 4949 ● ● till 20:00
11 Pier 89 statue foundation formwork and concreting to the new location Mr. Akesha (072) 389 4949 ● ● till 20:00
Utility
12 Pier 96 manhole r/f preparation. Mr. Akesha (072) 389 4949 ● ● till 20:00
13 Pier 103 data center finishing works & excavation for manhole constructions and R/F works Mr. Akesha (072) 389 4949 ● ● till 20:00
14 Pier 105 excavation for manhole constructions and R/F works Mr. Akesha (072) 389 4949 ● ● till 20:00
15 MS-0 site formwork work of the segment Mr. Shashi (071) 886 8722 ● ● till 20:00
16 SS-0 reinforcement work and formwork work of the segment Mr. Shashi (071) 886 8722 ● ● till 20:00
17 Pier 4 Excavation for pile cap Mr. Shashi (071) 886 8722 ● ● till 20:00
18 Pier 5 reinforcement work for pile cap Mr. Shashi (071) 886 8722 ● ● till 20:00
19 Pier 6 reinforcement work pier stem Mr. Shashi (071) 886 8722 ● ● till 20:00
20 Pier 7 Backfilling for the Pile cap Mr. Shashi (071) 886 8722 ● ● till 20:00
21 Pier 93 Reinforcement work of the capping beam Mr. Shashi (071) 886 8722 ● ● till 20:00
22 Pier 94 Installation of the form traveler Mr. Shashi (071) 886 8722 ● ● till 20:00
23 Pier 29 RHS trial pit excavation Mr. Ruwan (076) 758 8179 ● ● till 20:00
24 Pier 39A sheet pile drive and welding work Mr. Kumara (077) 518 0838 ● ● till 20:00
25 Pier 104 pile hacking and pile cap excavation Mr. Kumara (077) 518 0838 ● ● till 20:00
26 Pier 105 backfilling work Mr. Kumara (077) 518 0838 ● ● till 20:00
27 Pier 98 P2 Sonic tubes cleaning and grouting Mr. Pasan (077) 948 4556 ● ● till 20:00
28 Pier 101 RHS Shoring work Mr. Pasan (077) 948 4556 ● ● till 20:00
29 Pier 32 LHS Pier 2nd stage re-bar Mr. Ruwan (076) 758 8179 ● ● till 20:00
30 Pier 34 R1 & R2 Pier 2nd stage and tie beam re-bar Mr. Ruwan (076) 758 8179 ● ● till 20:00
31 Pier 95 LHS Pier 2nd stage re-bar Mr. Ruwan (076) 758 8179 ● ● till 20:00
32 Elevated Bridge Pier 95 RHS Pier 1st stage concrete Mr. Ruwan (076) 758 8179 ● ● 18:00 till 24:00
33 Construction Pier 99 RHS Pier 3rd stage concrete Mr. Ruwan (076) 758 8179 ● ● 15:00 till 20:00
34 Pier 100 MID pile cap backfilling Mr. Ruwan (076) 758 8179 ● ● till 20:00
35 Pier 102 Pier 2nd stage re-bar Mr. Ruwan (076) 758 8179 ● ● till 20:00
36 Pier 44, 46,49 Capping Beam supporting structure work. Mr. Lakshan (076) 685 9238 ● ● till 20:00
37 Pier 45: Capping Beam capping beam arrange for bottom formwork. Mr. Lakshan (076) 685 9238 ● ● till 20:00
38 Pier 48: Capping Beam capping beam bearing plinth rebar and PT bar fixing work Mr. Lakshan (076) 685 9238 ● ● till 20:00
39 Pier 52: Capping Beam capping beam bearing plinth location chipping work. Mr. Lakshan (076) 685 9238 ● ● till 20:00
40 Pier 53: Capping Beam capping beam end sealing formwork. Mr. Lakshan (076) 685 9238 ● ● till 20:00
41 Pier 54: Capping Beam capping beam end sealing formwork and supporting structure removing. Mr. Lakshan (076) 685 9238 ● ● till 20:00
42 Pier 56: Capping Beam removing supporting structure removing. Mr. Lakshan (076) 685 9238 ● ● till 20:00
43 Pier 56-57 span segment transport & lifting Mr.Sadaruwan (071) 4391795 ● ● till 20:00
44 Pier 58-59 LHS span grouting Mr.Sadaruwan (071) 4391795 ● ● till 20:00
45 Pier 37 : Capping Beam end seal work. Mr. Sanjeewa (077) 4823509 ● ● till 20:00
46 Pier 46 : Capping Beam Portal beam supporting structure works Mr. Sanjeewa (077) 4823509 ● ● till 20:00
47 Pier 47: Capping Beam Portal beam reinforcement. Mr. Sanjeewa (077) 4823509 ● ● till 20:00
48 Pier 50: Capping Beam Portal beam formwork. Mr. Sanjeewa (077) 4823509 ● ● till 20:00
49 Pier 107: Capping Beam Portal beam chipping work. Mr. Sanjeewa (077) 4823509 ● ● till 20:00
50 Pier 109: Capping Beam tensioning works. Mr. Sanjeewa (077) 4823509 ● ● till 20:00
Note: Please note that due to the shortage of fuel we are facing difficulties in finding machinery and also materials. As a result of that the efficiency of site construction has become low during these troubled times. At our site many activities has been stopped or getting delayed because of the lack of machinery and material. There for the progress of other activities are also low because of the
material and fuel issue.

Prepared By Checked and Approved By:

Planning Engineer - H.M.G.J.Bandaranayake Deputy Technical Manager: Tian Pengfei