Professional Documents
Culture Documents
Case Study: Best Practice (Project Timeline Workshop)
Case Study: Best Practice (Project Timeline Workshop)
2
6. Planning steps (Best Practice) cont.
10. Check Your Schedule ( Open Ends - critical path
- Float - …..).
11. Prepare Baseline documents for submission.
12. Receive Client and / or Consultant Comments.
13. Resubmit Baseline documents
3
6. Planning steps (Best Practice) cont.
4
6. Planning steps (Best Practice) cont.
5
6. Planning steps (Best Practice) cont.
6
6. Planning steps (Best Practice) cont.
Q. What is a contract ?
An agreement made between two or
more parties which is enforceable by
law to provide something in return for
something else from a second party.
7
6. Planning steps (Best Practice) cont.
A. Contract Type
B. Conditions of Contract
C. Contract Duration
D. Project Start and Finish Date
E. Contract Value
F. Project parties
G. Project Location
H. Description of the Project
I. Scope of work
8
6. Planning steps (Best Practice) cont.
For Example:-
9
6. Planning steps (Best Practice) cont.
A. Contract Type
Lump Sum Contract / Contract Agreement
10
6. Planning steps (Best Practice) cont.
B. Conditions of Contract
Special Conditions, FIDIC, NEC, …etc.
C. Contract Duration
Contract Agreement
11
6. Planning steps (Best Practice) cont.
E. Contract Value
Contract Agreement
F. Project parties
Contract Agreement
G. Project Location
Contract Agreement
12
6. Planning steps (Best Practice) cont.
I. Scope of work
Specifications or Conditions of Contract
13
6. Planning steps (Best Practice) cont.
c. Data Date time to be match with Project Start and Finish time.
14
6. Planning steps (Best Practice) cont.
15
6. Planning steps (Best Practice) cont.
16
6. Planning steps (Best Practice) cont.
17
6. Planning steps (Best Practice) cont.
18
6. Planning steps (Best Practice) cont.
r. Include Civil to MEP and MEP to Civil clearance dates for 1st , 2nd
and 3rd fix.
19
6. Planning steps (Best Practice) cont.
20
6. Planning steps (Best Practice) cont.
21
6. Planning steps (Best Practice) cont.
22
6. Planning steps (Best Practice) cont.
23
6. Planning steps (Best Practice) cont.
24
6. Planning steps (Best Practice) cont.
25
6. Planning steps (Best Practice) cont.
26
6. Planning steps (Best Practice) cont.
1. Pre-Qualification Submittals
Ready Mix Concrete Pre-Qualification Submittal ( Approximate 10
Days)
2. Pre-Qualification Approvals From Consultant / stakeholders
Ready Mix Concrete Pre-Qualification Approvals ( Approximate 14
Days)
27
6. Planning steps (Best Practice) cont.
28
6. Planning steps (Best Practice) cont.
Level 1
a. KEY DATES
b. MOBILIZATION
c. ENGINEERING
d. PROCUREMENT
e. CONSTRUCTION WORKS
f. PROJECT CLOSE OUT
29
6. Planning steps (Best Practice) cont.
Level 2
a. KEY DATES
30
6. Planning steps (Best Practice) cont.
Level 2
b. MOBILIZATION
Tarek Yehia Fouda, B.sc, PMP®, PMI-RMP®, PMI-SP® Mahmoud Yehia Fouda, B.sc, PMP®, PMI-RMP® 31
