Professional Documents
Culture Documents
Final Estimate For Tender
Final Estimate For Tender
Earth work in filling:-Earth filling with soft soil in rooms and verandah in
Cum 320.12
layers of 15-15 cm thick by sprinkling water and hand compaction.
2.0 Stone Works:-
Stone masonry work in cement sand mortar in 1:6 foundation and super -
structure with quarry stones in perfect line & level including wetting,
Cum 1143.73
packing the joints and curing the work in all types & thickness of walls,
column etc.as per instruction & specification all complete work.
P.C.C. M15 (1:2:4) Work (for un-reinforced works) etc.with cement sand
and graded coarse aggregate (river bed foruwa) & (waterproof material if
reqd.) including mixing with concrete, lead upto 30m, laying, compacting
Cum 125.38
the concrete mix with vibrator machine, finishing to approved level lines
and dimensions and curing as per instruction & specification complete
work.
P.C.C. M15 (1:2:4) for R.C.C. Work in foundation, walls, beams, slabs,
sill, stitches, lintels etc.with cement sand and graded coarse aggregate
(river bed foruwa) including mixing concrete, lead upto 30m, laying,
Cum 21.00
compacting the concrete mix with vibrator machine,finishing to approved
level lines and dimensions and curing as per instruction & specification
complete work.
P.C.C. M20 (1:1.5:3) for R.C.C. Work in Super structure, columns, beams,
decks, slabs, etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing with concrete, lead upto 30m, compacting the
Cum 1070.74
concrete mix with vibrator machine,laying, finishing to approved level
lines and dimensions and curing as per instruction & specification
complete work.
5.0 Steel Works/ Metal Works:-
TMT Reinforcement bar (Fe 500) for RCC Works, tested including
straightening, cleaning, cutting, bending and fixing in position with 20
Ton 167.70
B.G. annealed binding wire as per drawing, specifications and instructions
by site-engineer all complete work.
M.S Grill Work by 12*12 mm Solid core with 4.5 x20 Ms Strips frame
work of approved quality and manufacturer including 2 coats of
Sqm 376.56
aluminium paints over one coat of primer and fixing in position as per
instructions & specifications all complete work.
Supplying & installing Aluminium Framed Casement Door one way/ two
ways openable with ventilator Natural Colour in the Section of 101x45
x1.5 mm including 9mm thick pre-laminated board or 5 mm thick Glass, Sqm 43.47
silicon sealant and accessories as per drawing, specification & instruction
all complete.
Supplying & installing Aluminium Framed Casement Door one way/ two
ways openable with Natural Colour in the Section of 101x45 x1.5 mm
including 9mm thick pre-laminated board or 5 mm thick Glass, silicon Sqm 246.48
sealant and accessories as per drawing, specification & instruction all
complete.
6.0 Composite Wall Works:-
Supplying and fixing double leaf solid corelead protected wooden flush
door with solid wood frame including necessary handles , locks etc. of Sqm 3.15
medium quality as per drawings.
8.0 Plaster/ Pointing Works:-
12.5mm thick cement sand plaster (1:3) on ceiling of good finish including
cleaning, scrubing, wetting the surface before plaster work and curing the Sqm 2284.83
same as per specifications & instructions all complete work
Providing and laying 50mm thick cement screed 1:4 (1 cement : 4 sand)
above PCC including surface preparation, cleaning of debris, applying
Sqm 1813.10
cement slurry over hardened PCC, finishing, curing, protection, etc., all
complete as per drawings and instruction of the Engineer.
Supplying & laying 25mm thick anti-slip Cement Tile (Parking tile)
(250x250) on (1:4) cement sand mortar all complete as per specification & Sqm 167.69
direction.
Porcelain Glazed Tiles white/coloured in dado, skirting etc. laid with
cement sand mortar 1:4 with white cement slurry including polishing to
Sqm 294.91
smooth finished glazed surface as per instruction & specification all
complete work.
Porcelain Non glazed (spartic) Tiles white/ coloured in floor with cement
sand mortar 1:4 with white cement slurry including polishing to smooth
Sqm 1974.04
finished glazed surface as per instruction & specification all complete
work.
Marble flooring works for staircase in ground and first floor Sqm 61.48
10.0 Painting Works:-
2 Coats Plastic emulsion Painting in inner part of building over one coat
primer or equivalent primer to give uniform colouring after rending the
Sqm 7358.61
surface clean & moist as per specification and instruction all complete
work.
2 Coats weather guard 100% acrelic paint work over one coat primer on
( Epex Aultima or equivalent) Outer Part of building of filter and primer
Sqm 2490.23
to give uniform colouring after rending the surface clean & moist as per
specification and instruction complete work.
Supply required materials and fixing in position 3mm thick fibre sheet all
Sqm 209.04
complete as per specifications, drawings and instructions.
point 486.00
{b} International pin 11/13 A general outlet point with 2x2.5+1x1.5 sq.
point 201.00
mm / equivalent cu cable, bends, circular & Junction Boxes
{b} 220 V, 50 Hz, 48" Edge, 3 Blade ceiling fan (Brown/white/bianco) set 75.00
4. Switches and sockets
Supply of Modular type switches, sockets as mentioned below, 18 SWG
GI metal boxes , screw, and other necessary materials with its Installation,
4.1 Interconnection and commissioning including civil works as per drawing ,
specification all complete
Brands: ABB,Schneider, Legrand or equivalent
{a} 10 A 1 Gang 1 way switch set 79.00
{b} 10 A 1 Gang 2 way switch set 12.00
{c} 10 A 2 Gang 1 way switch set 32.00
{d} 10 A 3 Gang 1 way switch set 12.00
{e} 10 A 4 Gang 1 way switch set 43.00
{f} 5/6 pin 6/16 A switch socket set 486.00
{g} international pin 11/13A switch socket set 201.00
{h} 5 step Fan Speed Regulator set 75.00
{I} 20 A switch socket, AC set 10.00
{j} 50A 500V 1 Gang 5 Pin surface socket outlet, IP66 Industrial Socket set 3.00
5. Power Cable
Supply, delivery, laying and connecting of the following
Armoured/unarmoured power cable including cable sockets, pull boxes
5.1 and necessary materials. chiselling of wall/ floors and redoing the chiselled
area with cement & sand mortar as per drawing and site condition all
complete.
{c} (4x10+1x4) sq. mm copper cable from MDB TO FDB TO SDB (GF-8
rm 350.00
DB, FF-4)
{d} (4x25+1x16) sq. mm copper cable from MPB to FFDB rm 15.00
6. Earthing system
Supply of materials and Installation of loke copper plate (600x600x3.14
mm), 25*3 sq. mm copper bare conductor, salt, charcoal dust, bare copper
cable as per drawing with solid CAD weld ( Brazing) & watering 32 mm
dia PVC pipe & its installation in a whole of 90x90x250 cm with the
layers of Earthing materials as per standard, specification, drawing and
6.1 refilling the ground all complete.5 set for Lightning Arrestor, 1 set for set 9.00
Major OT, 1 set for Minor OT and 2 set for DG, See drawings for details
16.3 Supply, Testing and commisoning of Ceiling Cassette/ Wall Mounted nos 5.00
Type indoor units 1 Tr Capacity 220-240v 1Ph 50Hz 6A.
16.4 Supply, Testing and commisoning of Ceiling Cassette/ Wall Mounted nos 4.00
Type indoor units 1.5 Tr Capacity 220-240v 1Ph 50Hz 6A.
16.5 Supply, Testing and commisoning of Ceiling Cassette Type indoor units 2 nos 2.00
Tr Capacity 220-240v 1Ph 50Hz 6A.
16.6 Supply, Testing and commisoning of Ceiling Cassette Type indoor units 3 nos 2.00
Tr Capacity 220-240v 1Ph 50Hz 6A.
SET 9.00
SET 14.00
Supplying and fitting of Stainless steel sink size 550x400mm with 32
mm pvc bottle trap including 32mm CP waste coupling with CP
4.0
chain and rubber plug etc., 15mm cp sink cock, 1.5x45cm (½"x18")
pipe connector and screw all complete work.
kitchen sink single SET 13.00
7.0 Supplying and fitting of 15 mm dia. C.P. fancy type Bib-cock (heavy)
nos 14.00
Supplying and fitting of 15mm C.P. Commode Spray (Health faucet)
8.0
with 1.2 m. long flexible pipe.
nos 14.00
9.0 Supplying and fitting of 15 mm dia. C.P. Angle Valve
nos 64.00
10.0 Supplying and fitting of CP Soap Dish with necessary screws.
nos 49.00
Supplying and fitting of C P towel rod 1.5x60cm (½"x 18") size with
11.0
necessary screws.
nos 37.00
Supplying and fitting of Chrome Plate Toilet Paper Holder with
12.0
necessary screw.
nos 14.00
Supplying and fitting of Looking Mirror Modi guard 450x600mm
13.0
(18"x 24") with necessary screw
nos 17.00
Supplying and fitting of shower head with arm and flang in
14.0
bathrooms.
nos 2.00
nos 3.00
19.0 Supplying and Installation of Hospital Scrub Sink nos
nos 1.00
20.0 50 mm. dia. P.V .C Pipes.
R.M 120.89
21.0 75 mm. dia. P.V .C Pipes.
R.M 221.30
22.0 110 mm. dia.P.V.C. Pipes
R.M 166.60
23.0 4" UPVC Pipe 6 kg pressure
R.M 68.00
24.0 PVC 40 mm. dia.specials
Bend NOS 85.00
tee NOS 45.00
25.0 PVC 75 mm. dia.specials
Socket NOS 44.00
Bend NOS 38.00
tee NOS 25.00
26.0 PVC 110 mm. Dia specials
Socket NOS 25.00
Bend NOS 36.00
tee NOS 42.00
27.0 110 mm dia. C.P. Grating heavy quality.
Ground Floor NOS 21.00
28.0 Supplying and fitting 110 x 75 mm dia. Multi Floor Trap
NOS 40.00
Supplying and fixing with necessary fittings 20 mm CPVC
29.0 (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2
(Flowguard or ISI Standard)
R.M 88.90
Supplying and fixing with necessary fittings 25 mm CPVC
30.0 (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2
(Flowguard or ISI Standard)
R.M 48.32
Supplying and fixing with necessary fittings 32 mm CPVC
31.0 (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2
(Flowguard or ISI Standard)
R.M 22.35
32.0 32 mm dia CPVC Ball Valve
NO 2.00
Supplying and installation of 2000 ltr PVC water tank with Inlet,
33.0
outlet, over flow, cleanout hole etc., nipples and with wash out plug.
NO 2.00
Supplying and installtion of 300 ltr with 3 panel solar water heater
34.0
with electric booster all complete set.
NO 1.00
35.0 Supplying and installtion of urinal partition.
NO 4.00
WATER TANK WORKS
1.0 Earth Works:-
Earth Work in Excavation in foundation (All Type of soil) for lift up
to1.5 m. including stacking the soil 0.90 m. minimum from the edge of
foundation, filling the excavated place & grub of soil in foundation trench Cum 40.39
& disposing the excess soil upto a lead of 10 m as per instruction &
specification all complete work
2.0 Concrete Works:-
Plain Cement Concrete (1:3:6) M10 in foundation & wall with cement,
sand and aggregate including mixing, laying, finishing to approved level,
Cum 1.38
line and dimensions and curing as per instruction & specification
complete work.
P.C.C. M20 (1:1.5:3) for R.C.C. Work in Super structure, columns, beams,
decks, slabs, etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing with concrete, lead upto 30m, compacting the
Cum 13.97
concrete mix with vibrator machine,laying, finishing to approved level
lines and dimensions and curing as per instruction & specification
complete work.
Providing and laying 15mm thick (average) cement plaster 1:4 ) on brick
surface with or on other similar location or as instructed for all lead lift
Sqm 57.31
and scaffolding etc. required to execute the work complete to the entire
satisfaction of Engineer for external surface.
Earth work in filling:-Earth filling with soft soil in rooms and verandah in
Cum 16.09
layers of 15-15 cm thick by sprinkling water and hand compaction.
Stone masonry work in cement sand mortar in 1:6 foundation and super -
structure with quarry stones in perfect line & level including wetting,
Cum 6.17
packing the joints and curing the work in all types & thickness of walls,
column etc.as per instruction & specification all complete work.
