Download as pdf or txt
Download as pdf or txt
You are on page 1of 97

ITA/AITES

ITA/AITES – Training Course


TUNNEL ENGINEERING

MECHANIZED FULL FACE TUNNELLING


RELEVANT EXAMPLES
Prepared by “Rick P. LOVAT, P.Eng, President & CEO – LOVAT Inc.”

Seoul, 2006

April 19, 2006 1/97


Index
1
Introduction

2
Chapter 1 – Pougues Run Upgrade, Indiannapolis, USA

3
Chapter 2 – Docklands Light Rail Extension, London, UK

4
Chapter 3 – Krolsky Railway Tunnel, Kraznoyarsk, Russia

5 Conclusions and references

MECHANIZED FULL FACE TUNNELLING


RELEVANT EXAMPLES 2/97
INTRODUCTION Chapter 1
1
Sections: Pougues Run RME167SE
Project, TBM Specifications, Special Features
2
DLR Extension – ME238SE
Project, TBM Specifications, Special Features
3
Krolosky Railway Tunnel RMP375SE
Project, TBM Specifications, Special Features
4
Conclusions
5
Questions

3/97
Chapter 2

Consolidation of Pogues Run CSO


Outfalls 034 & 035
Indianapolis, USA

LOVAT RME167SE

4/97
Consolidation of Pogues Run Chapter 2
1
• Location: Marion County
2 Indianapolis, USA
• Owner: City of Indianapolis
3 Department of Public Works
• Consultant: Clark Dietz Inc.
4 Christopher Burke Eng. Ltd.
• Contractor: Super Excavators Inc.
5
• Purpose: Combined Sewer Outfall

5/97
Consolidation of Pogues Run Chapter 2
1
• Length: 500 m
2 • Maximum Depth: 14.6 m
• Minimum Depth: 6.7 m
• Water Pressure: 0.8 bar
3 • Estimated EPB Pressure: 1.5 bar
• Tunnel Lining:
4 – Inside Diameter: 3.66 m
– Outside Diameter: 4.11 m

5 Length: 1.5 m
– Configuration: 6 Piece Universal Ring

6/97
Consolidation of Pogues Run Chapter 2
1
• Geology:
– Fill
2
– Glacial outwash sands and gravels
– Glacial Till
3 – High presence of cobbles and boulders

7/97
LOVAT RME167SE Chapter 2
1

8/97
TBM Specifications Chapter 2
1
• Shield Diameter: 4229 mm
2 • Cut Diameter: 4267 mm
• Length: 9.0 m
• Overall Length: 50 m
3 • Overall Weight: 206 tonne
• Total Installed Thrust: 1840 tonne
4 • Propulsion Stroke: 2250 mm
• Total installed power: 1043 kW
5

9/97
TBM Specifications Chapter 2
1
• Forward and Rear Articulation Joints
2 • Independent control of propulsion cylinders
• Class 1 Division 2 Electrical System for
operation in “Potentially Gasey Environments”
3 • High Voltage Cable Tray – 300m capacity
• A/B Component Grout Injection System
4 – 2 No. Injection Points
– 10m3/hr injection capacity
• Trailing Belt Conveyor
5
• Trailing Gantry

10/97
Cuttinghead Chapter 2
1
• Mixed Face Design
2 • Incorporates either Ripper Teeth and/or Disc
Cutters
• Four Spoke Layout
3 • Face Isolation Doors
• 5 No. Independent Injection Ports
4 • Chromium Carbide Plating
• Grizzly Bars Across Cuttinghead Openings
5

11/97
Cuttinghead Layout Chapter 2
1

12/97
Main Drive Design Chapter 2
1
• Ring Gear on Extrados of Main Bearing
2
• Use of fewer but higher capacity gear reducers
(resulting in larger teeth on the ring gear)
3
• Use of large diameter rollers in the bearing to
4 achieve required load capacity and life

13/97
Main Drive Design Chapter 2
1
• The use of a VDF for the benefit of higher
overall efficiency
2
– 90% for VFD vs. 72% for Hydraulic Drive
– ie: 540 kW at the Cuttinghead face requires 600 kW
3 input in a VFD drive vs 750 kW on a hydraulic
drive
• Additional power is lost due to mechanical and
4 volumetric inefficiencies in the hydraulic
pumps and motors
5 • This is the seventh LOVAT TBM to be
equipped with VF Drives

