Environmental Impact Assessment Report & Environmental Management Plan
Environmental Impact Assessment Report & Environmental Management Plan
[Schedule 5 (f) Category –“B” Synthetic Organic Chemical Industry located in a Notified Industrial
Area/Estate as per EIA Notification 2006]
ABBREVIATIONS .................................................................................................................................. XV
CONTENTS
I
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
II EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
CONTENTS
III
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
IV EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
LIST OF TABLES
IX
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
X EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
LIST OF FIGURES
Figure No. 2.1 – Map Showing General and Specific Location of Project Site............................................................ 7
Figure No. 2.2 – Short View of the Project site with Project Boundary ......................................................................... 8
Figure No. 2.3 – Toposheet ........................................................................................................................................................... 9
Figure No. 2.4 – Seismic Zone Map ......................................................................................................................................... 10
Figure No. 2.5 –Drainage Map .................................................................................................................................................. 10
Figure No. 2.6 – Hydrogeological Map ................................................................................................................................... 12
Figure No. 2.7 – Layout Plan ...................................................................................................................................................... 14
Figure No. 2.8 – Water Balance Diagram (Existing, KLD) ............................................................................................... 36
Figure No. 2.9 – Water Balance Diagram (After Proposed Expanstion, KLD) .......................................................... 36
Figure No. 2.10 – ETP flow Diagram ....................................................................................................................................... 37
Figure No. 3.1 – Study Area map ............................................................................................................................................. 40
O
Figure No. 3.2 – Graphical presentation of Min. & Max. Temperature ( C) for the March – 2019. ................. 43
O
Figure No. 3.3 – Graphical presentation of Min. & Max. Temperature ( C) for the April – 2019. .................... 43
O
Figure No. 3.4 – Graphical presentation of Min. & Max. Temperature ( C) for the May – 2019. ..................... 44
Figure No. 3.5 – Graphical presentation of Min. & Max. Humidity (%) for the March – 2019........................... 44
Figure No. 3.6 – Graphical presentation of Min. & Max. Humidity (%) for the April – 2019. ............................. 44
Figure No. 3.7 – Graphical presentation of Min. & Max. Humidity (%) for the May – 2019. .............................. 44
st st
Figure No. 3.8 – Wind Rose Diagram (1 March, 2019 to 31 May, 2019) ............................................................... 45
Figure No. 3.9 – Ambient Air Monitoring Locations in the 10 km Study Region .................................................... 47
Figure No. 3.10 – Graphical Presentaiton of Min. & Max. value for PM10 ................................................................. 49
Figure No. 3.11 – Graphical Presentaiton of Min. & Max. value for PM2.5 ................................................................ 49
Figure No. 3.12 – Graphical Presentaiton of Min. & Max. value for SO 2 ................................................................... 49
Figure No. 3.13 – Graphical Presentaiton of Min. & Max. value for Nox ................................................................... 50
Figure No. 3.14 – Soil Sampling Locations in the 10 km Study Region ...................................................................... 51
Figure No. 3.15 – Land Use Map .............................................................................................................................................. 54
Figure No. 3.16 – Pie Chart of Land Use Statistics (%) (10 km) .................................................................................... 55
Figure No. 3.17 – Ground Water Sampling Locations in the 10 km Study Region ................................................ 57
Figure No. 3.18 – Surface Water Sampling Locations in the 10 km Study Region ................................................. 60
Figure No. 3.19 – Noise Level Monitoring Locations in the 10 km Study Region ................................................... 64
Figure No. 3.20 – Graphical presentation of min. & max. Value of noise level during day time ...................... 65
Figure No. 3.21 – Graphical presentation of min. & max. Value of noise level during night time................... 65
Figure No. 4.1 – Isopleths for Concentration of PM ........................................................................................................... 99
Figure No. 4.2 – Isopleths for Concentration of SO2 ....................................................................................................... 100
Figure No. 4.3 – Isopleths for Concentration of NOx ..................................................................................................... 101
Figure No. 7.1 – Location of Storage of Various Chemicals ......................................................................................... 140
Figure No. 7.2 – Late Pool Fire and Toxic Dose due to 5 mm leak in storage drum at weather condition
1.5/D. ............................................................................................................................................................................................... 142
Figure No. 7.3 – Catastrophic Late Pool Fire and Toxic Dose due to leak in storage drum at weather
condition 1.5/D ............................................................................................................................................................................ 143
Figure No. 10.1 – Schematic Diagram of APCM for Process Emission (HCl Gas) ................................................ 167
Figure No. 10.2 – ETP flow Diagram .................................................................................................................................... 170
Figure No. 10.3 – Schematic Diagram of Rain Water Harvesting Pit ..................................................................... 178
Figure No. 10.4 – Organogram of the Environment Management Cell .................................................................. 182
LIST OF FIGURES
XI
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
XII EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
LIST OF ANNEXURES
ANNEXURE 1 – LAND DOCUMENTS .................................................................................................................................. 189
ANNEXURE 2 – CC&A COPY AND IT‘S COMPLIANCE REPORT ................................................................................ 190
ANNEXURE 3 – GIDC WATER PERMISSION LETTER ..................................................................................................... 191
ANNEXURE 4 – CETP MEMBERSHIP CERTIFICATE ......................................................................................................... 192
ANNEXURE 5 – TSDF MEMBERSHIP CERTIFICATE ......................................................................................................... 193
ANNEXURE 6 – ENVIRONMENT POLICY ........................................................................................................................... 194
ANNEXURE 7 – UNDERTAKING ............................................................................................................................................ 195
ANNEXURE 8 – ADEQUACY CERTIFICATE ......................................................................................................................... 196
ANNEXURE 9 – APPLIACTION GRANTED SCREENSHOT OF CTE AFTER TOR .................................................... 197
ANNEXURE 10 – HIGH COURT STAY ORDER .................................................................................................................. 198
ANNEXURE 11 – SHOW – CAUSE NOTICES AND CLOSURE NOTICES SERVED BY THE GPCB .................... 199
ANNEXURE 12 – ANALYSIS REPORTS AND COPIES OF INSTRUCTIONS WITH POINT WISE COMPLIANCE
........................................................................................................................................................................................................... 200
ANNEXURE 13 – MSDS ............................................................................................................................................................ 201
UNDERTAKING BY PROJECT PROPONENT
UNDERTAKING BY CONSULTANT
ABBREVIATIONS
EIA - Environmental Impact Assessment
EC - Environmental Clearance
CC&A - Consolidated Consent & Authorization
SEIAA - State Level Environment Impact Assessment Authority
TOR - Terms of References
SEAC - State Expert Appraisal Committee
EMP - Environmental Management Plan
AMSL - Average Mean Sea Level
MoEF&CC - Ministry of Environment, Forest & Climate Change
N. H. - National Highway
S. H. - State Highway
PPEs - Personnel Protective Equipments
GLC - Ground Level Concentration
ISCST – 3 - Industrial Source Complex – Short Term
MSDS - Material Safety Data Sheet
CPCB - Central Pollution Control Board
GPCB - Gujarat Pollution Control Board
NAAQS - National Ambient Air Qualtiy Standard
GIDC - Gujarat Industrial Development Corporation
PHAST - Process Hazard Analysis Software Tool
BLEVE - Boiling Liquid Expanding Vapor Explosion
QRA - Quantitative Risk Assessment
TLV - Threshold Limit Value
STEL - Short Time Exposure Limit
IDLH - Immediately Dangerous to Life and Health
LCLo - Lethal Concentration Low
TCLo - Toxic Concentration Low
ERPG - Emergency Response Planning Guidelines
LDAR - Leak Detection and Repair
DMP - Disaster Management Plan
ABBREVIATIONS
XV
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
XVI EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
TOR COMPLIANCE
Sr.
TOR Points Compliance of TOR
No.
Specific TOR
Compliance of MOEFCC‗s OM dated 01/05/2018 regarding ―Corporate environment Corporate environment responsibility is mentioned in Section 10.6, Page
responsibility‖ (CER). Fund allocation for Corporate environment responsibility No. 175.
1.
(CER) Shall be made as per MOEFCC‗s OM 22-65/2017-IA.III dated 01/05/2018 for
various activities for CER shall be incorporated in EIA/EMP project.
Explore the use of renewable energy to the maximum extent possible. Details of Measures proposed for energy conservation is mentioned in Section
provisions to make the project energy-efficient through energy-efficient devises 10.9.2, Page No. 179.
2.
and adoption of modes of alternative eco-friendly sources of energy like solar
water heater, solar lighting etc. Measures proposed for energy conservation.
PP Shall furnish status of all the applicable Rules, Acts, Regulations, Clearance in a The applicable Rules, Acts, Regulations, Clearance are mentioned in
3.
tabular form. Section 10.4, Page No. 2.
Existing and proposed product wise quantity and quality of industrial waste water Existing and proposed product wise quantity of industrial waste water
generation along with its source (Process, Washing, utility etc.) generation is mentioned in Section 2.8.2, Page No. 34.
4.
Quality of industrial waste water generation is mentioned in Section
10.4, Page No. 2.
5. To justify Quantity of ETP sludge generation against treatment of industrial effluent. ETP sludge generation is mentioned in Section 2.8.3, Page No. 37.
Segregation of waste water stream based on characteristics and its proper Only normal effluent will be generated from the existing as well as
management keeping in view direction under section 18 (1) (b) of the Water proposed production activity. Hence segregation fo waste water stream
6.
(Prevention and Control of pollution) act, 1974 issued by CPCB regarding is not application. However characteristics of waste water stream and its
compliance of CETP. proper management mentioned in Section 10.2.2, Page No. 169.
Standard TOR
A tabular chart with index for point-wise compliance of below mentioned TORs. Complied.
1.
Refer Page No. XXII.
Sr.
TOR Points Compliance of TOR
No.
Executive summary of the project — giving a prima facie idea of the objectives of Complied.
the proposal, use of resources, justification, etc. In addition, it should provide a Executive summary of the project mentioned in Chapter 11, Page No.
2.
compilation of EIA report; including EMP and the post project monitoring plan in 184.
brief.
Justification for selecting the proposed product and unit size. The Company is in the production of various dyes since past few years.
Due to demand of existing as well as proposed products in the present
market scenario, company will need to proposed expansion and/or
reduction in existing production capacity and addition of new products
3. within existing premises in the various dyes manufacturing. Proposed
expansion and/or reduction in existing production capacity and addition
of new products having total capacity of 5.0 MT/Month (Either individual
or Total production shall not exceed 5.0 MT/Month). Hence total plot
2
area i.e. 704.00 m is sufficient after proposed expansion.
Land requirement for the project including its break up for various purposes, its Land requirement for the project including its break up for various
availability and optimization. purposes along with its optimization are mentioned in Section 2.4.1,
4.
Page No. 13. Land document is attached as Annexure – 1, Page No.
189.
Land possession documents. Copy of NA order showing permission to use the Land is located in Ankleshwar GIDC. Hence, NA copy is not required.
5. project land for industrial purpose. If located in GIDC, copy of plot holding Land document is attached as Annexure – 1, Page No. 189.
certificate obtained from GIDC Authority.
Location of the project site and nearest habitats with distances from the project site Location of the project site and nearest habitats with distances from the
6.
to be demarcated on a Toposheet (1:50000 scale). project site and Toposheet are mentioned in Section 2.3.2, Page No. 9.
Topography details of the project area. Topography detail of the project area is mentioned in Section 2.3.3,
7.
Page No. 10.
Geological features and geo-hydrological status of the study area. Geological features and geo-hydrological status of the study area is
8.
mentioned in Section 2.3.3, Page No. 10.
In case of project located outside notified area: Legal Undertaking stating that unit Not application as project is located in notified industrial area.
3
9. is complying the three conditions [i.e. water consumption less than 25 M /day; Fuel
consumption less than 25 TPD; and not covered in the category of MAH units as
TOR COMPLIANCE
XXIII
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
XXIV EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
TOR Points Compliance of TOR
No.
per the Management, Storage, import of Hazardous Chemical Rules (MSIHC Rules),
1989] as per the amendment to EIA Notification, 2006 vide SO 1599 (E) dated
25/06/2014.
Present land use pattern of the study area shall be given based on satellite imagery. Present land use pattern of the study area based on satellite imagery is
10.
mentioned in Section 3.8, Page No. 54.
Layout plan of the factory premises clearly demarcating various units within the Layout plan of the factory premises is mentioned in Section 2.4.1, Page
plant. Provision of separate entry & exit and adequate margin all-round the No. 13.
11.
periphery for unobstructed easy movement of the emergency vehicle / fire tenders
without reversing back. Mark the same in the plant layout.
Technical details of the plant‗s along with details on best available technologies Technical details of the plant‗s along with details on best available
12. (BAT), proposed technology and reasons for selecting the same. technologies (BAT), proposed technology and reasons for selecting the
same are mentioned in Section 2.7, Page No. 22.
Product spectrum (Proposed products along with production Capacity) and Proposed products along with production Capacity are mentioned in
13. processes. Section 2.5, Page No. 17 and processes are mentioned in Section 2.7,
Page No. 22.
Chemical name of each proposed product to be manufactured. Details on end use Products and product wise raw material consumption along with
14. of each product. (Provide CAS number of all the products & raw materials. In case chemical name, CI/CAS number, end use of products are mentioned in
of Dyes, Cl number). Section 2.5 & Section 2.6, Page No. 17 & Page No. 19 respectively.
Details on raw materials, source and storage within the premises. All the raw materials are available in the domestic market. Details of raw
15. materials and storage within the premises are mentioned in Section
7.2.6, Page No. 116.
Details of complete manufacturing process/ operations of each product along with Details of complete manufacturing process, operations of each product
chemical reactions, process flow diagram describing each unit processes and unit along with chemical reactions, process flow diagram describing each unit
16.
operations along with material balance, consumption of raw materials etc. processes and unit operations along with material balance, consumption
of raw materials are mentioned in Section 2.7, Page No. 22.
Details on strategy for the implementation of cleaner production activities. Details on cleaner production activities are mentioned in Section 10.10,
17.
Page No. 180.
Sr.
TOR Points Compliance of TOR
No.
Assessment of source of the water supply with adequacy of the same to meet with Source of water is GIDC. Permission letter from GIDC water supply is
18. the requirements for the project. Permission obtained from the concern authority attached as Annexure – 3, Page No. 191.
for supply of raw water.
Undertaking stating that no bore well shall be dug within the premises (If project is Undertaking is attached as Annexure – 7, Page No. 195.
19.
located within the Industrial estate).
Details on water balance including quantity of effluent generated, recycled & Water consumption and wastewater generation are mentioned in
reused. Details of methods to be adopted for the water conservation. Section 2.4.4, Page No. 15 and Section 2.8.2, Page No. 34 respectively.
20.
Water conservation details are mentioned in Section 10.2, Page No.
169.
Efforts to minimize effluent discharge and to maintain quality of receiving water Wastewater generation during operation phase from industrial activities
21.
body. will be send to ETP and finally discharged to CETP – ETL for further
Explore the possibilities for Zero Liquid Discharge (ZLD) option for the proposed treatment after achieving all norms in permissible limit.
22. CETP certificate is attached as Annexure – 4, Page No. 192.
project.
Only normal effluent will be generated from the existing as well as
Segregation of waste streams, characterization and quality with specific treatment proposed production activity. Hence segregation of waste water stream
23. and disposal of each stream including action plan for maximum recycle of treated is not applicable. However characteristics of waste water stream and its
waste water and minimum discharge for effluent. proper management mentioned in Section 10.2.2, Page No. 169.
Capacity of ETP in KL/day. Details of ETP including dimensions of each unit along Capacity of Existing ETP is 5 KL/day. Details of ETP including dimensions
with schematic flow diagram. Inlet, transitional and treated effluent qualities with of each unit along with schematic flow diagram mentioned in Section
specific efficiency of each treatment unit in reduction in respect of all 10.2.2, Page No. 169.
24.
concerned/regulated environmental parameters. Inlet effluent quality should be
based on worst case scenario considering production of most polluting products
that can be manufactured in the plant concurrently.
25. In case of discharge into GIDC drainage/Pipeline: Not applicable.
Copy of permission letter with quantity (KL/day) from the concern authority of
I. drainage network/ pipeline with confirmation for spare capacity available to take
additional effluent.
Characteristics of the combined effluent and treated water to be sent to Common
II.
pipeline with reference to the MoEFCC/ CPCB/ GPCB discharge norms.
TOR COMPLIANCE
XXV
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
XXVI EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
TOR Points Compliance of TOR
No.
III. Provision for continuous monitoring system for waste water discharge.
In case of waste water sent to Common Facilities (CF) like CETP, MEE, Spray Dryer Wastewater generation during operation phase from industrial activities
26.
etc. will be send to ETP and finally discharged to CETP – ETL for further
a. Details of Common facilities Including treatment after achieving all norms in permissible limit.
CETP certificate is attached as Annexure – 4, Page No 192.
1. Total capacity of the CF
2. Copy of CC&A of the CF.
3. Actual load at present (Qualitative and Quantitative — KL per day)
4. Booked quantity & Spare capacity of CF
Copies of XGN generated Inspection reports with analysis reports of the water/ Air/
5. Hazardous samples collected by GPCB (Last 2 year). Copies of instructions issued by
GPCB in last 2 year and point wise compliance thereof.
Copies of Show- cause notices, closure notices etc. served by the GPCB and its
6.
compliance
Recommendations and suggestions of the last two Environments Audit reports of
6.
CETP and its compliance report.
7. Common Facility Up gradation scheme, if any.
Status of compliance to the 18(1) (b) direction issued by the CPCB with respect to
b.
CETP compliance & CEPI area action plan along with relevant supportive document.
Give status of compliance of Environmental norms of existing Common
c. Infrastructure i. e. CETP, MEE & Spray Dryer (Whichever is applicable) in which you
are a member.
Submit adequacy of Common Infrastructure i. e. CETP, MEE & Spray Dryer for
additional load (whichever is applicable) along with written confirmation/
d.
membership certificate mentioning the same (Total consented quantity, total
quantity booked so far, quantity booked for the unit, spare quantity available).
Sr.
TOR Points Compliance of TOR
No.
27. In case of Zero Liquid Discharge (ZLD): Not applicable.
Action plan for ‗Zero‘ discharge of effluent shall be included. Notarized undertaking
I. for assuring that underground drainage connection will not be taken in the unit
and there shall be no effluent discharge outside the plant premises.
Economical and technical viability of the effluent treatment system to achieve Zero
II.
Liquid Discharge (ZLD).
Certification of adequacy of proposed ZLD scheme through credible institutes of
III.
National repute.
To estimate & monitor ground water quality & its contamination status, piezometer
wells, one on up gradient of the groundwater flow and other three on down
IV. gradient side of the ground water flow of the proposed project at different depth
based on available ground water depth shall be established and all the parameters
mentioned in IS 10:500 for potable water standard shall be monitored.
In case of in-house MEE/Spray dryer for waste water treatment: Capacity of Not Applicable.
MEE/Spray dryer in KL/hr. Technical details of MEE including evaporation capacity,
steam required for evaporation, adequacy of the proposed boiler to supply steam
28. for evaporation in addition to the steam required for the process etc. Techno-
economical viability of the evaporation system. Control measures proposed for the
evaporation system in order to avoid/reduce gaseous emission/ VOC from
evaporation of industrial effluent containing solvents & other chemicals.
29. Technical details of ATFD/Crystallizer/ spray Dryer, RO/NF system etc. (If any). Not Applicable.
Details of the treatability and feasibility of wastewater to be disposed off by means Not applicable.
30.
of spray dryer and its impact on environment and Human health.
Undertaking stating that a separate electric meter will be provided for the waste Undertaking is attached as Annexure – 7, Page no. 195.
31.
water treatment system viz. ETP, RO, MEE, Spray dryer etc. (Whichever is applicable)
32. Economical and technical viability of the effluent treatment system. Not applicable as our effluent will be send to CETP for further treatment.
Plans for management, collection and disposal of waste streams to be generated Details of wastewater management plan are mentioned in Section 10.2,
33.
from spillage, leakages, vessel washing, used container washing etc. Measures Page No. 169.
TOR COMPLIANCE
XXVII
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
XXVII NAVDURGA DYES &
EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
I PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
TOR Points Compliance of TOR
No.
proposed for preventing effluent discharge during unforeseen circumstances.
Action plan for reuse of liquid waste streams like Spent acids, Poly Aluminium Not Applicable.
34. Chloride etc. within premises to convert into valuable products instead of sending
outside to actual end-users.
Adequacy of the proposed EMS with respect to the pollution load envisaged in Proposed EMS is designed based on the proposed pollution load and all
terms of Air, Water and hazardous waste. parameters will within the standard of CPCB/MoEF&CC. Proposed EMS is
adequate with respect to the pollution load envisaged in terms of Air,
35.
Water and Hazardous waste.
Adequacy from schedule II Auditor of the proposed EMS is attached as
Annexure – 8, Page No. 196.
One season Site-specific micro-meteorological data using temperature, relative One season Site-specific micrometeorological data using temperature,
36. humidity, hourly wind speed and direction and rainfall should be incorporated. relative humidity, hourly wind speed and direction and rainfall are
mentioned in Section 3.5, Page No. 42.
Anticipated environmental impacts due to the proposed project/production may be Anticipated environmental impacts due to the proposed
evaluated for significance and based on corresponding likely impacts VECs (Valued project/production are mentioned in the Chapter – 4, Page No. 90.
37. Environmental Components) may be identified. Baseline studies may be conducted Baseline studies were conducted within the study area of 10 km which is
within the study area for all the concerned/identified VECs and likely impacts will mentioned in Chapter – 3, Page No. 40.
have to be assessed for their magnitude in order to identify mitigation measures.
One complete season base line ambient air quality data (except monsoon season) To establish the baseline status around the project site of the study
st
to be given along with the dates of monitoring. The parameters to be covered shall region, monitoring was conducted for 9 numbers of locations during 1
st
be in accordance with the revised National Ambient Air Quality Standards (NAAQS) March, 2019 to 31 May, 2019. At the time of location selection previous
as well as project specific parameters like NH3, HCI, CL2, HBr, VOC etc. Locations of micrometeorological data was referred and general wind pattern in the
38. the monitoring stations should be so decided so as to take into consideration the study region was considered for the selection of minimum one location
pre-dominant downwind direction, population zone and sensitive receptors. There in the downwind direction. However, ambient air monitoring locations
should be at least one monitoring station in the upwind direction. There should be were selected in all the directions looking towards the possibility of
at least one monitoring station in the pre dominant downwind direction at a change in wind pattern during the study period. Refer Section 3.6, Page
location where maximum ground level concentration is likely to occur. No. 46.