Brick work in cement sand mortar in 1:4 foundation and super -structure
with 1 st class bricks in perfect line & level including wetting the bricks,
Cum 27.62
packing the joints and curing the work in all types & thickness of
walls,column etc.as per instruction & specification complete work.
P.C.C. M15 (1:2:4) for R.C.C. Work in foundation, walls, beams, slabs,
sill, stitches, lintels etc.with cement sand and graded coarse aggregate
(river bed foruwa) including mixing concrete, lead upto 30m, laying,
Cum 1.05
compacting the concrete mix with vibrator machine,finishing to approved
level lines and dimensions and curing as per instruction & specification
complete work.
P.C.C. M20 (1:1.5:3) for R.C.C. Work in Super structure, columns, beams,
decks, slabs, etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing with concrete, lead upto 30m, compacting the
Cum 36.72
concrete mix with vibrator machine,laying, finishing to approved level
lines and dimensions and curing as per instruction & specification
complete work.
Supplying & installing Aluminium Framed Casement Door one way/ two
ways openable with ventilator Natural Colour in the Section of 101x45
x1.5 mm including 9mm thick pre-laminated board or 5 mm thick Glass, Sqm 4.41
silicon sealant and accessories as per drawing, specification & instruction
all complete.
6.0 Wood Works:-
Formwork/ Centering & Shuttering with 18mm thick Plywood for all type
of concrete works necessary propping, scaffolding, staging, supporting
Sqm 283.33
inclusive wedging and cutting holes for utilization work till the support is
fully unyielding as per instructions & specifications complete work .
12.5mm thick cement sand plaster (1:3) on ceiling of good finish including
cleaning, scrubing, wetting the surface before plaster work and curing the Sqm 115.02
same as per specifications & instructions all complete work
12.5 mm thick cement sand plaster (1:4) on Brick masonry walls
(inside/outside) of good finish including racking the joints, wetting the Sqm 94.66
surface & curing the work as per specifications & direction all complete.
Providing and laying 3/4" thick cement screed 1:4 (1 cement : 4 sand)
above PCC including surface preparation, cleaning of debris, applying
Sqm 89.51
cement slurry over hardened PCC, finishing, curing, protection, etc., all
complete as per drawings and instruction of the Engineer.
3mm thick (1:1) Cement sand punning work on floor, walls etc including
mixing, laying, finishing to approved level, line and dimensions and curing Sqm 89.51
as per instruction & specification all complete work.
2 Coats weather guard 100% acrelic paint work over one coat primer on
( Epex Aultima or equivalent) Outer Part of building of filter and primer
Sqm 119.87
to give uniform colouring after rending the surface clean & moist as per
specification and instruction complete work.
1.1 Site Clearance Work including cutting & uprooting shrubs, thick herbs &
vegetables, top soil cutting , levelling & removal of waste, transporting to the
specified place as per instruction by site engineer all complete.
Construction site area 1 1698.73 1698.73
sum 1698.73 Sqm
Earth Work in Excavation in foundation (All Type of soil) for lift up to1.5
m. including stacking the soil 0.90 m. minimum from the edge of foundation,
1.2 filling the excavated place & grub of soil in foundation trench & disposing the
excess soil upto a lead of 10 m as per instruction & specification all complete
work
Earth Works in Foundation Footings
Footing, F1 21 2.60 2.60 2.33 330.06
Footing, F2 18 3.30 3.30 2.33 455.75
Footing, F3 24 1.20 1.20 2.33 80.36
Footing, CF 3 2.50 3.80 2.33 66.27
Earth Back Filling in foundation trenches & Floor in 15 c.m. layers with
1.3 water sprinking & manual compaction as per speciication and instruction all
complete.
Excavation Work from item no C-1.02 1 1377.20 1377.20
Deduct Stone Soling, Item no. C-2.01 -1 89.90 -89.90
Deduct Stone Masonry, Item no. C-2.02 -1 143.69 -143.69
Deduct PCC (1:3:6) Works, Iem no. C-4.01 -1 44.83 -44.83
Deduct PCC (1:1.5:3), Item no C-4.04 -1 252.63 -252.63
sum 846.15 Cum
1.4 Earth work in filling:-Earth filling with soft soil in rooms and verandah in area
layers of 15-15 cm thick by sprinkling water and hand compaction.
Plinth Area 1.00 1698.73 1.00 0.225 382.22
Deduct from
Columns (for main block) -45.00 0.70 0.70 0.23 -4.97
Columns (for ramp) -24.00 0.45 0.45 0.23 -1.10
For Foundation Beams Deduction
Grid 1-1, 2-2, 3-3 & 4-4 -4.00 59.50 0.450 0.225 -24.10
Grid 5-5 -1.00 6.50 0.450 0.225 -0.66
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K -8.00 19.50 0.450 0.225 -15.80
Grid D-D -1.00 13.00 0.450 0.225 -1.32
Grid G-G & H-H -2.00 26.00 0.450 0.225 -5.27
For Ramp -3.00 29.23 0.450 0.225 -8.88
sum 320.12 Cum
2.1 Stone Soling in foundation trench, finishing to approved level, line and
dimensions as per instruction & specification all complete work.
Stone Soling Works in Foundation Footings
Footing, F1 21.00 2.60 2.60 0.15 21.30
Footing, F2 18.00 3.30 3.30 0.15 29.41
Footing, F3 24.00 1.20 1.20 0.15 5.19
Footing, CF 3.00 2.50 3.80 0.15 4.28
In Floors
Plinth Area 1.00 1698.73 1.00 0.15 254.81
Deduct from
Columns (for main block) -45.00 0.70 0.70 0.15 -3.31
Columns (for ramp) -24.00 0.45 0.45 0.15 -0.73
For Foundation Beams Deduction
Grid 1-1, 2-2, 3-3 & 4-4 -4.00 58.50 0.45 0.15 -15.80
Grid 5-5 -1.00 6.50 0.45 0.15 -0.44
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K -8.00 19.50 0.45 0.15 -10.53
Grid D-D -1.00 13.00 0.45 0.15 -0.88
Grid G-G & H-H -2.00 26.00 0.45 0.15 -3.51
For Ramp
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,R-R -7.00 3.60 0.45 0.15 -1.71
Grid 5a-5a , 5b-5b, 5c-5c -3.00 25.63 0.45 0.15 -5.20
sum 302.69 Cum
Stone masonry work in cement sand mortar in 1:6 foundation and super -
2.2 structure with quarry stones in perfect line & level including wetting, packing
the joints and curing the work in all types & thickness of walls, column etc.as
per instruction & specification all complete work.
For Foundation Beams
Grid 1-1, 2-2, 3-3 & 4-4 4.00 58.50 0.30 0.85 59.67
Grid 5-5 1.00 6.50 0.30 0.85 1.66
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K 8.00 19.50 0.30 0.85 39.78
Grid D-D 1.00 13.00 0.30 0.85 3.32
Grid G-G & H-H 2.00 26.00 0.30 0.85 13.26
For Ramp 0.00
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,R-R 7.00 3.60 0.30 0.85 6.43
Grid 5a-5a , 5b-5b, 5c-5c 3.00 25.63 0.30 0.85 19.61
sum 143.73 Cum
Brick work in cement sand mortar in 1:4 foundation and super -structure with
3.1 1 st class bricks in perfect line & level including wetting the bricks, packing
the joints and curing the work in all types & thickness of walls,column etc.as
per instruction & specification complete work.
Ground floor
Grid 1-1 between F-G 1.00 6.50 0.35 3.05 6.94
Grid 1-1 1.00 52.00 0.25 3.05 39.65
18.00 0.30 0.25 3.75 5.07
Grid 2-2 between E-F 1.00 4.05 0.35 3.05 4.33
Grid 2-3 between H-I 1.00 3.75 0.25 3.63 3.40
Grid 3-3 between C-D 1.00 6.50 0.25 3.63 5.90
2.00 0.30 0.25 3.75 0.57
Grid 3-3 between E-F 1.00 4.05 0.35 3.05 4.33
Grid 3-3 between F-G 1.00 4.10 0.25 3.05 3.13
Grid 3-3 between G-H 1.00 2.44 0.25 3.05 1.87
Grid 3-3 between H-I 1.00 3.40 0.25 3.05 2.60
Grid 4-4 between A-F 1.00 19.50 0.25 3.05 14.87
6.00 0.30 0.25 3.75 1.69
Grid 4-4 between F-G 1.00 2.40 0.25 3.05 1.83
Grid 4-4 between I-K 1.00 13.00 0.25 3.05 9.92
4.00 0.30 0.25 3.75 1.13
Grid 5-5 between G-H 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid A-A between 1-4 1.00 19.50 0.25 3.05 14.87
6.00 0.30 0.25 3.75 1.69
Grid C-C between 3-4 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid D-D between 2-3 1.00 6.50 0.35 3.05 6.94
Grid E-E between 3-4 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid E-F between 2-3 1.00 6.85 0.35 3.05 7.32
Grid F-F between 1-2 1.00 4.25 0.25 3.05 3.25
Grid F-G between 3-4 1.00 7.05 0.25 3.63 6.39
Grid G-G between 3-5 1.00 13.00 0.25 3.05 9.92
4.00 0.30 0.25 3.75 1.13
Grid G-G between 1-2 1.00 4.25 0.25 3.05 3.25
Grid H-H between 3-5 1.00 11.38 0.25 3.05 8.68
4.00 0.30 0.25 3.75 1.13
Grid H-I between 2-3 1.00 3.40 0.25 3.05 2.60
Grid I-I between 3-4 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid I-I between 2-3 1.00 3.10 0.25 3.05 2.37
Grid K-K between 1-4 1.00 19.50 0.25 3.05 14.87
6.00 0.30 0.25 3.75 1.69
First Floor
Grid 1-1 between F-G 1.00 6.50 0.35 3.05 6.94
Grid 1-1 1.00 52.00 0.25 3.05 39.65
18.00 0.30 0.25 3.75 5.07
Grid 2-2 between A-B 1.00 6.50 0.25 3.05 4.96
Grid 3-3 between B-G 1.00 26.00 0.25 3.05 19.83
6.00 0.30 0.25 3.75 1.69
Grid 3-3 between I-K 1.00 13.00 0.25 3.05 9.92
4.00 0.30 0.25 3.75 1.13
Grid 4-4 between G-H 1.00 6.50 0.25 3.05 4.96
Grid A-A between 1-2 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid B-B between 2-3 1.00 6.50 0.25 3.05 4.96
Grid F-F between 1-2 1.00 4.25 0.25 3.05 3.25
Grid G-G between 1-2 1.00 4.25 0.25 3.05 3.25
Grid G-G between 3-4 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid H-H between 2-3 1.00 6.50 0.25 3.05 4.96
Grid H-H between 3-4 1.00 6.50 0.25 3.05 4.96
2.00 0.30 0.25 3.75 0.57
Grid H-I between 2-3 1.00 6.67 0.25 3.63 6.05
Grid I-I between 2-3 1.00 6.50 0.25 3.05 4.96
Grid K-K between 1-3 1.00 13.00 0.25 3.05 9.92
4.00 0.30 0.25 3.75 1.13
Top floor
Grid 1-1 between F-G 1.00 6.50 0.35 3.05 6.94
2.00 0.30 0.25 3.75 0.57
Grid 2-2 between F-G 1.00 6.50 0.25 3.05 4.96
Grid G-G between 1-1 1.00 6.50 0.35 3.05 6.94
2.00 0.30 0.25 3.75 0.57
Grid G-G between 2-2 1.00 6.50 0.35 3.05 6.94
2.00 0.30 0.25 3.75 0.57
Top Floor
DW2 -1.00 1.50 0.25 1.40 -0.53
-1.00 1.00 0.25 2.60 -0.65
W2 -4.00 2.50 0.25 1.40 -3.50
Ground Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 1.00 3.70 11.99
1.00 3.46 1.00 3.70 12.81
1.00 7.07 1.00 3.70 26.16
1.00 0.75 1.00 3.70 2.78
1.00 2.44 1.00 3.70 9.03
1.00 4.48 1.00 3.70 16.58
2.00 1.96 1.00 3.70 14.52
1.00 4.18 1.00 3.70 15.47
Universal toilet 3.00 2.40 1.00 3.70 26.64
Janitor 1.00 5.04 1.00 3.70 18.65
Toilet 1.00 3.61 1.00 3.70 13.36
Toilet 3.00 2.20 1.00 3.70 24.42
1.00 3.60 1.00 3.70 13.32
1.00 4.90 1.00 3.70 18.13
1.00 1.38 1.00 3.70 5.11
2.00 1.58 1.00 3.70 11.70
1.00 4.10 1.00 3.70 15.17
1.00 4.90 1.00 3.70 18.13
First Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 1.00 3.70 11.99
1.00 3.46 1.00 3.70 12.81
1.00 7.07 1.00 3.70 26.16
1.00 0.75 1.00 3.70 2.78
1.00 2.44 1.00 3.70 9.03
1.00 4.48 1.00 3.70 16.58
2.00 1.96 1.00 3.70 14.52
1.00 4.18 1.00 3.70 15.47
Universal toilet 1.00 4.14 1.00 3.70 15.32
2.00 4.60 1.00 3.70 34.04
1.00 4.80 1.00 3.70 17.76
1.00 6.28 1.00 3.70 23.24
1.00 4.86 1.00 3.70 17.99
2.00 4.80 1.00 3.70 35.52
2.00 2.50 1.00 3.70 18.50
1.00 1.90 1.00 3.70 7.03
Deduction for Opening
Ground Floor
D3 -4.00 1.00 1.00 2.60 -10.40
D4 -1.00 1.00 1.00 2.60 -2.60
D5 -4.00 0.75 1.00 2.60 -7.80
D6 -7.00 0.75 1.00 2.10 -11.03
First Floor
D3 -3.00 1.00 1.00 2.60 -7.80
D4 -1.00 1.00 1.00 2.60 -2.60
D5 -5.00 0.75 1.00 2.60 -9.75
D6 -7.00 0.75 1.00 2.10 -11.03
Plain Cement Concrete (1:3:6) M10 in foundation & wall with cement,
sand and aggregate including mixing, laying, finishing to approved level, line
and dimensions and curing as per instruction & specification complete work.
