Professional Documents
Culture Documents
05new Bournes LOVAT 01
05new Bournes LOVAT 01
Seoul, 2006
2
Chapter 1 – Pougues Run Upgrade, Indiannapolis, USA
3
Chapter 2 – Docklands Light Rail Extension, London, UK
4
Chapter 3 – Krolsky Railway Tunnel, Kraznoyarsk, Russia
3/97
Chapter 2
LOVAT RME167SE
4/97
Consolidation of Pogues Run Chapter 2
1
• Location: Marion County
2 Indianapolis, USA
• Owner: City of Indianapolis
3 Department of Public Works
• Consultant: Clark Dietz Inc.
4 Christopher Burke Eng. Ltd.
• Contractor: Super Excavators Inc.
5
• Purpose: Combined Sewer Outfall
5/97
Consolidation of Pogues Run Chapter 2
1
• Length: 500 m
2 • Maximum Depth: 14.6 m
• Minimum Depth: 6.7 m
• Water Pressure: 0.8 bar
3 • Estimated EPB Pressure: 1.5 bar
• Tunnel Lining:
4 – Inside Diameter: 3.66 m
– Outside Diameter: 4.11 m
–
5 Length: 1.5 m
– Configuration: 6 Piece Universal Ring
6/97
Consolidation of Pogues Run Chapter 2
1
• Geology:
– Fill
2
– Glacial outwash sands and gravels
– Glacial Till
3 – High presence of cobbles and boulders
7/97
LOVAT RME167SE Chapter 2
1
8/97
TBM Specifications Chapter 2
1
• Shield Diameter: 4229 mm
2 • Cut Diameter: 4267 mm
• Length: 9.0 m
• Overall Length: 50 m
3 • Overall Weight: 206 tonne
• Total Installed Thrust: 1840 tonne
4 • Propulsion Stroke: 2250 mm
• Total installed power: 1043 kW
5
9/97
TBM Specifications Chapter 2
1
• Forward and Rear Articulation Joints
2 • Independent control of propulsion cylinders
• Class 1 Division 2 Electrical System for
operation in “Potentially Gasey Environments”
3 • High Voltage Cable Tray – 300m capacity
• A/B Component Grout Injection System
4 – 2 No. Injection Points
– 10m3/hr injection capacity
• Trailing Belt Conveyor
5
• Trailing Gantry
10/97
Cuttinghead Chapter 2
1
• Mixed Face Design
2 • Incorporates either Ripper Teeth and/or Disc
Cutters
• Four Spoke Layout
3 • Face Isolation Doors
• 5 No. Independent Injection Ports
4 • Chromium Carbide Plating
• Grizzly Bars Across Cuttinghead Openings
5
11/97
Cuttinghead Layout Chapter 2
1
12/97
Main Drive Design Chapter 2
1
• Ring Gear on Extrados of Main Bearing
2
• Use of fewer but higher capacity gear reducers
(resulting in larger teeth on the ring gear)
3
• Use of large diameter rollers in the bearing to
4 achieve required load capacity and life
13/97
Main Drive Design Chapter 2
1
• The use of a VDF for the benefit of higher
overall efficiency
2
– 90% for VFD vs. 72% for Hydraulic Drive
– ie: 540 kW at the Cuttinghead face requires 600 kW
3 input in a VFD drive vs 750 kW on a hydraulic
drive
• Additional power is lost due to mechanical and
4 volumetric inefficiencies in the hydraulic
pumps and motors
5 • This is the seventh LOVAT TBM to be
equipped with VF Drives
14/97
Main Drive Design Chapter 2
1
• Variable Frequency Electric Drive
2 • Installed Power: 600 kW
• Maximum Torque: 265 t•m
• Maximum Speed: 4.8 rpm
3 • Torque at maximum speed: 106 t•m
• Peak Starting Torque: 314 t•m
4 • Torque vs Face Area: 18.8 t•m / m2
• External Ring Gear on Main Drive Bearing
5
15/97
Main Drive Layout Chapter 2
1
16/97
Main Drive Layout Chapter 2
1
17/97
1
Screw Conveyor Design Chapter 2
• Located at invert of cuttinghead chamber
• Primary and secondary drives
2 • Two independent auger sections capable of
varying speeds between the two sections
• Multiple injection ports for lubrication and
3 ground conditioning
• Length of screw to allow for pressure
dissipation, maintaining of clean working area
4 for segment erection
• Emergency Closure System
5
18/97
1
Screw Conveyor Design Chapter 2
• Total Length of 30m
2 • 610mm Nominal Diameter
• Installed power of 200kW
• Both drives are variable speed and reversible
3 • Total installed torque for Rear Drive of 3.3t•m
• Total installed torque for Front Drive of 3.0t•m
