Facility Roof Survey: Prepared For: Prepared by
Facility Roof Survey: Prepared For: Prepared by
Facility Roof Survey: Prepared For: Prepared by
Sample Manufacturing
In accordance with your request, a visual inspection of the roof at the referenced building was conducted on Jul 20, 2004. The
purpose of the inspection was to obtain a general overview of the current condition of the roof and to provide recommendations
for replacement of the existing roof as well as related budget cost estimates for the work.
The building is of masonry and steel reinforced concrete construction and is two stories in height. The roof area consists of
eight (8) roof sections. The existing roof is comprised of a several types of edpm and shingle roofing systems adhered,
ballasted and mechanically attached to the decking. The roof system is in poor condition and is leaking throughout the interior
of the building. Numerous holes and other breaches in the roof membrane were observed and are noted here in this report.
Total removal and replacement or repair of the existing roofing systems is recommended at this time. Budget cost estimates for
the replacement and repairs are included in this report. We have also included repair recommendations and estimates for each
roof section as well, to help you budget accordingly. The level of importance for work varies from roof to roof, below is a
prioritized list from worst to best for you to consider when planning the completion of this work.
1) Roof #8
2) Roof #1
3) Roof #2
4) Roof #6
5) Roof #5
6) Roof #3
7) Roof #4
8) Roof #7
It is understood that the foregoing information as well as the information contained in this report is based on visual
observations only.Additional testing would be needed to verify deckings structural integrity and the presence of asbestos
containing materials (ACM's) in any of the existing roofing components. It is further understood that the cost estimates offered
are for budgeting purposes only.
Please feel free to contact me at (419) 739-2751, if you have any questions or if you require any additional assistance.
Sincerely,
Adam Lenhart
EMR Technologies
201 East Auglaize Street
Wapakoneta, Ohio 45895
Sample Manufacturing
4th Street
Kalida, Ohio 45853
Roof #6
Roof #4 Roof #2
Roof #1
Roof #5
Roof #3
Roof #7
Roof #8
Facility Summary
Recommendations - Summary
Section Name Replacement Value Activity Amount $
1 NP System $85,120 Replacement/Repair Pg 6
2 Shingle $42,432 Replacement/Repair Pg 9
3 Ballasted Rear Addition $52,800 Repair Pg 13
4 Fully Adhered Front $20,416 Repair Pg 18
5 Ballasted Upper Level $14,144 Repair Pg 24
6 Lower Front Gymnasium $71,200 Repair Pg 30
7 Upper Gymnasium $115,200 Repair Pg 32
8 Lower Rear Gymansium $22,400 Replacement/Repair Pg 37
$423,712 See Pages
Prepared by: EMR Technologies Page 2 Inspection Date: July 20, 2004
Facility Roof Survey Facility:Sample Manufacturing NP System Roof 1
Roof Designation: 1
Height: 16 feet
Slope: Slight
Drainage: Inadequate
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 3 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing NP System Roof 1
Existing Conditions
PHOTO DETAILS
Photo #: 2
Severity: Moderate
Prepared by: EMR Technologies Page 4 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing NP System Roof 1
Photo #: 4
Type: Hole
Severity: Moderate
Details: Hole
Photo #: 3
Severity: Major
Prepared by: EMR Technologies Page 5 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing NP System Roof 1
Recommendations
Type of Activity Urgency $
Replacement/Repair High Below
Due to the Severity we recommend replacement of the total system, but we also have given you an option for repairs, on this
roof area at this time. The roof is deteriorating and allowing water to enter the building.
ROOF REPLACEMENT:
* Furnish and Install a new complete 1/8" tapered isocyanurate insulation system.
* Install a new 36 mil reinforced Fibertite re-enforced elvaloy roofing system. Utilizing heat welded seams.
Please Note: All bad decking to be replaced on a time and material basis.
ROOF REPAIRS:
* Cut out wet insulation in three major buckling areas where the insulation is buckling and replace with new insulation and
membrane. Tie into existing roof using current industry standards.
* Strip in all seams, units and perimeter using new 9" pressure sensitive flashing. (Total of 2,615 lineal feet)
Prepared by: EMR Technologies Page 6 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Shingle Roof 2
Roof Designation: 2
Height: 16 feet
Slope: 4 in 12
Drainage: Adequate
Currently Leaking? No
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 7 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Shingle Roof 2
Existing Conditions
PHOTO DETAILS
Photo #: 7
Type: Buckling
Severity: Moderate
Details: Buckling
Prepared by: EMR Technologies Page 8 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Shingle Roof 2
Recommendations
Type of Activity Urgency $
Replacement/Repair High Below
Due to the Severity we recommend replacement of the total system, but we also have given you an option for repairs, on this
roof area at this time. The roof is deteriorating and allowing water to enter the building.