Sr.
TOR Points Compliance of TOR
No.
Modeling indicating the likely impact on ambient air quality due to proposed Air Quality modeling along with its impact identification were carried out
activities. The details of model used and input parameters used for modeling and mentioned in Section 4.4.1, Page No. 97.
should be provided. The air quality contours may be shown on location map clearly
indicating the location of sensitive receptors, if any, and the habitation. The wind
39.
rose showing pre-dominant wind direction should also be indicated on the map.
Impact due to vehicular movement shall also be included into the prediction using
suitable model. Results of Air dispersion modeling should be superimposed on
satellite Image/ geographical area map.
Base line status of the noise environment, impact of noise on present environment Base line status of the noise environment is mentioned in Section 3.10,
40. due to the project and proposed measures for noise reduction including Page No. 63. Impact of noise on present environment due to the project
engineering controls. and proposed measures are mentioned in Section 4.4.4, Page No. 105.
41. Specific details of
a. Process gas emission from each unit process with its quantification. There is no process emission from existing production activity. After
Air pollution Control Measures (APCM) proposed for process gas emission. Proposed expansion HCl will be generated from the Chlorosulphonic
b. Adequacy of the air pollution control measures (APCM) for process gas emission Storage Tank details are mentioned in Section 2.8.1, Page No. 34.
measures to achieve the GPCB norms.
c. Details of the utilities required. Details of utilities are mentioned in Section 2.4.3, Page No. 15.
d. Type and quantity (MT/hr & MT/Day) of fuel to be used for each utility.
e. Flue gas emission rate emission from each utility. Details of flue gas emission and its APCM are mentioned in Section
Air Pollution Control Measures (APCM) proposed to each of the utility along wan its 2.8.1, Page No. 34.
f. adequacy. Adequacy from schedule II Auditor of the proposed EMS is attached as
Annexure – 8, Page No. 196.
List the project specific sources of fugitive emission along with its quantification Fugitive emission and its control measures are mentioned in Section
g.
and proposed measures to control it. 10.1.2, Page No 167.
h. Details on tail gas treatment. (lf any) Not applicable.
42. Provisions of CEMS (Continuous Emission Monitoring System) Industry will be provided CEMS for the proposed expansion project.
43. Action plan for odor control to be submitted. Odour control plan is mentioned in Section 10.8, Page No. 177.
TOR COMPLIANCE
XXIX
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
XXX EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
TOR Points Compliance of TOR
No.
Management plan for hazardous/Solid waste including storage, handling, utilization Solid/Hazardous waste Management Plan is mentioned in Section 10.4,
and safe disposal as per the Hazardous and Other Wastes (Management and Trans Page No. 172.
44.
Boundary Movement) Rules 2016. CPCB guidelines in respect of specific treatment,
such as solar evaporation, incineration, etc., need to be followed.
How the manual handling of the hazardous wastes will be minimized? Methodology of de-contamination and disposal of discarded containers
45. Methodology of de-contamination and disposal of discarded containers and its and its record keeping and minimized manual handling of hazardous
record keeping. wastes are mentioned in Section 10.4.2, Page No. 172.
Management of by-products which fall under the purview of the Hazardous and Hazardous wastes generation is mentioned in Section 2.8.3, Page No.
46. Other Wastes (Management and Transboundary Movement) Rules 2016 as per the 37.
said rules and necessary permissions from the concern authority.
Membership of Common Environmental Infrastructure like TSDF, Common Membership of BEIL is attached as Annexure - 5, Page No. 196.
47.
Incineration Facility (CHWIF), MEE, Spray dryer etc.
Name and quantity of each type of solvents to be used for proposed production. Not Applicable as no spent solvent will be generated from the existing as
Details of in-house solvent recovery system including mass balance, solvent loss, well proposed manufacturing activity.
48.
recovery efficiency (% recovery), feasibility of reusing the recovered solvents etc. for
each type of solvent.
Appropriate monitoring network has to be designed and proposed, to assess the Proposed Environment Monitoring plan is mentioned in Chapter – 6,
49.
possible residual impacts on VECs. Page No. 110.
A detailed EMP including the protection and mitigation measures for impact on Proposed Environmental Management Plan is mentioned in Chapter –
human health and environment as well as detailed monitoring plan and 10, Page No. 166.
environmental management cell proposed for implementation and monitoring of
50. EMP. The EMP should also include the concept of waste minimization, recycle/
reuse/ recover techniques, energy conservation, and natural resource conservation.
Total capital cost and recurring cost/annum earmarked for environment pollution
control measures.
Details of in-house monitoring capabilities and the recognized agencies if Industry will be provided in house monitoring for noise and wastewater.
51.
proposed for conducting monitoring. However for complete monitoring of Air, Water, Noise, Hazardous, etc.,
Sr.
TOR Points Compliance of TOR
No.
Industry will be carried out third party monitoring through NABL
accredited laboratory.
52. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any. Not Applicable.
Occupational health impacts on the workers and mitigation measures proposed to Details of occupational health impacts and its mitigation measures are
avoid the human health hazards along with the personal protective equipment to mentioned in Section 7.7, Page No. 159.
be provided. Provision of industrial hygienist and monitoring of the occupational
53.
injury to workers as well as impact on the workers. Plan for periodic medical
checkup of the workers exposed. Details of work place ambient air quality
monitoring plan as per Gujarat Factories Rules.
Details on volatile organic compounds (VOCs) from the plant operations and Details of occupational safety and health protection measures are
occupational safety and health protection measures. Proposal for Leak Detection mentioned in Section 7.7, Page No. 159.
54.
and Repair (LDAR) program as per the CPCB guidelines. Proposal for LDAR program is mentioned in Section 7.5.7, Page No.
148.
Risk assessment including prediction of the worst-case scenario and maximum Risk Assessment is mentioned in Section 7.2, Page No. 144.
credible accident scenarios should be carried out. The worst-case scenario should
take into account the maximum inventory of storage at site at any point of time.
55. The risk contours should be plotted on the plant layout map clearly showing which
of the facilities would be affected in case of an accident taking place. Based on the
same, proposed safeguard measures including On-Site / Off-Site Emergency Plan
should be provided.
MSDS of all the products and raw materials. MSDS of all the products and raw materials are attached as Annexure –
56.
13, Page No. 201.
Details of hazardous characteristics and toxicity of raw materials and products to be Details of hazardous characteristics and toxicity of raw materials and
handled and the control measures proposed to ensure safety and avoid the human products to be handled are mentioned in Section 7.2.7, Page No. 119.
57. health impacts. This shall include the details of Antidotes also. Control measures proposed to ensure safety and avoid the human health
impacts are mentioned in Section 7.5, Page No. 144.
Antidotes are mentioned in Section 7.5.6, Page No. 148.
Details of quantity of each hazardous chemical (including solvents) to be stored, Details of quantity of each hazardous chemical to be stored, Material of
58.
Material of Construction (MoC) of major hazardous chemical storage tanks, dyke Construction (MoC) of major hazardous chemical storage are mentioned
TOR COMPLIANCE
XXXI
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
XXXII EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
TOR Points Compliance of TOR
No.
details, threshold storage quantity as per schedules of the Manufacture, Storage & in Section 7.2.6, Page No. 116.
Import of Hazardous Chemicals Rules of major hazardous chemicals, size of the
biggest storage tank to be provided for each raw material & product etc. How the
manual handling of the hazardous chemicals will be minimized?
Details of the separate isolated storage area for flammable chemicals. Details of Details of fire extinguishers and other safety measures are mentioned in
flame proof electrical fittings, DCP extinguishers and other safety measures Section 7.5 & 7.7, Page No. 144 & 159 respectively.
59. proposed. Detailed fire control plan for flammable substances and processes
showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump,
toxic gas detectors etc.
Submit checklist in the form of Do‗s & Don‗ts of preventive maintenance, Checklist in the form of Do‘s & Don‘ts of preventive maintenance,
60. strengthening of HSE, manufacturing utility staff for safety related measures. strengthening of HSE, manufacturing utility staff for safety related
measures are mentioned in Section 10.5, Page No. 173.
Specify safety precautions to be taken for Chemical storage, process, handling & Details of safety measures are mentioned in Section 7.5, Page No. 144.
61.
transportation hazard.
Details on workers training before engaging work, periodical, in-house, outside, etc. Periodic Internal/external Training will be given to the workers before
62.
engaging work.
Details on various SOP to be prepared. SOP for the hazardous waste handling will be prepared in local and
63.
English language.
64. Details on safety audit to be taken for general public living in the vicinity. Safety audit will be carried out annually after proposed expansion.
65. Specific safety measures to be taken for general public living in the vicinity. Details are incorporated in Section 7.5, Page No. 144.
Details on hazard identification i. e. HAZOP, HAZAN, Fault tree analysis, Checklist, Risk Assessment Study has been carried out for the proposed expansion
66.
Audit, etc., to be adopted for the safety operation of the plant. and is mentioned in Section 7.2, Page No. 114.
67. Detection and monitoring of VOC‘s/ gases. Detailed are mentioned in Section 10.1, Page No. 168.
Detailed five year greenbelt development program including annual budget, Greenbelt development plan is mentioned in Section 10.7, Page No.
68. planning schedule, species, width of plantations, number of trees to be planted, 175.
area under green belt development [with map], budgetary outlay etc. along with Undertaking is attached as Annexure – 7, Page No. 195.
Sr.
TOR Points Compliance of TOR
No.
commitment of the management to carry out the tree plantation activities outside
the premises at appropriate places in the nearby areas and elsewhere.
Action plan for the greenbelt development — species, width of plantations,
69.
planning schedule, etc., in accordance to CPCB published guidelines.
Detailed socio-economic development measures including community welfare Mentioned in Section 10.6, Page No. 175.
program most useful in the project area for the overall improvement of the
70. environment. Submit a detailed plan for social corporate responsibilities, with
appropriate budgetary provisions for the next five years and activities proposed to
be carried out; specific to the current demographic status of the area.
(a) Does the company have a well laid down Environment Policy approved by its Mentioned in Section 10.12, Page No. 181.
Board of Directors? If so, it may be detailed in the EIA report. (b) Does the
71. Environment Policy prescribe for standard operating process/ procedures to bring
into focus any infringement / deviation / violation of the environmental or forest
norms / conditions? If so, it may be detailed in the EIA.
What is the hierarchical system or administrative order of the company to deal with
72. the environmental issues and for ensuring compliance with the EC conditions.
Details of this system may be given.
Does the company have a system of reporting of non-compliances / violations of
environmental norms to the Board of Directors of the company and / or
73.
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA Report.
Phase wise project implementation schedule with bar chart and time frame, in Project implementation schedule is mentioned in Section 2.10, Page No.
74.
terms of site development, infrastructure provision, EMS implementation etc. 39.
Certificate of accreditation issued by the NABET, QCI to the environmental Certificate is attached as Annexure – 10, Page No. 198.
75.
consultant should be incorporated in the EIA Report.
An undertaking by the Project Proponent on the ownership of the EIA report as per Complied.
76. the MoEF&CC OM dated 05/10/2011 and an undertaking by the Consultant Undertaking by the Project Proponent and Consultant refer Page No.
regarding the prescribed TORs have been complied with and the data submitted is XIII and XIV respectively.
Sr.
TOR Points Compliance of TOR
No.
factually correct as per the MoEF&CC OM dated 04/08/2009.
All documents to be properly referenced with index and continuous page Complied.
77.
numbering.
Where data are presented in the Report especially in Tables, the period in which the Complied.
78.
data were collected and the sources should be indicated.
Project proponent shall enclose all the analysis/testing reports of water, air, soil, All the analysis has been done by MoEF&CC/NABL accredited laboratory
79. noise, etc., using the MoEF&CC/NABL accredited laboratories. All the original and summary has been incorporated in EIA/EMP report which are
analysis/testing reports should be available during appraisal of the project. mentioned in Chapter – 3, Page No. 40.
80. In case of Expansion of the project
Need for the proposed expansion should be justified in detail. Need for the proposed expansion should be justified in Section 2.2,
a.
Page No. 6.
Adequacy of existing EMS (Environmental Management System). Adequacy Certificate from Schedule II auditors is attached as Annexure –
b.
8, Page No. 196.
Explore the possibility to achieve Zero Liquid Discharge (ZLD) for existing as well as Wastewater generation during operation phase from industrial activities
proposed activity. will be send to ETP and finally discharged to CETP – ETL for further
c.
treatment after achieving all norms in permissible limit.
CETP certificate is attached as Annexure – 4, Page No. 192.
Records of any legal breach of Environmental laws i.e. details of show – cause Details of show – cause notices and closure notices served by the GPCB
d. notices, closure notices etc. served by the GPCB to the existing unit in last five years to the existing unit in last five years is attached as Annexure – 11, Page
and actions taken then after for prevention of pollution. No.199.
Copies of Environmental Clearances obtained for the existing plant, its point wise Industry was established in the year 1980. Hence, Environmental
e.
compliance report. Clearance was not obtained for their existing production activity.
Environmental audit reports for last 3 years and compliance of its Not Applicable.
f.
recommendations/ Suggestions. (Include latest audit report and its compliance.).
g. Copy of Consent to Operate (CC&A) obtained along with point wise compliance Copy of CC&A and its compliance report is attached as Annexure – 2,
Sr.
TOR Points Compliance of TOR
No.
status of all the conditions stipulated therein. Page No. 190.
Compliance of MoEFCC circulars vide No: J-11011/618/2010-lAIl (I) dated Copy of CC&A and its compliance report is attached as Annexure - 2,
30/05/2012 and J-11013/41/2006-IA-ll (I) dated 20/10/2009. Page No. 190.
h. There was no any court case pending against the project.
There was no any notice issued to the project under section 5 of the EP
act 1986, and section 18 of the air act.
Copies of XGN generated Inspection reports with analysis reports of the water/ Air/ Copies of XGN generated analysis reports and Copies of instructions
i. Hazardous samples collected by GPCB (last 2 year). Copies of instructions issued by issued by GPCB in last 2 year and point wise compliance attached as
GPCB in last 2 year and point wise compliance thereof. Annexure – 12, Page No. 200.
81. In case of project is located in Ankleshwar-Panoli, Vatva-Narol & Vapi GIDC. Unit is located in GIDC Ankleshwar.
Compliance of MOEFCC‗s OM no. J-11013/5/2010-IA.ll (I) dated 25/11/2016 Compliance report of MOEFCC‘s OM no. J-11013/5/2010-IA.II (I) dated
regarding lifting of moratorium on the consideration of projects for environmental 25/11/2016 is not applicable to individual units.
clearance. We understand in this line that compliance of MOEFCC‘s OM.no J-
11013/5/2010-IA.II (I), dated 25/11/2016 regarding lifting of moratorium
A.
is not in our purview.
Wastewater generation during operation phase from industrial activities
will be send to ETP and finally discharged to CETP – ETL for further
treatment after achieving all norms in permissible limit.
Compliance of direction under section 18 (1) (b) of the Water (Prevention and Wastewater generation during operation phase from industrial activities
B. Control of Pollution) Act, 1974 issued by CPCB dated 31/03/2016 regarding will be send to ETP and finally discharged to CETP – ETL for further
compliance of CETP. treatment after achieving all norms in permissible limit.
Action initiated by GPCB, if any, against proposed unit regarding non-compliance Industry is not having any legal breach of Environmental laws i.e. details
a. of prescribed standards under the various environmental laws. of show cause notices, closure notices etc. from GPCB for the existing
unit in last five years.
Performance of CETP with respect to current hydraulic load & prescribed standards Industrial Effluent will be will be send to ETP and finally discharged to
b. with No Objection Certificate of CETP regarding incorporation of the proposed unit CETP – ETL for further treatment after achieving all norms in permissible
for acceptance of waste water. limit.
c. Performance of TSDF site with respect to current load & prescribed standards with Unit has BEIL membership certificate is attached as Annexure – 5, Page
TOR COMPLIANCE
XXXV
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
XXX NAVDURGA DYES &
EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
VI PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
TOR Points Compliance of TOR
No.
No Objection Certificate of TSDF site regarding incorporation of the proposed unit No. 193.
for acceptance of hazardous waste to the common infrastructure.
d. Copies of quarterly action report taken for the above points submitted to the CPCB. Not applicable
Report of GPCB which have conducted monitoring as per the said direction by We have no report of GPCB conducted monitoring as per the said
e.
CPCB dated 31/03/2016. direction by CPCB dated 31/03/2016.
CHAPTER 1 – INTRODUCTION
1.1 PURPOSE OF THE REPORT
The purpose of this report is to make an Environmental Impact Assessment (EIA) study as a part of the process
to obtain Environmental Clearance (EC) for Navdurga Dyes and Chemicals for proposed expansion and/or
reduction in existing production capacity and addition of new products within existing premises located at Plot
No. C1B/414, GIDC Estate, Ankleshwar – 393002, Dist – Bharuch, Gujarat. The overall objective of any EIA study
is to identify and assess the adverse impacts of a project in the planning stage itself, so that necessary
mitigation measures to prevent or minimize these adverse impacts can be planned early and cost-effectively.
Table No. 1.1 – Name and Contact details for the Project
The latitude and longitude of the proposed project site are 21°37'14.75"N and 73°01'10.50"E
respectively.
Land is in possession with owner and project is located in the notified industrial area. Total land area of
2
the project is 704.00 m . Land document is attached as Annexure – 1. The topography of the project
CH 1: INTRODUCTION
1
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
2 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
site for project is plain terrain. There is no change in land use/topography as the project is already
There is no any National Park, Forest, Wild Life Sanctuary and Eco Sensitive Area are presented within 10
Key infrastructure such as hospitals, schools, bank, places of worship and social/ community facilities
such as parks, market, playground etc. education, health care, community development, income
distribution, employment and social welfare are available in nearby area of the project site.
Industry has valid Consolidated Consent & Authorization (CC&A) order No: AWH – 92598, dated:
24/04/2018 which is valid up to 25/02/2023 for their existing products. Existing CC&A is attached as
Annexure – 2.
As per the provision of the S. O. 1533, it is necessary to get EC for the proposed expansion project prior to
commissioning of the project activities. Hence it is necessary to seek EC by applying to State Level Environment
Impact Assessment Authority (SEIAA), Gujarat. Therefore the EIA is required to comply with the provisions of S.
O. 1533 made for Category 5 (f) – B of the notification.
As part of EC process, Navdurga Dyes and Chemicals has submitted Form-1 (as per the EIA Notification, 2006, as
amended), along with Prefeasibility Report and proposed Terms of References (ToR) for carrying out
Environmental Studies, to the SEIAA, Gujarat with proposal No: SIA/GJ/IND2/30502/2018 and File No:
SIA/GJ/17702/2019. Presentation for approval of proposed ToR was done at the State Expert Appraisal
Committee (SEAC), Gandhinagar on 05/03/2019. SEAC has recommended the proposed TOR to SEIAA and
SEIAA has approved the ToRs vide Letter No. SEIAA/GUJ/TOR/5(f)/685/2019 dated 04/05/2019. Since, the
project is located in notified industrial area, public hearing is not required as per paragraph 7 (i) (III) (i) (b) of the
EIA Notification, 2006. The scope of study includes detailed characteristics of environmental components for
one season. For the purpose of environmental assessment, the villages in the surrounding areas have been
surveyed and relevant data has been collected.
Sr.
EIA Structure Contents
No.
Purpose of the report
Identification of project & project proponent
Brief description of nature, size, location of the project and its
1. Introduction
importance to the country, region
Scope of the study – details of regulatory scoping carried out (As per
TOR).
Condensed description of those aspects of the project (based on
project feasibility study), likely to cause environmental effects.
Description contains the details of the following:
o Type of project
o Need for the project
o Location (map showing general location, specific location, project
boundary & project site layout)
o Size or magnitude of operation
2. Project Description
o Proposed schedule for approval and implementation
o Technology and process description
o Project description including drawings showing project layout,
components of project etc.
o Schematic representations of the feasibility drawings which give
information important for EIA purpose.
o Description of mitigation measures incorporated into the project to
meet environmental standards.
Study area, period, components & methodology.
Description of the
3. Establishment of baseline for valued environmental components, as
Environment
identified in the scope.
CH 1: INTRODUCTION
3
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
4 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr.
EIA Structure Contents
No.
Study Period: March 2019 to May 2019
Base maps of all environmental components.
Details of Investigated Environmental impacts due to project location,
possible accidents, project design, project construction and regular
operations.
Anticipated Environmental Measures for minimizing and / or offsetting adverse impacts identified.
4. Impacts & Mitigation Irreversible and Irretrievable commitments of environmental
Measures components
Assessment of significance of impacts (Criteria for determining
significance, Assigning significance)
Mitigation measures
In case, the scoping exercise results in need for alternatives:
o Description of each alternative
Analysis of Alternatives
5. o Summary of adverse impacts of each alternative
(Technology & Site)
o Mitigation measures proposed for each alternative and
o Selection of alternative
Technical aspects of environmental monitoring for the effectiveness of
Environmental Monitoring mitigation measures (incl. Measurement methodologies, frequency,
6.
Program location, data analysis, reporting schedules, emergency procedures,
budget & procurement schedules)
Risk Assessment
7. Additional Study Public Consultation
Disaster Management
Improvements in the physical infrastructure
Improvements in the social infrastructure
8. Project Benefits
Employment potential – Skilled, Semi-skilled and unskilled
Other tangible benefits of the project.
Environmental Cost Benefit If recommended at the Scoping stage
9.
Analysis
Description of the administrative aspects of ensuring that mitigation
measures are implemented and their effectiveness monitored, after
approval of the Clearance. The Chapter consist of:
o Mitigation measures for impacts
Environmental Management
10. o Pollution Prevention Plan
Plan (EMP)
o Greenbelt Development Plan
o Waste management plan
o Environment Management Cell
o Budgetary Provisions for EMS
Overall justification for implementation of the project
11. Summary & Conclusion Explanation of how, adverse effects have been mitigated.
Description of brief of EIA report & Conclusion
Disclosure of Consultant The names of the Consultants engaged with their brief resume and
12.
Engaged nature of Consultancy rendered
1.6 SUMMARY
The Company is in the production of various dyes since past few years. Due to demand of existing as well as
proposed products in the present market scenario, company will need to proposed expansion and/or reduction
in existing production capacity and addition of new products within existing premises in the various dyes
manufacturing. Proposed expansion and/or reduction in existing production capacity and addition of new
products having total capacity of 5.0 MT/Month (Either individual or Total production shall not exceed 5.0
MT/Month) and it is located at Ankleshwar GIDC. Industry has valid CC&A order No: AWH – 92598, dated:
24/04/2018 which is valid up to 25/02/2023 for their existing products. Proposed project falls under Schedule 5
(f) i.e. Synthetic organic chemicals industry under Category B located in a Notified Industrial Area/Estate.