4 • Discharge capacity of 100m3/hr
• Maximum Speed of 22 rpm
5 • Maximum boulder size of 188 mm
19/97
1
Screw Conveyor Layout Chapter 2
20/97
1
Screw Conveyor Layout Chapter 2
21/97
1
Screw Conveyor Layout Chapter 2
22/97
1
Screw Conveyor Layout Chapter 2
23/97
1
Screw Conveyor Layout Chapter 2
24/97
1
Screw Conveyor Layout Chapter 2
25/97
Segment Erector Chapter 2
1
• Bulkhead Mounted
– Ease of access to TBM
2
• Mechanical Pick-Up System
– Ball and Cup
3 • Hydraulic Controls from fixed stations
26/97
Segment Erector Chapter 2
1
27/97
Segment Erector Chapter 2
1
28/97
TBM Assembly Chapter 2
1
29/97
TBM Assembly Chapter 2
1
30/97
TBM Assembly Chapter 2
1
31/97
BREAK THROUGH! Chapter 2
1
32/97
Chapter 3
33/97
DLR Extension Chapter 3
1
• Location: London, UK
2 • Owner: Woolwich Aresenal Rail
Enterprise (WARE)
3 • Contractor: AMEC
• Purpose: Light Rail Line
4
34/97
DLR Extension Chapter 3
1
• Length: 2 x 1830 m
2 • Maximum Depth: 30 m
• Minimum Depth: 7m
• Water Pressure: 3.4 bar
3 • Estimated EPB Pressure: 3.5 bar
• Tunnel Lining:
4 – Inside Diameter: 5.3 m
– Outside Diameter: 5.8 m
–
5 Length: 1.5 m
– Configuration: 8 Piece Trapezoidal
35/97
DLR Extension Chapter 3
1
• Geology:
– Fill
2
– Alluvium
– Terrace Gravels
3 – Chalk c/w Flints
– Thanet Sand
– Bullhead Clays
4
36/97
TBM Specifications Chapter 3
1
• Shield Diameter: 6026 mm
2 • Cut Diameter: 6064 mm
• Length: 9.0 m
• Overall Length: 93 m
3 • Overall Weight: 527 tonne
• Total Installed Thrust: 4320 tonne
4 • Propulsion Stroke: 2250 mm
• Total installed power: 1995 kW
5
37/97
TBM Specifications Chapter 3
1
• Forward and Rear Articulation Joints
2 • Independent control of propulsion cylinders
• ‘CE’ Certification
• HSE Approval and Certification
3 • A/B Component Grout Injection System
– 2 No. Injection Points
4 – 10m3/hr injection capacity
• Trailing Belt Conveyor discharge to tunnel
conveyor
5
• Trailing Gantry
• Computer Tunnel Guidance System
38/97
LOVAT ME238SE Chapter 3
1
39/97
LOVAT ME238SE Chapter 3
1
40/97
Cuttinghead Chapter 3
1
• Soft Ground Cuttinghead
2 • Independently Operated Face Isolation Doors
• 6 No. Independent Injection Ports
• Lovat Scraper Teeth
3 • Grizzly Bars
• Lovat Ripper TeethLovat Center Nose Cutter
4 • 5 No. Secondary Opening ports – Additional
openings at Cuttinghead center when required
5
41/97
Cuttinghead Chapter 3
1
42/97
Cuttinghead Chapter 3
1
43/97
Cuttinghead Chapter 3
1
44/97
Main Drive Design Chapter 3
1
• Variable Frequency Electric Drive
2 • Installed Power: 1020 kW
• Maximum Torque: 537 t•m
• Maximum Speed: 3.8 rpm
3 • Torque at maximum speed: 243 t•m
• Peak Starting Torque: 671 t•m
4 • Torque vs Face Area: 18.7 t•m / m2
45/97
Main Drive Chapter 3
1
46/97
1
Screw Conveyor Design Chapter 3
• Located at invert of cuttinghead chamber
• Peripheral Drive
2 • Multiple injection ports for lubrication and
ground conditioning
• Two Discharge Options:
3 – Discharge to trailing belt and tunnel conveyor
– Closed Discharge to Muck Pump
• Boulder Catcher for Muck Pump Discharge
4 • Emergency Closure System
47/97
1
Screw Conveyor Design Chapter 3
• Total Length of 14m
2 • 790mm Nominal Diameter
• Installed power of 188kW
• Discharge capacity of 300m3/hr
3 • Maximum Speed of 22 rpm
• Maximum boulder size of 250 mm
4
48/97
Screw Conveyor Chapter 3
1
49/97
Screw Conveyor Chapter 3
1
50/97
Screw Conveyor Chapter 3
1
51/97
Screw Conveyor Chapter 3
1
52/97
Trailing Gantry Chapter 3
1
53/97
Trailing Gantry Chapter 3
1
54/97
Trailing Gantry Chapter 3
1
55/97
TBM Assembly Chapter 3
1
56/97
TBM Assembly Chapter 3
1
57/97
TBM Assembly Chapter 3
1
58/97
TBM Assembly Chapter 3
1
59/97
TBM Assembly Chapter 3
1
60/97
TBM Assembly Chapter 3
1
61/97
Chapter 4
LOVAT RMP3753SE
62/97
1
Krolsky Railway Tunnel Chapter 4