PCC Works in Foundation Footings
Footing, F1 21 2.6 2.6 0.075 10.65
Footing, F2 18 3.3 3.3 0.075 14.71
Footing, F3 24 1.2 1.2 0.075 2.60
Footing, CF 3 2.5 3.8 0.075 2.14
P.C.C. M15 (1:2:4) Work (for un-reinforced works) etc.with cement sand and
graded coarse aggregate (river bed foruwa) & (waterproof material if reqd.)
including mixing with concrete, lead upto 30m, laying, compacting the
concrete mix with vibrator machine, finishing to approved level lines and
dimensions and curing as per instruction & specification complete work.
Ground Floor:-
In Floors
Plinth Area 1.00 1698.73 1.00 0.08 127.41
Column deduction
Columns (for main block) -45.00 0.70 0.70 0.08 -1.66
Columns (for ramp) -24.00 0.45 0.45 0.08 -0.37
sum 125.38 Cum
P.C.C. M15 (1:2:4) for R.C.C. Work in foundation, walls, beams, slabs, sill,
stitches, lintels etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing concrete, lead upto 30m, laying, compacting the
concrete mix with vibrator machine,finishing to approved level lines and
dimensions and curing as per instruction & specification complete work.
First Floor
Grid 1-1 between F-G 1.00 6.50 0.35 0.15 0.35
Grid 1-1 1.00 52.00 0.25 0.15 1.95
18.00 0.30 0.25 0.15 0.21
Grid 2-2 between A-B 1.00 6.50 0.25 0.15 0.25
Grid 3-3 between B-G 1.00 26.00 0.25 0.15 0.98
6.00 0.30 0.25 0.15 0.07
Grid 3-3 between I-K 1.00 13.00 0.25 0.15 0.49
4.00 0.30 0.25 0.15 0.05
Grid 4-4 between G-H 1.00 6.50 0.25 0.15 0.25
Grid A-A between 1-2 1.00 6.50 0.25 0.15 0.25
2.00 0.30 0.25 0.15 0.03
Grid B-B between 2-3 1.00 6.50 0.25 0.15 0.25
Grid F-F between 1-2 1.00 4.25 0.25 0.15 0.16
Grid G-G between 1-2 1.00 4.25 0.25 0.15 0.16
Grid G-G between 3-4 1.00 6.50 0.25 0.15 0.25
2.00 0.30 0.25 0.15 0.03
Grid H-H between 2-3 1.00 6.50 0.25 0.15 0.25
Grid H-H between 3-4 1.00 6.50 0.25 0.15 0.25
2.00 0.30 0.25 0.15 0.03
Grid H-I between 2-3 1.00 6.67 0.25 0.15 0.26
Grid I-I between 2-3 1.00 6.50 0.25 0.15 0.25
Grid K-K between 1-3 1.00 13.00 0.25 0.15 0.49
4.00 0.30 0.25 0.15 0.05
Top floor
Grid 1-1 between F-G 1.00 6.50 0.35 0.15 0.35
2.00 0.30 0.25 0.15 0.03
Grid 2-2 between F-G 1.00 6.50 0.25 0.15 0.25
Grid G-G between 1-1 1.00 6.50 0.35 0.15 0.35
2.00 0.30 0.25 0.15 0.03
Grid G-G between 2-2 1.00 6.50 0.35 0.15 0.35
2.00 0.30 0.25 0.15 0.03
First Floor
D1 -1.00 1.50 0.25 0.08 -0.03
DW1 -1.00 1.50 0.25 0.08 -0.03
DW2 -6.00 1.00 0.25 0.08 -0.12
Top Floor
DW2 -1.00 1.00 0.25 0.08 -0.02
Ground Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 0.10 0.15 0.05
1.00 3.46 0.10 0.15 0.06
1.00 7.07 0.10 0.15 0.11
1.00 0.75 0.10 0.15 0.02
1.00 2.44 0.10 0.15 0.04
1.00 4.48 0.10 0.15 0.07
2.00 1.96 0.10 0.15 0.06
1.00 4.18 0.10 0.15 0.07
Universal toilet 3.00 2.40 0.10 0.15 0.11
Janitor 1.00 5.04 0.10 0.15 0.08
Toilet 1.00 3.61 0.10 0.15 0.06
Toilet 3.00 2.20 0.10 0.15 0.10
1.00 3.60 0.10 0.15 0.06
1.00 4.90 0.10 0.15 0.08
1.00 1.38 0.10 0.15 0.03
2.00 1.58 0.10 0.15 0.05
1.00 4.10 0.10 0.15 0.07
1.00 4.90 0.10 0.15 0.08
First Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 0.10 0.15 0.05
1.00 3.46 0.10 0.15 0.06
1.00 7.07 0.10 0.15 0.11
1.00 0.75 0.10 0.15 0.02
1.00 2.44 0.10 0.15 0.04
1.00 4.48 0.10 0.15 0.07
2.00 1.96 0.10 0.15 0.06
1.00 4.18 0.10 0.15 0.07
Universal toilet 1.00 4.14 0.10 0.15 0.07
2.00 4.60 0.10 0.15 0.14
1.00 4.80 0.10 0.15 0.08
1.00 6.28 0.10 0.15 0.10
1.00 4.86 0.10 0.15 0.08
2.00 4.80 0.10 0.15 0.15
2.00 2.50 0.10 0.15 0.08
1.00 1.90 0.10 0.15 0.03
Deduction for Opening
Ground Floor
D3 -4.00 1.00 0.10 0.08 -0.03
D4 -1.00 1.00 0.10 0.08 -0.01
D5 -4.00 0.75 0.10 0.08 -0.03
D6 -7.00 0.75 0.10 0.08 -0.04
First Floor
D3 -3.00 1.00 0.10 0.08 -0.03
D4 -1.00 1.00 0.10 0.08 -0.01
D5 -5.00 0.75 0.10 0.08 -0.03
D6 -7.00 0.75 0.10 0.08 -0.04
P.C.C. M20 (1:1.5:3) for R.C.C. Work in Super structure, columns, beams,
decks, slabs, etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing with concrete, lead upto 30m, compacting the
concrete mix with vibrator machine,laying, finishing to approved level lines
and dimensions and curing as per instruction & specification complete work.
Sub-Structure
Foundation Footings
Footing, F1, bottom box portion 21.00 2.60 2.60 0.20 28.40
a1 a2 h
Footing, F1, trapezoidal portion 21.00 0.52 1.32 0.25 4.68
Footing, F2, bottom box portion 18.00 3.30 3.30 0.20 39.21
a1 h
Footing, F2, tapezoidal portion 18.00 0.66 1.32 0.25 4.38
Footing, F3, bottom box portion 24.00 1.20 1.20 0.20 6.92
a1 h
Footing, F3, tapezoidal portion 24.00 0.24 0.81 0.25 2.98
Footing, CF, bottom box portion 3.00 2.50 3.80 0.20 5.70
a1 h
Footing, CF, tapezoidal portion 3.00 0.50 1.32 0.25 0.66
Sub-Total
Foundation Beams
Grid 1-1, 2-2, 3-3 & 4-4 4.00 58.50 0.35 0.35 28.67
Grid 5-5 1.00 6.50 0.35 0.35 0.80
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K 8.00 19.50 0.35 0.35 19.11
Grid D-D 1.00 13.00 0.35 0.35 1.60
Grid G-G & H-H 2.00 26.00 0.35 0.35 6.37
For Ramp
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,R-R 8.00 3.60 0.23 0.23 1.53
Grid 5a-5a , 5b-5b, 5c-5c 3.00 25.63 0.23 0.23 4.07
Sub-Total
Columns upto plinth level (Excluding FDN & Plinth beam)
Columns (for main block) 45.00 0.70 0.70 2.10 46.31
Columns (for ramp) 24.00 0.45 0.45 2.10 10.21
Super-Structure
Columns
From plinth to FF 45.00 0.70 0.70 3.90 86.00
From FF to SF 34.00 0.70 0.70 3.90 64.98
Roof floor 4.00 0.70 0.70 3.90 7.65
First floor terrace 11.00 0.70 0.70 1.00 5.39
Top floor Terrace 24.00 0.70 0.70 1.00 11.76
Roof floor Terrace 4.00 0.70 0.70 1.00 1.96
Columns (for ramp) 9.00 0.45 0.45 4.95 9.03
3.00 0.45 0.45 4.40 2.68
3.00 0.45 0.45 3.90 2.37
3.00 0.45 0.45 3.70 2.25
6.00 0.45 0.45 3.05 3.71
Floor Beams
First Floor Beams
Grid 1-1, 2-2, 3-3 & 4-4 4.00 58.50 0.40 0.48 44.46
Grid 5-5 1.00 6.50 0.40 0.48 1.24
Grid A-A, B-B & C-C D-D E-E F-F I-I J-J K-K 9.00 19.50 0.40 0.48 33.35
Grid G-G H-H 2.00 26.00 0.40 0.48 9.88
Secondary beam
box type -1
along x-x 23.00 6.80 0.30 0.28 12.91
along y-y 23.00 6.80 0.30 0.28 12.91
box type -2
along x-x 1.00 6.80 0.30 0.28 0.57
along y-y 1.00 7.02 0.30 0.28 0.58
Slab 0.00
First floor 1.00 1552.84 1.00 0.125 194.11
Second floor 1.00 1170.00 1.00 0.125 146.25
Ramp 2.00 29.31 2.70 0.125 19.79
Staircase Cover 1.00 9.70 9.70 0.125 11.77
Lift void cover 1.00 5.10 1.70 0.125 1.09
Deduct lift area -2.00 3.35 2.50 0.125 -2.10
Deduction staircase -2.00 37.62 1.00 0.125 -9.41
Staircase 0.00
landing 4.00 2.43 2.00 0.15 2.91
1st Flight slope slab 2.00 2.75 1.20 0.15 0.99
2nd Flight slope slab 2.00 2.75 1.33 0.15 1.10
Steps 46.00 1.50 0.25 0.08 1.38
Supplying & installing Aluminium Framed Casement Door one way/ two
ways openable with ventilator Natural Colour in the Section of 101x45 x1.5
mm including 9mm thick pre-laminated board or 5 mm thick Glass, silicon
sealant and accessories as per drawing, specification & instruction all
complete.
D6 14.00 2.10 0.75 22.05
D7 1.00 2.10 1.20 2.52
LD1 1.00 2.10 1.50 3.15
HD1 3.00 2.10 1.50 9.45
HD2 3.00 2.10 1.00 6.30
sum 43.47 Sqm
Supplying & installing Aluminium Framed Casement Door one way/ two
ways openable with Natural Colour in the Section of 101x45 x1.5 mm
including 9mm thick pre-laminated board or 5 mm thick Glass, silicon
sealant and accessories as per drawing, specification & instruction all
complete.