* Remove all roofing and insulation down to the wood decking on the North side of the roof only.
* Along the gutter and rake edges install new ice and water shield.
* Install new metal expansion joint covers. Metal will be fabricated out of 24 gauge kynar finished steel.
* Replace the small EPDM roof connected to the North side of the roof and make the proper tie-in to manufacturer
specifications.
* Install new 24 gauge metal drip and rake edge to all perimeters.
Please Note: All bad decking to be placed on a time and material basis.
* Remove and dispose of three feet by thirty four feet section of shingles on North and South side of the shingle roof.
* Install new metal expansion joint covers. Metal will be fabricated out of 24 gauge kynar finished steel.
Alternate Repair #1: Remove and replace the existing damaged shingles only on the North and South Side ( No
expansion joint work). Complete for the Total Sum of $ 2, 250.00
Prepared by: EMR Technologies Page 9 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Rear Addition Roof 3
Roof Designation: 3
Height: 16 feet
Slope: Slight
Drainage: Inadequate
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 10 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Rear Addition Roof 3
Existing Conditions
PHOTO DETAILS
Photo #: 11
Severity: Moderate
Photo #: 9
Type: Patches
Severity: Moderate
Details: Patches
Prepared by: EMR Technologies Page 11 Inspection Date: July 20, 2004
Facility Roof Survey Facility:Sample Manufacturing Ballasted Rear Addition Roof 3
Photo #: 10
Type: Repairs
Severity: Moderate
Details: Repairs
Prepared by: EMR Technologies Page 12 Inspection Date: July 20, 2004
Facility Roof Survey Facility:Sample Manufacturing Ballasted Rear Addition Roof 3
Recommendations
Type of Activity Urgency $
Repair Moderate Below
Due to the Severity we recommend repair of this roof area at this time. The roof is deteriorating and allowing water to enter
the building.
* Strip in all seams, units using new 9" pressure sensitive flashing. (Total of 260' lineal feet)
* Replace all existing 36" wall flashing around the entire perimeter. ( Total of 300' lineal feet)
Prepared by: EMR Technologies Page 13 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Fully Adhered Front Roof 4
Roof Designation: 4
Height: 18 feet
Slope: Slight
Drainage: Inadequate
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 14 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Fully Adhered Front Roof 4
Existing Conditions
PHOTO DETAILS
Photo #: 14
Severity: Minor
Prepared by: EMR Technologies Page 15 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Fully Adhered Front Roof 4
Photo #: 15
Type: Ponding
Severity: Moderate
Details: Ponding
Prepared by: EMR Technologies Page 16 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Fully Adhered Front Roof 4
Photo #: 17
Type: Repairs
Severity: Major
Details: Repairs
Photo #: 13
Severity: Moderate
Prepared by: EMR Technologies Page 17 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Fully Adhered Front Roof 4
Recommendations
Type of Activity Urgency $
Repair Low Below
Due to the Severity we recommend repair of this roof area at this time. The roof is deteriorating and allowing water to enter
the building.
* Strip in all seams, units using new 9" pressure sensitive flashing. (Total of 528 lineal feet)
* Replace all existing 36" wall flashing around the entire perimeter. ( Total of 220 lineal feet)
Prepared by: EMR Technologies Page 18 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Upper Level Roof 5
Roof Designation: 5
Height: 16 feet
Slope: Slight
Drainage: Inadequate
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 19 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Upper Level Roof 5
Existing Conditions
PHOTO DETAILS
Photo #: 23
Type: Debris
Severity: Major
Details: Debris
Prepared by: EMR Technologies Page 20 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Upper Level Roof 5
Photo #: 19
Severity: Major
Photo #: 22
Severity: Major
Prepared by: EMR Technologies Page 21 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Upper Level Roof 5
Photo #: 20
Type: Repairs
Severity: Major
Details: Repairs
Prepared by: EMR Technologies Page 22 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Upper Level Roof 5
Severity: Major
Details: Repairs
Photo #: 24
Type: Repairs
Severity: Major
Details: Repairs
Prepared by: EMR Technologies Page 23 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Ballasted Upper Level Roof 5
Recommendations
Type of Activity Urgency $
Repair Moderate Below
Due to the Severity we recommend repair of this roof area at this time. The roof is deteriorating and allowing water to enter
the building.