14/97
Main Drive Design Chapter 2
1
• Variable Frequency Electric Drive
2 • Installed Power: 600 kW
• Maximum Torque: 265 t•m
• Maximum Speed: 4.8 rpm
3 • Torque at maximum speed: 106 t•m
• Peak Starting Torque: 314 t•m
4 • Torque vs Face Area: 18.8 t•m / m2
• External Ring Gear on Main Drive Bearing
5

15/97
Main Drive Layout Chapter 2
1

16/97
Main Drive Layout Chapter 2
1

17/97
1
Screw Conveyor Design Chapter 2
• Located at invert of cuttinghead chamber
• Primary and secondary drives
2 • Two independent auger sections capable of
varying speeds between the two sections
• Multiple injection ports for lubrication and
3 ground conditioning
• Length of screw to allow for pressure
dissipation, maintaining of clean working area
4 for segment erection
• Emergency Closure System
5

18/97
1
Screw Conveyor Design Chapter 2
• Total Length of 30m
2 • 610mm Nominal Diameter
• Installed power of 200kW
• Both drives are variable speed and reversible
3 • Total installed torque for Rear Drive of 3.3t•m
• Total installed torque for Front Drive of 3.0t•m
4 • Discharge capacity of 100m3/hr
• Maximum Speed of 22 rpm
5 • Maximum boulder size of 188 mm

19/97
1
Screw Conveyor Layout Chapter 2

20/97
1
Screw Conveyor Layout Chapter 2

21/97
1
Screw Conveyor Layout Chapter 2

22/97
1
Screw Conveyor Layout Chapter 2

23/97
1
Screw Conveyor Layout Chapter 2

24/97
1
Screw Conveyor Layout Chapter 2

25/97
Segment Erector Chapter 2
1
• Bulkhead Mounted
– Ease of access to TBM
2
• Mechanical Pick-Up System
– Ball and Cup
3 • Hydraulic Controls from fixed stations

26/97
Segment Erector Chapter 2
1

27/97
Segment Erector Chapter 2
1

28/97
TBM Assembly Chapter 2
1

29/97
TBM Assembly Chapter 2
1

30/97
TBM Assembly Chapter 2
1

31/97
BREAK THROUGH! Chapter 2
1

32/97
Chapter 3

Docklands Light Rail Extension


Woolwich Aresenal to
King George V
London, UK
LOVAT ME2383SE

33/97
DLR Extension Chapter 3
1
• Location: London, UK
2 • Owner: Woolwich Aresenal Rail
Enterprise (WARE)

3 • Contractor: AMEC
• Purpose: Light Rail Line
4

34/97
DLR Extension Chapter 3
1
• Length: 2 x 1830 m
2 • Maximum Depth: 30 m
• Minimum Depth: 7m
• Water Pressure: 3.4 bar
3 • Estimated EPB Pressure: 3.5 bar
• Tunnel Lining:
4 – Inside Diameter: 5.3 m
– Outside Diameter: 5.8 m

5 Length: 1.5 m
– Configuration: 8 Piece Trapezoidal

35/97
DLR Extension Chapter 3
1
• Geology:
– Fill
2
– Alluvium
– Terrace Gravels
3 – Chalk c/w Flints
– Thanet Sand
– Bullhead Clays
4

36/97
TBM Specifications Chapter 3
1
• Shield Diameter: 6026 mm
2 • Cut Diameter: 6064 mm
• Length: 9.0 m
• Overall Length: 93 m
3 • Overall Weight: 527 tonne
• Total Installed Thrust: 4320 tonne
4 • Propulsion Stroke: 2250 mm
• Total installed power: 1995 kW
5

37/97
TBM Specifications Chapter 3
1
• Forward and Rear Articulation Joints
2 • Independent control of propulsion cylinders
• ‘CE’ Certification
• HSE Approval and Certification
3 • A/B Component Grout Injection System
– 2 No. Injection Points
4 – 10m3/hr injection capacity
• Trailing Belt Conveyor discharge to tunnel
conveyor
5
• Trailing Gantry
• Computer Tunnel Guidance System
38/97
LOVAT ME238SE Chapter 3
1

39/97
LOVAT ME238SE Chapter 3
1

40/97
Cuttinghead Chapter 3
1
• Soft Ground Cuttinghead
2 • Independently Operated Face Isolation Doors
• 6 No. Independent Injection Ports
• Lovat Scraper Teeth
3 • Grizzly Bars
• Lovat Ripper TeethLovat Center Nose Cutter
4 • 5 No. Secondary Opening ports – Additional
openings at Cuttinghead center when required
5