D1 6.00 2.60 1.50 23.40
D2 9.00 2.60 1.20 28.08
D3 51.00 2.60 1.00 132.60
D4 2.00 2.60 1.00 5.20
D5 12.00 2.60 0.75 23.40
DW1 4.00 2.60 1.50 15.60
DW2 6.00 2.60 1.00 15.60
DW3 1.00 2.60 1.00 2.60
sum 246.48 Sqm
First Floor
D2 -6.00 1.20 2.60 -18.72
D3 -10.00 1.00 2.60 -26.00
V3 -17.00 1.80 0.60 -18.36
W4 -1.00 1.80 1.40 -2.52
Ground Floor
D1 -2.00 1.50 2.60 -7.80
D2 -2.00 1.20 2.60 -6.24
D3 -28.00 1.00 2.60 -72.80
HD1 -2.00 1.50 2.10 -6.30
HD2 -2.00 1.00 2.10 -4.20
W1 -2.00 2.50 1.40 -7.00
W5 -2.00 1.80 1.40 -5.04
sum 1692.65 Sqm
Formwork/ Centering & Shuttering with 18mm thick Plywood for all type of
concrete works necessary propping, scaffolding, staging, supporting inclusive
wedging and cutting holes for utilization work till the support is fully
unyielding as per instructions & specifications complete work .
Sub-Structure
Sub-Structure
Foundation Footings
F1 21.00 10.40 0.20 43.68
F2 18.00 13.20 0.20 47.52
F3 24.00 4.80 0.20 23.04
F4 3.00 11.60 0.20 6.96
0.00
Sub-Total 0.00
Foundation Beams 0.00
Grid 1-1, 2-2, 3-3 & 4-4 4.00 58.50 0.70 163.80
Grid 5-5 1.00 6.50 0.70 4.55
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K 8.00 19.50 0.70 109.20
Grid D-D 1.00 13.00 0.70 9.10
Grid G-G & H-H 2.00 26.00 0.70 36.40
For Ramp 0.00
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,R-R 8.00 3.60 0.46 13.25
Grid 5a-5a , 5b-5b, 5c-5c 3.00 25.63 0.46 35.37
Sub-Total 0.00
Plinth (Tie) Beams 0.00
Grid 1-1, 2-2, 3-3 & 4-4 4.00 58.50 0.70 163.80
Grid 5-5 1.00 6.50 0.70 4.55
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K 8.00 19.50 0.70 109.20
Grid D-D 1.00 13.00 0.70 9.10
Grid G-G & H-H 2.00 26.00 0.70 36.40
For Ramp 0.00
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,R-R 8.00 3.60 0.60 17.28
Grid 5a-5a , 5b-5b, 5c-5c 3.00 25.63 0.60 46.14
0.00
Sub-Total 0.00
Columns upto plinth level (Excluding FDN & Plinth beam) 0.00
Columns (for main block) 45.00 2.80 2.10 264.60
Columns (for ramp) 24.00 1.80 2.10 90.72
Sub-Total 0.00
Super-Structure 0.00
Columns 0.00
From plinth to FF 45.00 2.80 3.90 491.40
From FF to SF 34.00 2.80 3.90 371.28
First floor terrace 11.00 2.80 1.00 30.80
Top floor Terrace 24.00 2.80 1.00 67.20
Roof floor Terrace 4.00 2.80 1.00 11.20
Columns (for ramp) 9.00 1.80 4.95 80.19
3.00 1.80 4.40 23.76
3.00 1.80 3.90 21.06
3.00 1.80 3.70 19.98
6.00 1.80 3.05 32.94
Roof floor 4.00 2.80 3.20 35.84
Sub-Total 0.00
First Floor Beams
Grid 1-1, 2-2, 3-3 & 4-4 4.00 58.50 0.95 222.30
Grid 5-5 1.00 6.50 0.95 6.18
Grid A-A, B-B & C-C D-D E-E F-F I-I J-J K-K 9.00 19.50 0.95 166.73
Grid G-G H-H 2.00 26.00 0.95 49.40
Secondary beam
box type -1
along x-x 23.00 6.80 1.00 0.55 86.02
along y-y 23.00 6.80 1.00 0.55 86.02
box type -2
along x-x 1.00 6.80 1.00 0.55 3.74
along y-y 1.00 7.02 1.00 0.55 3.87
Slab
First floor 1.00 1552.84 1.00 1552.84
Second floor 1.00 1170.00 1.00 1170.00
along perimeter first floor 1.00 233.75 1.00 233.75
along perimeter second floor 1.00 186.60 1.00 186.60
Staircase Cover 1.00 62.40 1.00 62.40
along perimeter staircase cover 1.00 38.80 1.00 38.80
Ramp floor slab 2.00 29.31 2.70 158.28
along perimeter ramp floor slab 1.00 128.04 1.00 128.04
Deduction staircase -2.00 37.62 1.00 -75.24
Staircase 0.00
landing 4.00 2.43 2.00 19.40
1st Flight slope slab 2.00 2.75 1.20 6.60
2nd Flight slope slab 2.00 2.75 1.33 7.29
Steps 46.00 1.50 0.25 17.25
Lift wall
First Floor
Grid 1-1 between F-G 1.00 6.50 0.30 1.95
Grid 1-1 1.00 52.00 0.30 15.60
18.00 0.30 0.30 1.62
Grid 2-2 between A-B 1.00 6.50 0.30 1.95
Grid 3-3 between B-G 1.00 26.00 0.30 7.80
6.00 0.30 0.30 0.54
Grid 3-3 between I-K 1.00 13.00 0.30 3.90
4.00 0.30 0.30 0.36
Grid 4-4 between G-H 1.00 6.50 0.30 1.95
Grid A-A between 1-2 1.00 6.50 0.30 1.95
2.00 0.30 0.30 0.18
Grid B-B between 2-3 1.00 6.50 0.30 1.95
Grid F-F between 1-2 1.00 4.25 0.30 1.28
Grid G-G between 1-2 1.00 4.25 0.30 1.28
Grid G-G between 3-4 1.00 6.50 0.30 1.95
2.00 0.30 0.30 0.18
Grid H-H between 2-3 1.00 6.50 0.30 1.95
Grid H-H between 3-4 1.00 6.50 0.30 1.95
2.00 0.30 0.30 0.18
Grid H-I between 2-3 1.00 6.67 0.30 2.01
Grid I-I between 2-3 1.00 6.50 0.30 1.95
Grid K-K between 1-3 1.00 13.00 0.30 3.90
4.00 0.30 0.30 0.36
Top floor
Grid 1-1 between F-G 1.00 6.50 0.30 1.95
2.00 0.30 0.30 0.18
Grid 2-2 between F-G 1.00 6.50 0.30 1.95
Grid G-G between 1-1 1.00 6.50 0.30 1.95
2.00 0.30 0.30 0.18
Grid G-G between 2-2 1.00 6.50 0.30 1.95
2.00 0.30 0.30 0.18
Top Floor
DW2 -1.00 1.00 0.15 -0.15
Ground Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 0.30 0.98
1.00 3.46 0.30 1.04
1.00 7.07 0.30 2.13
1.00 0.75 0.30 0.23
1.00 2.44 0.30 0.74
1.00 4.48 0.30 1.35
2.00 1.96 0.30 1.18
1.00 4.18 0.30 1.26
Universal toilet 3.00 2.40 0.30 2.16
Janitor 1.00 5.04 0.30 1.52
Toilet 1.00 3.61 0.30 1.09
Toilet 3.00 2.20 0.30 1.98
1.00 3.60 0.30 1.08
1.00 4.90 0.30 1.47
1.00 1.38 0.30 0.42
2.00 1.58 0.30 0.95
1.00 4.10 0.30 1.23
1.00 4.90 0.30 1.47
First Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 0.30 0.98
1.00 3.46 0.30 1.04
1.00 7.07 0.30 2.13
1.00 0.75 0.30 0.23
1.00 2.44 0.30 0.74
1.00 4.48 0.30 1.35
2.00 1.96 0.30 1.18
1.00 4.18 0.30 1.26
Universal toilet 1.00 4.14 0.30 1.25
2.00 4.60 0.30 2.76
1.00 4.80 0.30 1.44
1.00 6.28 0.30 1.89
1.00 4.86 0.30 1.46
2.00 4.80 0.30 2.88
2.00 2.50 0.30 1.50
1.00 1.90 0.30 0.57
Deduction for Opening
Ground Floor
D3 -4.00 1.00 0.15 -0.60
D4 -1.00 1.00 0.15 -0.15
D5 -4.00 0.75 0.15 -0.45
D6 -7.00 0.75 0.15 -0.79
First Floor
D3 -3.00 1.00 0.15 -0.45
D4 -1.00 1.00 0.15 -0.15
D5 -5.00 0.75 0.15 -0.57
D6 -7.00 0.75 0.15 -0.79
Supplying and fixing double leaf solid corelead protected wooden flush door
with solid wood frame including necessary handles , locks etc. of medium
quality as per drawings.