Navdurga Dyes and Chemicals has submitted Form-1 along with Prefeasibility Report and proposed ToR for
carrying out Environmental Studies, to the SEIAA, Gujarat with proposal No: SIA/GJ/IND2/30502/2018 and File
No: SIA/GJ/17702/2019. Presentation for approval of proposed ToR was done at the SEAC, Gandhinagar on
05/03/2019. SEAC has recommended the proposed TOR to SEIAA and SEIAA has approved the ToRs vide Letter
No: SEIAA/GUJ/TOR/5(f)/685/2019 dated 04/05/2019. Since, the project is located in notified industrial area,
public hearing is not required as per paragraph 7 (i) (III) (i) (b) of the EIA Notification, 2006.
CH 1: INTRODUCTION
5
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
6 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Table No. 2.1 – Four Corner Latitude and Longitude of the Project Site
Figure No. 2.1 – Map Showing General and Specific Location of Project Site
CH 2: PROJECT DESCRIPTION
7
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
8 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Figure No. 2.2 – Short View of the Project site with Project Boundary
2.3.2 Site connectivity
The project location is well connected with road, rail and air route and details are mentioned in the Table No.
2.2. Toposheet showing the connectivity of the project site is mentioned in Figure No. 2.3.
CH 2: PROJECT DESCRIPTION
9
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
10 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Seismic Zone: South Gujarat is fall under seismic zone – III, which is classified as Moderate Damage Risk Zone.
Drainage: The drainage in the region is controlled to a large extent by the Narmada River and their tributaries,
which generally are seasonal in nature. There are several water bodies present within the study area of the
project. Drainage map is shown in Figure No. 2.5.
Geomorphology: Geo-morphologically, the project site is located south of the Narmada River which is about
7.31 km from site. The surrounding landscape is adulatory and characterized by small hillocks gentle slope show
ever; the project site is a flat land and comprising soils & alluvium.
Hydrogeology:
The geology of the district with vast area affected by inherent/coastal salinity, presents a complex
hydrogeological pattern. Hydrogeological map is shown in figure no. 2.6. The hard rocks, the semiconsolidated
Cretaceous, and Tertiary formations and unconsolidated alluvial deposits, all comprise multi – aquifer systems
thereby presenting unconfined as well as confined groundwater conditions in the entire district.
Tertiary formations are inherently saline and contain poor quality of groundwater. Groundwater occurs under
unconfined conditions in the limestone and sandstone aquifers of Bagh beds. Occurrence and movement of
groundwater is restricted mainly to the fractures and joints in the lime stones and sandstones. The discharge in
3
dug wells varies from 30 to 50 m /day. The bagh beds, where overlain by Deccan Trap are likely to yield
groundwater under confined conditions. The Deccan Trap have given rise to multi-layered stratified aquifers.
Each individual flow comprises two distinct units, namely the upper vesicular basalt and the lower massive
basalt.
The massive basalt is hard and compact with primary porosity but the vesicular basalts exhibit porosity. The
movement of groundwater is therefore controlled by the secondary porosity developed by the presence of
fractures and joints. The paleo weathering which is invariably observed at depth near the top of every flow, has
given rise to good aquifers at depth.
The yield of the dug wells in Deccan traps, which range in depth from 5 to 25 m bgl, sustain pumping from 1/2
hour to 10 hour with discharge varying from 200 to 1200 litre per minute (LPM) for drawdown of 4 to 7 m. Bore
well tapping deeper zones down to 150m below ground level (bgl), have yielded 100 to 600 LPM for a
drawdown of 6 to 15 m. The sandstone are the main aquifers in the Tertiary formations but the limestone also
yield significant quantities of groundwater wherever karstic development have taken place. Deep tube well
tapping the Tertiary formations is capable of yielding 300 to 3000 LPM of water for meager drawdown of 1 to 7
m. The alluvium formations in the western most part of the area do not constitute potential aquifers on account
of inferior quality of water.
(Source: Ground Water Brochure Bharuch District, March - 2014)
CH 2: PROJECT DESCRIPTION
11
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
12 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
CH 2: PROJECT DESCRIPTION
13
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
14 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Existing power requirement will be sufficient for the proposed expansion project.
2.4.3 Fuel
Name of the fuel, quantity and fuel used for are mentioned in the below Table No. 2.4:
Table No. 2.4 – Name of the fuel, quantity and fuel used for
2.4.4 Water
Water requirement during construction phase will be 1.00 KLD as minor construction activity will be carried out.
The water requirement is being/will be fulfilled by the GIDC, Ankleshwar. During Operation Phase, water
requirement for the project will be met by the GIDC. No ground water shall be drawn for the proposed
expansion project. Water supply permission from GIDC is attached as Annexure – 3. Details of water
consumption and productwise water consumption mentioned in Table No. 2.5 and Table No. 2.6 respectively.
Table No. 2.5 – Total Water Consumption
CH 2: PROJECT DESCRIPTION
15
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
16 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
2.4.5 Manpower
Manpower requirement during construction phase will be 10 Nos. as minor construction activity will be carried
out. During Operation Phase, manpower will be employed directly and indirectly through contracts, services, etc.
Local person based on their qualification and skill will be hired for various industrial activities. 5 nos. of
manpower is required during existing production activity and 4 nos. of manpower is required during proposed
production activity. After proposed expansion, Total 9 nos. of manpower will be required during operation
phase.
Existing Proposed
Sr.
No. Quantity Quantity
Name of the equipment Capacity Name of the equipment Capacity
(Nos.) (Nos.)
1. SS Vessel 2 3.5 kl 14 mm MS Storage tank 1 10 kl
2. SS Vessel 1 1.2 kl MS vessel 1 3.5 kl
3. MSRL Centrifuge 1 36‘‘ HDPP vessel 1 5 kl
4. Boiler 1 300 kgs Boiler RBL 1 500 kgs
5. Filter press 1 36‘‘ * 36‘‘ Filter press 1 36‘‘ * 36‘‘
6. Pump 3 --- Pump 2 ---
Existing Proposed
Sr.
No. Quantity Quantity
Name of the equipment Capacity Name of the equipment Capacity
(Nos.) (Nos.)
7. Tray Dryer 1 200 Tray Dryer 1 200
8. Filter Trolley 1 --- Distillation unit 1 5 kl
9. MSRL – BL Vessel 1 3 kl HDPP tank 2 12 kl
10. MSRL – BL Vessel 1 6 kl
11. MSRL – BL Vessel 1 3 kl
12. Nutch filter 2 ---
13. Cooling system 1 ---
14. Air compressor 1 7 HP
15. ETP 1 ---
16. Electricity penel board 1 ---
17. S.S Clarifier 1 ---
Quantity (MT/Month)
Sr. End use of the
Name of Product CAS No./CI Name Total after
No. Existing Proposed products
Expansion
EXISTING PRODUCT
Reactive Blue MR 13324-20- These days are used
1.
And/or 4/Reactive Blue – 4 in plant, textiles,
garments and other
industry sectors
widely used for
18976-74- 0.5
Reactive Yellow dyeing and printing
2. 4/Reactive Blue – of cellulose textiles
M4R And/or 5.0 5.0
14 like linen cotton,
MT/Month MT/Month
viscose and
(Either (Either
polynosic rayon.
individual individual
Acid Blue 25 6408-78-2/Acid or Total or Total Acid Dyes are used
3.
And/or Blue 25 production production to dye protection
Acid Yellow GL 61901-51-7/Acid shall not shall not fibers such as wool,
4. exceed 5.0 exceed 5.0 angora, cashmere,
And/or Yellow 114
MT/Month) MT/Month) and silk, as well the
Acid Black – 1 1064-48-8/Acid milk protein fiber
5. 5.0
And/or Black–1 called silk little, the
Acid Orange – RL 1320-07-6/Acid soy protein fiber
6.
And/or Orange – 24 called soy silk, and
the synthetic
Acid Brown 2RL 148262-90-2/Acid
7. polyamide fiber
And/or Brown – 45
CH 2: PROJECT DESCRIPTION
17
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
18 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Quantity (MT/Month)
Sr. End use of the
Name of Product CAS No./CI Name Total after
No. Existing Proposed products
Expansion
nylon in textile
industries.
Basic dyes are used
on cotton, paper,
leather, wool, silk,
Basic Violet – 1 8004-87-3/Basic
8. 9.50 and nylon. They are
(Liquid) And/or Violet – 1 (Liquid)
also used as pH
indicators and as
biological stains.
APMS (2 – Amino In Manufacturing
Phenyl Hydroxy Dyes
9. 98-30-6/-- 3.0
Methyl Sulfone)
And/or
PROPOSED PRODUCT
1 – Amino – 4 In manufacturing
Bromo Intermediates dyes
1. Anthraquinone – 2 7726-95-6/-- 0.0
Sulfamic Acid
And/or
Acid Dyes are used
to dye protection
fibers such as wool,
angora, cashmere,
and silk, as well the
milk protein fiber
10097-74-8/Acid
2. Acid Yellow 2GLN 0.0 called silk little, the
Yellow – 59
soy protein fiber
called soy silk, and
the synthetic
polyamide fiber
nylon in textile
industries.
2.6 RAW MATERIALS
The raw materials required for the proposed expansion products will be easily available in the domestic market
and all the raw materials will be transported through existing road network in standard packing. Product wise
raw material consumption is shown in Table No. 2.9.
CH 2: PROJECT DESCRIPTION
19
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
20 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
CH 2: PROJECT DESCRIPTION
21
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
22 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Condensation: MPDSA, Bromamine Acid, Soda Ash and water are charged in S.S. Vessel for condensation.
Above mass is condensed with Cyanuric Chloride and maintain the temperature with Ice.
Isolation: The mass is than isolated with Salt. The mass is then filtered followed by drying and pulverization to
obtain finished product.
Chemical Reaction:
Mass Balance:
Input Kg Output Kg
MPDSA 60 Reaction Mass 1374
Bromamine Acid 100
Soda Ash 39 Condensation
Water 400
Cynuric Chloride 75
Ice 700
Input Kg Output Kg
Salt 250 Reaction Mass 1624
Reaction Mass 1374 Isolation
Input Kg Output Kg
Reaction Mass 1624 Effluent 1100
Isolation
Filtration Reaction Mass 524
Input Kg Output Kg
Reaction Mass 524 Evaporation Loss 324
Isolation
Drying Reaction Mass 200
Input Kg Output Kg
Reaction Mass 200 Product 200
Pulverisation
Process Description:
Charge Sulpho Tobias Acid in vessel and add HCl, NaNO 2 and water for Diazotization. Maintain the temperature
with Ice. N-Methyl J-Acid and Soda Ash are dissolved in water. Above diazotized and dissolved mass are
coupled in coupling vessel. Than condensed with Cynuric Chloride in presence of Soda Ash. The mass is then
isolated and filtered followed by drying and pulverization to obtain finished product.
CH 2: PROJECT DESCRIPTION
23
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
24 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Chemical Reaction:
Mass Balance:
2.7.3 Acid Blue 25
Process Description:
Condensation: Aniline oil, Bromamine acid, Soda ash and water are charged in Vessel for Condensation. The
mass is then filtered followed by drying and pulverization to obtain finished product.
Chemical Reaction:
Mass Balance:
Input Kg Output Kg
Bromine Acid 325 Reaction Mass 1625
Aniline Oil 80
Soda Ash 120 Condensation
Water 1100
Total 1625 Total 1625
Input Kg Output Kg
Reaction Mass 1625 Effluent 1000
Filtration Reaction Mass 625
Total 1625 Total 1625
Input Kg Output Kg
Reaction Mass 625 Drying Loss 300
Reaction Mass 325
Total 625 Total 625
Input Kg Output Kg
Reaction Mass 325 Pulverisation Product 325
CH 2: PROJECT DESCRIPTION
25
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
26 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Process Description:
Diazotization: Amino Benzoic Acid is charged in vessel and NaNO2, HCl and water added. Maintain the
temperature with Ice.
Dissolution: MCPMP, Caustic Lye and water are charged in vessel and stirring for complete dissolution.
Coupling: Above both diazotized masses is coupled in coupling vessel. The mass is then filtered followed by
drying and pulverization to obtain finished product.
Chemical Reaction:
Mass Balance:
Input Kg Input Kg
Amino Benzoic Acid 100 MCPMP 100
HCL 40 Water 400
Sodium Nitrite 55 Caustic Lye 25
Ice 500 Diazotisation Dissolution
Water 500
Input Kg Output Kg
Reaction Mass 1720 Coupling Reaction Mass 1720
Input Kg Output Kg
Reaction Mass 1720 Reaction Mass 1720
Heating
Input Kg Output Kg
Reaction Mass 1720 Effluent 1300
Filtration Reaction Mass 420
Total 1720 Total 1300
Input Kg Output Kg
Reaction Mass 420 Drying Loss 120
Reaction Mass 300
Total 420 Total 420
Input Kg Output Kg
Reaction Mass 300 Pulverisation Product 300
Process Description:
6-Nitro Diazo and HCl are dissolved in presence of water and Ice. Beta Naphthol and Caustic Lye are dissolved
in presence of water and Ice. Above both dissolved mass are coupled in coupling vessel and then the mass is
isolated with Salt. The mass is then filtered followed by drying and pulverization to obtain finished product.
Chemical Reaction:
Mass Balance:
Input Kg Input Kg
4NAP 145 Beta Napthol 140
HCL 150 Caustic Lye 200
Ice 500 Ice 500
Water 600 Diazotisation Dissolution Water 600
Input Kg Output Kg
Reaction Mass 2835 Coupling Reaction Mass 2835
Input Kg Output Kg
Reaction Mass 2835 Reaction Mass 3335
Salt 500
Isolation
Input Kg Output Kg
Reaction Mass 3335 Effluent 2500
Filtration Reaction Mass 835
Total 3335 Total 2500
Input Kg Output Kg
Reaction Mass 835 Drying Loss 410
Reaction Mass 425
Total 835 Total 835
Input Kg Output Kg
Reaction Mass 425 Pulverisation Product 425
CH 2: PROJECT DESCRIPTION
27
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
28 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Process Description:
Take Amino Phenol Methyl Sulfon (APMS) in vessel and charge HCl, NaNO2 and water for Diazotization.
Maintain the temperature with Ice. Take Meta Chloro PMP, Caustic Lye, Soda Ash and water in vessel and start
stirring. Maintain the temperature with Ice. Above diazotized and dissolved mass are coupled in coupling vessel.
The mass is than isolated with Salt. The mass is then filtered followed by drying and pulverization to obtain
finished product.
Chemical Reaction:
Material Balance:
Input Kg Input Kg
APMS 188 MCPMP 188
HCL 175 Caustic Lye 125
Sodium Nitrite 70 Ice 500
Water 500 Diazotisation Dissolution Water 500
Ice 500 Soda Ash 25
Input Kg
Water 500 Output Kg
Ice 300 Coupling Reaction Mass 3571
Reaction Mass 2771
Total 3571 Total 3571
Input Kg Output Kg
Reaction Mass 3571 Reaction Mass 3946
Salt 375
Isolation
Input Kg Output Kg
Reaction Mass 3946 Effluent 2800
Filtration Reaction Mass 1146
Total 3946 Total 2800
Input Kg Output Kg
Reaction Mass 1146 Drying Loss 646
Reaction Mass 500
Total 1146 Total 1146
Input Kg Output Kg
Reaction Mass 500 Pulverisation Product 500
Process Description:
Amino Phenyl Methyl Sulfone is charged in vessel and HCL, NaNO2 and water are added. Maintain the
temperature with Ice. Amino-7-Naphthol Chloro Formete, Meta Chloro PMP, Caustic Lye, Soda Ash and water
are charged in vessel and start stirring for complete dissolution. Maintain the temperature with Ice. Above
diazotized and dissolved mass are coupled in coupling vessel. The mass is than isolated with Salt. The mass is
then filtered followed by drying and pulverization to obtain finished product.
Chemical Reaction:
Mass Balance:
Input Kg Input Kg
Amino Benzoic Acid 227 MCPMP 125
HCL 90 Amino 7-Napthol 75
Sodium Nitrite 125 Ice 400
Water 780 Diazotisation Dissolution Water 700
Ice 400 Soda Ash 35
Caustic Lye 115
Total 1622 Total 1450
Input Kg
Water 480 Output Kg
Ice 300 Coupling Reaction Mass 3852
Reaction Mass 3072
Total 3852 Total 3852
Input Kg Output Kg
Reaction Mass 3852 Reaction Mass 4302
Salt 450
Isolation
Input Kg Output Kg
Reaction Mass 4302 Effluent 3150
Filtration Reaction Mass 1152
Total 4302 Total 4302
Input Kg Output Kg
Reaction Mass 1152 Drying Loss 652
Reaction Mass 500
Total 1152 Total 1152
Input Kg Output Kg
Reaction Mass 500 Pulverisation Product 500
CH 2: PROJECT DESCRIPTION
29
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
30 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Process Description:
Take Acetic Acid, Methane Base, Mono Methyl Aniline and Chloranil in reaction vessel and pass oxygen.
o
Maintain the temperature to 50-55 C for 12 hours and then allow to cool down to room temperature. This is a
single step reaction and there is no water consumption in process and there is no generation of waste water.
Chemical Reaction:
Mass Balance:
Input Kg
Acetic Acid 200 Output Kg
Methane Base 80 Reaction Vessel Evaporation Loss 140
Mono Methyl Aniline 100 Product 539
Di-Methyl Aniline 110 Total 679
Chlornil 4
Oxygen 45
Water 140
Total 679
Process Description:
In SS Reactor charge water and Para Chloro Nitrobenzene Sulfinic Acid (Na-Salt) stir and heat to 60°-65° C
temp. for 1 hour. Now charge Mono Chloro Acetic Acid and simultaneously adjust pH 7.0 to 7.5 by Caustic Lye
solution at 65°C temp. Then heat to 90°-95°C temp. for 6 hours at pH 7.0 to 7.5. Maintain for 4 hours then cool
to 40°-45°C. Product precipitation takes place. Filter the reaction mass, wash with water followed by centrifuge.
In another MS Reactor charge water. Then charge Caustic Lye solution. Heat up to 100°C and maintain this
temp. for 5 hours. Then cool to 60°C temp. and charge Sodium Hydrosulfide solution and heat to 95°-100°C
temp for 10 hours. Then cool to 30°-35°C temp. Now charge Sodium Bisulphite to remove excess Sodium
Hydrosulfide from process. Cool to 20°C and adjust pH 6.5-7.0 by dil. HCl. Stir at 20°C for 2 hours. Product
precipitation takes place. Filter & Centrifuge the reaction mass followed by drying at 50°-60°C temp. to obtain
Finished product APMS.
Chemical Reaction:
Material Balance:
Input Kg Output Kg
Para Chloro Nitrobenzene 300 Reaction Mass 1440
Sufinic Acid
Mono Chloro Acetic Acid 120
Caustic Lye olu. (50%) 520 SS Reactor
Water 500
Input Kg Output Kg
Reaction Mass 1440 Effluent 1000
Water 100 Isolation
Filtration Reaction Mass 540
Input Kg Output Kg
Caustic Lye olu. (50%) 150 Reaction Mass 1765
Water 700
Sodium Hydrosulfide Solu. 225 SS Reactor
Sodium Bisulfite 50
Dil. HCL 100
Reaction Mass 540
Total 1765 Total 1765
Input Kg Output Kg
Reaction Mass 1765 Effluent 1100
Centrifuge Reaction Mass 665
Input Kg Output Kg
Reaction Mass 665 Loss 465
Drying Product 200
CH 2: PROJECT DESCRIPTION
31
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
32 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Proposed Products:-
2.7.10 1 – Amino – 4 – Bromo Anthraquinone – 2 - Sulfamic Acid
Process Description:
In MS Sufonator charge ODCB and 1 – Amino Anthraquinone. Stir for 2 hours. Then charge Chloro Sulphonic
o o o
Acid. Stir and heat to 105 C to 120 C for 2 hours. Maintain at 120 C for 4 hours. Then cool to RT. Drown in water
o o
in Distillation unit and neutralize to pH 5.0. distilled out ODCB at 105 C – 107 C by applying steam and recover
ODCB in receiver. Now transfer whole reaction mass transfer to MSRL – BL vessel. Now charge slowly a solution
of sodium bromate and sodium bromide prepared in water. Stir for 2 hours and then adjust pH 6.5 to 7.0 by
soda ash solution. Then charge salt and stir for 4 hours. Precipitation takes place and check spot test. Then
o o
filtered the reaction mass through filter press. Wet cake dries at 80 C – 85 C followed by pulverization to obtain
finished product.
Chemical Reaction:
Mass Balance:
Input Kg Output Kg
Ortho Dichloro Benzene (Fresh) 30 Reaction Mass 904
Recovered ODCB 570
1 - Amino Anthraquinone 184 Condensation
Chlorosulfonic Acid 120
Input Kg Output Kg
Reaction Mass 314
Reaction Mass 904 Isolation
Distillation Recovery ODCB 570
Con. Water 20
Total 904 Total 904
Input Kg Output Kg
Water (Fresh) 1980
Con.Water 20 Isolation
MSRL BL Vessel Reaction Mass 2544
Sodium Bromate 40
Sodium Bromide 80
Soda Ash 60
Salt 50
Reaction Mass 314 Total 2544
Total 2544
Input Kg Output Kg
Reaction Mass 2544 Effluent 2200
Isolation
Filtration Reaction Mass 344
Input Kg Output Kg
Reaction Mass 344 Evaporation Loss 74
Drying Reaction Mass 270
Input Kg Output Kg
Reaction Mass 270 Product 270
Pulverisation
Chemical Reaction:
Mass Balance:
Input Kg Output Kg
Anthranilic Acid 150 Reaction Mass 1228
Sodium Nitrite 78
HCl 250 Preparation of Antranilic Acid
Ice 750
Input Kg Output Kg
PMP 194
Sodium Acetate 115 Reaction Mass 3787
Ice 950
Water 950 Coupling in Alkaline Medium
Formic Acid 350
Reaction Mass 1228
Total 3787
Total 3787
Input Kg Output Kg
Reaction Mass 3787
BCS 208 Isolation
Metalization Reaction Mass 3995
Input Kg Output Kg
Reaction Mass 3995
Caustic Flakes 150 Drying
Neutralization Reaction Mass 4145
Input Kg Output Kg
Reaction Mass 4145 Reaction Mass 4745
Disperse Agent 600 Cooling
Input Kg Output Kg
Reaction Mass 4745 Loss 3745
Drying Reactive Mass 1000
Input Kg Output Kg
Reaction Mass 1000
Standardization & Packing Product 1000
CH 2: PROJECT DESCRIPTION
33
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
34 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Sr. Stack attached Stack height Fuel used & Air Pollution
Permissible Limits
No. to (m) Its Quantity Control Equipment
A. Existing
3
Natural Gas: PM < 150 mg/Nm
Boiler – 1 Nos. Adequate Stack
1. 12 1,000 SO2< 100 ppm
(300 kg/hr.)* Height
SCM/Month NOx< 50 ppm
B. Proposed
3
Natural Gas: PM < 150 mg/Nm
Boiler – 1 Nos. Adequate Stack
1. 12 3,400 SO2 < 100 ppm
(500 kg/hr.) Height
SCM/Month NOx < 50 ppm
*After proposed expansion, existing boiler of 300 kg/hr will be dismantled.