41/97
Cuttinghead Chapter 3
1

42/97
Cuttinghead Chapter 3
1

43/97
Cuttinghead Chapter 3
1

44/97
Main Drive Design Chapter 3
1
• Variable Frequency Electric Drive
2 • Installed Power: 1020 kW
• Maximum Torque: 537 t•m
• Maximum Speed: 3.8 rpm
3 • Torque at maximum speed: 243 t•m
• Peak Starting Torque: 671 t•m
4 • Torque vs Face Area: 18.7 t•m / m2

45/97
Main Drive Chapter 3
1

46/97
1
Screw Conveyor Design Chapter 3
• Located at invert of cuttinghead chamber
• Peripheral Drive
2 • Multiple injection ports for lubrication and
ground conditioning
• Two Discharge Options:
3 – Discharge to trailing belt and tunnel conveyor
– Closed Discharge to Muck Pump
• Boulder Catcher for Muck Pump Discharge
4 • Emergency Closure System

47/97
1
Screw Conveyor Design Chapter 3
• Total Length of 14m
2 • 790mm Nominal Diameter
• Installed power of 188kW
• Discharge capacity of 300m3/hr
3 • Maximum Speed of 22 rpm
• Maximum boulder size of 250 mm
4

48/97
Screw Conveyor Chapter 3
1

49/97
Screw Conveyor Chapter 3
1

50/97
Screw Conveyor Chapter 3
1

51/97
Screw Conveyor Chapter 3
1

52/97
Trailing Gantry Chapter 3
1

53/97
Trailing Gantry Chapter 3
1

54/97
Trailing Gantry Chapter 3
1

55/97
TBM Assembly Chapter 3
1

56/97
TBM Assembly Chapter 3
1

57/97
TBM Assembly Chapter 3
1

58/97
TBM Assembly Chapter 3
1

59/97
TBM Assembly Chapter 3
1

60/97
TBM Assembly Chapter 3
1

61/97
Chapter 4

KROLSKY Railway Tunnel


Twinning
Kraznoyarsk, Russia

LOVAT RMP3753SE

62/97
1
Krolsky Railway Tunnel Chapter 4
• Location: Kraznoyarsk, Russia
2 • Owner: Russian National Railways
• Contractor: OAO Bamtonnelstroy
3
• Purpose: Twinning of Railway Tunnel
Trans Siberian Railway
4

63/97
1
Krolsky Railway Tunnel Chapter 4
• Length: 2252 m
2 • Maximum Depth: 80 m
• Minimum Depth: 5m
• Water Pressure: 2.9 bar
3 • Tunnel Lining:
– Inside Diameter: 8.4 m
4 – Outside Diameter: 9.2 m
– Length: 1.5 m
– Configuration: 6+Key Universal Ring
5

64/97
1
Krolsky Railway Tunnel Chapter 4
• Geology:
– Eluvium (Slate Detritus)
2
– Slate [30-70 MPa]
– Limestone [50-100 MPa]
3 – Granite [60-100 MPa]

65/97
TBM Specifications Chapter 4
1
• Shield Diameter: 9506 mm
2 • Cut Diameter: 9544 mm
• Length: 10 m
• Overall Length: 109 m
3 • Overall Weight: 1115 tonne
• Total Installed Thrust: 7905 tonne
4 • Propulsion Stroke: 2250 mm
• Total installed power: 3500 kW
5

66/97
TBM Specifications Chapter 4
1
• Forward and Rear Articulation Joints
2 • Independent control of propulsion cylinders
• Single Component Grout Injection System
– 4 No. Injection Points
3 – 30 m3/hr injection capacity
• Trailing Belt Conveyor
4 • Trailing Gantry
• Auxiliary Ventilation System
5 • Computer Tunnel Guidance System

67/97
Cuttinghead Chapter 4
1
• Rock Cuttinghead
2 • 15½” Replaceable Ring Disc Cutters
• Scraper Collector Tools
• Capable of Bi-Directional Operation
3 • 11 No. Face Injection Ports
• Grizzly Bars across openings
4 • 2 No. Access Ports to Face

68/97
Cuttinghead Chapter 4
1

69/97
Cuttinghead Chapter 4
1

70/97
Main Drive Chapter 4
1
• Variable Speed Hydraulic Drive
2 • Total Cuttinghead Power: 2100 kW
• Maximum Torque: 1452 t•m
• Minimum Torque: 675 t•m
3 • Peak Break Out Torque: 1959 t•m
• Maximum Speed: 3.0 rpm
4 • Speed at Maximum Torque: 1.4 rpm