12.5mm thick cement sand plaster (1:3) on ceiling of good finish including
cleaning, scrubing, wetting the surface before plaster work and curing the
same as per specifications & instructions all complete work
Ground Floor:-
Dental Clinic 1.00 3.50 4.70 16.45
Eye Clinic 1.00 3.50 4.70 16.45
General Clinic 1.00 3.50 4.70 16.45
General Clinic 2 1.00 3.50 4.70 16.45
OBG/GYN 1.00 3.80 4.86 18.47
OBG/GYN Consultation 1.00 3.30 3.65 12.05
Universal Toilet 1.00 2.40 2.40 5.76
Jonitor 1.00 1.32 2.40 3.17
MCH/FP/FPI 1.00 3.60 3.65 13.14
Male toilet 1.00 3.37 4.40 14.83
Female toilet 1.00 3.46 4.40 15.23
DOTS 1.00 3.35 3.50 11.73
Nutriton 1.00 3.70 4.50 16.65
Record Room 1.00 3.80 4.50 17.10
Registration 1.00 3.70 4.50 16.65
Immunization 1.00 3.50 4.40 15.40
Control and printing room 1.00 3.70 3.95 14.62
X-ray 1.00 4.70 6.85 32.20
Pathology/Lab 1.00 3.60 5.35 19.26
Sample collection and report distribution 1.00 3.55 3.20 11.36
Toilet 1.00 2.10 1.51 3.18
Queueing Area 1.00 3.49 4.57 15.93
SSU 1.00 2.60 3.80 9.88
ECG/USG 1.00 3.28 3.58 11.75
Toilet 1.00 1.50 2.20 3.30
Toilet 1.00 1.50 2.20 3.30
Dispensary 1.00 4.20 4.45 18.69
Counseling 1.00 3.58 4.45 15.94
Examination 1.00 3.65 4.45 16.25
Active Labor 1.00 6.95 6.95 48.31
NEO Natal Room 1.00 3.12 4.75 14.82
Toilet 1.00 1.30 2.05 2.67
Toilet 1.00 1.50 2.05 3.08
Recovery Room 1.00 4.18 6.95 29.06
Emergency 1.00 8.43 6.95 58.59
Anesthsia 1.00 4.20 3.70 15.54
Change room1 1.00 3.05 1.70 5.19
Change room2 1.00 2.01 3.13 6.30
Autoclave 1.00 4.70 2.40 11.28
Nurse Station 1.00 3.62 2.97 10.76
Staff Room 1.00 3.58 2.86 10.23
Sluice 1.00 4.20 1.70 7.14
Operating room 1.00 4.21 5.01 21.10
Autoclave 1.00 2.80 2.65 7.42
Delivery room 1.00 4.20 6.95 29.19
Sluice 1.00 4.50 2.80 12.60
Instrument Preparation and clean instrument storage 1.00 4.50 2.28 10.24
Major OT Room 1.00 6.95 5.45 37.88
Sorting and washing 1.00 3.90 2.40 9.36
Autoclave 1.00 4.00 2.80 11.20
Out patient Department 1.00 2.20 14.30 31.46
Waiting area 1.00 7.20 6.85 49.32
Passage 1.00 2.40 58.20 139.68
Out passage 1.00 4.50 4.45 20.03
Sterile corridor 1.00 8.30 6.65 55.20
Out passage 1.00 2.50 15.00 37.50
First Floor:- 0.00
Male Toilet 1.00 3.37 4.48 15.10
Female Toilet 1.00 3.36 4.48 15.06
Universal toilet 1.00 2.40 2.40 5.76
Toilet 1.00 1.50 2.40 3.60
Janitor Room 1.00 1.50 1.96 2.94
Cabin1 1.00 3.37 4.50 15.17
Cabin2 1.00 3.90 4.50 17.55
Ward Store 1.00 1.52 1.96 2.98
toilet 1.00 2.40 4.80 11.52
Ward Pantry 1.00 2.00 4.18 8.36
Nurse Station 1.00 2.80 4.60 12.88
Nurse Room 1.00 4.30 4.10 17.63
Toilet 1.00 1.20 1.80 2.16
Library 1.00 10.00 4.70 47.00
Pantry 1.00 1.80 4.50 8.10
Matrons Office 1.00 4.60 4.50 20.70
Hospital Development committee 1.00 5.00 4.50 22.50
Medical Supritendent Office 1.00 4.10 4.50 18.45
Reception 1.00 3.30 3.00 9.90
Counseling room 1.00 3.30 2.40 7.92
Toilet 1.00 1.80 1.50 2.70
OCMC 1.00 7.13 7.20 51.34
Seating 1.00 4.30 2.80 12.04
Male ward 1.00 7.90 7.20 56.88
Female ward 1.00 7.30 7.20 52.56
Blood storage 1.00 6.16 2.24 13.79
issue 1.00 2.10 1.80 3.78
Bleeding Area 1.00 4.50 7.10 31.95
Meeting hall 1.00 9.40 7.20 67.68
Admin and finance 1.00 4.70 3.40 15.98
Admin and finance 1.00 4.70 3.40 15.98
Passage 1.00 2.40 66.50 159.60
Out passage 1.00 4.50 4.45 20.03
Sterile corridor 1.00 8.30 6.65 55.20
Out passage 1.00 2.50 15.00 37.50
Washing 1.00 5.00 3.30 16.50
Laundry 1.00 7.10 3.40 24.14
Store 1.00 7.10 3.30 23.43
Staircase Cover:- 0.00
2nd floor 1.00 7.90 7.90 62.41
Outer slab with beat 2.00 0.65 66.50 86.45
Outer slab with beat 2.00 0.65 22.30 28.99
Staircase 0.00
landing 4.00 2.43 2.00 19.40
1st Flight slope slab 2.00 2.75 1.20 6.60
2nd Flight slope slab 2.00 2.75 1.33 7.29
Steps 46.00 1.50 0.25 17.25
Staircase Below 0.00
landing 4.00 2.43 2.00 19.40
1st Flight slope slab 2.00 2.75 1.20 6.60
2nd Flight slope slab 2.00 2.75 1.33 7.29
sum 2284.83 Sqm
First Floor
Grid 1-1 between F-G 1.00 6.50 3.90 25.35
Grid 1-1 1.00 52.00 3.90 202.80
36.00 0.30 3.90 42.12
Grid 2-2 between A-B 1.00 6.50 3.78 24.54
Grid 3-3 between B-G 1.00 26.00 3.90 101.40
12.00 0.30 3.90 14.04
Grid 3-3 between I-K 1.00 13.00 3.90 50.70
8.00 0.30 3.90 9.36
Grid 4-4 between G-H 1.00 6.50 3.78 24.54
Grid A-A between 1-2 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid B-B between 2-3 1.00 6.50 3.78 24.54
Grid F-F between 1-2 1.00 4.25 3.78 16.05
Grid G-G between 1-2 1.00 4.25 3.78 16.05
Grid G-G between 3-4 1.00 6.50 3.90 25.35
8.00 0.30 3.90 9.36
Grid H-H between 2-3 1.00 6.50 3.78 24.54
Grid H-H between 3-4 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid H-I between 2-3 1.00 6.67 3.78 25.18
Grid I-I between 2-3 1.00 6.50 3.78 24.54
Grid K-K between 1-3 1.00 13.00 3.90 50.70
8.00 0.30 3.90 9.36
Top floor
Grid 1-1 between F-G 1.00 6.50 3.90 25.35
2.00 0.30 3.90 2.34
Grid 2-2 between F-G 1.00 6.50 3.90 25.35
Grid G-G between 1-1 1.00 6.50 3.90 25.35
2.00 0.30 3.90 2.34
Grid G-G between 2-2 1.00 6.50 3.90 25.35
2.00 0.30 3.90 2.34
Top Floor
DW2 -1.00 1.50 1.40 -2.10
-1.00 1.00 2.60 -2.60
W2 -4.00 2.50 1.40 -14.00
Half deduction 9.35
Ground Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 3.78 12.24
1.00 3.46 3.78 13.07
1.00 7.07 3.78 26.69
1.00 0.75 3.78 2.84
1.00 2.44 3.78 9.22
1.00 4.48 3.78 16.92
2.00 1.96 3.78 14.82
1.00 4.18 3.78 15.78
Universal toilet 3.00 2.40 3.78 27.18
Janitor 1.00 5.04 3.78 19.03
Toilet 1.00 3.61 3.78 13.63
Toilet 3.00 2.20 3.78 24.92
1.00 3.60 3.78 13.59
1.00 4.90 3.78 18.50
1.00 1.38 3.78 5.21
2.00 1.58 3.78 11.93
1.00 4.10 3.78 15.48
1.00 4.90 3.78 18.50
First Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 3.78 12.24
1.00 3.46 3.78 13.07
1.00 7.07 3.78 26.69
1.00 0.75 3.78 2.84
1.00 2.44 3.78 9.22
1.00 4.48 3.78 16.92
2.00 1.96 3.78 14.82
1.00 4.18 3.78 15.78
Universal toilet 1.00 4.14 3.78 15.63
2.00 4.60 3.78 34.73
1.00 4.80 3.78 18.12
1.00 6.28 3.78 23.71
1.00 4.86 3.78 18.35
2.00 4.80 3.78 36.24
2.00 2.50 3.78 18.88
1.00 1.90 3.78 7.18
Deduction for Opening
Ground Floor
D3 -4.00 1.00 2.60 -10.40
D4 -1.00 1.00 2.60 -2.60
D5 -4.00 0.75 2.60 -7.80
D6 -7.00 0.75 2.10 -11.03
Half deduction 15.92
First Floor
D3 -3.00 1.00 2.60 -7.80
D4 -1.00 1.00 2.60 -2.60
D5 -5.00 0.75 2.60 -9.75
D6 -7.00 0.75 2.10 -11.03
Half deduction 15.59
Parapet Wall
over Brick wall 40.00 7.10 1.00 284.00
over Column 39.00 2.30 1.00 89.70
First Floor
Grid 1-1 between F-G 1.00 6.50 3.78 24.54
Grid 1-1 1.00 52.00 3.78 196.30
18.00 0.30 3.78 20.39
Grid 2-2 between A-B 1.00 6.50 3.78 24.54
Grid 3-3 between B-G 1.00 26.00 3.78 98.15
6.00 0.30 3.78 6.80
Grid 3-3 between I-K 1.00 13.00 3.78 49.08
4.00 0.30 3.78 4.53
Grid 4-4 between G-H 1.00 6.50 3.78 24.54
Grid A-A between 1-2 1.00 6.50 3.78 24.54
2.00 0.30 3.78 2.27
Grid B-B between 2-3 1.00 6.50 3.78 24.54
Grid F-F between 1-2 1.00 4.25 3.78 16.05
Grid G-G between 1-2 1.00 4.25 3.78 16.05
Grid G-G between 3-4 1.00 6.50 3.78 24.54
2.00 0.30 3.78 2.27
Grid H-H between 2-3 1.00 6.50 3.78 24.54
Grid H-H between 3-4 1.00 6.50 3.78 24.54
2.00 0.30 3.78 2.27
Grid H-I between 2-3 1.00 6.67 3.78 25.18
Grid I-I between 2-3 1.00 6.50 3.78 24.54
Grid K-K between 1-3 1.00 13.00 3.78 49.08
4.00 0.30 3.78 4.53
Top floor
Grid 1-1 between F-G 1.00 6.50 3.78 24.54
2.00 0.30 3.78 2.27
Grid 2-2 between F-G 1.00 6.50 3.78 24.54
Grid G-G between 1-1 1.00 6.50 3.78 24.54
2.00 0.30 3.78 2.27
Grid G-G between 2-2 1.00 6.50 3.78 24.54
2.00 0.30 3.78 2.27
Top Floor
DW2 -1.00 1.50 1.40 -2.10
-1.00 1.00 2.60 -2.60
W2 -4.00 2.50 1.40 -14.00
Half deduction 9.35
Ground Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 3.78 12.24
1.00 3.46 3.78 13.07
1.00 7.07 3.78 26.69
1.00 0.75 3.78 2.84
1.00 2.44 3.78 9.22
1.00 4.48 3.78 16.92
2.00 1.96 3.78 14.82
1.00 4.18 3.78 15.78
Universal toilet 3.00 2.40 3.78 27.18
Janitor 1.00 5.04 3.78 19.03
Toilet 1.00 3.61 3.78 13.63
Toilet 3.00 2.20 3.78 24.92
1.00 3.60 3.78 13.59
1.00 4.90 3.78 18.50
1.00 1.38 3.78 5.21
2.00 1.58 3.78 11.93
1.00 4.10 3.78 15.48
1.00 4.90 3.78 18.50
First Floor
along A-A/B-B/C-C between 1-2
2.00 1.62 3.78 12.24
1.00 3.46 3.78 13.07
1.00 7.07 3.78 26.69
1.00 0.75 3.78 2.84
1.00 2.44 3.78 9.22
1.00 4.48 3.78 16.92
2.00 1.96 3.78 14.82
1.00 4.18 3.78 15.78
Universal toilet 1.00 4.14 3.78 15.63
2.00 4.60 3.78 34.73
1.00 4.80 3.78 18.12
1.00 6.28 3.78 23.71
1.00 4.86 3.78 18.35
2.00 4.80 3.78 36.24
2.00 2.50 3.78 18.88
1.00 1.90 3.78 7.18
Deduction for Opening
Ground Floor
D3 -4.00 1.00 2.60 -10.40
D4 -1.00 1.00 2.60 -2.60
D5 -4.00 0.75 2.60 -7.80
D6 -7.00 0.75 2.10 -11.03
Half deduction 15.92
First Floor
D3 -3.00 1.00 2.60 -7.80
D4 -1.00 1.00 2.60 -2.60
D5 -5.00 0.75 2.60 -9.75
D6 -7.00 0.75 2.10 -11.03
Half deduction 15.59
3mm thick (1:1) Cement sand punning work on floor, walls etc including
mixing, laying, finishing to approved level, line and dimensions and curing as
per instruction & specification all complete work.
Supplying & laying 25mm thick anti-slip Cement Tile (Parking tile)
(250x250) on (1:4) cement sand mortar all complete as per specification &
direction.
On the Ramp portion(backside) 1.00 52.58 2.48 130.14
1.00 7.18 2.90 20.81
On the Ramp portion(Main ramp) 2.00 5.40 1.55 16.74
sum 167.69 Sqm
Porcelain Glazed Tiles white/coloured in dado, skirting etc. laid with cement
sand mortar 1:4 with white cement slurry including polishing to smooth
finished glazed surface as per instruction & specification all complete work.
Inside Ground Floor Walls
Universal Toilet 1.00 9.60 1.50 14.40
Male toilet 1.00 9.32 1.50 13.98
4.00 1.60 1.50 9.60
2.00 2.40 1.50 7.20
Female toilet 1.00 15.88 1.50 23.82
1.00 3.46 1.50 5.19
6.00 1.96 1.50 17.64
X-ray 1.00 7.22 1.50 10.83
Toilet 2.00 7.40 1.50 22.20
4.00 2.00 1.50 12.00
4.00 2.20 1.50 13.20
Toilet 2.00 6.90 1.50 20.70
Toilet 1.00 6.00 1.50 9.00
Porcelain Non glazed (spartic) Tiles white/ coloured in floor with cement
sand mortar 1:4 with white cement slurry including polishing to smooth
finished glazed surface as per instruction & specification all complete work.