• Location: Kraznoyarsk, Russia
2 • Owner: Russian National Railways
• Contractor: OAO Bamtonnelstroy
3
• Purpose: Twinning of Railway Tunnel
Trans Siberian Railway
4
63/97
1
Krolsky Railway Tunnel Chapter 4
• Length: 2252 m
2 • Maximum Depth: 80 m
• Minimum Depth: 5m
• Water Pressure: 2.9 bar
3 • Tunnel Lining:
– Inside Diameter: 8.4 m
4 – Outside Diameter: 9.2 m
– Length: 1.5 m
– Configuration: 6+Key Universal Ring
5
64/97
1
Krolsky Railway Tunnel Chapter 4
• Geology:
– Eluvium (Slate Detritus)
2
– Slate [30-70 MPa]
– Limestone [50-100 MPa]
3 – Granite [60-100 MPa]
65/97
TBM Specifications Chapter 4
1
• Shield Diameter: 9506 mm
2 • Cut Diameter: 9544 mm
• Length: 10 m
• Overall Length: 109 m
3 • Overall Weight: 1115 tonne
• Total Installed Thrust: 7905 tonne
4 • Propulsion Stroke: 2250 mm
• Total installed power: 3500 kW
5
66/97
TBM Specifications Chapter 4
1
• Forward and Rear Articulation Joints
2 • Independent control of propulsion cylinders
• Single Component Grout Injection System
– 4 No. Injection Points
3 – 30 m3/hr injection capacity
• Trailing Belt Conveyor
4 • Trailing Gantry
• Auxiliary Ventilation System
5 • Computer Tunnel Guidance System
67/97
Cuttinghead Chapter 4
1
• Rock Cuttinghead
2 • 15½” Replaceable Ring Disc Cutters
• Scraper Collector Tools
• Capable of Bi-Directional Operation
3 • 11 No. Face Injection Ports
• Grizzly Bars across openings
4 • 2 No. Access Ports to Face
68/97
Cuttinghead Chapter 4
1
69/97
Cuttinghead Chapter 4
1
70/97
Main Drive Chapter 4
1
• Variable Speed Hydraulic Drive
2 • Total Cuttinghead Power: 2100 kW
• Maximum Torque: 1452 t•m
• Minimum Torque: 675 t•m
3 • Peak Break Out Torque: 1959 t•m
• Maximum Speed: 3.0 rpm
4 • Speed at Maximum Torque: 1.4 rpm
71/97
Main Drive Chapter 4
1
72/97
Main Drive Chapter 4
1
73/97
TBM Assembly Chapter 4
1
74/97
TBM Assembly Chapter 4
1
75/97
TBM Assembly Chapter 4
1
76/97
TBM Assembly Chapter 4
1
77/97
TBM Assembly Chapter 4
1
78/97
TBM Assembly Chapter 4
1
79/97
TBM Status Chapter 4
1
80/97
Chapter 5
1
2
CONCLUSIONS
3 and
ACKNOWLEDGEMENTS
4
81/97
Conclusions Chapter 2
1
• The design and manufacture of the TBM
provided numerous challenges
2
• The incorporation of new features on a TBM is
3 not something that occurs frequently in the
tunnelling industry.
4
82/97
Conclusions Chapter 2
1
• There are numerous risks involved in putting
untested technology into a tunnel environment
2 that would prevent a contractor from allowing
experimentation.
3
• Therefore the commitment of the
manufacturers to push new technology is
4
required to keep the industry moving forward
83/97
Conclusions Chapter 5
1
• ADVANCES IN TBM TECHNOLOGY
2 • Variable Frequency Electric Drive
• Higher Efficiency
• Ease of Maintenance
• Lower Operating Costs (less power loss to heat)
3 • Computer aided trouble shooting of problems
• Cooler and Quieter Operating Environment
•
4
No increase in capital costs over traditional hydraulic
drives
• High Torque Drives
5 • Ability to handle more difficult ground conditions
• Achievable due to advances in Gear Box, and Bearing
Technology
84/97
Conclusions Chapter 5
1
• ADVANCES IN TBM TECHNOLOGY
2 • TBM Operation under High In-situ Pressures
• Long Screw Conveyors c/w multiple drives
• Muck Pumping direct from Screw Discharge
85/97
Acknowledgements Chapter 5
1
• Consolidation of Pogues Run CSO
– Super Excavators
2
– City of Indianapolis, USA
86/97
Acknowledgements Chapter 5
1
• Docklands Light Rail Extension
– AMEC
2
– WARE (Woolrich Aresenal Rail Enterprises)
– City of London, UK
3
87/97
Acknowledgements Chapter 5
1
• Krolsky Railway Tunnel Twining
– OAO Bamtonnelstroy
2
– Russian National Railways
– Region of Kraznoyarsk, Russia
3
88/97
89/97
90/97
91/97
92/97
93/97
94/97
95/97
96/97
ITA/AITES
97/97