Precedence Networks

Draw a network using precedence diagram method from the data on Table 1. Calculate all activity
times, project duration and Total float times.

Table 1: Project data

Activity Predecessor Duration


A - 2
B A 4
C A 3
D A 2
E B 3
F C 6
G C, D 5
H E,F 6
I G 5
J H, I 5

2. A particular phase of a project is made up of activities (A-L) as indicated in the table


below,

Activity Duration (weeks) Preceding Activity

A 3 -

B 4 A

C 3 A

D 5 A

E 7 B

F 7 C

G 7 C

H 7 C

I 8 D

J 15 E, F, G, H

K 10 I

L 4 J, K

Draw and analyse the network using precedence diagram