Dental Clinic 1.00 3.50 4.70 16.45
Eye Clinic 1.00 3.50 4.70 16.45
General Clinic 1.00 3.50 4.70 16.45
General Clinic 2 1.00 3.50 4.70 16.45
OBG/GYN 1.00 3.80 4.86 18.47
OBG/GYN Consultation 1.00 3.30 3.65 12.05
Universal Toilet 1.00 2.40 2.40 5.76
Jonitor 1.00 1.32 2.40 3.17
MCH/FP/FPI 1.00 3.30 3.65 12.05
Male toilet 1.00 3.37 4.40 14.83
Female toilet 1.00 3.46 4.40 15.23
DOTS 1.00 3.35 3.50 11.73
Nutriton 1.00 3.70 4.50 16.65
Record Room 1.00 3.30 4.50 14.85
Registration 1.00 3.70 4.50 16.65
Immunization 1.00 3.50 4.40 15.40
Control and printing room 1.00 3.70 3.95 14.62
X-ray 1.00 4.70 6.85 32.20
Pathology/Lab 1.00 3.60 5.35 19.26
Sample collection and report distribution 1.00 3.55 3.20 11.36
Toilet 1.00 2.10 1.51 3.18
Queueing Area 1.00 3.49 4.57 15.93
SSU 1.00 2.60 3.80 9.88
ECG/USG 1.00 3.28 3.58 11.75
Toilet 1.00 1.50 2.20 3.30
Toilet 1.00 1.50 2.20 3.30
Dispensary 1.00 4.20 4.45 18.69
Counseling 1.00 3.58 4.45 15.94
Examination 1.00 3.65 4.45 16.25
Active Labor 1.00 6.95 6.95 48.31
NEO Natal Room 1.00 3.12 4.75 14.82
Toilet 1.00 1.30 2.05 2.67
Toilet 1.00 1.50 2.05 3.08
Recovery Room 1.00 4.18 6.95 29.06
Emergency 1.00 8.43 6.95 58.59
Anesthsia 1.00 4.20 3.70 15.54
Change room1 1.00 3.05 1.70 5.19
Change room2 1.00 2.01 3.13 6.30
Autoclave 1.00 4.70 2.40 11.28
Nurse Station 1.00 3.62 2.97 10.76
Staff Room 1.00 3.58 2.86 10.23
Sluice 1.00 4.20 1.70 7.14
Operating room 1.00 4.21 5.01 21.10
Autoclave 1.00 2.80 2.65 7.42
Delivery room 1.00 4.20 6.95 29.19
Sluice 1.00 4.50 2.30 10.35
Instrument Preparation and clean instrument storage 1.00 4.50 2.28 10.24
Major OT Room 1.00 6.95 5.45 37.88
Sorting and washing 1.00 3.90 2.40 9.36
Autoclave 1.00 4.00 2.80 11.20
Out patient Department 1.00 2.20 14.30 31.46
Waiting area 1.00 7.20 6.85 49.32
Passage 1.00 2.50 51.15 127.88
Out passage 1.00 4.50 4.45 20.03
Sterile corridor 1.00 8.30 6.65 55.20
Out passage 1.00 2.50 15.00 37.50
First Floor:- 0.00
Male Toilet 1.00 3.37 4.48 15.10
Female Toilet 1.00 3.36 4.48 15.06
Universal toilet 1.00 2.40 2.40 5.76
Toilet 1.00 1.50 2.40 3.60
Janitor Room 1.00 1.50 1.96 2.94
Cabin1 1.00 3.37 4.50 15.17
Cabin2 1.00 3.90 4.50 17.55
Ward Store 1.00 1.52 1.96 2.98
toilet 1.00 2.40 4.80 11.52
Ward Pantry 1.00 2.00 4.18 8.36
Nurse Station 1.00 2.80 4.60 12.88
Nurse Room 1.00 4.30 4.10 17.63
Toilet 1.00 1.20 1.80 2.16
Library 1.00 10.00 4.70 47.00
Pantry 1.00 1.80 4.50 8.10
Matrons Office 1.00 4.60 4.50 20.70
Hospital Development committee 1.00 5.00 4.50 22.50
Medical Supritendent Office 1.00 4.10 4.50 18.45
Reception 1.00 3.30 3.00 9.90
Counseling room 1.00 3.30 2.40 7.92
Toilet 1.00 1.80 1.50 2.70
OCMC 1.00 7.13 7.20 51.34
Seating 1.00 4.30 2.80 12.04
Male ward 1.00 7.90 7.20 56.88
Female ward 1.00 7.30 7.20 52.56
Blood storage
2 Coats weather guard 100% acrelic paint work over one coat primer on
( Epex Aultima or equivalent) Outer Part of building of filter and primer to
give uniform colouring after rending the surface clean & moist as per
specification and instruction complete work.
Ground floor
Grid 1-1 between F-G 1.00 6.50 3.90 25.35
Grid 1-1 1.00 52.00 3.90 202.80
36.00 0.30 3.90 42.12
Grid 4-4 between A-F 1.00 19.50 3.90 76.05
12.00 0.30 3.90 14.04
Grid 4-4 between F-G 1.00 2.40 3.90 9.36
Grid 4-4 between I-K 1.00 13.00 3.90 50.70
4.00 0.30 3.90 4.68
Grid 5-5 between G-H 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid A-A between 1-4 1.00 19.50 3.90 76.05
12.00 0.30 3.90 14.04
Grid C-C between 3-4 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid D-D between 2-3 1.00 6.50 3.78 24.54
Grid E-E between 3-4 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid G-G between 3-5 1.00 13.00 3.90 50.70
8.00 0.30 3.90 9.36
Grid H-H between 3-5 1.00 11.38 3.90 44.39
8.00 0.30 3.90 9.36
Grid I-I between 3-4 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid K-K between 1-4 1.00 19.50 3.90 76.05
12.00 0.30 3.90 14.04
First Floor
Grid 1-1 between F-G 1.00 6.50 3.90 25.35
Grid 1-1 1.00 52.00 3.90 202.80
36.00 0.30 3.90 42.12
Grid 3-3 between B-G 1.00 26.00 3.90 101.40
12.00 0.30 3.90 14.04
Grid 3-3 between I-K 1.00 13.00 3.90 50.70
8.00 0.30 3.90 9.36
Grid A-A between 1-2 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid G-G between 3-4 1.00 6.50 3.90 25.35
8.00 0.30 3.90 9.36
Grid H-H between 3-4 1.00 6.50 3.90 25.35
4.00 0.30 3.90 4.68
Grid K-K between 1-3 1.00 13.00 3.90 50.70
8.00 0.30 3.90 9.36
Top floor
Grid 1-1 between F-G 1.00 6.50 3.90 25.35
2.00 0.30 3.90 2.34
Grid 2-2 between F-G 1.00 6.50 3.90 25.35
Grid G-G between 1-1 1.00 6.50 3.90 25.35
2.00 0.30 3.90 2.34
Grid G-G between 2-2 1.00 6.50 3.90 25.35
2.00 0.30 3.90 2.34
Deduction for Opening
GF
W -1.00 2.50 9.20 -23.00
W2 -29.00 2.50 1.40 -101.50
W3 -7.00 2.50 1.20 -21.00
W4 -2.00 1.80 1.40 -5.04
W6 -1.00 1.50 1.40 -2.10
W7 -2.00 0.90 1.40 -2.52
W8 -6.00 0.60 1.40 -5.04
DW1 -4.00 1.00 1.40 -5.60
-4.00 1.50 2.60 -15.60
DW3 -1.00 0.80 1.40 -1.12
-1.00 1.00 2.60 -2.60
LW1 -1.00 0.35 0.35 -0.13
LD1 -1.00 1.50 2.10 -3.15
LD2 -1.00 1.00 2.10 -2.10
V1 -5.00 2.50 0.60 -7.50
V2 -3.00 2.50 0.60 -4.50
Half deduction 101.25
First Floor
W2 -28.00 2.50 1.40 -98.00
W4 -4.00 1.80 1.40 -10.08
W7 -2.00 0.90 1.40 -2.52
W8 -7.00 0.60 1.40 -5.88
D1 -1.00 1.50 2.60 -3.90
DW1 -1.00 1.00 1.40 -1.40
-1.00 1.50 2.60 -3.90
DW2 -6.00 1.50 1.40 -12.60
-6.00 1.00 2.60 -15.60
V2 -3.00 2.50 0.60 -4.50
Half deduction 79.19
Top Floor
DW2 -1.00 1.50 1.40 -2.10
-1.00 1.00 2.60 -2.60
W2 -4.00 2.50 1.40 -14.00
Half deduction 9.35
Parapet Wall
over Brick wall 40.00 7.70 2.00 616.00
over Column 39.00 2.30 2.00 179.40
Supply required materials and fixing in position 3mm thick fibre sheet all
complete as per specifications, drawings and instructions.
Front shade area 1.00 34.80 4.50 156.60
First Floor Passage Area 1.00 13.80 3.80 52.44
1.00 Footing
F1 12 21.00 44.00 2.60 0.72 0.00 2402.40 0.89 2138.14
F2 12 18.00 54.00 3.30 0.72 0.00 3207.60 0.89 2854.77
F3 12 24.00 22.00 1.20 0.72 0.00 633.60 0.89 563.91
CF 12 3.00 31.00 2.50 0.72 0.00 232.50 0.89 206.93
12 3.00 21.00 3.80 0.72 0.00 239.40 0.89 213.07
For Ramp
Grid 5a-5a , 5b-5b, 5c-5c 16 3.00 6.00 28.33 0.96 2.00 515.70 1.59 819.97
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,F'-F' ,R-R 16 8.00 6.00 4.05 0.96 2.00 209.76 1.59 333.52
4.00 Column
Upto plinth level
Columns (for main block)
C1 25 8.00 4.00 3.00 1.50 2.00 120.00 3.86 463.20
20 8.00 16.00 3.00 1.20 8.00 460.80 2.47 1138.18
C2 25 3.00 8.00 3.00 1.50 4.00 90.00 3.86 347.40
20 3.00 12.00 3.00 1.20 6.00 129.60 2.47 320.12
C3 20 6.00 20.00 3.00 1.20 10.00 432.00 2.47 1067.04
C4 20 7.00 16.00 3.00 1.20 8.00 403.20 2.47 995.91
C5 25 1.00 12.00 3.00 1.50 6.00 45.00 3.86 173.70
C6 25 1.00 4.00 3.00 1.50 2.00 15.00 3.86 57.90
20 1.00 8.00 3.00 1.20 4.00 28.80 2.47 71.14
C7 25 4.00 12.00 3.00 1.50 6.00 180.00 3.86 694.80
C8 16 6.00 20.00 3.00 0.96 10.00 417.60 1.59 663.99
C9 20 9.00 8.00 3.00 1.20 4.00 259.20 2.47 640.23
16 9.00 12.00 3.00 0.96 6.00 375.84 1.59 597.59
Columns (for ramp) 16 24.00 8.00 3.00 0.96 0.00 576.00 1.59 915.84
Ground floor
Columns (for main block)
C1 25 8.00 4.00 3.00 1.50 2.00 120.00 3.86 463.20
20 8.00 16.00 3.00 1.20 4.00 422.40 2.47 1043.33
C2 25 3.00 8.00 3.00 1.50 4.00 90.00 3.86 347.40
20 3.00 12.00 3.00 1.20 6.00 129.60 2.47 320.12
C3 20 6.00 20.00 3.00 1.20 10.00 432.00 2.47 1067.04
C4 20 7.00 16.00 3.00 1.20 8.00 403.20 2.47 995.91
C5 25 1.00 12.00 3.00 1.50 6.00 45.00 3.86 173.70
C6 25 1.00 4.00 3.00 1.50 2.00 15.00 3.86 57.90
20 1.00 8.00 3.00 1.20 4.00 28.80 2.47 71.14
C7 25 4.00 12.00 3.00 1.50 6.00 180.00 3.86 694.80
C8 16 6.00 20.00 3.00 0.96 10.00 417.60 1.59 663.99
C9 20 9.00 8.00 3.00 1.20 4.00 259.20 2.47 640.23
16 9.00 12.00 3.00 0.96 6.00 375.84 1.59 597.59
First floor
Columns (for main block)
C1 16 3.00 20.00 3.90 0.96 10.00 262.80 1.59 417.86
C2 16 2.00 20.00 4.90 0.96 10.00 215.20 1.59 342.17
C3 16 6.00 20.00 5.90 0.96 10.00 765.60 1.59 1217.31
C4 20 7.00 8.00 6.90 1.20 4.00 420.00 2.47 1037.40