6. Planning steps (Best Practice) cont.
Level 2
c. ENGINEERING
32
6. Planning steps (Best Practice) cont.
Level 2
d. PROCUREMENT
1. PRE-QUALIFICATION SUBMITTALS
2. PRE-QUALIFICATION APPROVALS FROM CONSULTANT /
STAKEHOLDERS
3. MATERIAL SUBMITTALS
4. MATERIAL APPROVALS FROM CONSULTANT /
STAKEHOLDERS
5. ORDER PLACEMENT
6. FABRICATION & DELIVERY
33
6. Planning steps (Best Practice) cont.
Level 2
e. CONSTRUCTION WORKS
1. Main Building
2. Utility Building
3. Mosque
4. Driver & Storage Room
5. Guardhouses
6. External Works and Landscape
34
6. Planning steps (Best Practice) cont.
Level 2
f. PROJECT CLOSE OUT
35
6. Planning steps (Best Practice) cont.
Level 3
e. CONSTRUCTION WORKS
1. Main Building
i. Part 1
ii. Part 2
iii. Part 3
iv. Part 4
v. Façade Works
vi. Conveying systems
36
6. Planning steps (Best Practice) cont.
Level 3
e. CONSTRUCTION WORKS
1. Main Building
i. Part 1
a) Substructure
b) Super Structure
c) Internal Finishes
d) MEP Works
37
6. Planning steps (Best Practice) cont.
38
6. Planning steps (Best Practice) cont.
Plan-1000 350 mm Thick retaining wall M2 826 34.742 28696.89 DIV-03 Reinforced cement concrete Main Building
Plan-1001 200 mm Thick Core wall M2 10 21.225 212.25 DIV-03 Reinforced cement concrete Main Building
Plan-1002 Column M3 130 126.89 16495.7 DIV-03 Reinforced cement concrete Main Building
40
6. Planning steps (Best Practice) cont.
• For Example
i. Commencement Date
ii. Completion Date
iii. Intermediate Milestones if any
41
6. Planning steps (Best Practice) cont.
• For Example
42
6. Planning steps (Best Practice) cont.
• For Example
43
6. Planning steps (Best Practice) cont.
44
6. Planning steps (Best Practice) cont.
45
6. Planning steps (Best Practice) cont.
46
6. Planning steps (Best Practice) cont.
4. Calendars.
4.1. Prepare different Calendars (6 working days ,8 working Hours)
47
6. Planning steps (Best Practice) cont.
4. Calendars.
4.1. Prepare different Calendars ( 8 working Hours with Summer Break)
48
6. Planning steps (Best Practice) cont.
4. Calendars.
4.1. Prepare different Calendars (5 Working Days ,8 working Hours)
49
6. Planning steps (Best Practice) cont.
4. Calendars.
4.1. Prepare different Calendars (7 Working days, 24 Working Hours)
50
6. Planning steps (Best Practice) cont.
4. Calendars.
4.2. Assign Calendars to related activities
51
6. Planning steps (Best Practice) cont.
52
6. Planning steps (Best Practice) cont.
54
6. Planning steps (Best Practice) cont.
55
6. Planning steps (Best Practice) cont.
56
6. Planning steps (Best Practice) cont.
57
6. Planning steps (Best Practice) cont.
1. Understand project document.
2. Create WBS.
3. Define activities and milestones list.
4. Calendars.
5. Sequence activities(Logical relationships).
6. Cost and Resources loading.
7. Estimate Activity duration.
8. Crashing and Fast tracking.
9. Resource Levelling and Resource Smoothing.
58
6. Planning steps (Best Practice) cont.
59
6. Planning steps (Best Practice) cont.
1. Understand project document.
2. Create WBS.
3. Define activities and milestones list.
4. Calendars.
5. Sequence activities(Logical relationships).
6. Cost and Resources loading.
7. Estimate Activity duration.
8. Crashing and Fast tracking.
9. Resource Levelling and Resource Smoothing.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
60
6. Planning steps (Best Practice) cont.
10. Check Your Schedule ( Open Ends - critical path - Float - …..)
(View Log).
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............Yes
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor Activity Calendar
61
6. Planning steps (Best Practice) cont.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................527
# Not Started....................................................527
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................1049
# Activities with Constraint.....................................0
62
6. Planning steps (Best Practice) cont.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
Warnings:
---------
Activities without predecessors..................................1
Project: PV Course D Activity: ADI-CM-AL-AL-01-E002 Project Start Date
Out-of-sequence activities.......................................0
63
6. Planning steps (Best Practice) cont.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................527
# Relationships with other projects..............................0
Data Date........................................................01-Oct-20
Earliest Early Start Date........................................01-Oct-20
Latest Early Finish Date.........................................31-Mar-22
…………………………………………………………………………………………………………………………………..
