YASHO Industries Limited

Job Safety Analysis (JSA) Name of Job Assessed: ERECTION OF PIPE RACK Department: EHS JSA Date:

JSA Done By: (Name) SOPs that Identifies This Job:

Required Baseline PPE: FULL BODY HARNESS , HELMET ,SAFETY SHOES , REFLECTING JACKET,GOGGELS , HAND GLOVES , LIFE LINE.

Controls to Eliminate or Mitigate Hazard/s


Basic Job Steps (Step=Task) Potential Hazards (Type of hazard: description) (Type of control: description) Comments

Elimination Substitute Engineering Administrative

1.Uneven Road 1.Follow lifiting work permit


2.inspection of all lifyimg tools befour use.
Shifting 2. lifiting tool failure
3.Farana speed will be in normal walking speed
3.road accident 4.Road & traffic movement care will be carried out by supervisor.

1.material must be properly secured with sling.


2.Balancing to be verify before shifting.
3.Farana will be set up at level.
1.Farana failure due to hydrolic system 4.Farana must be 3 rd party certified .
Setting up farana for lifting. 2.Material unbalance or any lifting 5.All lifts will be under the rated capacity of
equipement failure farana .i.e (load chart)

Inspection of farana and rigging gears 1.Fall of object 1.Cerified farana operator and riggers will carry out the lifting activity .

1.Toll and joints etc. should be lift by rope and basket .


1. Materal can fall 2.Scaffolding should be erected under skilled supervision.
Work at height on pipe rack 2.Personal fall
3.full body harness must be errected with standerd with lifeline and inspected
3.Improper scaffoliding erection by HSE person. 4.Scaffolding inspection checklist will be follow .

1.Farana load calculation against height must be evaluate & calculated for erection work
2.Base of land will be monitore and verified.
3.Boom length will be measure practically.
4.Area barricading will be done surrounding radious of farana
Erection of ms rack on civil foundation & rack. 5.Train& experience rigger available
1. Fall of rack & farana due to under 6.Training to be provided & skill
on 7 meter height by farana capacity &height of the job . must be verify. 7.Engginer &
safety person must be present at site.
8.All rack must be check by lifting at 1 feet height for balance.

1. Enviroment hazad. 1.Waste material should be stacked properly and dumped in designated places.
Housekeeping 2.Slip , Trip and fall. 2.Waste material should be barricated.

Comments / Remarks: -

Name of Area Supervisor or Manager: ARJUN PRASAD Signature


Signature

EHS Representative Name & Sign

VAIBHAV KUMAR RAI Signature


Sr.No Name of Participants Department Designation Sign

1 MECH. FORMAN

2 MECH. RIGGER

3 MECH. FITTER

4 MECH. WELDER

5 MECH. HELPER