16 7.00 8.00 7.90 0.96 4.00 469.28 1.59 746.16
C5 25 1.00 4.00 8.90 1.50 2.00 38.60 3.86 149.00
20 1.00 8.00 9.90 1.20 4.00 84.00 2.47 207.48
C6 20 1.00 12.00 10.90 1.20 6.00 138.00 2.47 340.86
C7 25 3.00 6.00 11.90 1.50 3.00 227.70 3.86 878.93
20 3.00 6.00 12.90 1.20 3.00 243.00 2.47 600.21
C8 16 6.00 20.00 13.90 0.96 10.00 1725.60 1.59 2743.71
C9 20 5.00 8.00 14.90 1.20 4.00 620.00 2.47 1531.40
16 5.00 12.00 15.90 0.96 6.00 982.80 1.59 1562.66
Second floor
C2 16 2.00 20.00 4.90 0.96 10.00 215.20 1.59 342.17
C3 16 1.00 20.00 5.90 0.96 10.00 127.60 1.59 202.89
C8 16 1.00 20.00 13.90 0.96 10.00 287.60 1.59 457.29
First floor terrace
C1 25 5.00 4.00 1.00 1.50 2.00 35.00 3.86 135.10
20 5.00 16.00 1.00 1.20 8.00 128.00 2.47 316.16
C2 25 1.00 8.00 1.00 1.50 4.00 14.00 3.86 54.04
20 1.00 12.00 1.00 1.20 6.00 19.20 2.47 47.43
C7 25 1.00 12.00 1.00 1.50 6.00 21.00 3.86 81.06
C9 20 4.00 8.00 1.00 1.20 4.00 51.20 2.47 126.47
16 4.00 12.00 1.00 0.96 6.00 71.04 1.59 112.96
Columns (for ramp) 16 9.00 4.00 4.95 0.96 0.00 178.20 1.59 283.34
16 3.00 4.00 4.40 0.96 0.00 52.80 1.59 83.96
16 3.00 4.00 3.90 0.96 0.00 46.80 1.59 74.42
16 3.00 4.00 3.70 0.96 0.00 44.40 1.59 70.60
16 6.00 4.00 3.05 0.96 0.00 73.20 1.59 116.39
1% LD 310.09
For Ramp
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,F'-F' ,R-R 8 8.00 196.00 0.91 0.48 0.00 1426.88 0.40 570.76
Grid 5a-5a , 5b-5b, 5c-5c 8 3.00 19.00 0.91 0.48 0.00 51.87 0.40 20.75
For Ramp
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,F'-F' ,R-R 8 8.00 196.00 0.91 0.48 0.00 1426.88 0.40 570.76
Grid 5a-5a , 5b-5b, 5c-5c 8 3.00 19.00 0.91 0.48 0.00 51.87 0.40 20.75
Ground Floor
Columns (for main block)
for 20no. Long. Rebars
stirrups -1 8 32.00 39.00 2.63 0.48 0.00 3282.24 0.40 1312.90
stirrups -2 8 32.00 156.00 1.64 0.48 0.00 8176.90 0.40 3270.76
First floor
Columns (for main block)
for 20no. Long. Rebars
stirrups -1 8 22.00 39.00 2.63 0.48 0.00 2256.54 0.40 902.62
stirrups -2 8 22.00 156.00 1.64 0.48 0.00 5621.62 0.40 2248.65
Second Floor
for 20no. Long. Rebars
stirrups -1 8 4.00 39.00 2.63 0.48 0.00 410.28 0.40 164.12
stirrups -2 8 4.00 156.00 1.64 0.48 0.00 1022.11 0.40 408.85
Small block
Grid 1-1 16 1.00 9.00 20.90 0.96 2.00 190.02 1.59 302.14
Grid 2-2, 3-3 16 2.00 11.00 20.90 0.96 2.00 463.64 1.59 737.19
Grid 4-4 16 1.00 11.00 20.90 0.96 2.00 231.82 1.59 368.60
Grid A-A 16 1.00 9.00 20.90 0.96 2.00 190.02 1.59 302.14
Grid B-B 16 1.00 9.00 20.90 0.96 2.00 190.02 1.59 302.14
Grid C-C 16 1.00 9.00 20.90 0.96 2.00 190.02 1.59 302.14
Grid D-D 16 1.00 9.00 13.70 0.96 2.00 125.22 1.59 199.10
(EX)
Grid 1-1, 2-2, 3-3 20 4.00 3.00 25.65 1.20 0.00 307.80 2.47 760.27
20 4.00 3.00 25.65 1.20 0.00 307.80 2.47 760.27
Grid 4-4 20 4.00 3.00 26.65 1.20 0.00 319.80 2.47 789.91
20 4.00 3.00 26.65 1.20 0.00 319.80 2.47 789.91
Grid 5-5 20 1.00 3.00 5.30 1.20 0.00 15.90 2.47 39.28
20 1.00 3.00 5.30 1.20 0.00 15.90 2.47 39.28
Grid A-A, B-B, C-C, E-E, F-F, I-I, J-J &K-K 20 8.00 3.00 9.60 1.20 0.00 230.40 2.47 569.09
20 8.00 3.00 9.60 1.20 0.00 230.40 2.47 569.09
Grid D-D 20 1.00 3.00 7.45 1.20 0.00 22.35 2.47 55.21
20 1.00 3.00 7.45 1.20 0.00 22.35 2.47 55.21
Grid G-G & H-H 20 2.00 3.00 11.75 1.20 0.00 70.50 2.47 174.14
20 2.00 3.00 11.75 1.20 0.00 70.50 2.47 174.14
1% LD 131.47
9.00 Second Floor Beam
Big block
Grid 1-1 16 1.00 10.00 42.50 0.96 2.00 426.92 1.59 678.81
Grid 2-2, 3-3 16 2.00 10.00 42.50 0.96 2.00 853.84 1.59 1357.61
Grid 4-4 16 1.00 10.00 6.50 0.96 2.00 66.92 1.59 106.41
Grid E-E 16 1.00 10.00 13.70 0.96 2.00 138.92 1.59 220.89
Grid F-F 16 1.00 11.00 13.70 0.96 2.00 152.62 1.59 242.67
Grid G-G & H-H 16 2.00 11.00 20.90 0.96 2.00 463.64 1.59 737.19
Grid I-I 16 1.00 11.00 13.70 0.96 2.00 152.62 1.59 242.67
Grid J-J 16 1.00 11.00 13.70 0.96 2.00 152.62 1.59 242.67
Grid K-K 16 1.00 10.00 13.70 0.96 2.00 138.92 1.59 220.89
Small block
Grid 1-1 16 1.00 9.00 20.90 0.96 2.00 190.02 1.59 302.14
Grid 2-2 16 1.00 11.00 20.90 0.96 2.00 231.82 1.59 368.60
Grid 3-3 16 1.00 11.00 13.70 0.96 2.00 152.62 1.59 242.67
Grid A-A 16 1.00 9.00 6.50 0.96 2.00 60.42 1.59 96.07
Grid B-B 16 1.00 9.00 6.50 0.96 2.00 60.42 1.59 96.07
Grid C-C 16 1.00 9.00 6.50 0.96 2.00 60.42 1.59 96.07
Grid D-D 16 1.00 9.00 6.50 0.96 2.00 60.42 1.59 96.07
(EX)
Grid 1-1, 2-2 20 2.00 2.00 25.65 1.20 0.00 102.60 2.47 253.43
20 2.00 2.00 25.65 1.20 0.00 102.60 2.47 253.43
Grid 3-3 20 1.00 2.00 23.50 1.20 0.00 47.00 2.47 116.09
20 1.00 2.00 23.50 1.20 0.00 47.00 2.47 116.09
Grid 4-4 20 1.00 2.00 5.30 1.20 0.00 10.60 2.47 26.19
20 1.00 2.00 5.30 1.20 0.00 10.60 2.47 26.19
Grid A-A 20 1.00 2.00 5.30 1.20 0.00 10.60 2.47 26.19
20 1.00 2.00 5.30 1.20 0.00 10.60 2.47 26.19
Grid B-B & C-C D-D E-E F-F I-I J-J K-K 20 8.00 2.00 7.45 1.20 0.00 119.20 2.47 294.43
20 8.00 2.00 7.45 1.20 0.00 119.20 2.47 294.43
Grid G-G H-H 20 2.00 2.00 9.60 1.20 0.00 38.40 2.47 94.85
20 2.00 2.00 9.60 1.20 0.00 38.40 2.47 94.85
1% LD 69.70
10.00 Roof Floor Level Beam
(TH)
Grid 1-1, 2-2 16 2.00 10.00 6.50 0.96 2.00 133.84 1.59 212.81
Grid F-F,G-G 16 2.00 10.00 6.50 0.96 2.00 133.84 1.59 212.81
(EX)
Grid 1-1, 2-2 20 2.00 2.00 5.30 1.20 0.00 21.20 2.47 52.37
20 2.00 2.00 5.30 1.20 0.00 21.20 2.47 52.37
Grid F-F,G-G 20 2.00 2.00 5.30 1.20 2.00 26.00 2.47 64.22
20 2.00 2.00 5.30 1.20 2.00 26.00 2.47 64.22
1% LD 6.59
box type -2
TH
along x-x 16 1.00 6.00 6.80 0.96 2.00 42.72 1.59 67.93
along y-y 16 1.00 6.00 7.05 0.96 2.00 44.19 1.59 70.27
EX
along x-x 16 1.00 2.00 1.45 0.96 2.00 4.82 1.59 7.67
along y-y 16 1.00 2.00 1.45 0.96 2.00 4.82 1.59 7.67
box type -1
along x-x 8 23.00 68.00 1.40 0.48 2.00 2211.68 0.40 884.68
along y-y 8 23.00 68.00 1.40 0.48 2.00 2211.68 0.40 884.68
box type -2
along x-x 8 1.00 68.00 1.40 0.48 2.00 96.16 0.40 38.47
along y-y 8 1.00 71.00 1.40 0.48 2.00 100.36 0.40 40.15
16.00 Second Floor Level Slab
Bottom bar
I 10 1.00 66.00 7.20 0.60 0.00 475.20 0.62 294.63
10 1.00 49.00 9.70 0.60 0.00 475.30 0.62 294.69
II 10 1.00 114.00 29.80 0.60 0.00 3397.20 0.62 2106.27
10 1.00 200.00 16.90 0.60 0.00 3380.00 0.62 2095.60
III 10 1.00 162.00 9.70 0.60 0.00 1571.40 0.62 974.27
10 1.00 66.00 24.10 0.60 0.00 1590.60 0.62 986.18
IV 10 1.00 87.00 4.70 0.60 0.00 408.90 0.62 253.52
10 1.00 32.00 12.95 0.60 0.00 414.34 0.62 256.89
V 10 1.00 114.00 16.90 0.60 0.00 1926.60 0.62 1194.50
10 1.00 114.00 16.90 0.60 0.00 1926.60 0.62 1194.50
Top bar
(TH)
I 10 1.00 50.00 7.20 0.60 0.00 360.00 0.62 223.20
10 1.00 33.00 9.70 0.60 0.00 320.10 0.62 198.47
II 10 1.00 82.00 29.80 0.60 0.00 2443.60 0.62 1515.04
10 1.00 136.00 16.90 0.60 0.00 2298.40 0.62 1425.01
III 10 1.00 114.00 9.70 0.60 0.00 1105.80 0.62 685.60
10 1.00 50.00 24.10 0.60 0.00 1205.00 0.62 747.10
IV 10 1.00 87.00 4.70 0.60 0.00 408.90 0.62 253.52
10 1.00 32.00 12.95 0.60 0.00 414.34 0.62 256.89
V 10 1.00 82.00 16.90 0.60 0.00 1385.80 0.62 859.20
10 1.00 82.00 16.90 0.60 0.00 1385.80 0.62 859.20
(Cut piece )
I 10 1.00 16.00 3.41 0.60 0.00 54.56 0.62 33.83
10 1.00 16.00 6.82 0.60 0.00 109.12 0.62 67.66
II 10 1.00 32.00 18.53 0.60 0.00 592.96 0.62 367.64
10 1.00 64.00 11.14 0.60 0.00 712.96 0.62 442.04
III 10 1.00 48.00 6.82 0.60 0.00 327.36 0.62 202.97
10 1.00 16.00 15.46 0.60 0.00 247.36 0.62 153.37
V 10 1.00 32.00 11.14 0.60 0.00 356.48 0.62 221.02
10 1.00 32.00 11.14 0.60 0.00 356.48 0.62 221.02
1% LD 183.84
17.00 First Floor Level Slab
Bottom bar
I 10 1.00 156.00 68.60 0.60 0.00 10701.60 0.62 6635.00
10 1.00 458.00 23.20 0.60 0.00 10625.60 0.62 6587.88
II 10 1.00 49.00 9.70 0.60 0.00 475.30 0.62 294.69
10 1.00 66.00 7.20 0.60 0.00 475.20 0.62 294.63
Top bar
(TH)
I 10 1.00 108.00 68.60 0.60 0.00 7408.80 0.62 4593.46
10 1.00 314.00 23.20 0.60 0.00 7284.80 0.62 4516.58
II 10 1.00 33.00 9.70 0.60 0.00 320.10 0.62 198.47
10 1.00 50.00 7.20 0.60 0.00 360.00 0.62 223.20
(Cut piece )
I 10 1.00 48.00 41.38 0.60 0.00 1986.24 0.62 1231.47
10 1.00 144.00 14.21 0.60 0.00 2046.24 0.62 1268.67
II 10 1.00 16.00 6.82 0.60 0.00 109.12 0.62 67.66
10 1.00 16.00 5.57 0.60 0.00 89.12 0.62 55.26
1% LD 259.67
18.00 Roof Floor Level Slab