71/97
Main Drive Chapter 4
1

72/97
Main Drive Chapter 4
1

73/97
TBM Assembly Chapter 4
1

74/97
TBM Assembly Chapter 4
1

75/97
TBM Assembly Chapter 4
1

76/97
TBM Assembly Chapter 4
1

77/97
TBM Assembly Chapter 4
1

78/97
TBM Assembly Chapter 4
1

79/97
TBM Status Chapter 4
1

80/97
Chapter 5
1

2
CONCLUSIONS
3 and
ACKNOWLEDGEMENTS
4

81/97
Conclusions Chapter 2
1
• The design and manufacture of the TBM
provided numerous challenges
2
• The incorporation of new features on a TBM is
3 not something that occurs frequently in the
tunnelling industry.
4

82/97
Conclusions Chapter 2
1
• There are numerous risks involved in putting
untested technology into a tunnel environment
2 that would prevent a contractor from allowing
experimentation.
3
• Therefore the commitment of the
manufacturers to push new technology is
4
required to keep the industry moving forward

83/97
Conclusions Chapter 5
1
• ADVANCES IN TBM TECHNOLOGY
2 • Variable Frequency Electric Drive
• Higher Efficiency
• Ease of Maintenance
• Lower Operating Costs (less power loss to heat)
3 • Computer aided trouble shooting of problems
• Cooler and Quieter Operating Environment

4
No increase in capital costs over traditional hydraulic
drives
• High Torque Drives
5 • Ability to handle more difficult ground conditions
• Achievable due to advances in Gear Box, and Bearing
Technology

84/97
Conclusions Chapter 5
1
• ADVANCES IN TBM TECHNOLOGY
2 • TBM Operation under High In-situ Pressures
• Long Screw Conveyors c/w multiple drives
• Muck Pumping direct from Screw Discharge

3 • Bulkhead Erectors on small diameter TBMs


• Better access for safety

85/97
Acknowledgements Chapter 5
1
• Consolidation of Pogues Run CSO
– Super Excavators
2
– City of Indianapolis, USA

86/97
Acknowledgements Chapter 5
1
• Docklands Light Rail Extension
– AMEC
2
– WARE (Woolrich Aresenal Rail Enterprises)
– City of London, UK
3

87/97
Acknowledgements Chapter 5
1
• Krolsky Railway Tunnel Twining
– OAO Bamtonnelstroy
2
– Russian National Railways
– Region of Kraznoyarsk, Russia
3

88/97
89/97
90/97
91/97
92/97
93/97
94/97
95/97
96/97
ITA/AITES

Clause de non-responsabilité pour les rapports des groupes de travail de l'AITES


L’Association Internationale des Travaux en Souterrain (AITES) publie ce rapport, conformément à ses Statuts, pour faciliter les échanges d’informations afin :
d’encourager l’utilisation du sous-sol au profit du grand public, de l’environnement et du développement durable;
de promouvoir les progrès dans la planification, le projet, la construction, l’entretien, la réhabilitation et la sécurité des tunnels et de l’espace souterrain en
rassemblant et confrontant les informations, ainsi qu’en étudiant les questions qui s’y rapportent.
Cependant, l’AITES décline toute responsabilité en ce qui concerne les informations publiées dans ce rapport.
Ces informations :
sont exclusivement de nature générale et ne visent pas la situation particulière d’une personne physique ou morale;
ne sont pas nécessairement complètes, exhaustives, exactes ou à jour ;
proviennent parfois de sources extérieures sue lesquelles les services de l’AITES n’ont aucun contrôle et pour lesquelles l’AITES décline toute responsabilité ;
ne constituent pas un avis professionnel or juridique (si vous avez besoin d’avis spécifiques, consultez toujours un professionnel dûment qualifié).

Disclaimer for the reports of ITA working groups


The International Tunnelling Association (ITA) publishes this report to, in accordance with its statutes, facilitate the exchange of information, in order:
to encourage planning of the subsurface for the benefit of the public, environment and sustainable development
to promote advances in planning, design, construction, maintenance and safety of tunnels and underground space, by bringing together information thereon and
by studying questions related thereto.
However ITA accepts no responsibility or liability whatsoever with regard to the material published in this report.
This material is:
information of a general nature only, which is not intended to address the specific circumstances of any particular individual or entity;
not necessarily comprehensive, complete, accurate or up to date;
sometimes collected from external sources over which ITA services have no control and for which ITA assumes no responsibility;
not professional or legal advice (if you need specific advice, you should always consult a suitably qualified professional).

97/97

You might also like