Process Emission: There is no process gas emission from existing manufacturing activity. After proposed
expansion process gas emission and its control measures are mentioned in Table No. 2.10 (b).
Specific source of
Sr. Stack/Vent Air Pollution Control Permissible
emission (Name of the Parameter
No. Height (m) Equipment Limit
product & Process)
Existing
There is no process gas emission from existing manufacturing activity.
Proposed
Chlorosulphonic Storage Closed Loop Two Stage Alkali 3
1. HCl 20 mg/Nm
Tank Deeping System Scrubber
CH 2: PROJECT DESCRIPTION
35
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
36 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Figure No. 2.9 – Water Balance Diagram (After Proposed Expanstion, KLD)
Table No. 2.13 – Size of different units of ETP
Table No. 2.14 – Hazardous/Solid Waste Generation, Source, Category, Quantity and Diposal
CH 2: PROJECT DESCRIPTION
37
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
38 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
2.11 SUMMARY
The proposed expanstion project is a manufacturing unit for Dyes, due to demand of existing as well as
proposed products in the present market scenario, company will need to proposed expansion and/or reduction
in existing production capacity and addition of new products within existing premises in the various dyes
manufacturing. Proposed expansion and/or reduction in existing production capacity and addition of new
products having total capacity of 5.0 MT/Month (Either individual or Total production shall not exceed 5.0
MT/Month) and it is located at Plot No: C1B/414, GIDC Estate, Ankleshwar – 393002, Dist.: Bharuch, Gujarat.
Industry has valid CC&A order No: AWH – 92598, dated: 24/04/2018 which is valid up to 25/02/2023 for their
existing products. No National Park/ Wildlife Sanctuary/ Marine Sanctuary are located within 10 km radius of
proposed expansion project. Project cost after proposed expansion is Rs. 84 Lakhs, out of which Rs. 16.00 Lakhs
are allotted for EMS. Existing power 65 KVA is being /will be sufficient for the proposed expansion project.
Source of power is DGVCL. Total 9 nos. of manpower will be required after proposed expansion project during
operation phase. During opertaional phase, water requirement will be 9.70 KLD and it will be met from GIDC.
Wastewater generation during operation phase from industrial activities will be 3.80 KLD send to existing ETP
and finally discharged to CETP – ETL for further treatment after achieving all norms in permissible limit. 12 m
stack heigh is being/will be attached with the Boiler for proper dispersion of pollutants in the atmosphere.
Existing as well as after proposed expanstion natural gas is being/will be used as a fuel. There is no process gas
emission from the existing production activity. After proposed expansion, HCl gas will be generated from the
chlorosulphonic storage tank and pollution will be controlled by provided Two Stage Alkali Scrubber.
Hazardous/Solid waste is being/will be collected, stored and disposed as per the Hazardous and Other Waste
2 2
(Management and Transboundary Movement) Rules, 2016. Total plot area is 704.00 m and 234.32 m will be
developed as Greenbelt. Once all the regulatory clearances for the project will be approved, the estimated time
for the project completion is 6 months.
CH 2: PROJECT DESCRIPTION
39
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
40 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
3.3 METHODOLOGY
The baseline environmental study was conducted as per the guidelines of Ministry of Environment, Forest &
Climate Change (MoEF&CC) and TOR issued by SEIAA, Gujarat. The baseline environmental study was carried
out for the various environmental components viz, Air, Water, Noise, Soil, Ecology & Biodiversity and Socio
Economic. During the study, 5 km radius was considered as core zone and rest 5 km radius was considered as
buffer zone. All the locations have been selected within 10 km radius from the project site as per the
requirement of TOR and environmental samples were collected from the selected locations of the study area.
Sampling
Sr.
Attributes Locations within Frequency during
No. Parameters
10 km study area study period
PM2.5, PM10, SO2, NOx, VOC, Twice a week, 24
1. Ambient Air Quality 9 locations
HCl hourly
2. Noise 7 Locations Noise Levels in dB(A)
Physical, Chemical,
Grab samples
3. Ground Water Microbiological and Heavy
from 6 Locations
Metal
Physical, Chemical,
Grab samples
4. Surface Water Microbiological and Heavy
from 5 Locations
Metal
Once
Physical, Chemical
5. Soil Quality 6 Locations
Characteristics, Soil Texture
6. Land Use & Land Cover Existing Land use pattern
7. Ecological & Biodiversity Data Within 10 km Existing Flora & Fauna
radius of study Socio-economic
8. Socio-Economic Data area characteristics of the
affected area
Sr. Methods
Attributes
No. Sampling/Preservation Analysis
As per IS: 5182 & AWMA. As per IS:5182, CPCB & AWMA
1. Ambient air quality Instrument operated as per it‘s
manual
2. Noise Instrument : Noise level meter Survey carried out as per CPCB guideline.
3. Ground Water Standard Methods for Examination IS 3025 & Standard Methods for
of Water and Wastewater (APHA), Examination of Water and Wastewater
4. Surface Water nd
22 edition, 2012
nd
(APHA), 22 edition, 2012
IS 2720, Soil Testing in India IS 2720, Laboratory developed Method
(Department of Agriculture and as per NABL requirement and Book - Soil
5. Soil Quality
Cooperation). Testing in India (Department of
Agriculture and Cooperation).
Land Use & Land Primary data by site visit and Primary data by site visit and verified by
6.
Cover verified by reviewing various reviewing various literature, internet
7. Ecological Data literature, internet
Socio-Economic Primary Survey and verified with Primary Survey and verified with Census
8.
Data census of India 2011 of India 2011
3.5 MICROMETEOROLOGY
Bharuch has a tropical savanna climate, moderated strongly by the Sea to the Gulf of Cambay. The summer
begins in early March and lasts till June. April and May are the hottest months. Monsoon begins in late June and
normally the city receives about 873 millimeters (34 inch) of rain by the end of September. October and
November see the retreat of the monsoon and a return of high temperatures till late November. Winter starts in
December and ends in late February. Air borne pollutants is dispersed by atmospheric motion. Knowledge of
these motions which range is scale from turbulent diffusion to long-range transport by weather systems. It is
essential to simulate such dispersion and quality of impacts of air pollution on the environment.
The variations in temperature, humidity and wind speed during study period are represented graphically in
Figure No. 3.2 to 3.7.
O
Figure No. 3.2 – Graphical presentation of Min. & Max. Temperature ( C) for the March – 2019.
O
Figure No. 3.3 – Graphical presentation of Min. & Max. Temperature ( C) for the April – 2019.
O
Figure No. 3.4 – Graphical presentation of Min. & Max. Temperature ( C) for the May – 2019.
Figure No. 3.5 – Graphical presentation of Min. & Max. Humidity (%) for the March – 2019.
Figure No. 3.6 – Graphical presentation of Min. & Max. Humidity (%) for the April – 2019.
Figure No. 3.7 – Graphical presentation of Min. & Max. Humidity (%) for the May – 2019.
3.5.2 Wind Rose Diagram
Wind rose diagram is a graphical representation of the magnitude and direction of wind speed considering all
the directions. From the knowledge of wind rose one can easily predict the direction and extent of spreading of
the gaseous and particulate matter from the source. Wind direction and velocity data have been collected
during the study period. Dominant wind direction in the study period was from SW – NE during the study
period. Wind speed was observed from 0.0 to 11.5 km/h in the month of March, from 0.0 to 17.3 km/h in the
month of April and from 0.1 to 22.5 km/h in the Month of May, 2019. Month wise min., max., and average wind
speed data are mentioned in Table No. 3.3. Wind rose diagram has been prepared by using hourly wind
velocity and dominant wind direction data and is presented in Figure No. 3.8.
st st
Figure No. 3.8 – Wind Rose Diagram (1 March, 2019 to 31 May, 2019)
Avoidance of proximity of roads, construction activity or any other perturbing activity which may be
At the time of location selection previous micrometeorological data was referred and general wind pattern in
the study region was considered for the selection of minimum one location in the downwind direction.
However, ambient air monitoring locations were selected in all the directions looking towards the possibility of
change in wind pattern during the study period. Ambient Air Quality monitoring locations are presented in
Table No. 3.4 and Figure No. 3.9.
Table No. 3.4 – Ambient Air Monitoring Locations in the 10 km Study Region
Figure No. 3.9 – Ambient Air Monitoring Locations in the 10 km Study Region
Table No. 3.5 – Min., Max., Avg. & 98 Percentile Analysis value for Ambient Air
3
Parameter (µg/m )
Sampling Location 3
PM10 PM2.5 SO2 NOx CO Total VOC (ppm) HCl (mg/Nm )
Min. 72.38 37.57 14.66 18.39 BDL 0.40 BDL
Max. 79.84 41.73 18.38 21.67 BDL 0.60 BDL
A1
Avg. 76.19 39.50 16.32 20.12 BDL 0.50 BDL
98 Percentile 79.36 41.71 18.05 21.65 BDL 0.60 BDL
Min. 68.05 30.79 10.86 14.02 BDL 0.20 BDL
Max. 71.32 34.56 13.81 16.77 BDL 0.50 BDL
A2
Avg. 69.52 33.10 12.41 15.33 BDL 0.30 BDL
98 Percentile 71.27 34.40 13.66 16.66 BDL 0.50 BDL
Min. 69.52 33.51 13.64 15.56 BDL 0.30 BDL
Max. 75.82 38.41 15.98 18.87 BDL 0.60 BDL
A3
Avg. 73.30 35.82 14.80 17.50 BDL 0.40 BDL
98 Percentile 75.67 38.11 15.89 18.86 BDL 0.60 BDL
Min. 60.93 29.56 7.12 9.12 BDL 0.20 BDL
Max. 64.96 34.83 9.68 11.86 BDL 0.50 BDL
A4
Avg. 63.60 32.40 8.60 10.41 BDL 0.31 BDL
98 Percentile 64.94 34.79 9.67 11.79 BDL 0.50 BDL
Min. 62.31 28.06 9.86 11.47 BDL 0.10 BDL
Max. 65.88 33.82 12.81 15.88 BDL 0.40 BDL
A5
Avg. 64.41 31.30 11.49 13.68 BDL 0.20 BDL
98 Percentile 65.80 33.77 12.70 15.84 BDL 0.35 BDL
Min. 71.38 35.51 13.37 14.73 BDL 0.30 BDL
Max. 78.84 39.46 15.88 17.92 BDL 0.60 BDL
A6
Avg. 75.22 37.61 14.59 16.22 BDL 0.40 BDL
98 Percentile 78.60 39.36 15.84 17.89 BDL 0.60 BDL
Min. 66.19 29.56 7.12 9.31 BDL 0.20 BDL
Max. 68.31 34.83 10.86 12.86 BDL 0.50 BDL
A7
Avg. 67.12 32.50 9.10 11.31 BDL 0.30 BDL
98 Percentile 68.08 34.79 10.72 12.86 BDL 0.45 BDL
Min. 66.12 29.62 12.59 14.02 BDL 0.20 BDL
Max. 67.34 36.83 14.88 15.67 BDL 0.50 BDL
A8
Avg. 66.70 33.70 13.69 15.13 BDL 0.31 BDL
98 Percentile 67.33 36.67 14.85 15.62 BDL 0.50 BDL
Min. 68.12 24.62 8.12 11.47 BDL 0.10 BDL
Max. 69.29 34.83 11.86 15.88 BDL 0.40 BDL
A9
Avg. 68.51 31.82 10.10 13.60 BDL 0.20 BDL
98 Percentile 69.11 34.67 11.73 15.85 BDL 0.35 BDL
NAAQS 100 60 80 80 2000 --- 20
Figure No. 3.10 – Graphical Presentaiton of Min. & Max. value for PM10
Figure No. 3.11 – Graphical Presentaiton of Min. & Max. value for PM2.5
Figure No. 3.12 – Graphical Presentaiton of Min. & Max. value for SO2
Figure No. 3.13 – Graphical Presentaiton of Min. & Max. value for Nox
3.7 SOIL
Soil samples of 6 nos. were collected within 10 km radius to evaluate the baseline status of soil. Analysis was
carried out for the collected samples. Standard procedures have been followed for soil sampling and analysis.
Soil sampling locations are tabulated in Table No. 3.6 & presented in Figure No. 3.14 and soil sampling
analysis results are mentioned in Table No. 3.7.
Sr. Distance
Location Symbol Latitude Longitude Direction Selection Criteria
No. (km)
1. Project Site S1 21°37'14.75"N 73°01'10.50"E 0.00 ---- Non agriculture land
2. Kapodra S2 21°35'39.69"N 73°00'43.07"E 3.02 SSW Agriculture land
3. Motali S3 21°38'50.49"N 73°02'30.23"E 3.76 NE Agriculture land
4. Boidara S4 21°37'48.44"N 72°58'42.37"E 4.38 WWN Agriculture land
5. Mandwa Bujrg S5 21°40'35.45"N 73°03'51.20"E 7.72 NE Agriculture land
6. Sengpur S6 21°35'49.64"N 73°06'33.22"E 9.65 EES Agriculture land
Figure No. 3.14 – Soil Sampling Locations in the 10 km Study Region
Methodology Adopted for Thematic Data Extraction from the Satellite Imageries ERDAS image
processing 10.0 software and ARC/GIS 10.0 software were used for the project.
Survey of India reference map on 1:50,000 scales have been used for the preparation of base map and
geometric correction of satellite data.
Digital image processing techniques were applied for the mapping of the land use land cover classes of
the provided area from the satellite data.
LULC map of 10 km radius around the project site is presented in Figure No. 3.15. Land Use Statistic of 10 km
radius is presented in Table No. 3.9 and Figure No. 3.16.
Figure No. 3.16 – Pie Chart of Land Use Statistics (%) (10 km)
Predict the likely impacts of water quality due to the project and related activities.
The survey was undertaken and monitoring locations were finalized based on:
Water Samples for the analysis of physicochemical parameters were collected in plastic carboy and parameter
wise preserved onsite as per the technique defined in the book of Standard Methods for Examination of Water
nd
and Wastewater, APHA, 22 edition, 2012. Temperature, pH and DO were analyzed onsite and samples were
brought to the laboratory for the analysis of remaining parameters.
Table No. 3.10 – Ground Water Sampling Locations in the 10 km Study Region
3. Salinity ppt 0.45 1.17 0.21 1.96 0.95 0.52 --- ---
4. Electrical Conductivity µS/cm 1389 1496 680 3358 2048 1438 --- ---
6. Dissolved Oxygen mg/L 6.4 6.8 6.6 6.3 6.7 6.6 --- ---
7. Total Dissolved Solids (TDS) mg/L 826 899 451 2251 1372 978 500 2000
8. Total Suspended Solids (TSS) mg/L 1.2 2.8 8.7 1.0 2.3 5.9 --- ---
9. Total Solids (as TS) mg/L 827.2 927 459.7 2252 1374.3 983.9 --- ---
10. Chemical Oxygen Demand (COD) mg/L <1.0 <1.0 11.5 <1.0 <1.0 60.9 --- ---
11. Biochemical Oxygen Demand (BOD) mg/L <1.0 <1.0 3.4 <1.0 <1.0 19.1 --- ---
12. Chlorides (as Cl-) mg/L 249.8 245.9 117.9 1084.4 523.3 287.6 250 1000
13. Sulphates (as SO4-2) mg/L 143.9 161.1 175.1 495.2 159.6 291.4 200 400
14. Total Alkalinity (as CaCO3) mg/L 408.8 453.1 309.4 276.3 508.3 442 200 600
15. Total Hardness (as CaCO3) mg/L 239.2 193.2 165.6 380 828 395.6 300 600
16. Calcium Hardness mg/L 55.3 29.4 29.5 268.8 114.2 73.7 75 200
17. Magnesium Hardness mg/L 24.6 29.1 22.4 110.6 132.1 51.5 30 100
18. Ammonical Nitrogen (as NH3-N) mg/L BDL BDL BDL BDL BDL BDL --- ---
Drinking Water Specification IS
Sr. 10500:1992 (Reaffirmed 2012
Parameter Unit G1 G2 G3 G4 G5 G6
no.
Desirable Limit Permissible Limit
19. Copper (as Cu) mg/L BDL BDL BDL BDL BDL BDL 0.05 1.5
-
20. Fluoride (as F ) mg/L 0.53 0.71 0.74 0.93 0.62 0.59 --- ---
21. Total Iron (as Fe) mg/L 0.8 BDL BDL BDL BDL 0.62 0.3 No Relaxation
22. Phenol (as C6H5OH) mg/L BDL BDL BDL BDL BDL BDL 0.01 0.02
23. Oil & Grease mg/L BDL BDL BDL BDL BDL BDL --- ---
27. Zinc (as Zn) mg/L BDL BDL BDL BDL BDL BDL 5 15
28. Lead (as Pb) mg/L BDL BDL BDL BDL BDL BDL --- ---
29. Sodium (as Na) mg/L 293 284 344 693 288 255 --- ---
30. Potassium (as K) mg/L 2.39 3.89 3.95 25.35 5.41 5.11 --- ---
31. Arsenic (as As) mg/L BDL BDL BDL BDL BDL BDL --- ---
32. Cadmium (as Cd) mg/L BDL BDL BDL BDL BDL BDL --- ---
33. Colour Pt. Co. Scale <5 <5 <5 <5 <5 <5 5 25
34. Odour --- Agreeable Agreeable Agreeable
Table No. 3.12 – Surface Water Sampling Locations in the 10 km Study Region
Sr. Selection
Location Symbol Latitude Longitude Distance Direction
No. Criteria
1. Ankleshwar GIDC SW1 21°36'44.15"N 73°00'28.00"E 1.57 SW Lake
2. Amlakhadi SW2 21°35'44.10"N 73°00'38.15"E 2.97 SSW Khadi
3. Amravati River SW3 21°38'04.40"N 73°03'52.83"E 4.82 EEN River
4. Kosamdi SW4 21°34'46.69"N 73°02'25.35"E 5.00 SSE Lake
5. Narmada River SW5 21°41'17.96"N 73°00'12.34"E 7.83 NNW River
Figure No. 3.18 – Surface Water Sampling Locations in the 10 km Study Region
Table No. 3.13 – Surface Water Analysis Results
1. Immediate investigative action shall be taken if either E.coli or total coliform bacteria are detected. The
minimum action in the case of total coliform bacteria is repeat sampling; if these bacteria are detected
in the repeat sample, the cause shall be determined by immediate further investigation.
2. Although, E. coli is the more precise indicator of fecal pollution, the count of thermotolerant coliform
bacteria is an acceptable alternative. If necessary, proper confirmatory tests shall be carried out. Total
coliform bacteria are not acceptable indicators of the sanitary quality of rural water supplies, particularly
in tropical areas where many bacteria of no sanitary significance occur in almost all untreated supplies.
3. It is recognized that, in the great majority of rural water supplies in developing countries, fecal
contamination is widespread. Under these conditions, the national surveillance agency should set
Noise level monitoring was carried out with the help of sound level meter at 7 different locations fall under
residential and industrial noise generating sources. Noise sampling locations are shown in Figure No. 3.19 and
Table No. 3.15. Noise monitoring report during day time and night time are presented in Table No. 3.16.
Graphical presentation of Min. & Max. Values are shown in Figure No. 3.20 & Figure No. 3.21.
Table No. 3.15 – Noise Level Monitoring Locations in the 10 km Study Region
Sr. Selection
Location Symbol Latitude Longitude Distance Direction
No. Criteria
1. Project Site N1 21°37'14.75"N 73°01'10.50"E 0.00 --- Industrial
2. Kapodra N2 21°35'39.80"N 73°00'44.64"E 3.00 SSW Residential
3. Motali N3 21°38'50.36"N 73°02'32.11"E 3.76 NE Residential
4. Boidara N4 21°37'47.80"N 72°58'41.86"E 4.37 WWN Residential
5. Umarwada N5 21°34'52.26"N 72°58'21.60"E 6.56 SW Residential
6. Mandwa Bujrg N6 21°40'35.34"N 73°03'57.31"E 7.72 NE Residential
7. Sengpur N7 21°35'46.22"N 73°06'30.29"E 9.64 EES Residential
Figure No. 3.19 – Noise Level Monitoring Locations in the 10 km Study Region
Table No. 3.16 – Noise Monitoring Report During Day Time and Night Time
Note: Day time –6:00 AM to 10:00 PM, Night time – 10:00 PM to 6:00 AM
Figure No. 3.20 – Graphical presentation of min. & max. Value of noise level during day time
Figure No. 3.21 – Graphical presentation of min. & max. Value of noise level during night time
Since Indian traffic is heterogeneous in character, it is common practice to convert the traffic in terms of
passenger car units (PCUs). The values of passenger car equivalency for different vehicles types are mentioned
in Table No. 3.17.
Table No. 3.17 – Recommended PCU Factors for various types of Vehicles
Level of Service (LOS) describes conditions in terms of factors such as speed and travel time, freedon to
manoeuvre, traffic interruptions, confort, convenience and safety. Six levels of service are recognized commonly,
designated from A to F, with Level of Service A representing the best operating condition and Level of Service F
the worst. Different level of service with percentage are mentioned in Table No. 3.18.
Traffic load will play a major role in air pollution as well as noise pollution. From the location of the project site,
it is shows that project is connect to N. H. No. 8. Due to proposed expansion project, there will be increased in
existing traffic scenario near the project site. For the traffic survey, 4 surveyors were appointed to survey the
existing traffic scenario at N. H. No. 8. Traffic data were collected by surveyours for 24 hours continuously by
visual observation and counting of vehicles under different categories i.e. two/three wheelers, light motor
vehicles and heavy motor vehicles. Existing traffic scenario at N. H. No – 8 are mentioned in Table No. 3.19.
