(၆)ခန္းတြဲနွင့္(၄)ခန္းတြဲ ဝန္ထမ္ းအိမ္ယာေရွ႕မွ ေက်ာင္းအဝင္ Community Hall လမ္းဆံ ု းအထိ ကြ န္ကရစ္ခင္း

ျခင္းလု ပ္င န္း (1533'x18'x6")(3' wide Shoulder)

DETAIL MEASUREMENT

Measurement Deducti
Sr.no Particular No Content Total Unit
on
L B H

1 Cutting and Filling Road Base 1 57.14' 18' 1.52' 1563.35 cu.ft
Leveling Work
1 45.22' 18' 1.62' 1318.62 cu.ft
1 121.57' 18' 1.56' 3413.69 cu.ft

1 66.84' 18' 1.63' 1961.09 cu.ft


1 84.02' 18' 1.65' 2495.39 cu.ft

1 39.52' 18' 1.61' 1145.29 cu.ft

1 71.18' 18' 1.53' 1960.29 cu.ft

1 102.56' 18' 1.7' 3138.34 cu.ft

1 50.95' 18' 1.97' 1806.69 cu.ft

1 66.68' 18' 2.04' 2448.49 cu.ft

1 43.17' 18' 2.06' 1600.74 cu.ft

1 78.76' 18' 1.99' 2821.18 cu.ft


1 65.16' 18' 1.81' 2122.91 cu.ft
1 76.25' 18' 1.79' 2456.78 cu.ft

1 116.62' 18' 1.84' 3862.45 cu.ft

34115 cu.ft

2 Site Clearing Work 1 1533' 24' 36792 36792 sq.ft

3 Road Base Level Compacting 1 1533' 24' 36792 36792 sq.ft


Work
4 Sand Filling Work 1 1533' 18' 6" 13797 13797 cu.ft

5 Timber Shuttering For 3 1533' 6" 2299.5 sq.ft


Formwork

9' Length joint 340 9' 6" 1530 sq.ft

3829.5 sq.ft

6 Laying Of Plastic Sheet 1 1533' 18' 27594 27594 sq.ft

7 1:2:4 Cement Concrete work 1 1533' 18' 6" 13797 13797 cu.ft
8 Back Fill Work For Shoulder 2 1533' 3' 3' 27594 27594 cu.ft
BUILDER ESTIMATE

Sr.no Particular Quantity Unit Rate Per Amount(kyats) Remark

1 Cutting and Filling Road Base 34115.3 cu.ft


Leveling Work
Soil 341.153 sud 24994.34 sud 8526894.34
Excavator 2.15 day 200000 day 430000
Grader 0.5 day 200000 day 100000
Machine Driver 2.5 nos 15000 nos 37500
Worker 2.5 nos 10000 nos 25000
9119394.34

2 Site Clearing Work 36792 sq.ft


Worker 92.32 nos 10000 923200

3 Road Base Level Compacting Work 36792 sq.ft

Grader 2.14 day 200000 day 428000


Compactor 6.14 day 280000 day 1719200
Water Bowzer 5.875 day 120000 day 705000
Roller 2.3 day 150000 day 345000
Head Worker 13.7 nos 15000 nos 205500
Worker 56.4 nos 10000 nos 564000
operator 15 nos 15000 nos 225000
Driver 5.13 nos 15000 nos 76950
Helper 20.51 nos 10000 nos 205100
4473750

4 Sand Filling Work 13797 cu.ft


sand 488.29 cu.m 6350 cu.m 3100641.5
Worker For Carrying And Ramming 70.31 nos 10000 nos 703100
Worker For Watering 70.31 nos 10000 nos 703100
4506841.5

5 Timber Shuttering For Formwork 1276.5 sq.ft 3 time used


timber Scantling 0.5 ton 900000 ton 450000
Timber Plank 0.5 ton 920000 ton 460000
Nails 22.54 kg 2688 kg 60587.52
Carpenter 24.913 nos 15000 nos 373695
Worker 13.05 nos 10000 nos 130500
1474782.52

6 Laying Of Plastic Sheet 27594 sq.ft


Plastic Sheet 2692.72 sq.m 1291 sq.m 3476301.52
Head Worker 1 nos 15000 nos 15000
Worker 8.44 nos 10000 nos 84400
3575701.52

