Beton plant CRBC sayung Pekerjaan Rigid dan Gentry crane

MUTU BETON
batching
tanggal pekerjaan total TM kubikasi truck mixer
plan
FC 10/ E FC 20 FC 28 C FC 30/ B FC 35 FC 40
20-Feb-23 36 m³ rigid jalan 6 truck VUB 6,5.6,5.6,5.6,5.6,5.3,5
21-Feb-23 15 m³ lantai bawah silo 3 truck VUB 6,5.6,5.2
23-Feb-23 40 m³ rigid jalan 7 truck MJB 6.6.6.6.6.6.4
25-Feb-23 40 m³ rigid jalan 7 truck MJB 6,6,6,6,6,6,4
28-Feb-23 20 m³ rigid jalan ,(10m³ area silo, 10m³ lt gentry crane) 4 truck MJB 5,5,5,5
01-Mar-23 20 m³ rigid jalan ,(10m³ area silo, 10m³ lt gentry crane) 4 truck MJB 5,5,5,5
03-Mar-23 10 m³ rigid jalan 2 truck MJB 5,5
04-Mar-23 15 m³ rigid jalan 3 truck MJB 5,5,5
07-Mar-23 20 m³ rigid 3 truck MJB 7,6,7,
08-Mar-23 20 m³ rigid 3 truck MJB 7,6,7
08-Mar-23 21 m³ gentry crane 3 truck MJB 7,7,7
09-Mar-23 12 m³ rigid 2 truck MJB 6,6
09-Mar-23 8 m³ gentry crane 2 truck MJB 4,4
11-Mar-23 20 m³ rigid depan mess crbc 3 truck MJB 7,7,6
13-Mar-23 18 m³ 6m³gentry,12m³ rigid depan mess 3 truck MJB 6,6,6
13-Mar-23 15 m³ rigid depan mess CRBC 3 truck MJB 5,5,5
14-Mar-23 15 m³ rigid depan mess crbc 3 truck MJB 5,5,5
15-Mar-23 15 m³ depan mess crbc 3 truck MJB 5,5,5
16-Mar-23 20 m³ depan mess crbc 4 truck MJB 5,5,5,5
17-Mar-23 20 m³ depan mess crbc 3 truck MJB 7,7,6
18-Mar-23 10 m³ depan mess crbc 2 truck MJB 5,5
19-Mar-23 15 m³ samping hopper/area tengah 3 truck MJB 5,5,5
20-Mar-23 4 m³ akses jalan 1 truck MJB 4
21-Mar-23 29 m³ Lantai gentry crane 5 truck MJB 6,6,6,6,5
21-Mar-23 10 m³ Pondasi gentry/akses jalan 2 truck MJB 5,5
24-Mar-23 6 m³ rigid 1 truck MJB 6
24-Mar-23 7 m³ Gentry 1 truck MJB 7
25-Mar-23 7 m³ rigid /akses jalan 1 truck MJB
25-Mar-23 10 m³ Gentry crane 2 truck MJB 7,3
26-Mar-23 20 m³ Gentry crane depan 3 truck MJB 6.5,7,6.5
27-Mar-23 29 m³ Pondasi gentry 6 truck MJB 5,5,5,5,5,4
29-Mar-23 15 m³ Pondasi gentry 3 truck MJB 5,5,5
29-Mar-23 27 m³ rigid, gentry 5m³ 6 truck MJB 5,5,5,4,3
30-Mar-23 19 m³ Pondasi /slop gentry depan 4 truck MJB 5,5,5,4
31-Mar-23 57 m³ 11 truck MJB 5,5,5,5,5,5,5,5,5,6,6

total volume 467 m³ 40 m³ 0 m³ 58 m³ 81 m³ 0 m³