Table No. 3.19 – Existing Traffic Scenario
Ecological studies are one of the important aspects of Environmental Impact Assessment with a view to
conserve environmental quality and biodiversity. Ecological systems show complex inter-relationships between
biotic and abiotic components including dependence, competition and mutualism. Biotic components comprise
of both plant and animal communities, which interact not only within and between themselves but also with the
biotic components viz. physical and chemical components of the environment. The study also designed to
suggest suitable mitigation measures if necessary for protection of wildlife habitats conservation of Rare or
Endangered or Endemic or Threatened (REET) species if any. The present Ecological study was undertaken with
the following objectives:
To assess the nature and distribution of vegetation in and around the project site
To assess the flora & fauna in the study area.
To ascertain the migratory routes of fauna, presence of breeding grounds and sensitive habitats in the
study area, if any.
Impact prediction based on primary and secondary data sources to formulate mitigation measures.
3.12.1 Methodology
During the study period, the field survey was conducted at identified survey area within 10 km distance from the
project site. Following methodology was adopted for the survey:
Field survey area is selected based on the ecologically diverse and dense vegetation identified from
Google map and land use pattern map. Verification (ground truthing) of the secondary data obtained is
conducted specific to the study area of the project.
Observations were made at different sampling points and qualitative as well as quantitative analysis of
Assessment of general habitat type, vegetation pattern, preparation of inventory flora and fauna of
terrestrial ecosystem.
The list of floral species is prepared based on visual observation during site visit and through review of
site literatures and secondary data available online as published flora and fauna on various websites
Biological assessment of the site was done to identify whether there are any REET species of flora or
fauna in the project site or core area as well its buffer zone and to identify whether there are any
ecologically sensitive area within the area that is likely to be impacted (buffer zone).
Conservation status of species were checked according to Indian Wildlife Protection Act (1972) and
IUCN.
3.12.2 Flora
The list of flora found during field survey is given in Table No. 3.20.
3.12.3 FAUNA
The list of fauna found during field survey is given in Table No. 3.21.
3.13 SOCIO-ECONOMIC
An assessment of socio – economic environment forms an integral part of an EIA study. Therefore, baseline
information for the same was collected during the study period. The baseline socio - economic data collected
for the study region, before the project is in operation and it has been identified for the four major indicators
viz. demography, civic amenities, economy and social culture.
3.13.1 Methodology
A Basic detailed study of socio-economic facade is collected with the primary data collection and secondary
data method which is 2011 census and NIC data. Further to enhance and give justice to the secondary data,
meetings and discussions with Tahsildars, Sarpanchs, various Government officials, local heads, etc. as well as by
suitable field surveys was scheduled. The study brings out the following features in this respect.
3.13.2 Demography
As per census 2011, the demographic status of the study area is mentioned in Table No. 3.22. Sex ratio i.e. the
number of females per 1,000 males indirectly reveals certain sociological aspect in relation to female births,
infant mortality among female children. Details of the same are mentioned in Table No. 3.23.
Table No. 3.25 – Literacy Rate within 10 Km Radial Distance of Study Area
Main worker is a worker who has worked last year for six month or more. Marginal worker is a worker who has worked last year for less than six months. Non-worker
is worker who did not work at all during the reference period of one year.
Distribution of main worker and marginal worker into further following four categories are shown in Table 3.27.
I) Cultivators
II) Agricultural labors
III) Household industry
IV) Others workers
3.13.5 Amenities
Infrastructure resources base of the surveyed villages with reference to educational, medical, water resources, post and telegraph, communication, power supply is
presented in Table 3.28. Significant observations with respect to availability of amenities in study area are as follows.
3.14 SUMMARY
Micrometeorology: During the study, wind was blowing mostly from SW – NE direction and wind speed range
0.0 to 22.5 km/h. Based on the wind direction and wind speed it is interpreted that maximum dispersion of air
pollutant will be in NE direction during the period of March to May.
Ambient Air: All the results of ambient air quality parameters have been found within the limit as per NAAQS. It
is interpreted that ambient air quality of studied locations is decent. This interpretation relate to the results
found for particular locations and study period.
Soil: The results of pH shows that soils are acidic to alkaline in reaction. The soils are categorized as sandy loam
based on different soil separates (sand, silt and clay). The levels of total Cu, Ar and Ni are within the safe limits.
The soil at the project site requires improvement. The soil should be periodically monitored for pH and density.
Ground Water: Results of all villages meet with the standard, while the results of calcium and megnesium are
having high value at location of Umarwada and Mandwa Bujrg respectively. The reason of high concentration of
calcium and magnesium in ground water may be due to high content of Iron in nearby surface water resources.
Also it is interpreted that water supply by GIDC at project site.
Surface Water: On the basis of test results of River Water quality, it is understood that River water quality does
not meet with drinking water norms as per IS 10500:2012. From the Results of BOD, COD & Iron shows that the
water has been contaminated with organic matter and Iron due to directly or indirectly disposal of untreated
sewage and effluent. This water may be used for drinking purpose after proper treatment followed by
disinfection but it would not be directly used for driking purpose.
Noise: Based on noise level data for residential area and industrial area, it is understood that noise levels are
within the standard norms prescribed by MoEF&CC.
Traffic Survey: Based on existing traffic scenario, LOS values for N. H. No. – 8 have been found 0.57 i.e. good.
Ecology & Biodiversity: In core zone, the vegetation mostly comprises of open scrub vegetation. There is a
domestic animal like buffalo, cow, goat, dog were find out in the study area. There was no Rare or Endangered
or Endemic or Threatened species observed during primary survey.
Socio-Economic: On the basis of survey, it was observed that almost pakka road facility, all basic amenities like
Education facilities Health care facilities, water supply, electric power supply, mode of transportation etc. are
available in all villages.
During the construction phase which may be regarded as temporary or short term; and
During the operation phase which would have long term effects.
Sr. Impact
Category Description of Category
No. Adverse Beneficial
1. No Impact --- 0 0
2. No Appreciable Impact Short Term Reversible -1 1
3. Significant Impact Long Term Reversible -2 2
4. Major Impact Irreversible but of Lesser Extent -3 3
5. High Impact Irreversible but of Medium Extent -4 4
6. Permanent Impact Severe Irreversible Impact -5 5
Impact
Very Low Low Medium High Very High
1 2 3 4 5
Very High 5 5 10 15 20 25
Probability
High 4 4 8 12 16 20
Medium 3 3 6 9 12 15
Low 2 2 4 6 8 10
Very Low 1 1 2 3 4 5
Table No. 4.3 – Cumulative Score Range for Beneficial and Adverse Impacts
Sr. Cumulative
Meaning
No. Score
1. +ve / -ve Beneficial Impact / Adverse Impact
2. 0 – 150 No appreciable Beneficial Impact / Adverse Impact
3. 151 – 300 Appreciable but reversible adverse impact-mitigation measures are needed
Significant adverse impacts: most of the impacts are reversible. Mitigation measures
4. 301 – 450
are crucial.
Major adverse impacts; most of the impacts are reversible. Alternative site selection
5. 451 – 600
to be considered.
6. >600 Permanent irreversible impact; alternatives to the project need to be explored.
Environmental Attributes
Sr.
Activities
No. LU Hydro Risk and Ecology and Socio
Air Water Soil Noise Geology SHW
/LC Geology Hazards Biodiversity Economic
Transportation and Storage
1. ✔ --- --- ✔ --- --- --- --- ✔ ✔ ✔
of construction material
Modification and
2. commissioning of plant and ✔ ✔ --- ✔ --- --- --- ✔ ✔ --- ✔
machinery
3. Sewage disposal --- ✔ --- --- --- --- --- --- --- --- ---
Solid/ Hazardous Waste
4. --- --- ✔ --- --- --- --- ✔ --- --- ---
Disposal
5. Green Belt Development ✔ ✔ ✔ ✔ ✔ --- --- --- --- ✔ ✔
Development of Internal
6. ✔ ✔ ✔ ✔ --- --- --- ✔ --- --- ✔
road
Table No. 4.5 – Environmental Impact Assessment Matrix During Construction Phase (Without Mitigation
Measures)
Environmental Attributes
Sr.
Activities LU Hydro Risk and Ecology and Socio
No. Air Water Soil Noise Geology SHW Total
/LC Geology Hazards Biodiversity Economic
Transportation and Storage
1. -9 0 0 -6 0 0 0 0 -4 -6 6 -19
of construction material
Modification and
2. commissioning of plant -8 -6 0 -8 0 0 0 -8 -9 0 9 -30
and machinery
3. Sewage disposal 0 -4 0 0 0 0 0 0 0 0 0 -4
Solid/ Hazardous Waste
4. 0 0 -6 0 0 0 0 -6 0 0 0 -12
Disposal
5. Green Belt Development 12 -6 9 6 4 0 0 0 0 6 4 35
Development of Internal
6. -8 -6 -8 -8 0 0 0 -4 0 0 4 -30
road
Total -13 -22 -5 -16 4 0 0 -18 -13 0 23 -60
Total Cumulative Score without mitigation measures during construction phase for various Environmental
Parameters is –60 shows there is no appreciable adverse impact.
Table No. 4.6 – Environmental Impact Assessment Matrix During Operation Phase
Environmental Attributes
Sr.
Activities LU Hydro Risk and Ecology and Socio
No. Air Water Soil Noise Geology SHW
/LC Geology Hazards Biodiversity Economic
1. Transportation ✔ --- ✔ ✔ --- --- --- --- ✔ ✔ ✔
Storage and handling of
2. ✔ --- ✔ --- --- --- --- ✔ ✔ --- ✔
Raw Material and Product
3. Manufacturing Process ✔ ✔ ✔ ✔ --- --- --- ✔ ✔ --- ✔
Sewage and Effluent
4. --- ✔ ✔ --- --- --- --- ✔ ✔ ✔ ---
Generation
Solid/ Hazardous Waste
5. ✔ --- ✔ --- --- --- --- ✔ ✔ ✔ ✔
Disposal
6. Green Belt Development ✔ ✔ ✔ ✔ ✔ --- --- --- --- ✔ ✔
7. Employment ✔ ✔ --- ✔ --- --- --- ✔ --- ✔ ✔
8. CSR Activity --- --- --- --- --- --- --- --- --- --- ✔
Table No. 4.7 – Environmental Impact Assessment Matrix during Operation Phase (without Mitigation
Measures)
Environmental Attributes
Sr.
Activities LU Hydro Risk and Ecology and Socio
No. Air Water Soil Noise Geology SHW Total
/LC Geology Hazards Biodiversity Economic
1. Transportation -6 0 -4 -6 0 0 0 0 -6 -6 4 -24
Storage and handling of
2. Raw Material and -4 0 -4 0 0 0 0 -6 -9 0 4 -19
Product
3. Manufacturing Process -4 -9 -4 -6 0 0 0 -6 -9 0 4 -34
Sewage and Effluent
4. 0 -6 -6 0 0 0 0 -4 -4 -4 4 -20
Generation
Solid/ Hazardous Waste
5. -3 0 -4 0 0 0 0 -6 -6 -6 4 -21
Disposal
6. Green Belt Development 6 -4 4 4 2 0 0 0 0 4 2 18
7. Employment -9 -3 0 -9 0 0 0 -9 0 6 6 -18
8. CSR Activity 0 0 0 0 0 0 0 0 0 0 12 12
Total -20 -22 -18 -17 2 0 0 -31 -34 -6 40 -106
Total Cumulative Score without mitigation measures during operation phase for various Environmental
Parameters is -106 shows there is no appreciable adverse impact.
4.3 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES DURING
CONSTRUCTION PHASE
4.3.1 Air Environment
Table No. 4.8 – Impact and Mitigation Measures on Air Environment
4.3.6 Hydrogeology
Source of water is being/will be GIDC and after proposed expansion GIDC will be provided water so there will be
no Impact on Hydrogeology.
4.3.7 Geology
Project site located in GIDC, Ankleshwar so there will be no impact on Geology.
4.3.11 Socio-Economic
Table No. 4.14 – Impact and Mitigation Measures on Socio-Economic
Measures)
Environmental Attributes
Sr.
Activities LU Hydro Risk and Ecology and Socio
No. Air Water Soil Noise Geology SHW Total
/LC Geology Hazards Biodiversity Economic
Transportation and
1. Storage of -6 0 0 -4 0 0 0 0 -2 -4 12 -4
construction material
Modification and
2. commissioning of -4 -3 0 -4 0 0 0 -2 -6 0 16 -3
plant and machinery
3. Sewage disposal 0 -2 0 0 0 0 0 0 0 0 0 -2
Solid/ Hazardous
4. 0 0 -4 0 0 0 0 -4 0 0 0 -8
Waste Disposal
Green Belt
5. 16 -6 12 9 6 0 0 0 0 9 6 52
Development
Development of
6. -4 -6 -6 -6 0 0 0 -3 0 0 6 -19
Internal road
Total 2 -17 2 -5 6 0 0 -9 -8 5 40 16
Total Cumulative Score with mitigation measures during construction phase for various Environmental
Parameters is 16 shows there is no appreciable beneficial impact.
To identify the incremental load on ambient air quality, it is necessary to assess the impact of existing ambient
air quality with respect to the proposed emission. In order to predict the impact of air pollutants on ambient air
quality, the incremental Ground Level Concentration (GLC) has been computed using Industrial Source Complex
– Short Term (ISCST – 3) model, which is a steady-state Gaussian plume model.
INPUT OF ISCST – 3:
The air pollution caused by the gaseous emissions from a stack is a local phenomenon. Its impact will occur at a
distance ranging from within the immediate vicinity of the stack to 1 km away from the stack. To evaluate the
impact on air quality following data is required to input in simulation.
O
Micro-metrological data such as cloud cover, temperature ( C), relative humidity (%), wind direction
(Degree), wind speed (km/h), hourly precipitation for study period.
OUTPUT OF ISCST – 3:
The proposed air emissions of various parameters i.e. PM, SO 2, NOx and HCl have been stimulated in ISCST – 3
model and based on the final output contour of maximum ground level concentration for sampling location are
plotted. Isopleths of each parameter are depicted as Figure – 4.1 to 4.3.
Figure No. 4.1 – Isopleths for Concentration of PM
Sr. No. Location Background Average Conc. Incremental Conc. Resultant Conc.
3 3
A. PM10 µg/m (Permissible Limit:100 µg/m )
1. A1 76.19 0.00 76.19
2. A2 69.52 0.27 69.79
3. A3 73.30 0.09 73.39
4. A4 63.60 0.04 63.64
5. A5 64.41 0.01 64.42
6. A6 75.22 0.05 75.27
7. A7 67.12 0.00 67.12
8. A8 66.70 0.02 66.72
9. A9 68.51 0.00 68.51
3 3
B. SO2 µg/m (Permissible Limit: 80 µg/m )
1. A1 16.32 0.00 16.32
2. A2 12.41 0.46 12.87
3. A3 14.80 0.15 14.95
4. A4 8.60 0.07 8.67
5. A5 11.49 0.02 11.51
6. A6 14.59 0.08 14.67
7. A7 9.10 0.01 9.11
8. A8 13.69 0.03 13.72
9. A9 10.10 0.00 10.10
3 3
C. NOx µg/m (Permissible Limit: 80 µg/m )
1. A1 20.12 0.00 20.12
2. A2 15.33 0.13 15.46
3. A3 17.50 0.04 17.54
4. A4 10.41 0.02 10.43
5. A5 13.68 0.00 13.68
6. A6 16.22 0.02 16.24
7. A7 11.31 0.00 11.31
8. A8 15.13 0.01 15.14
9. A9 13.60 0.00 13.6
Conclusion
It is noted that the maximum impact zone is within 2 – 4 km radial zone from the stack of industrial Plant. The
modeling study proved that the air emissions from the proposed plant would not affect the ambient air quality
of the region in any significant manner because after proposed expansion natural gas will be used as a fuel to
control air emissions. The ambient air quality around the project site will remain within the NAAQS. NAAQS are
indicative air quality criteria that are adequate to protect the human health and vegetation.
Emission from vehicles used for transportation would be affecting the pollutant concentrations in project area.
Details of traffic after proposed expansion are mentioned below:
Total nos. of trucks require per month after expansion = 41.625/20 = 2.08 = 2 Nos. of Truck/Month
We have consider maximum 2 Nos. of truck/day. It is calculated that total 60 Nos./month of trucks will be
arrived/leaved at the project site. Traffic load on internal and external road is calculated as under:
Table No. 4.17 – Traffic load due to material transportation & employment
Existing road traffic at the proposed expansion project site is mentioned in Chapter – 3. However, the impact
would be negligible due to less nos. of vehicles.
Table No. 4.18 – Traffic Scenario and LOS after Proposed Expansion
Sr.
Vehicles at N. H. No. – 8 Modified V C Modified V/C Ratio Modified V/C Grade
No.
2,044 + 1 =
1. N. H. No. – 8 3600 0.56 C
2,045
The LOS value from the proposed expansion project will be the almost same i.e. ―C‖ ―Good‖ for the National
Highway falling in the study area. So, the additional load on the carrying capacity of the concern roads is not
likely to have any significant adverse effect.
4.4.6 Hydrogeology
Projects site falls in already developed GIDC Ankleshwar and source of water is GIDC so there will be no Impact
on Hydrogeology.
4.4.7 Geology
Projects site falls in already developed GIDC Ankleshwar so there will be no impact on Geology.
4.4.11 Socio-Economic
Table No. 4.26 – Impact and Mitigation Measures on Socio-Economic
Table No. 4.27 – Environmental Impact Assessment Matrix during Operation Phase (with Mitigation
Measures)
Environmental Attributes
Sr.
Activities LU Hydro Risk and Ecology and Socio
No. Air Water Soil Noise Geology SHW Total
/LC Geology Hazards Biodiversity Economic
1. Transportation -4 0 -2 -4 0 0 0 0 -4 -4 6 -12
Storage and handling of
2. Raw Material and -2 0 -3 0 0 0 0 -2 -6 0 6 -7
Product
3. Manufacturing Process -2 -6 -2 -4 0 0 0 -4 -6 0 12 -12
Sewage and Effluent
4. 0 -4 -2 0 0 0 0 -3 -2 -2 6 -7
Generation
Solid/ Hazardous Waste
5. -2 0 -2 0 0 0 0 -4 -4 -4 6 -10
Disposal
6. Green Belt Development 12 -4 9 9 6 0 0 0 0 6 4 42
7. Employment -4 -2 0 -6 0 0 0 -6 0 9 12 3
8. CSR Activity 0 0 0 0 0 0 0 0 0 0 16 16
Total -2 -16 -2 -5 6 0 0 -19 -22 5 68 13
Total Cumulative Score with mitigation measures during operation phase for various Environmental Parameters
is 13 shows there is no appreciable beneficial impact.
4.5 SUMMARY
During the construction and operation phase various activities are considered to be important towards
development of impacts, impacts are identified and proper mitigation measures are suggested. Impact
identification matrix with quantitative impact matrix with and without mitigation measures during construction
and operation phase have also been carried out. From air modeling study, it has proved that the air emission
from the proposed expansion project is not increased in significant manner. The resultant concentrations are
within the NAAQS. It can be concluded that the overall negative impacts from various activities on different
environmental parameters is negligible with proper EMP in place.
CHAPTER 5 – ANALYSIS OF ALTERNATIVES (TECHNOLOGY
& SITE)
The proposed expansion and/or reduction in existing production capacity and addition of new products within
existing premises having total capacity of 5.0 MT/Month (Either individual or Total production shall not exceed
5.0 MT/Month) and it is located at Plot No: C1B/414, GIDC Estate, Ankleshwar – 393002, Dist.: Bharuch, Gujarat,
India.
Technology: Industry will choose automatic machineries between automatic and semi-automatic
because these machineries will consume less electricity, generate minimum noise and air pollution.
Employment: Local employment will be preferred by the industry as per their skills & qualification.
Industry will be provided financial benefits to the local employee.
Labor Transport: Industry will be deputed local employees so they will not require public transport.
Workers and local employees will be reached by their own vehicles to minimize the cost of
transportation.
Raw material & Product Transport: Industry will be used private vehicles for the transportation of the
raw material and product. Due to this, indirect employment will be generated.
Water requirement: Industry is being/will be used GIDC water because it does not want to alter the
5.2 SUMMARY
Project is located in GIDC, Ankleshwar is a well-developed Notified Industrial Area with necessary infrastructure
facilities.
CH 5: ANALYSIS OF ALTERNATIVES
109
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
110 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Assessment of the changes in Environmental Conditions, if any, during the project operation/activities.
Monitoring and tracking the effectiveness of EMP and implementation of Mitigation Measures planned.
Identification of any significant adverse transformation in Environmental Condition due to the project.
Sr. Frequency of
Particulars Parameter for Monitoring
No. Monitoring
Ambient Air Quality Monitoring PM10, PM2.5, SOx, NOx, CO, Total VOC, HCl
1. Monthly
within plant premises
Noise Quality within Plant premises Equivalent noise level - dB (A) (min. 5
5. Monthly
locations) during day and night time
Renewal of Consents and Renewing consent to operate under applicable 3 months before
10.
Authorization acts expiry of validity
Medical surveillance program The health status of all the workers in respect
12. Half yearly
of occupational health hazards
Monitoring of the above parameters will be carried out to assess the performance of pollution control
equipment‗s installed to achieve the statutory norms. In case emissions/pollutant will found to exceed the
norms, the on duty personnel will check the relevant parameters and take appropriate corrective actions. A
record of corrective and preventive action will be maintained as per requirement.
Sr. Methods
Attributes
No. Sampling/Preservation Analysis
As per IS: 5182 & AWMA. As per IS:5182, CPCB & AWMA
Ambient air
1. Instrument operated as per it‘s
quality
manual
2. Noise Instrument : Noise level meter Survey carried out as per CPCB guideline.
3. Ground Water Standard Methods for Examination IS 3025 & Standard Methods for Examination
nd
of Water and Wastewater (APHA), of Water and Wastewater (APHA), 22
4. Surface Water nd
22 edition, 2012 edition, 2012
chemicals required for monitoring of general parameters of ambient air, wastewater, noise within plant
premises.
Monthly and annual progress reports: Immediately upon the completion of monitoring as per the
planned schedule, report shall be prepared & necessary documents shall be forwarded to the
concerned person.
Instruction manual for operation and maintenance of pollution control equipment
Instruction manual for monitoring of water & gaseous parameter and hazardous waste management.
Records of medical check-up of employees.
Regularly all documents & records shall be reviewed for necessary improvement of the monitoring
plan/mitigation measures/environmental technologies as well as for necessary actions of Environmental
Management Cell.
All environmental monitoring data will be stored as a computer database for proper storage, retrieval
and interpretation.