* Strip in all seams, units using new 9" pressure sensitive flashing. (Total of 260' lineal feet)
* Replace all existing 36" wall flashing around the entire perimeter. ( Total of 300' lineal feet)
Prepared by: EMR Technologies Page 24 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Front Gymnasium Roof 6
Roof Designation: 6
Height: 16 feet
Slope: Flat
Drainage: Inadequate
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 25 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Front Gymnasium Roof 6
Existing Conditions
PHOTO DETAILS
Photo #: 36
Type: Debris
Severity: Minor
Details: Debris
Prepared by: EMR Technologies Page 26 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Front Gymnasium Roof 6
Photo #: 29
Severity: Major
Photo #: 27
Severity: Major
Prepared by: EMR Technologies Page 27 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Front Gymnasium Roof 6
Photo #: 28
Type: Repairs
Severity: Major
Details: Repairs
Photo #: 30
Type: Repairs
Severity: Major
Details: Repairs
Prepared by: EMR Technologies Page 28 Inspection Date: July 20, 2004
Facility Roof Survey Facility:Sample Manufacturing Lower Front Gymnasium Roof 6
Photo #: 31
Type: Repairs
Severity: Major
Details: Repairs
Photo #: 34
Type: Repairs
Severity: Major
Details: Repairs
Prepared by: EMR Technologies Page 29 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Front Gymnasium Roof 6
Recommendations
Type of Activity Urgency $
Repair High Below
Due to the Severity we recommend repair of this roof area at this time. The roof is deteriorating and allowing water to enter
the building.
* Strip in all seams, units using new 9" pressure sensitive flashing. (Total of 700 lineal feet)
* Replace all existing 36" wall flashing around the entire perimeter. ( Total of 800 lineal feet)
* Re Flash four 5" roof drains along the North Gym wall with new epdm, to meet current manufacturer specifications.
Alternate #1 - Replace the tenting wall flashing and repair the drains along the North Gym Wall only.
Repairs complete for the total sum of $ 3, 450.00
Prepared by: EMR Technologies Page 30 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Upper Gymnasium Roof 7
Roof Designation: 7
Height: 28 feet
Slope: Moderate
Drainage: Adequate
Currently Leaking? No
History of Leaking? No
Prepared by: EMR Technologies Page 31 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Upper Gymnasium Roof 7
Recommendations
Type of Activity Urgency $
Repair Low Below
Due to the good only on this roof area situation we recommend maintenance repairs in the future. No work is necessary
though at this time.
* Strip in all seams, wall and penetrations with new 9" pressure sensitive flashing. (Total of 2,900 lineal feet)
Prepared by: EMR Technologies Page 32 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Rear Gymansium Roof 8
Roof Designation: 8
Height: 16 feet
Slope: Flat
Drainage: Inadequate
Drainage and Leak Details: This roof has been leaking for several
years and deterioration has increased.
Prepared by: EMR Technologies Page 33 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Rear Gymansium Roof 8
Existing Conditions
PHOTO DETAILS
Photo #: 37
Severity: Major
Photo #: 42
Severity: Major
Prepared by: EMR Technologies Page 34 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Rear Gymansium Roof 8
Photo #: 38
Type: Patches
Severity: Moderate
Details: Patches
Prepared by: EMR Technologies Page 35 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Rear Gymansium Roof 8
Photo #: 41
Type: Repairs
Severity: Major
Details: Repairs
Photo #: 45
Type: Repairs
Severity: Major
Details: Repairs
Prepared by: EMR Technologies Page 36 Inspection Date: July 20, 2004
Facility Roof Survey Facility: Sample Manufacturing Lower Rear Gymansium Roof 8
Recommendations
Type of Activity Urgency $
Replacement/Repair High Below
Due to the Severity we recommend replacement of the total system, but we also have given you an option for repairs, on this
roof area at this time. The roof is deteriorating and allowing water to enter the building.
ROOF REPLACEMENT:
* Furnish and Install a new complete 1/8" tapered isocyanurate insulation system.
* Install a new 36 mil reinforced Fibertite re-enforced elvaloy roofing system. Utilizing heat welded seams.
Please Note: All bad decking to be replaced on a time and material basis.
* Cut out roofing & wet insulation in area where the decking is gone and replace with new metal deck insulation and
membrane. Tie into existing roof using current industry standards. (20' x 20')
* Strip in all seams, units using new 9" pressure sensitive flashing. (Total of 350 lineal feet)
* Replace all existing 36" wall flashing around the entire perimeter. ( Total of 350 lineal feet)
Prepared by: EMR Technologies Page 37 Inspection Date: July 20, 2004