64
6. Planning steps (Best Practice) cont.
1. Understand project document.
2. Create WBS.
3. Define activities and milestones list.
4. Calendars.
5. Sequence activities(Logical relationships).
6. Cost and Resources loading.
7. Estimate Activity duration.
8. Crashing and Fast tracking.
9. Resource Levelling and Resource Smoothing.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
11. Prepare Baseline documents for submission.
65
6. Planning steps (Best Practice) cont.
11. Prepare Baseline documents for submission.
66
6. Planning steps (Best Practice) cont.
1. Understand project document.
2. Create WBS.
3. Define activities and milestones list.
4. Calendars.
5. Sequence activities(Logical relationships).
6. Cost and Resources loading.
7. Estimate Activity duration.
8. Crashing and Fast tracking.
9. Resource Levelling and Resource Smoothing.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
11. Prepare Baseline documents for submission.
12. Receive Client and / or Consultant Comments.
67
6. Planning steps (Best Practice) cont.
12. Receive Client and / or Consultant Comments.
Private Villa B + G + 1st + Roof Compliance Sheet
S.N Consultant Comment Planning Response
1 Calendar
Referring to sub-clause 43.1 “Time for Completion”, the
duration of the project is 548 Calendar days. In the submitted
1.1 Complied
programme, the duration of the project is incorrect.
68
6. Planning steps (Best Practice) cont.
1. Understand project document.
2. Create WBS.
3. Define activities and milestones list.
4. Calendars.
5. Sequence activities(Logical relationships).
6. Cost and Resources loading.
7. Estimate Activity duration.
8. Crashing and Fast tracking.
9. Resource Levelling and Resource Smoothing.
10. Check Your Schedule ( Open Ends - critical path - Float - …..).
11. Prepare Baseline documents for submission.
12. Receive Client and / or Consultant Comments.
13. Resubmit Baseline documents.
69
6. Planning steps (Best Practice) cont.
13. Resubmit Baseline documents.
70
7. Reasons of Delay and / or Claim
REASONS FOR CLAIMS
• Slow Progress
• Client Changes
• Client or consultant delays
• Force Majeure
7. Reasons of Delay and / or Claim
Different Opinions (6 Reasons of delay)
• Inefficient management
• Construction implementation failure
• Environmental catastrophes/Unavoidable events
• Design issues
• Scope increase
• Economical changes
• Failure in coordination between time schedule and execution
8. Types of Delay
1. Critical Delays
A. Excusable Delays
i. Compensable
ii. Non-Compensable
B. In-Excusable Delays
C. Concurrent Delays
2. Non-Critical Delays
8. Types of Delay
A. Excusable Delays
Regarding construction schedules, delay events are classified into the following three
types:-
• Excusable delays An excusable delay entitles the contractor to additional time for completing
the contract work. Excusable delays usually stem from reasons beyond the contractor’s
control. These delays are further classified into:
• Delays that are beyond the control of, and are not the fault of, the owner, such as those
caused by unusual weather conditions, natural disasters (earthquakes, floods, hurricanes,
etc.), wars or national crises, or labor strikes. These types of delays most likely entitle the
contractor to a time extension but not to monetary compensation (no compensable delay).
• Delays caused by the owner or the designer (architect/engineer). These types of delays
typically allow the contractor to recover the costs and time associated with the delays and
are known as “compensable delays.”
8. Types of Delay
B. Non-Excusable Delays
• Non-excusable delays :- By definition, a non excusable delay does not entitle the
contractor to either a time extension or monetary compensation. Typically, a non
excusable delay is any delay that is either caused by the contractor or not caused by
the contractor but should have been anticipated by the contractor under normal
conditions. Examples of the first type include slow mobilization, poor workmanship,
labor strikes due to unfair labor practices, or accidents on the project site caused by
the contractor’s negligence or lack of preparation. Other examples include late
delivery of the contractor’s furnished materials and equipment, the contractor’s cash-
flow problems, adverse weather conditions that are expected for that location during
that time of the year, or a lack of skilled labor.
8. Types of Delay
C. Concurrent Delays
• A combination of two or more independent causes of delay during the same general
time period may be considered concurrent delays. Often the concurrent delays are
excusable and non excusable delays. For example, the author was involved in a case in
which the contractor was performing at a slow rate and falling behind schedule
because the contractor didn’t have an adequate workforce on the site. During the
middle of the project, the owner issued a major change order. The contractor
requested 120 days of time extension due to this change order. In order to prove his
point, the contractor presented two schedules: an original (baseline) schedule and an
“impact schedule.” After an analysis, this author found that the change order justified
only 56 days of delay. The rest, that is, 64 days, were a non excusable delay. The
contractor was trying to hide this non excusable delay behind the owner’s change
order.
9. Scheduling Mistakes Related to Delay Claims
1. Negotiation
2. Mediation
3. Dispute review board
4. Arbitration
5. Litigation
6. Adjudication
Thank You
هذا العمل خالص لوجه هللا تعالى