The in-charge of environment, health and safety department will co-ordinate with monitoring agency
and analysis report with interpretation will be submitted regularly to the statutory authority after
3. Noise 0.05
4. Other 0.24
Sr. No. Description Amount (Lakhs/Annum)
Total 2.99
6.6 SUMMARY
Environmental samples will be collected as per the guidelines provide by MoEF&CC/ CPCB/ GPCB. The method
followed will be recommended/standard method approved/recommended by MoEF&CC/ CPCB. Industry will be
propsed Rs. 2.99 Lakhs/Annum for environmental monitoring. Industry will maintain the pollution load under
permissible limit and will take necessary precautions to maintain the same. Regular records review for change in
financial requirements of environment management shall be done and appropriate budgetary provisions shall
be made and revised regularly on requirement.
To identify various hazards in the plants, processes, storages and utility area of the unit.
To consider the consequential impact on nearby areas, population, etc. in case of any accidental
To evaluate and quantify the available measures and resources for containing any eventuality.
PHAST Professionals sophisticated modeling calculates distances effect produced by hazardous events. With
this information, you can evaluate the need for mitigating measures such as changes in design, operation or
response. PHAST software can be used to model a proposed facility or operational change to ease the selection
of the most effective solutions. With PHAST Professional, you can define special events, model the change in a
leak over time, and investigate the details of behavior with special stand-alone models and much, much more.
PHAST is integrated into safety and meets regulatory requirements. It uses unified dispersion modeling to
calculate the results of the release of material into atmosphere
It gives the consequence results in terms of – Flammable, Toxic and Explosion effects.
Jet fire and pool fire scenario along with their respective effect zones (risk contour).
2. Toxic parameters-
Categorize the toxic results in terms of ERPG, IDLH and STEL values.
Summarize results in terms of equivalent toxic dose along with effect zones.
3. Explosion parameters-
Categorize the explosion effects in terms of overpressures levels along with distance covered.
7.2.5 Methodology
The methodology includes,
Data collection
Data Analysis
Hazard identification,
CH 7: ADDITIONAL STUDIES
115
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
116 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Storage Storage
Sr. Means of Storage Storage Storage
Name of Chemical State Pressure Temperature
No. (Tank/Drum/Bag) quantity Capacity O
(atm) ( C)
1. Reactive Blue MR Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
2. Reactive Yellow M4R Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
3. Acid Blue 25 Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
4. Acid Yellow GL Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
5. Acid Black – 1 Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
6. Acid Orange – RL Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
7. Acid Brown 2RL Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
8. Basic Violet – 1 Liquid Drum 200 L 5 KL Atmospheric Ambient
9. APMS (2 – Amino Phenyl Hydroxy Methyl Sulfone) Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
10. 1 – Amino – 4 Bromo Anthraquinone – 2 Sulfamic Acid Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
11. Acid Yellow 2GLN Solid HDPE Bag 25/50 kg 300 Kg Atmospheric Ambient
12. Meta Phenyle Diamine Sulfonic Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
13. Bromamine Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
14. Soda Ash Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
15. Cynuric Chloride Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
16. Salt Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
17. Sulpho Tobias Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
18. Hydrochloric Acid Liquid Drum 200 L 5 KL Atmospheric Ambient
19. Sodium Nitrite Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
Storage Storage
Sr. Means of Storage Storage Storage
Name of Chemical State Pressure Temperature
No. (Tank/Drum/Bag) quantity Capacity O
(atm) ( C)
20. N-Methyl J-Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
21. Aniline Liquid HDPE Carboy 200 L 200 L Atmospheric Ambient
22. Amino Benzoic Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
23. Meta Chloro Phenyl Methyl Pyrazolone Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
24. 4 Nitro Amino Phenol Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
25. Beta Nephthol Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
26. Amino Phenol Methyl Sulfon And/ or 4 – NAP Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
27. Amino-7-Napthol Chloro Formete Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
28. Acetic Acid Liquid HDPE Carboy 200 L 200 L Atmospheric Ambient
29. Methane Base Powder HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
30. Mono Methyl Aniline Liquid HDPE Carboy/Drum 200 L 200 L Atmospheric Ambient
31. Chloranil Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
32. Oxygen Gas Cylinder 25/50 kg 500 kg Atmospheric Ambient
33. Di Methyl Aniline Liquid HDPE Carboy 200 L 5 KL Atmospheric Ambient
34. Para Chloro Nitrobenzene sulfuric acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
35. Mono choloro Acetic Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
36. Sodium Hydrosulfide Liquid HDPE Carboy 200 L 5 KL Atmospheric Ambient
37. Sodium Bisulfite Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
38. Ortho Dichloro Benzene Liquid HDPE Carboy 200 L 5 KL Atmospheric Ambient
39. 1 – Amino Anthraquinone Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
40. Chlorosulfonic Acid Liquid MS Tank/Glass Line 200 L 10 MT Atmospheric Ambient
41. Sodium Bromate Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
42. Sodium Bromide Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
43. Anthranilic Acid Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
CH 7: ADDITIONAL STUDIES
117
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
118 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Storage Storage
Sr. Means of Storage Storage Storage
Name of Chemical State Pressure Temperature
No. (Tank/Drum/Bag) quantity Capacity O
(atm) ( C)
44. Sodium Acetate Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
45. Phenyl Methyl Pyrazolone Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
46. Formic Acid Liquid Drum 200 L 5 KL Atmospheric Ambient
47. BCS (16% Cr) Solid HDPE Bag 25/50 kg 500 kg Atmospheric Ambient
7.2.7 Physico-Chemical properties of chemicals handle in the plant
Physico-Chemical properties of these hazardous chemicals are mentioned in the Table No. 7.2.
Main Properties
Sr. Physical
Name of Chemical Hazardous Boiling Flash LEL & Vapour
No. State TLV LD50 LC50 Odor
Involved Point Point UEL% Presuure
Acute toxicity
> 200 Acute oral
Inhalation
Non - 190 °C - °C - 0.6 hPa at toxicity (LD50):
1. Cynuric Chloride Solid NA NA (LC50): 150 NA
Flammable lit. closed 20 °C 315 mg/kg
mg/l 4 hours
cup [Rat male];
[Rat male]
Acute toxicity
Acute oral of the dust
Non - toxicity (LD50): (LC50): 1200
2. Soda Ash Solid NA NA NA NA NAP 3 Odorless
Flammable 4090 mg/kg mg/m
[Rat]; 2 hours
[Mouse].
Oral LD50: >
3. Sulpho Tobias Acid Solid NA NA NA NA NA NA 10 gm/kg; NA NA
(Mouse)
Acute toxicity
Acute toxicity
of the vapor Pungent.
Non- 108.58 16 kPa (at Oral (LD50):
4. Hydrochloric Acid Liquid NAP NA NA (LC50): 1108 Irritating
flammable °C 20°C) 900 mg/kg
ppm 1 hours (Strong)
[Rabbit];
[Mouse]
Acute toxicity
271°C at Oral (LD50):
5. Sodium Nitrite Solid Flammble 320 °C NA NA NA NA NA
25 °C 157.9 mg/kg
[Rat]
CH 7: ADDITIONAL STUDIES
119
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
120 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Main Properties
Sr. Physical
Name of Chemical Hazardous Boiling Flash LEL & Vapour
No. State TLV LD50 LC50 Odor
Involved Point Point UEL% Presuure
Acute toxicity
Oral (LD50): Acute toxicity
Lower:1.3 0.5 250 mg/kg Inhalation
181 - 7.6 Rotten
6. Aniline Liquid NA 76 °C % Upper: 3 mmHg at [Rat]; Dermal (LC50): 248
185 °C mg/m egg
11 % 20°C (LD50): 820 ppm 4 hours
mg/kg [Mouse]
[Rabbit]
2 < 0.1 hPa
7. Caustic Lye Liquid NA 1388 °C NAP NA 3 NA NA Odourless
mg/m (20°C)
Acute toxicity
4 Nitro Amino Oral (LD50):
8. Solid NA NA 100 °C NA NA negligible NA NA
Phenol 2400 mg/kg
[Rat]
Acute toxicity
Oral (LD50):
153 °C - 10 mmHg 1960 mg/kg
285 -
9. Beta Nephthol Solid NA closed NA NA at 145.5 [Rat]; Dermal NA NA
286 °C
cup °C (LD50): >
10,000 mg/kg
[Rabbit]
Acute toxicity
Oral (LD50): Acute toxicity
Lower:
3310 mg/kg Inhalation
117 - 4% 25 55 mmHg Pungent
10. Acetic Acid Liquid NA NA 3 [Rat]; Dermal (LC50): 11.4
118 °C Upper: mg/m at 50 °C vinegar
(LD50): 1112 mg/l 4 hours
19.9 %
mg/kg [Rat]
[Rabbit];
Main Properties
Sr. Physical
Name of Chemical Hazardous Boiling Flash LEL & Vapour
No. State TLV LD50 LC50 Odor
Involved Point Point UEL% Presuure
Extremely
flammable Lower:
Closed
in the - 5%
11. Methane Base Powder cup: - NA NA NA NA Odorless
presence 161.48°C Upper:
104°C
of open 14 %
flames
Acute toxicity
0.4 mbar Oral (LD50):
12. Mono Methyl Aniline Liquid NA 195 °C 86 °C NA NA NA NA
at 20 °C 360 mg/kg
[Rat]
Acute toxicity
Acute toxicity Inhalation
13. Chloranil Solid NA Sublimes NAP NA NA Negligible Oral (LD50): 4 (LC50): 2485 NA
3
gm/kg [Rat]; mg/m 4
hours [Rat]
NAP for
Non gases
14. Oxygen Gas -183 °C NA NA NA NA NA NA
flammable and gas
mixtures
Lower: Acute toxicity
193 - 1.2 % 0.53 mbar Oral (LD50): Amine-
15. Di Methyl Aniline Liquid Toxic 63 °C NA NA
194 °C Upper: 7 at 20 °C 951 mg/kg like - fish
% [Rat]
Oral (LD50): Oral (LD50):
55 mg/kg 55 mg/kg
Mono choloro Acetic Lower: 8 0.22 mbar [Rat]; [Rat];
16. Solid NA 189 °C 126 °C NA NA
Acid % @ 20 C Inhalation Inhalation
(LC50): 180 (LC50): 180
3 3
mg/m mg/m
CH 7: ADDITIONAL STUDIES
121
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
122 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Main Properties
Sr. Physical
Name of Chemical Hazardous Boiling Flash LEL & Vapour
No. State TLV LD50 LC50 Odor
Involved Point Point UEL% Presuure
Rotten
17. Sodium Hydrosulfide Liquid NA NA 90 °C NA NA NA NA NA
egg
Acute toxicity
5 Sulfurous
18. Sodium Bisulfite Solid NA NAP NA NA NA Oral (LD50): 2 NA
mg/m3 odor
gm/kg [Rat]
Acute toxicity
Acute toxicity
Lower: Oral (LD50):
1.15 Inhalation
Ortho Dichloro 179 - 2.20 % 1516 mg/kg
19. Liquid NA 67°C NA mmHg at (LC50): 14,04 NA
Benzene 180°C Upper: [Rat]; Dermal
20 °C mg/l 4 hours
12 % (LD50): >10
[Rat]
g/kg [Rabbit];
Acute toxicity
Lower:
Inhalation
151 - 3.30 %
20. Chlorosulfonic Acid Liquid NAP NA NA NA NA (LC50): 0.0385 NA
152°C Upper:
mg/L 4 h
37.70 %
[Rat]
Acute toxicity
Oral (LD50):
4200 mg/kg
10
21. Sodium Bromide Solid NA 1390°C NA NA 3 NA [Rat]; Dermal NA Odorless
mg/m
(LD50): > 2000
mg/kg
[Rabbit]
Main Properties
Sr. Physical
Name of Chemical Hazardous Boiling Flash LEL & Vapour
No. State TLV LD50 LC50 Odor
Involved Point Point UEL% Presuure
Acute toxicity
Oral
(LD50):1400
mg/kg
22. Anthranilic Acid Solid NA Sublimes 150°C NA NA NA NA NA
[Mouse];
Dermal (LD50):
5410 mg/kg
[Rat]
Acute toxicity
Phenyl Methyl Oral (LD50):
23. Solid NA 287°C NA NA NA NA NA NA
Pyrazolone 1683 mg/kg
[Mouse]
Acute toxicity
Acute toxicity
Lower: 10 Inhalation
44 mbar Oral (LD50):
24. Formic Acid Liquid Toxic 101 °C 50 °C % Upper: NA (LC50): 15 pungent
at 20°C 730 mg/kg 3
45 % g/m 15
[Rat];
min[Rat]
CH 7: ADDITIONAL STUDIES
123
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
124 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Table No. 7.3 – Scenario Selected for simulation of hazardous chemicals stored
Consider above all, Qualitative and Quantitative risk assessment study has been carried out and presented in following section.
7.3 QUALITATIVE RISK ASSESSMENT
Many a times Risk involved in various processes / process equipments cannot be addressed completely
by Consequence Analysis. As a conservative approach, these risks have been considered separately
under this topic. The approach is to identify hazards associated in operation of equipments as well as in
processes, assessing its impacts, ranking the risk posed by it and finally to propose remedial
actions/mitigation measures such that the risk is minimized to tolerable level.
In Qualitative Risk Assessment, risk has been analyzed using methodology called HIRA-Hazards
Identification & Risk Assessment. In HIRA, major manual activities carried out by plant personnel as well
as contract labors have been considered.
For the following areas, Qualitative Risk Assessment has been carried out to identify the risk, ranking
them as per their severity & probability, identifying mitigation measures.
SEVERITY
Catastrophic Major/Critical Moderate (Less Minor/ Marginal Insignificant/
LIKEHOOD/
(Death/System (Serious Serious Injury/ (Minor Negligible (No
PROBABILITY
Loss) injury/Illness) Illness) Injury/Illness) injury/ illness)
1 2 3 4 5
Almost Certain E H H H M M
Likely D H H M M L
Possible C H M M M L
Unlikely B M M M L L
Impossible A M M L L L
CH 7: ADDITIONAL STUDIES
125
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
126 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Likelihood
Likelihood
Sr. Associated
Severity
Severity
or Safety Impact Mitigation Measures
Risk
Risk
No. Hazards
Activity (Risk)
Handling Chemical Skin/ Eye/ 4 C M Operators/Workers is being/will be trained for Safe Work Practices. 2 B L
Chemical Exposure gastro- Chemical handling bag is being/will be labeled properly.
bags and intestinal or Chemical is being/will be stored in an isolated storage rooms having
drums respiratory provision for natural & forced ventilation.
1.
tract Certified Dust respirator is being/will be used.
irritation. Approved/certified vapor and dust respirator is being/will be provided.
Use of suitable protective clothing like Synthetic apron, splash goggles,
hand gloves, boots.
Cleaning Dust Severe 3 C M Do not let products enter in to drains. 1 B L
of formation. irritation to Use of Suitable protective clothing, gloves, boots and approved
Chemical Vapor, eyes, skin respiratory PPE‗s will be ensured.
Spillage. mist or gas dermatitis. Spillage is being/will be cleaned or neutralized with suitable media.
2.
formation. Respiratory Cleaning activities is being/will be carried out under strict vigilance.
Splashing irritation or
lung
damage.
CH 7: ADDITIONAL STUDIES
127
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
128 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Likelihood
Likelihood
Sr. Associated Health & Safety
Severity
Severity
Or Mitigation Measures
Risk
Risk
No. Hazards Impact (Risk)
Activity
Chemical Exposure to Blistering of skin, 4 C M SOPs are being/will be prepared and same will be followed. 2 B L
handling / vapours Skin burn. Containers are being/will be stored in well-ventilated area and
Loading & (due to Eye and skin away from all possible sources of ignition.
Unloading leakage irritation and Eye wash station and Safety Shower is/will be installed in nearby
from joints, respiratory location of storage facility.
corroded disorder. Employee is being/will be provided with protective equipment
lines failure like aprons (full suit), vapour respirator, gloves, boots and splash
etc.). goggles.
1. Handling trainings is being/will be provided to the operators/
workers periodically.
Spill control procedure is being/will be made available at storage
facility.
Provided an automatic leak detection system.
In case of Skin Contact, immediately flush skin with plenty of
water for at least 15 minutes while removing contaminated
clothing and shoes. Cover the irritated skin with an emollient.
Wash clothing before reuse. Thoroughly clean shoes before reuse.
Working in Exposure to Severe burns, 4 C M Use of provided PPE‗s is being/will be ensured by Safety officer/ 2 B L
Storage vapours corneal damage, Plant In-charge.
2. Area due to possible Eye wash station or Safety shower is being/will be installed in
spillage. irreversible eye storage area.
damage etc. Display of Safety warning postures/signs inside the area, also
Initial Risk Residual Risk
Process
Likelihood
Likelihood
Sr. Associated Health & Safety
Severity
Severity
Or Mitigation Measures
Risk
Risk
No. Hazards Impact (Risk)
Activity
CH 7: ADDITIONAL STUDIES
129
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
130 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Likelihood
Likelihood
Sr. Process Or Associated Health & Safety
Severity
Severity
Mitigation Measures
Risk
Risk
No. Activity Hazards Impact (Risk)
1. Loading & Exposure to Skin/Eye 4 C M Loading & Unloading activity is being/will be carried out in well- 2 B L
Unloading acid fumes irritation. ventilated area under proper supervision.
(due to Lung irritation Training for lifting and chemical transporting technique from one
leakage in due to vapor location to another location is being/will be provided periodically.
pipe/ inhalation. Periodic inspection of flanges/ferrule joints is being/will be carried
container/ out.
valves etc.). Neutralization media is being/will be kept available in areas where
Spillage. acids are stored/handled/used.
PPEs like chemical safety goggles or full face shield, Rubber or
neoprene gloves and additional protection including impervious
boots, apron will be used.
National Institute for Occupational Safety and Health an approved
respirator is being/will be used.
Store in a segregated and approved area. Keep container in a cool,
well-ventilated area. Keep container tightly closed and sealed until
ready for use. Avoid all possible sources of ignition (spark or flame).
2. Working in Exposure to Severe irritation 3 C M Acid proof floorings is being/will be constructed. 2 B L
Storage acid fumes. to eyes, skin. Storage area is being/will be well ventilated.
Area. Body burns. NIOSH approved respirators shall be used.
PPEs like chemical safety goggles or full face shield, Rubber or
neoprene gloves and additional protection including impervious
Initial Risk Residual Risk
Likelihood
Likelihood
Sr. Process Or Associated Health & Safety
Severity
Severity
Mitigation Measures
Risk
Risk
No. Activity Hazards Impact (Risk)
CH 7: ADDITIONAL STUDIES
131
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
132 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Finally, suggesting the measures to minimize or mitigate risks to meet appropriate acceptability criteria.
The planning for emergency evacuation has borne in mind whilst interpreting the results.
In consequence analysis studies, in principal three types of exposure to hazardous effects are
distinguished:
Explosion
The chosen damage criteria are given and explained as per the Guidelines for QRA – PHAST Software,
version 6.7 (DNV) & Purple Book for QRA released by Centre for Chemical Process Safety (CCPS).
The effect is expressed in term of the probability of death and different degree of burn. The
consequence effects studied to assess the impact of the events on the receptors are provided in Table
No. 7.9.
Radiation
2 Damage to Equipment Damage to People
(kW/m )
1.2 Solar heat at noon -
1.6 - Minimum level of pain threshold
2.0 PVC insulated cable damage
4.0 - Causes pain if duration is longer than
Radiation
2 Damage to Equipment Damage to People
(kW/m )
20 sec. But blistering is unlikely.
Pain threshold reached after 8 sec.
6.4 -
Second degree burns after 20 sec.
Minimum energy to ignite wood with a 1% lethality in one minute. First
12.5
flame; melts plastic tubing. degree burns in 10 sec.
16.0 - Severe burns after 5 sec.
Minimum energy to ignite wood at 100% lethality in 1 min.
25.0
identifying long exposure without a flame. Significant injury in 10 sec.
100% lethality in 1 min.
37.5 Severe damage to plant 50% lethality in 20 sec.
1% lethality in 10 sec.
Consequences of Explosion
A flash fire over the whole length of the explosive gas cloud;
A blast wave, with typical peak overpressures circular around ignition source.
As explained above, 100% lethality is assumed for all people who are present within the cloud proper.
The following damage criteria may be distinguished with respect to the peak overpressures resulting
from a blast wave.
The effects of the shock wave vary depending on the characteristics of the material, the quantity
involved and the degree of confinement of the vapor cloud. The peak pressures in an explosion
therefore vary between a slight over-pressure and a few hundred kilopascals (kPa). The pressure of the
shock wave decreases rapidly with the increase in distance from the source of the explosion. Details of
Type of Damage and Peak overpressure are provided in Table No. 7.10
CH 7: ADDITIONAL STUDIES
133
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
134 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
The effect of exposure to toxic substance depends upon the duration of exposure and the
concentration of the toxic substance. Short-term exposures to high concentration give Acute Effects
while long term exposures to low concentrations result in Chronic Effects. Only acute effects are
considered under hazard analysis. Since they are likely credible scenarios. These effects are:
Following are some of the common terms used to express toxicity of materials.
Threshold Limit Value (TLV): it is the permitted level of exposure for a given period on a
Short Time Exposure Limit (STEL): It is the permitted short term exposure limit usually for a 15
minutes exposure.
Immediately Dangerous to life and health (IDLH): It represents the maximum concentration of a
chemical from which, in the event of respiratory failure, one could escape within 30 minutes
without a respirator and without experiencing any escape/impairing (eg. Severe irritation) or
Lethal Concentration Low (LCLo): It is the lowest concentration of a material in air, other than
Toxic Concentration Low (TCLo): It is the lowest concentration of a material in air, to which
humans or animals have been exposed for any given period of time that has produced a toxic
below which it is believed that nearly all individuals could be exposed for up to 1 hour (without
a respirator) without experiencing other than mild transient adverse health effects or without
below which it is believed that nearly all individuals could be exposed for up to 1 hour without
experiencing or developing irreversible or other serious health effects or symptoms that could
Hazards that can lead to accidents in operations are discussed in this section. Important hazardous
events classification is provided in Table 7.11.
Table No. 7.11 – Event Classification
CH 7: ADDITIONAL STUDIES
135
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
136 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Meteorological
Atmospheric stability plays an important role in the dispersion of the chemicals. ―Stability means, its
ability to suppress existing turbulence or to resist vertical motion‖.
Variations in thermal and mechanical turbulence and in wind speed are greatest in the atmospheric
layer in contact with the surface. The air temperature has influenced these turbulences greatly and air
temperature decreases with the height. The rate at which the temperature of air decreases with height is
called Environment Lapse Rate (ELR). It will vary from time to time and from place to place. The
atmosphere is said to be stable, neutral or unstable according to ELR less than, equal to or greater than
Dry Adiabatic Lapse Rate (DALR), which is a constant value of 0.98ºC per 100 meters. Weather
conditions selected for consequence analysis are provided in Table no. 7.12.