Sr.no Particular Quantity Unit Rate Per Amount(kyats) Remark

7 1:2:4 Cement Concrete work 13797 cu.ft


Cement 2592.055 bag 7000 bag 18144420
River Shingle 390.63 cu.m 35320 cu.m 13797051.6
River Sand 195.314 cu.m 6350 cu.m 1240243.9
Fuel 1253.92 lit 3500 lit 4388720
Workers 414.07 nos 10000 nos 4140700
Machine Driver 70.313 nos 15000 nos 1054695
42765830.5

8 Back Fill Work For Shoulder 27594 cu.ft


soil 275.94 sud 24994.34 sud 6896938.18
Head Worker 16.41 nos 15000 nos 246150
Worker 67.68 nos 10000 nos 676800
Operator 18 nos 15000 nos 270000
Driver 6.15 nos 15000 nos 92250
Helper 24.61 nos 10000 nos 246100
Compactor 7.69 day 280000 day 2153200
Water Bowzer 7.05 day 120000 day 846000
Roller 2.76 day 150000 day 414000
Grader 2.56 day 200000 day 512000
12353438.18
BILL OF QUANTITY

Sr.no Particular Quantity Unit Rate Per Amount(KYATS) Remark

MATERIALS

1 Soil 617.093 sud 24994.34 sud 15423832.25


2 Cement 2592.055 bag 7000 bag 18144385
3 River Sand 683.604 cu.m 6350 cu.m 4340885.4
4 River shingle 390.63 cu.m 35320 cu.m 13797051.6
5 Fuel 1253.92 lit 3500 lit 4388720
6 Timber Scantling 0.5 ton 900000 ton 450000
7 Timber Plank 0.5 ton 920000 ton 460000
8 Nails 22.54 kg 2688 kg 60587.52
9 Grader 5.2 day 200000 day 1040000
10 Excavator 2.15 day 200000 day 430000
11 Compactor 14 day 280000 day 3920000
11 Water Bowzer 12.93 day 120000 day 1551600
12 Roller 5.06 day 150000 day 759000
13 Palstic Sheet 2692.72 sq.m 1291 sq.m 3476301.52
MATERIAL CHARGES 68242363.29

LABOUR

1 Worker 795.08 nos 10000 nos 7950800


2 Head Worker 31.11 nos 15000 nos 466650
3 Machine Driver 84.093 nos 15000 nos 1261395
4 Helper 45.12 nos 10000 nos 451200
5 Operator 33 nos 15000 nos 495000
6 Carpenter 24.913 nos 15000 nos 373695
LABOUR CHARGES 10998740

1 River Sand 683.604 cu.m 10000 cu.m 6836040


2 River Shingle 390.63 cu.m 10600 cu.m 4140678
TRANSPORTATION CHARGES 10976718
NAME OF WORK : ရ န္ကုန္နာက္ပိုင္းနည္းပညာတကၠသို လ္

(၆)ခန္းတြဲနွင့္(၄)ခန္းတြဲ ဝန္ထမ္ းအိမ္ယာေရွ႕မွ ေက်ာင္းအဝင္ Community Hall လမ္းဆံ ု းအထိ ကြ န္ကရစ္ခင္းျခင္း


လု ပ္င န္း (1533'x18'x6")(3' wide Shoulder)

Sr.no Particular Amount(Kyats) Remark

1 Material Charges 68242363.29

2 Labour Chargrs 10998740

3 Transportation Charges 10976718

Total 90217821.29

Commercial (5%) and QC (2%) 6315247.49

Grand Total 96533068.78

Say 96400000
သိပၸံ နွင့္နည္းပညာဝန္ၾကီးဌာန

အဆင့္ျမင့္သိပၸံ နွင့္နည္းပညာဦးစီးဌာန

ရ န္ကုန္နာက္ပိုင္းနည္းပညာတကၠသို လ္

(၆)ခန္းတြဲနွင့္(၄)ခန္းတြဲ ဝန္ထမ္ းအိမ္ယာေရွ႕မွ ေက်ာင္းအဝင္ Community Hall လမ္းဆံ ု း


အထိ ကြ န္ကရစ္ခင္းျခင္းလု ပ္င န္း (1533'x18'x6") (3' wide Shoulder)

HNIN WAI SOE FAMILY CO.LTD