Professional Documents
Culture Documents
Lecture-3 (Planning Tools)
Lecture-3 (Planning Tools)
Lecture 3
Date: July 11, 2022
PROJECT PLANNING TOOLS
1. WBS (Work Breakdown Structure)
4. Milestone Chart
5. Network Analysis: CPM (Critical Path Method) and PERT (Program/ project Evaluation and Review
Technique)
• Furthermore, interior has to be broken down into (1) Acoustics (2) General Interios
PROJECT PLANNING TOOLS
2. Bar Chart (Gantt Chat)
• A conventional, simple and oldest method
• Henry L. Gantt who developed it during 1900 AD
• Horizontal axis represents the time and the vertical represent the jobs or activities.
1 Excavation
2 PCC
3 RCC footing
4 RCC wall
5 Plastering
6 Painting
7 Fencing
PROJECT PLANNING TOOLS
• Benefits of Bar Chart are as follows:
1. Easy to construct
2. Easy to understand
3. suitable for small projects
4. Easiest way of communicating information with common personnel
5. Final presentation of the Network Analysis is also in this form.
• Demerits of Bar Chart:
1. Lacks degree of details
2. The activities bigger or small are depicted by the same straight line. Important or
unimportant activities cannot be distinguished.
3. Does not show the interdependencies of the activities clearly.
4. Ddoes not show the progress of the work
5. Less effective tool for monitoring and control
6. Not suitable for large projects.
PROJECT PLANNING TOOLS
3. Linked Bar Chart: - Activities are linked to each other by line or dotted line with arrow in order to show
dependencies in Bar Chart.
• (Example of Link Bar Chart and Mile Stone Chart )
1 Excavation
2 PCC
3 RCC footing
4 RCC wall
5 Plastering
6 Painting
7 Fencing
PROJECT PLANNING TOOLS
4. Milestone Chart: -
• Improved version of Bar chart
• Important milestones (events) are indicated by small inverted triangles / circles / squares
• The milestones are specific stage or point where major activity (either begins or) ends
• Generally, it focuses mainly on end-dates by which something needs to be complete or by which certain
objective needs to be achieved
• Earliest finish time (or Eft):- Earliest finish time is the earliest
time by which an activity can be finished.
It is the sum of the earliest start time and the estimated
time to perform the concerning activity.
PROJECT PLANNING TOOLS
NETWORK ANALYSIS (CPM)
After of above terminologies we can draw network as follows:
• List down all the activities with their predecessors or successors or both [ make a table], with their
corresponding duration
• Activities are shown with arrows and events are shown with circle. [It can also be other way round]
• Draw network sequentially, logically, and considering dependencies and successor activity of
activities. Write down duration of each activity.
• Remember, network starts from a single point (start event) and closes at a single point (event).
• Now try to make network with trail and error that is logically justified and gives true picture of
activities.
• Assign respective durations. The beginning of the network (event 0) has duration 0.
PROJECT PLANNING TOOLS
NETWORK ANALYSIS (CPM)
• Class work (Example 1) :
• Draw a network diagram for the following information.
A 8 - D, E
B 11 - F
C 10 - G
D 7 A F
E 12 A -
F 9 B, D -
G 9 C -
PROJECT PLANNING TOOLS
NETWORK ANALYSIS (CPM)