Weather Condition
Time Remarks Temperature Wind speed Stability
o
( C) (m/s) Class
Day Time Prevalent during the day, most times of the year 32 1.5 D
Night Time Prevalent during the night, most times of the year 23 1.5 E
Monsoon Period Prevalent during the monsoon months 25 4.0 D
A - Extremely unstable
B - Moderately unstable
C - Slightly unstable
D - Neutral
E - Slightly stable
F - Moderately stable
Solar radiation
Surface wind
When the atmosphere is unstable and wind speeds are moderate or high or gusty, rapid dispersion of
vapors will occur. Under these conditions, air concentrations will be moderate or low and the material
will be dispersed rapidly. When the atmosphere is stable and wind speed is low, dispersion of material
will be limited and air concentration will be high.
7.4.3 Consequences Analysis
The consequences of the release of Hazardous substances by failures or catastrophes and the damage
to the surrounding area can be determined by means of models. Models help to calculate the physical
effects resulting from the release of hazardous substances and to translate the physical effects in terms
of injuries and damage to exposed population and environment. To assess the damage level caused by
the various accidental events, it is essential to firm up the damage criteria with respect to different types
of accidents e.g. thermal radiation, explosion overpressure etc.
Consequence analysis involves the application of mathematical, analytical and computer models for
calculation of effects and damages subsequent to a chemical release accident. Consequence models are
used to predict the physical behavior of the hazardous incidents. The techniques used to model the
consequences of chemical and other hazardous material releases cover the following:
Modeling of the size and shape of flammable and toxic gas clouds from releases in the
atmosphere
Modeling of the flame and radiation field of the releases that are ignited and burn as jet fire,
Modeling of the explosion fields of releases, which are ignited away from the point of release
The information normally required for consequence analysis includes meteorological conditions, failure
data of equipment and components, ignition sources, population characteristics within and outside the
plant, acceptable levels of risk etc.
The consequence analysis for the modeled scenarios has been done using DNV‘s software PHAST
(Process Hazard Analysis Software Tool) which allows assessment of situations which present potential
hazards to life, property and the environment, and to quantify their severity. PHAST examines the
progress of a potential incident from the initial release to far-field dispersion including modeling of
pool spreading and evaporation, and flammable and toxic effects. It is recommended for use by the
Ministry of Environment & Forests per its EIA Guidelines, dated January 2001.
PHAST Professionals sophisticated modeling calculates distances effect produced by hazardous events.
With this information, you can evaluate the need for mitigating measures such as changes in design,
operation or response. PHAST software can be used to model a proposed facility or operational change
to ease the selection of the most effective solutions. With PHAST Professional, you can define special
events, model the change in a leak over time, and investigate the details of behavior with special stand-
alone models and much, much more.
PHAST is integrated into safety and meets regulatory requirements. It uses unified dispersion modeling
to calculate the results of the release of material into atmosphere
1. It gives the consequence results in terms of – Flammable, Toxic and Explosion effects.
CH 7: ADDITIONAL STUDIES
137
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
138 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Jet fire and pool fire scenario along with their respective effect zones (risk contour).
3. Toxic parameters-
Categorize the toxic results in terms of ERPG, IDLH and STEL values.
Summarize results in terms of equivalent toxic dose along with effect zones.
4. Explosion parameters-
Categorize the explosion effects in terms of overpressures levels along with distance covered.
Assumption
For consequence analysis, assumptions regarding Meteorological, Pasquil Stability Classes, Wind
velocity, Ambient Temperature, Relative Humidity, Inventory, Ground Roughness, Model used etc. are
very important. In this report, the following assumptions have been considered.
1. Meteorological conditions
Atmospheric Conditions: No Inversion
3. Other assumptions
Ground Roughness: Ground Roughness has been considered as 0.3 M.
Dispersion model of both Heavy Model and also Gaussian distribution have been used as
applicable/appropriate.
Inventory: Release of 100% of the inventory will be considered. For this, failure ofthe container
Storage conditions: Storage conditions will be considered as they are practically stored at site.
Leak
Catastrophic rupture
3. Leak size
5 mm hole
4. Storage conditions
Pressure
Temperature
5. Weather condition
Wind speed
Pasqual stability
Atmospheric temperature
Relative humidity
As a first step towards risk assessment is to identify the possible release scenarios based on available
information about scenario development for Maximum Credible Accident Scenarios (MCAS).
CH 7: ADDITIONAL STUDIES
139
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
140 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Radiation level effect distance and overpressure effect distance due to the release of Dimethyl Aniline
are presented below:
Table No. 7.13 – Radiation effect distance due to release of Dimethyl Aniline
Effective Distance in
Name of Failure Met meter to Toxic Level
Consequence
Chemical Scenario Data
IDLH (100 ppm)
1.5/D 3.65
5 mm leak 1.5/E 3.64
Late Pool Fire 4/D 3.64
Dimethyl Aniline and Toxic
Dose 1.5/D 3.66
Catastrophic
1.5/E 3.65
Rupture
4/D 3.65
The contours for effect distance generated due the release of Dimethyl Aniline is presented below;
CH 7: ADDITIONAL STUDIES
141
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
142 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Figure No. 7.2 – Late Pool Fire and Toxic Dose due to 5 mm leak in storage drum at weather
condition 1.5/D.
Figure No. 7.3 – Catastrophic Late Pool Fire and Toxic Dose due to leak in storage drum at
CH 7: ADDITIONAL STUDIES
143
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
144 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
The effect of Late Pool Fire and Toxic Dose due to 5 mm leak and Catastrophic Rupture are inside project
site.
Table No. 7.15 – Control Measures to Reduce the Risk of Fire and Explosion
Sr.
Activity Safety Precautions
No.
1. Transportation of Training is being/will be provided to driver and cleaner regarding the safe
Chemicals by driving, hazards of chemicals, emergency handling, and use of SCBA sets.
road tanker TREM card is being/will be kept at the time of TL.
/truck. SCBA set is being/will be kept at the time of TL.
Fire extinguishers are being/will be kept at the time of TL.
Instructions are being/will give not to stop tanker/truck in populated area.
Hazard Identification symbol and emergency telephone number are displayed as
per HAZCHEM CODE.
Appropriate PPEs will be kept with TL.
In case of leak or spill: Source of leakage will be checked.
Damaged containers or spilled material will not attend without wearing
appropriate protective clothing.
Leak is being/will be stopped, if possible to do so without risk.
Water spray is being/will be used to reduce vapors (but do not put water directly
on leak, spill area or inside container).
Combustibles (wood, paper, oil, etc.) will keep away from spilled material.
2. Unloading of
Priority will give to Tanker/truck to immediately enter the storage premises at
Chemicals from site and shall not be kept waiting near the gate or the main road.
tanker/truck. Security person checks License, TREM CARD, Fire extinguisher condition; SCBA
set condition, Antidote Kit, required PPEs as per SOP laid down.
Following precautions are taken during unloading:
Wheel stopper will be provided during TL at platform.
Tanker unloading procedure will be followed according to check list and
implemented strictly.
Flexible SS hose connection will done at TL outlet line.
Sr.
Activity Safety Precautions
No.
Static earthing provision is/will be made for tanker unloading.
Only day time unloading will be permitted.
3. Drum Storage Drum is being/will be stored at designated location or secured in a safety
and Handling storage cabinet.
Approved methods of equipping a drum and dispensing liquids from it is
being/will be followed.
Drums, carboys and related accessories is being/will be inspected on regular
basis for maintenance purpose.
All the vessels and equipment‗s is being/will be earthed properly and protected
against static electricity. Also, proper earthing facilities shall be provided for
drums.
Materials are being/will be transferred by pumping through pipeline or by
vacuum, from drums.
Drum for flammable liquid is being/will proper closures that can withstand the
expected handling conditions without leaking.
Drum will be inspected at regular intervals.
All storage areas is being/will be isolated from all sources of open flame and well
posted with 'NO SMOKING' signs and provided with adequate fire
fighting/extinguishing systems.
Combustibles (wood, paper, oil, etc.) is being/will be keep away from spilled
material.
Dyke wall of sufficient capacity (i.e. 10% extra) is being/will be available around
the storage tanks.
4. During Process Process parameters control is being/will be provided vide Standard Operating
Procedures.
All reaction vents is being/will be connected to either vapor condensers system
or gaseous scrubber system.
Trained person is being/will be engaged for handling of hazardous materials.
Proper safety precautions is being/will be taken during handling of hazardous
materials.
Further all the vessels is being/will be examined periodically by a recognized
competent person.
All the vessels and equipments is being/will be well earthed and well protected
against Static Electricity. Also for draining in drums, proper earthing facilities
should be provided.
Reaction column pressure and temperature data should be regularly monitored
and assessment of properties of flammable chemicals should be evaluated
periodically to avoid fire/explosion scenarios.
Temperature indicators is being/will be provided near all reactors.
Caution note, safety posters, stickers, periodic training & updation in safety and
emergency preparedness plan must be displayed and conducted.
Total reaction is being/will be carried out in closed jacketed vessel having
cooling water supply to control temperature in case of run-away reaction.
Emergency reactor shutdown system is being/will be implemented
CH 7: ADDITIONAL STUDIES
145
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
146 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Mitigation Measures
Regular monitoring of plant area is being/will be conducted and records will be maintained. At strategic
point of the plants, online detectors will be provided for detection of such emissions.
Lines of such hazardous chemicals is being/will be tested periodically and such tests will be recorded.
All lines carrying toxic liquid is being/will be continuous welded and provided with proper slopes,
special tongue and groove joints to avoid liquid stagnation and leakage.
In the process area, all the strategic pumps is being/will be of submerged type so as to eliminate
leakages from glands.
Safe Operating Procedures and EMERGENCY RESPONSE PROCEDURES is being/will be followed strictly.
Level transmitter is being/will be also available with low level/high level auto cut-off provision.
Unit will be provided various types of fire extinguishers inside the factory premises which are mentioned in
below Table No. 7.16.
Unit will be provided one underground fire water storage tank of capacity 1,50,000 Lit.
Unit will be provided fire detection & alarm system at key location.
There is one fire station in Ankleshwar GIDC at a distance of approx. 2.5 km from project site. The time taken by
fire tender to reach the site is about 3 to 5 minutes.
Other Fire fighting facilities like, fire monitor, foam trolley, fire hose boxes with hose pipe, sand buckets,
fire blanket, etc. have been provided within the company at conspicuous locations.
Emergency Action Team members is being/will be working round the clock in all shifts.
First aider is being/will be available round the clock in all shifts of all plants / sections.
Rescue kits with SCBA (Self-Contained Breathing Apparatus) sets will be available at site to treat with
any kind of chemical emergencies.
Volume level indication with alarm and trips for high level is being/will be provided for vessels
CH 7: ADDITIONAL STUDIES
147
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
148 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Only trained persons to be engaged in reaction processes like charging of raw material, loading &
unloading of chemicals and operation of reactor, etc.
Adequate open space to be kept around the periphery of reactor for the ease of operation.
All the electrical fittings in the factory to be made of flame proof type.
Training will be provided to the persons involved in preparation of LDAR program. Internal as well as
external audits will be carried out for effective implementation of LDAR program.
Parameter will be set for repair and monitor the leaks; the said parameters will be more stringent than
regulatory values.
The detected leaks will be repaired within time bound. Frequency for monitoring leaks will be quarterly
or monthly basis.
Plant oriented – due to design errors, operational defects, chemical changes, failure of equipments
human errors etc. (in the plant area).
Degrees of Disaster
LOW – Can cause injury, illness and equipments damage but not very serious and quickly manageable.
MEDIUM – Critical situation, can cause serious injuries to personnel, serious illness property and
equipment damage.
HIGH – Catastrophic situation, major danger, can cause death, major widespread illness, injuries, loss of
On site Emergency Plan will be required to meet the emergency condition during disastrous event in the plant.
Its objectives are to:
Minimize damage
CH 7: ADDITIONAL STUDIES
149
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
150 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Key Personnel.
This is the main center from where the operations to handle the emergency are directed and co-ordinated.
Facilities to be made available in the emergency control are:
Pollution records
Walky-talky
Telephone directory
Company Directory
Layout plan showing Storage area of hazardous materials, Storage of safety equipments, Fire fighting
system and additional source of water, Site entrance, roadway and emergency exist, Assembly points,
surrounding location.
Display board containing emergency telephone number of local fire brigade, GIDC Police station,
Assembly Points
A safe place far away from the plant but within the premises should be pre determined as assembly point where
in case of emergency personnel evacuated from the affected areas are to be assembled. The plant workers,
contract workers and visitors should assemble in assembly point in case of emergency and the time office clerk
should take their attendance so as to assess the missing persons during emergency.
The Key Personnel for onsite emergency
Incident Controller
a. Communication Officer
c. Telephone Operators
d. Medical Officer
e. Personnel/Administrative Officer
The general manager of the Plant will be the site main controller. His task will be to co-ordinate all internal and
external activities from the Emergency Control Centre at Main Security Gate from where all operations will be
directed. He shall:
Assess the magnitude of the situation and decide whether the evacuation of staff from the plant is
needed.
Exercise and direct operational control over areas other than those affected.
Maintain a continuous review of possible development and assess in consultation with work incident
Liaison with Police, Fire Service, Medical Services, Factory Inspectorate and other Govt. Agencies.
Intimate Off-site Emergency controller if the emergency spreads beyond the factory premises and likely
The Site Main Controller will declare the emergency and he will instruct gate office to operate the
CH 7: ADDITIONAL STUDIES
151
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
152 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
He is the next responsible officer after the Site Main Controller. In case of emergency he will rush to the place of
occurrence and take overall charge and report to the Site Main Controller by personnel communication system
like cell phones or walky-talky and inform about the magnitude of emergency.
He will assess the situation and considering the magnitude of emergency he will take decision and inform
Communication Officer to communicate the news of emergency to different agencies. He will give direction to
stop all operations within the affected area. He will take the charge of Main Controller till the Main Controller
arrives. He will order for shutdown and evacuation of workers and staffs from affected area. He will inform all
Key Personnel and all outside agency for help. He will inform security and fire officers and State Fire Services. He
will ensure that all non-essential workers/staff are evacuated to assembly point and areas searched for
casualties. He will report all significant development to Communication Officer. Moreover he will advise to
preserve evidence of emergency into the cause of emergency.
Communication Officer - On hearing the emergency siren/alarm he will proceed to the control center and
communicate to Incident Controller. He will collect information from the emergency affected area and send
correct message to Site main controller for declaration of emergency. He will maintain a log book of incident.
He will contact all essential departments. He will take stock of the meteorological condition from local
meteorological Department. He will communicate all information as directed by Works Main Controller.
Security or Fire Officer - The Security or Fire officer will be responsible for the fire fighting. On hearing the
emergency alarm/siren, he will reach the incident area with fire and security staff. Immediately after arrival to
the emergency area, he will inform through telephone or walky-talky to the communication officer. He will
inform to the Incident Controller about the situation and requirement of outside help like State Fire Service and
other mutual aid members. At the site, the entire fire squad member will respond to the advice and information
given by the incident controller. The security will control the visitors and the vehicle entry.
Telephone Operator - In case of fire is discovered but no emergency siren is operated, he shall ensure the
information about the location of the fire/emergency incident from the persons discovered/notices the above
and communicate to different Key Personnel immediately with clear message.
Medical Officer - Medical Officer with his team will report to the Incident Controller on hearing the
fire/emergency siren immediately. The ambulance will be parked nearest to the site of incident. Name of injured
and other casualties carried to the Hospital will be recorded and handed over to Incident Controller. The
ambulance will carry the injured to the nearest hospital for treatment.
Personnel/Administrative Officer - He should work as a liaison officer liaisoning with site main controller and
other essential departments such as Police, Press and Statutory authorities. His responsibilities shall include:-
To ensure that casualties receive adequate attention to arrange additional help if required and inform
relatives.
To control traffic movement into the factory and ensure that alternative transport is available when
needed.
When emergency is prolonged, arrange for the relief of personnel and organize refreshment and
catering facilities.
Essential Works and Team Leaders - During emergency the plants immediately affected or likely to be
affected, as determined by the Site Main Controller, need to be shut down for safety. In the area immediately
affected, it may be possible to isolate equipment from which flammable or toxic material is leaking. This work
must be immediately carried out by plant supervisors and essential operators. Workers/staff need to be
nominated to carry out the following essential works at the time of emergency:
The Site Main Controller will require a task force of suitable trained people for the following works:-
Manning the factory entrance in liaison with security to direct emergency vehicle containing the gate
For these essential jobs designated teams should be made available. The responsibilities of the team and the
leader should be given.
Communication team.
Security Team.
Transport Team.
Safety team.
CH 7: ADDITIONAL STUDIES
153
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
154 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Communication System
Communication is a key component to control an emergency. The following communication system may be
provided in the plant-
Walky-Talky
Cell phone
Intercom/paging
Alarm System
Suitable alarms require to be made for each of emergencies. The alarm should be audible in every part of the
site. In areas of high noise levels, an alternative to an audible alarm, such as flashing lights may be installed.
There are three levels of emergencies;
Any person noticing an emergency should be able to raise or cause to be raised, the First Level Emergency
Alarm. All employees must be trained to operate such emergency alarms. There should be adequate places
within the site, where provision to raise an alarm is available. This could be an audible warning, individual signal
or message to a manned location.
In case there is a risk of the event spreading beyond the original unit and / or outside the site premises, then a
second level emergency alarm can be raised. This could be across the entire site, as opposed to the first which
could be at a part of the site.
In case a third level or (major) emergency is to be declared, telephonic information to members of the local
crisis group, or in case of failure of power and formal communication systems, and non-availability of mobile
phone signals, a big bell or a messenger can be deployed.
Declaration of a major emergency should never be done on whims, immature judgement or without proper
thought. Further, because of the scale of activity that will commence due to declaration of a major emergency, it
is advisable to restrict the authority to declare it, and a limited number of persons may be invested the authority
to declare such an emergency, although care should be taken to ensure that at least one such person is always
at site.
Identifying the Type of Emergency through an Alarm:
Alarm systems vary and will depend upon the size of individual sites. The person noticing the incident should
warn all those in the site vicinity to either evacuate or take other immediate action according to a
predetermined plan. Automatic alarms may be considered. Audible alarms include sirens or other alarms over
public address systems.
Alarms for a particular type of emergency (toxic leak or fire) can be raised separately enabling different
emergency plans to be put in motion. However, this must be done after giving due thought about avoiding
confusion in the minds of the site personnel.
Use of alarms can be carried out to communicate different information such as:
Escape Route:
The escape route from each and every plant should be clearly marked. The escape route is the shortest route to
reach out of the plant area to open area, which leads to assembly point. This route should be indicated on the
layout plan attached to the On-site Emergency Plan.
Evacuation:
All non-essential staff should be evacuated from the emergency site. As soon as the emergency siren rings the
workers have to shut down the plant and move to the assembly point. The plant shut down procedure in case of
emergency should be prepared and kept ready and responsible persons should be nominated for the purpose.
Counting of Personnel:
All personnel working in the plant should be counted. Time office persons should collect the details of
personnel arriving at the assembly point. These should be checked with the attendances of regular workers,
contract workers present in the site on the day of emergency. The accident control should be informed and
arrangement should be made for searching missing persons in the emergency affected area. The employees‘
address, contact number of next to kin should be maintained in the time office so that during emergency
relatives of those affected due to emergency may be informed accordingly. Information in respect of emergency
should be given to the media and other agency.
After control of emergency the Work Incident Controller will communicate to the works main controller about
the cessation of emergency. The main controller can declare all clear by instructing the time office to sound ―All
Clear Sirens‖.
CH 7: ADDITIONAL STUDIES
155
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
156 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Mutual aid scheme should be introduced among industries so that in case of emergency necessary help from
mutual aid partner may be extended.
Mock drills on emergency planning should be conducted once in 6 months and sequence of events should be
recorded for improvement of the exercise. Exercises on On-site Emergency Planning should be monitored by
Factory Inspectorate and the high officials of the organization and the plan is reviewed every year.
Emergency facilities:
The following facilities should be provided in any factory to tackle any emergency at any time.
Emergency equipment and rescue equipment like breathing apparatus with compressed air cylinder,
Fire proximity suit, Resuscitator, Water gel Blanket, Low temperature suit, First aid kit, Stretchers,
Torches, Ladders.
Safety Equipment like Respirators, Gum boots, Safety helmets, Asbestos Rubber hand gloves, Goggles
and face shield, Toxic gas measuring instruments, Explosive meter, Oxygen measuring instruments,
Wind direction indicator.
Govt. Officials.
Transport provider.
To provide basic information on Risk and Environmental Impact Assessment to the Local/District
Authority, Police, Fire Brigade, Doctors, surrounding industries and the public and to appraise them on
the consequences and the protection/prevention measures and control plans and seek their help to
Formation of the Local Crisis Group: This Group is headed by the Deputy Collector or the Magistrate of
the Industrial area and is responsible for the management of any industrial emergency confined to the
local area.
Formation of the District Crisis Group: This Group is headed by the District Collector of the District and
is responsible for any major Industrial emergency affecting Local and beyond any industrial area of the
District.
Ensure dovetailing of the local emergency plan with the district off-site emergency plan;
Educate the population likely to be affected in a chemical accident about the remedies and existing
preparedness in the area;
Conduct at least one full scale mock-drill of a chemical accident at a site every six months and forward a
CH 7: ADDITIONAL STUDIES
157
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
158 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Review all the on-site emergency plans prepared by the occupier of Major Accident Hazards installation
Assist the district administration in the management of chemical accidents at a site lying within the
district;
Ensure continuous information flow from the district to the Centre and State Crisis Group regarding
Forward a report of the chemical accident within fifteen days to the State Crisis Group; and
Conduct at least one full scale mock-drill of a chemical accident at a site each year and forward a report
of the strength and the weakness of the plan to the State Crisis Group.
The Off-site Emergency Plan shall be prepared by the District Magistrate in consultation with the factory
management and Govt. agencies. The plan contains up-to-date details of outside emergency services and
resources such as Fire Services, Hospitals, and Police etc. with telephone number. The district authorities are to
be included in the plan area.
Police Department.
Revenue Department.
Fire Brigade.
Medical Department.
Municipality.
Gram Panchayat.
Railway Department.
Telephone Department.
Factory Department.
Electricity Department.
Explosive Department.
Mock exercises on Off-site plan should be carried out at least once in a year to train the employees, up to date
the plan, observe and rectify deficiencies.
7.7 OCCUPATIONAL HEALTH & SAFETY
Occupational health and safety is about preventing people from being harmed by work or becoming ill from
work by taking adequate precautions and providing a safe and healthy work environment. Working with
chemicals and/or in a chemical industry poses many risks, including causing diseases/injuries like chemical burn,
Asthma, Allergies, Cancer, Asphyxiation etc. The necessary personal protective equipments should be given to
all the workers.
During employment, every year to ascertain physical fitness of the person to do the particular job.
Medical records will be maintained by unit.
Once in a year, to ascertain the health status of all the workers in respect of occupational health hazards
to which they will be exposed and in cases where in the opinion of the Factory Medical Officer it will be
necessary to do so at a shorter interval in respect of any workers;
In periodic and pre-medical examinations, various parameters will be checked viz., LFT, Chest X-rays,
Audiometry, Spirometry, Vision testing (Far & near vision, color vision and any other ocular defect) ECG
and other parameters will be found necessary as per the opinion of Factory Medical officer.
CH 7: ADDITIONAL STUDIES
159
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
160 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Workers will be checked for physical fitness with special reference to the possible health hazards likely
to be present where he/she is being expected to work before being employed for that purpose. Basic
examinations like Liver Function tests, chest x ray, Audiometry, Spirometry Vision testing (Far & Near
vision, color vision and any other ocular defect) ECG, etc. will be carried out. However, the parameters
and frequency of such examination will be decided in consultation with Factory Medical Officer.
While in work, all the workers will be periodically examined for the health with specific reference to the
hazards which they are likely to be exposed to during work. Health evaluation will be carried out
considering the bodily functions likely to be affected during work. The parameters and frequency of
Each workplace must be evaluated to identify potential hazards from toxic & corrosive substances or
harmful physical agents. Air-borne concentration of toxic chemicals will be measured and record will be
kept.
The current state-of-the-art exposure measurement model is as follows: For purposes of measuring
worker exposure across a single shift it is sufficient to place a reasonably accurate exposure measuring
device on the worker, within the worker‘s breathing zone, and have it operate for nearly the full shift.
Work zone monitoring will be carried out in every month by independent competent third party. Records will be
kept as per Gujarat Factories Rules. Sampling locations will be identified. Ambient Air & Noise Monitoring shall
be done as per GPCB Consent to operate requirements. Following information will be incorporated in the
format for maintaining records of work zone monitoring:
Identified contaminant
Number of Samples
7.7.8 EMP to Keep Air-born Concentration of Toxic and Hazardous Chemicals below its PEL
/TLV
In work operations where employees only handle chemicals in sealed containers, which are not opened
under normal conditions.
Provide employees with information and training to the extent necessary to protect them in the event
The employer must ensure that each container of hazardous chemicals in the workplace is labeled,
Supply of proper PPEs like Air mask, Berating canisters at the places where there is possibility of
Regular maintenance program for pumps, equipment, instruments handling toxic and corrosive
chemicals.
CH 7: ADDITIONAL STUDIES
161
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
162 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Mitigation measures/ Safety Measures proposed to avoid the human health hazards are mentioned in
additional studies. In addition to these safety measures, personal protective equipment (IS approved) will also
be provided to the required personnel. List of PPE‗s are given below.
Air-borne concentration of toxic chemicals will be measured and records will be kept.
Impact of the above mentioned unsafe conditions on workers will be studied and remedial measures for the
same will be adopted.
Mock Drills
To evaluate the effectiveness of emergency preparedness and to spread the awareness among employees mock
drill will be carried out at the interval of every six months.
After completion of the mock drill, summary report shall be made and corrections will be done if any weakness
has been observed.
7.8 SUMMARY
Additional studies i.e. Public consultation i.e. public hearing details, Risk Assessment & Hazard study and
Disaster Management Plan has been incorporated in this report as per scope of TOR letter. Project site is
located within the Notified Industrial Area, GIDC Ankleshwar which was notified prior to the EIA Notification,
th
2006 coming in to force hence as per O.M. J-11011/321/2016-IA. II (I) dated 27 April, 2018, Public Consultation
is not applicable for proposed expansion project.
To identify major risks in the manufacturing process and to evaluate on-site and off-site consequences of
identified hazard scenarios qualitative and quantitative risk assessment has been conducted.
The installation of all the equipment will be as per guidelines of provision of Gujarat Factories Rule
1963.
First Aid facility and First-aid trained person will be available at the time of handling operation.
Chemical Drums will be stored at designated location or secured in a safety storage cabinet.
Drums, carboys and related accessories will be inspected on regular basis for maintenance purpose.
All the vessels and equipment‗s will be earthed properly and protected against static electricity.
Company will be made formal agreements with nearby hospitals to attend fire and/or emergency cases
for attending the affected persons in the emergency arising out of accident.
First Aid Boxes will be made available at Security gate, emergency room, process plants, etc,.
CH 7: ADDITIONAL STUDIES
163
NAVDURGA DYES AND CHEMICALS, GIDC ANKLESHWAR, BHARUCH
NAVDURGA DYES &
164 EIA & EMP REPORT FOR PROPOSED EXPANSION AND/OR REDUCTION IN EXISTING CHEMICALS
PRODUCTION CAPACITY AND ADDITION OF NEW PRODUCTS WITHIN EXISTING PREMISES
Upliftment of Local Peoples: Unit has already allotted budget (Rs. 0.40 Lakhs) for various welfare activities
within study area under CER plan which will have positive impact. The local people within nearby villages will
benefit of hygienic sanitation facilities, health facilities, drinking water facilities, etc. to be provided by
proponent.
area.
The implementation of Solar Street Light and roof top solar panel will help in energy conservation.
The implementation of Rain Water Harvesting Scheme will help in resource conservation.
Activities under CER plan will be decrease unemployment ratio and have upliftment of socioeconomic
8.4 SUMMARY
Expansion in established project will give major physical and social benefit as well as generation of employment.
It would help in increasing living standard of the nearly populations/ habitants through their different activity.
CHAPTER 9 – ENVIRONMENTAL COST BENEFIT
ANALYSIS
During the scoping/ToR stage, no recommendation of environmental cost benefit analysis was suggested by the
appraisal committee. Hence, conducting a detailed environmental cost benefit analysis is not necessary for this
particular project.
To treat and disposed-off all the pollutants viz. liquid, gaseous and solid waste within statuatory limits
with appropriate technology.
To promote green-belt development.
Construction materials will be covered with tarpaulin sheets throughout the construction phase to avoid
dust generation.
Regular water sprinkling will be done to avoid dust generation from transportation and stored material.
Trucks used for transportation of construction materials shall be covered with tarpaulin sheet to avoid
Only PUC vehicle will be used for the transportation of materials and equipment.
Regular maintenance/ inspection of vehicles used at site will be done.
PPEs will be provided to the construction workers. Hence there will be no significant impacts on their
After proposed expansion, Natural Gas will be used as a fuel in boiler with 12 m stack height.
The adequate greenbelt developed in and around the plant shall greatly serve as an efficient barrier for
prevention of air outside the plant premises.
Regular monitoring will be done as per monitoring plan mentioned in chapter 6.
PPEs will be provided to the workers. Hence there will be no significant impacts on their health due to
emission.
There is no process emission from the existing production activity. After proposed expansion, HCl will
be generated from the Chlorosulphonic storage tank and it will be controlled by providing two stage
alkali scrubber.
HCl will be generated from the proposed chlorosulphonic storage tank. Adequate scrubbing system will be
provided for the control of HCl gases to be emitted. The details of Air pollution control system for the HCl gas
emission are given in Table No. 10.1. Schematic diagram of air pollution control measures are given in Figure
No. 10.1.
Figure No. 10.1 – Schematic Diagram of APCM for Process Emission (HCl Gas)
Size of Capacity of
Sr. Scrubber (m) Scrubbing Pump
MOC Scrubber Output
No. Media Capacity
Ht. Dia. Tank (KL)
For control of fugitive emission following practices is already implemented in existing unit and same shall be
continued after proposed expansion.
The raw material is being/will be stored in closed containers and will be handled through closed system
Manufacturing activity is being/will be carried out in closed reactors/vessels and regular checking and
circulation.
Reactor handling pumps shall have mechanical seals to prevent leakages. Also provide with breather
The sprinkling of water is being/will be done along the internal roads in the plant in order to control the
Thick greenbelt is being/will be developed around the plant to arrest the fugitive emissions.
For control of VOC emission following practices is already implemented in existing unit and same shall be
continued after proposed expansion.
loading/unloading and they will be kept in proper working conditions through regular inspection and
maintenance.
Proper maintenance schedule is being/will be adhered to avoid emissions through flange joints, pump
seals etc.
Regular inspection of floating roof seals and proper preventive maintenance of roofs and seals for
tanks.
emissions.
Airborne dust at all transfers operations is being/will be controlled either by spraying water or
providing enclosures.
The water requirement will be met by GIDC and hence potential impact on groundwater resources is
not envisaged as source of water is not bore well.
Runoff from site is being/will be prevented by providing adequate drainage system.
o After liberal curing on the first day, all concrete structures shall be painted with curing chemical to save
water. This will stop daily water curing hence save water.
o Concrete structures shall be covered with thick cloth/gunny bags and then water should be sprayed on
o Ponds shall be made using cement and sand mortar to avoid water flowing away from the flat surface
while curing.
Total 3.80 KLD effluent will be generated after proposed expansion which will be send to existing ETP
and finally discharged to CETP – ETL for further treatment.
Detailed wastewater generation and water balance diagram mentioned in section 2.8.2 of chapter – 2.
Management, Collection and Disposal of Waste Streams to be generated from Spillage, Leakages, Vessel
Storage area of Raw Material and Finished Products is/will be provided with dyke walls to hold any
unforeseen spillage/leakage. Curb wall will be made all around the production areas which will be
connected to effluent collection tank.
Spillage from raw material and/or finished product handling will be collected in a sump through a drain
and flushed with water and pumped to the effluent collection tank for treatment. It will be diluted as
per the required properties of the spillage material.
All flooring in production and plant area is/will be made with impermeable concrete thus elimination
Do not touch damaged containers or spilled material unless wearing appropriate protective clothing.
Vessel washing water is/will be collected through appropriate channels and taken to effluent collection
Machinery used for construction will be of high standard of reputed make and will adhere to
International standards. These standards itself take care of noise pollution control / vibration control
hearing capacity of workers as well as planning of working hours and shift of workers.
The adequate greenbelt developed in and around the plant shall greatly serve as an efficient barrier for
prevention of noise propagation outside the plant premises.
Only PUC vehicle will be used for the transportation of materials and equipment.
All the equipment / machineries operated in the project will be designed / operated in such a way that
Periodical noise monitoring is being/will be carried out to ensure that ambient noise levels are
restricted to permissible limits.
Noise generating equipment like pump, motors, compressors, blower, engines etc. is being/will be
mounted on sturdy concrete foundations with proper and suitable rubber padding.
Safety blow off valves, discharge pipes, relief valves, etc. is being/will be equipped with silencers.
Regular lubrication and preventive maintenance is being/shall be done to reduce vibration and noise
generation.
The solid wastes generated will be disposed properly through municipal solid waste disposal site to
Collection, storage and disposal of solid / hazardous waste will be carried out as per Hazardous and
Other Wastes (Management and Trans Boundary Movement) Rules, 2016.
All the solid/hazardous waste generated shall be packed in HDPE bags and stored in Hazardous Waste
Used oil will be disposal by selling to GPCB/ MoEF approved recycler/ reuse as lubricant within
premises.
Properly packed and labeled waste is being/will be transported through dedicated vehicle to
authorized TSDF site.
Methodology of de‐contamination and disposal of discarded containers and its record keeping.
Rinse the discarded container twice with water, then completely fill the container with water and empty
to displace vapors.
Allow the container to drain. All rinse water will be disposed in to the drain of wastewater collection
tank.
Before disposing of the container remove the lid and write on the container's label ―EMPTY‖.
Mock drills will be periodically conducted and factors like response time will be evaluated.
Fire squad team is/will be formed for handling any emergency situation and regular training of squad
Housekeeping
Proper housekeeping is an essential part of sound environmental management. It is/will be rigorously seen that
there is no accumulation of wastes, especially combustible wastes inside the plant area. All firefighting
equipment and warning devices are/will be kept in perfect working conditions at all the times. It will be seen
that all personnel are aware of the implications of environmental pollution and simple practices to avoid
pollution.
Do's Don’ts
Do prepare a checklist for all preventive maintenance in Do not perform any maintenance
accordance to the guidelines laid in adopted quality systems. activity without a valid work permit.
Do affix identification tags / stickers on all equipment. Do not leave loose the free end of air
Do use appropriate PPEs as per job to be performed. line hoses.
Do use suitable tools only which are in good condition for any Do not work on any equipment when
maintenance job. Use spark‐less type of tools whenever required. it is in hot condition or with chemicals.
Do perform all maintenance activity only when authorized and Do not carry any gas cylinder / open
obtain a suitable work permit before start of any activity. flame / heated light source into tanks
Do place a warning sign board bearing a legend such as work in or confined spaces.
progress while working. Do not insert bare cable‐ends in the
Do maintain records for all maintenance / repairs done. Maintain a plug socket. Use proper plug at all
history card for all equipment. times.
Do use a lifting device within maximum safe working load. Do not start machinery or equipment
Do inspect the vessels / pipelines for their proper cleaning from unless authorized to do so.
chemicals, before staring any maintenance work. Also clean all Do not keep nuts, bolts, gaskets and
equipment including pipelines before handing it for operation. tools on top of vessels. Keep them in
Do check the earthing of equipment regularly. tool boxes provided.
Do check oxygen content before making a confined space entry. Do not undertake a confined space
Do dispose waste appropriately. Segregate them before disposal. entry without supervision.
Do's Don’ts
Do choose a PPE appropriately, after reading the MSDS incase Do not do any operation / act for which
of a chemical or depending on the plant operation to be you are not authorized.
performed. Do not use temporary supports &
Do use a gas detector and SCBA whenever there is any leakage connections during plant operations,
/ spillage of chemical. maintenance etc.
Do clean up any chemical spillage immediately. Consult Do not make changes to procedures,
supervisor for proper method when ever any doubt. follow the instructions.
In case there has been any contact of chemicals with body do Do not use compressed air for breathing.
stay under shower until all chemical is thoroughly washed off. In Do not carry any matches/cigarette
case of eye contact do wash eyes immediately by keeping eyes lighter, it is strictly prohibited inside the
open over the eye wash fountain for at least 15 minutes. factory.
In case of any declared emergency do gather at designated Do not ride or climb on fork lift, hoists or
assembly points only. on rear of trucks etc.
Do comply with all warning signs displayed at site. Do not block the exit passage,
Do report all accidents, however minor they may be, do report firefighting equipment, safety showers or
unsafe conditions and unsafe acts to your senior or safety access to them.
officer. Do not ignore any alarm you have heard,
Do's Don’ts
Do keep the work place clean and tidy; ensure proper it may be a real emergency.
segregation of scrap & non‐usable material.
Table No. 10.4 – CER Activities with Year wise Budget (Rs. in Lakhs)
Distribution of educational
1. books, stationary, uniforms 0.15 0.16 0.17 0.18 0.18 0.84
and aids etc.
Total 0.15 0.16 0.17 0.18 0.18 0.84
Type of pollution (air, noise, water and land pollution) likely from the activities at the site
Agro-climatic zone and sub-zone where the greenbelt is located (and hence the plant species which can
2
Industry will be developed green belt (234.32 m ) at the project site which is as per CPCB norms. The spacing
between the trees will be maintained slightly less than the normal spaces, so that the trees may grow vertically
and slightly increase the effective height of the green belt. The following points will be considered for selection
of plants species:
Greenbelt absorbs both gaseous as well as particulate pollutants to a great extent. For absorbance of
Characteristics of tree/plants including shapes of crowns considered necessary for effective removal of
dust particles.
Greenbelt/Plant species having good root system will be selected, so that soil erosion rates can be
controlled significantly.
Table No. 10.5 – List of trees to be planted within and outside premises
Table No. 10.6 – Year wise tree plantation program along with budget
Following activities will be carried out for maintaining the greenbelt area:
Annual planning for tree plantation with specific number of trees to be planted will be prepared and
fulfillment of the plan will be monitored by the EMC every six months
A plan for post plantation care will be reviewed in the monthly meetings. Any abnormal death rate of
In addition to above, following common practices shall be followed to control any odor from plant.
Sufficient Ventilation shall be provided in all plants as per Gujarat factory Rules.
Provision of exhaust fan for air circulation and odor dilution with the ambient air.
Pocket will have independent harvesting well. A de-silting chamber will be provided to de-silt and
Rain water outlets shall be provided at various locations on terrace based on the criteria that minimum
rainwater harvesting system consisting of Desilting-cum-Filter Chamber, Oil & Grease Separators than
Highly energy efficient Variable refrigerant volume (VRV) central air conditioning.
China mosaic on terrace floor to reduce heat.
Appropriate design to shut out excess heat and maintain Indoor air quality.
Throttling down and switching off construction equipment when not in use;
Switching off truck engines while they are waiting to access the site and while they are waiting to be
Switching off site office equipment and lights and using optimum lighting intensity for security and
safety purposes;
Regular maintenance of equipment to ensure optimum operations and fuel efficiency.
Identify the hazardous substance to be phased out, on the basis of the precautionary principle.
Facilitate the transition to cleaner production with social planning, involving workers and communities
affected.
The cost of complying with environmental legislation can be significantly reduced by companies that
adopt cleaner production techniques. The latter are often more cost-effective than control technologies.
The costs of dealing with wastes are reduced, and there is potential for new markets to be discovered
By demonstrating a commitment to cleaner production, companies can also improve their public image
Adoption of State of Art Technology for Prevention and Control of Environmental impacts.
Commit ourselves to prevent pollution & protect the environment by preventing or minimizing the
environmental impacts of its activities & products through appropriate design, manufacturing,
Review facilities and programs on regular basis and establish targets, quantified as appropriate for
Conversion of waste into wealth and optimum utilization of natural resources helps in reducing carbon
footprints.
Identification and Evaluation of Non-Conformance and/or Non-Compliances to determine specific
corrective and preventive actions. Management review of corrective actions to ensure the status and
effectiveness of the actions. Ensure that the policy is made available to interested parties & is reviewed
on periodic basis.
Work out action plan for implementation of the recommendations made under EMP.
Effective implementation of EMS and suggested environmental monitoring program at the plant level.
Measurement of various parameters suggested in environmental monitoring program as per suggested
schedule.
Prepare budget for environment management program and proper allocation of the funds for the
same.
To control the pollution levels below the prescribed limits. Analyze the data and decide the critical areas
To rectify the problem areas in the EMS, if any and provide necessary assistance in the form of
The unit has established an Environmental Policy which is attached as Annexure – 6. Organogram of the EMC is
mentioned below:
Ambient Air: All the results of ambient air quality parameters have been found within the limit as per NAAQS. It
is interpreted that ambient air quality of studied locations is decent. This interpretation relate to the results
found for particular locations and study period.
Soil: The results of pH shows that soils are acidic to alkaline in reaction. The soils are categorized as sandy loam
based on different soil separates (sand, silt and clay). The levels of total Cu, Ar and Ni are within the safe limits.
The soil at the project site requires improvement. The soil should be periodically monitored for pH and density.
Ground Water: Results of all villages meet with the standard, while the results of calcium and megnesium are
having high value at location of Umarwada and Mandwa Bujrg respectively. The reason of high concentration of
calcium and magnesium in ground water may be due to high content of Iron in nearby surface water resources.
Also it is interpreted that water supply by GIDC at project site.
Surface Water: On the basis of test results of River Water quality, it is understood that River water quality does
not meet with drinking water norms as per IS 10500:2012. From the Results of BOD, COD & Iron shows that the
water has been contaminated with organic matter and Iron due to directly or indirectly disposal of untreated
sewage and effluent. This water may be used for drinking purpose after proper treatment followed by
disinfection but it would not be directly used for driking purpose.
Noise: Based on noise level data for residential area and industrial area, it is understood that noise levels are
within the standard norms prescribed by MoEF&CC.
Traffic Survey: Based on existing traffic scenario, LOS values for N. H. No. – 8 have been found 0.57 i.e. good.
Ecology & Biodiversity: In core zone, the vegetation mostly comprises of open scrub vegetation. There is a
domestic animal like buffalo, cow, goat, dog were find out in the study area. There was no Rare or Endangered
or Endemic or Threatened species observed during primary survey.
Socio-Economic: On the basis of survey, it was observed that almost pakka road facility, all basic amenities like
Education facilities Health care facilities, water supply, electric power supply, mode of transportation etc. are
available in all villages.
To identify major risks in the manufacturing process and to evaluate on-site and off-site consequences of
identified hazard scenarios qualitative and quantitative risk assessment has been conducted.
Company had made formal agreements with nearby hospitals to attend fire and/or emergency cases for
attending the affected persons in the emergency arising out of accident. First Aid Boxes will be made available
at Security gate, emergency room, ETP and process plants. Mock drill will be carried out at the interval of every
year.
11.11 CONCLUSION
Proposed expansion project is located in notified industrial area of Ankleshwar and would not have any
considerable impact on environment with efficient mitigation measures implemented. The waste generation in
form of gas (flue gas and process gas), effluent and solid waste may have impacts on environmental parameters
but the proponent has planned and installed most efficient technologies for prevention of emission and
treatment of effluent. Further, the solid/hazardous waste will be disposed of through TSDF site. Hence there
would not be any considerable impacts on environment. With the implementation of the mitigation measures
and EMP, the proposed project activities will have positive beneficial effect on the local population, economic
output and other related facilities viz. employment, development of business, transportation etc. Rapid risk
assessment including emergency response plan and DMP has been prepared to handle any sort of emergencies.
Hence looking to the overall project justification, process, pollution potential and pollution prevention measures
/technologies installed by proponent, environmental management activities of proponent; it has been
concluded that the proposed expansion project would not have any considerable impacts on environment as
well as socio-economic and ecological conditions of the project area. Hence proposed expansion project is
considered environmentally safe.
Greenleaf Envirotech Pvt. Ltd. is one of the leading companies in the field of Environmental Consultancy Service
providers in India having NABL accredited laboratory. We also take up services which include and are not
limited to Environment Monitoring and Testing, Environment Audit, Risk Assessment Studies, Turnkey solutions,
Operation and Maintenance contracts and obtaining various statutory clearances from Ministry of Environment,
Forest and Climate Change (MoEF&CC) and State Pollution Control Boards.