Bottom bar
I 10 1.00 65.00 9.70 0.60 0.00 630.50 0.62 390.91
10 1.00 65.00 9.70 0.60 0.00 630.50 0.62 390.91
Top bar
(TH)
I 10 1.00 49.00 9.70 0.60 0.00 475.30 0.62 294.69
10 1.00 49.00 9.70 0.60 0.00 475.30 0.62 294.69
(Cut piece )
I 10 1.00 16.00 6.82 0.60 0.00 109.12 0.62 67.66
10 1.00 16.00 6.82 0.60 0.00 109.12 0.62 67.66
1% LD 15.07
19.00 Deduction
Staircase area 10 -4.00 29.00 7.20 0.60 0.00 -835.20 0.62 -517.83
10 -4.00 49.00 4.20 0.60 0.00 -823.20 0.62 -510.39
20.00 Staircase
Main bar
1st flight 16 2.00 14.00 4.70 0.96 0.00 131.60 1.59 209.25
2nd flight 16 2.00 14.00 4.70 0.96 0.00 131.60 1.59 209.25
3rd flight 16 2.00 14.00 4.86 0.96 0.00 136.08 1.59 216.37
Distribution bar 12 2.00 64.00 2.00 0.72 0.00 256.00 0.89 227.84
12 2.00 58.00 2.00 0.72 0.00 232.00 0.89 206.48
23.00 Ramp
Floor beam
Grid 5a-5a , 5b-5b, 5c-5c 16 4.00 8.00 0.00 0.96 2.00 7.68 1.59 12.22
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,F'-F' ,R-R 16 8.00 8.00 4.05 0.96 2.00 274.56 1.59 436.56
Beam Stirrups
Grid 5a-5a , 5b-5b, 5c-5c 8 3.00 294.00 2.13 0.48 0.00 1878.66 0.40 751.47
Grid L-L, M-M,N-N,O-O,P-P,Q-Q,F'-F' ,R-R 8 1.00 42.00 2.13 0.48 0.00 89.46 0.40 35.79
T- Unit Weight
S.No. Description Type No. Length(m) Total weight Unit Remark
Length(m) (kg/m)
Front shade area
Column post SHS 100 x 100 x 3mm 9 3.650 32.850 8.690 285.47
Rafter SHS 50 x 50 x 2mm 9 4.500 40.500 3.030 122.72
Bottom chord SHS 50 x 50 x 2mm 9 4.270 38.430 3.030 116.45
Bracings
Diagonal SHS 50 x 50 x 2mm 9 3.885 34.965 3.030 105.95
Vertical SHS 50 x 50 x 2mm 9 1.822 16.398 3.030 49.69
Purlin SHS 50 x 50 x 2mm 10 34.375 343.750 3.030 1,041.57
Base plate 230 x 230 x 12mm 10 4.983 49.84
Colunt-truss joint plate 230 x 230 x 10mm 10 4.153 41.53
Purlin cleat 180 x 80 x 6mm 270 0.678 183.13
nut bolt (1.5% of all) 29.95
Footing F1
rect portion 8 3.6 0.205 5.91
Column 8 1 1.04 8.32
Tie beam
along A-A/C-C/1-1/3-3 4 3.5 0.5 7.00
along B-B/2-2 2 3.75 0.5 3.75
sum 24.98 Sqm
2 Coats weather guard 100% acrelic paint work over one coat
primer on ( Epex Aultima or equivalent) Outer Part of
10.2 building of filter and primer to give uniform colouring after
rending the surface clean & moist as per specification and
instruction complete work.
along x-x 2 4.1 3.04 24.93
along y-y 2 4.1 3.04 24.93
deduct opening (half)
Door -0.5 1 2.1 -1.05
Window -3.5 1.5 1.5 -7.88
Gable wall 1 4.9 0.85 4.17
all around perimeter 4 4.25 0.45 7.65
Ridge cover
1 5.3 1.00 5.30
sum 5.30 Rm
Providing and fixing 3" dia UPVC pipe including bend and all
necessary fixtures as per drawing and instruction of site
12.2 engineer
2 5.49 1.00 10.98
sum 10.98 Rm
sum 861.33 KG
0.87 Ton
#REF!
#REF!
#REF!
#REF!
QUANTITY MEASUREMENT
###
Part: Canteen
S.N Description No. L(m) B(m) H(m) Quantity Unit Remarks
1.0 Earthwork in excavation
column footing 12 1.1 1.1 1.025 14.88
toe wall
along x-x 4 6.45 0.55 0.6 8.51
along y-y 3 7.2 0.55 0.6 7.13
sum 30.53 cum
2.0 Earthfilling
1 8.19 9.81 0.325 26.11
sum 26.11 cum
3.0 Stone Soiling
column footing 12 1.1 1.1 0.15 2.18
floor 1 9.68 8.19 0.15 11.89
toe wall
along x-x 4 8.19 0.3 0.15 1.47
along y-y 3 9.81 0.3 0.15 1.32
sum 16.87 cum
4.0 Laying of thin polythene sheets
floor 1 13.17 8.19 107.86
sum 107.86 sqm
5.0 Concrete works
5.1 M10 PCC works
column footing 12 1.1 1.1 0.05 0.73
toe wall
along x-x 4 8.19 0.23 0.05 0.38
along y-y 3 9.81 0.23 0.05 0.34
sum 1.44 cum
5.2 M15 PCC works
base floor 1 8.88 10.73 0.075 7.15
sum 7.15 cum
5.3 M20 RCC works
Footing
Rect. 12 0.9 0.9 0.205 1.99
a1 a2
trap. 12 0.81 0.1849 0.105 0.58
column 12 0.23 0.23 1.83 1.16
tie beam
along x-x 4 8.19 0.35 0.2 2.29
along y-y 3 9.81 0.23 0.2 1.35
sum 7.38 cum
6.0 Stone Masonry
toe wall
along x-x 4 8.19 0.35 0.75 8.60
along y-y 3 9.81 0.35 0.75 7.73
stage 1 7 1.2 0.45 3.78
1 7 0.23 0.3 0.48
sum 16.32 cum
7.0 Flooring works
base floor 1 8.88 10.73 95.28
sum 95.28 sqm
8.0 Formworks
Footing 12 3.6 0.205 8.86
column 12 0.92 1.04 11.48
along x-x 4 8.19 0.46 15.07
along y-y 3 9.81 0.46 13.54
sum 48.95 sqm
Earth Work in Excavation in foundation (All Type of soil) for lift up to1.5
m. including stacking the soil 0.90 m. minimum from the edge of foundation,
1.1 filling the excavated place & grub of soil in foundation trench & disposing the
excess soil upto a lead of 10 m as per instruction & specification all complete
work
Earth Works in Foundation Footings
Footing, F1 5 1.65 1.65 1.50 20.42
Footing, F2 5 1.95 1.95 1.50 28.52
Earth Back Filling in foundation trenches & Floor in 15 c.m. layers with
1.2 water sprinking & manual compaction as per speciication and instruction all
complete.
1.3 Earth work in filling:-Earth filling with soft soil in rooms and verandah in area
layers of 15-15 cm thick by sprinkling water and hand compaction.
Plinth Area 1.00 97.33 1.00 0.225 21.90
Deduct from
Columns (for main block) -10.00 0.35 0.35 0.80 -0.98
For Foundation Beams Deduction
Grid 1-1 -1 9.75 0.25 0.38 -0.92
Grid 2-2 -1 9.75 0.25 0.38 -0.92
Grid 3-3 -1 3.25 0.25 0.38 -0.31
Grid A-A -1 8.60 0.25 0.38 -0.81
Grid B-B -1 8.60 0.25 0.38 -0.81
Grid C-C -1 5.65 0.25 0.38 -0.53
Grid D-D -1 5.65 0.25 0.38 -0.53
Stone masonry work in cement sand mortar in 1:6 foundation and super -
2.2 structure with quarry stones in perfect line & level including wetting, packing
the joints and curing the work in all types & thickness of walls, column etc.as
per instruction & specification all complete work.
For Foundation Beams
Grid 1-1 1.00 9.75 0.30 0.40 1.17
Grid 2-2 1.00 9.75 0.30 0.40 1.17
Grid 3-3 1.00 3.25 0.30 0.40 0.39
Grid A-A 1.00 8.60 0.30 0.40 1.04
Grid B-B 1.00 8.60 0.30 0.40 1.04
Grid C-C 1.00 5.65 0.30 0.40 0.68
Grid D-D 1.00 5.65 0.30 0.40 0.68
Brick work in cement sand mortar in 1:4 foundation and super -structure with
3.1 1 st class bricks in perfect line & level including wetting the bricks, packing
the joints and curing the work in all types & thickness of walls,column etc.as
per instruction & specification complete work.
Ground floor
Grid 1-1 1.00 9.75 0.25 2.65 6.45
Grid 3-3 1.00 3.25 0.25 2.65 2.15
Grid A-A 1.00 8.60 0.25 2.65 5.69
Grid D-D 1.00 5.65 0.25 2.65 3.74
Deduct opening
D3 -1.00 0.90 0.25 2.10 -0.48
D4 -1.00 1.20 0.25 2.40 -0.72
P.C.C. M15 (1:2:4) Work (for un-reinforced works) etc.with cement sand and
graded coarse aggregate (river bed foruwa) & (waterproof material if reqd.)
including mixing with concrete, lead upto 30m, laying, compacting the
concrete mix with vibrator machine, finishing to approved level lines and
dimensions and curing as per instruction & specification complete work.
Ground Floor:-
In Floors
Plinth Area 1.00 97.33 1.00 0.08 7.30
Column deduction
Columns (for main block) -10.00 0.35 0.35 0.08 -0.10
sum 7.20 Cum #REF! #REF!
P.C.C. M15 (1:2:4) for R.C.C. Work in foundation, walls, beams, slabs, sill,
stitches, lintels etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing concrete, lead upto 30m, laying, compacting the
concrete mix with vibrator machine,finishing to approved level lines and
dimensions and curing as per instruction & specification complete work.
Sill and lintel bands on 250/100mm thick wall
Ground floor
Grid 1-1 1.00 9.75 0.25 0.15 0.37
Grid 3-3 1.00 3.25 0.25 0.15 0.13
Grid A-A 1.00 8.60 0.25 0.15 0.33
Grid D-D 1.00 5.65 0.25 0.15 0.22
0.00
Deduct opening
D2 -1.00 0.90 0.25 0.08 -0.02
D1 -1.00 1.20 0.25 0.08 -0.03
P.C.C. M20 (1:1.5:3) for R.C.C. Work in Super structure, columns, beams,
decks, slabs, etc.with cement sand and graded coarse aggregate (river bed
foruwa) including mixing with concrete, lead upto 30m, compacting the
concrete mix with vibrator machine,laying, finishing to approved level lines
and dimensions and curing as per instruction & specification complete work.
Sub-Structure
Foundation Footings
Footing, F1, bottom box portion 5.00 1.50 1.50 0.20 2.25
a1 a2 h
Footing, F1, trapezoidal portion 5.00 0.30 0.25 0.25 0.34
Footing, F2, bottom box portion 5.00 1.80 1.80 0.20 3.24
a1 h
Footing, F2, tapezoidal portion 5.00 0.36 0.25 0.25 0.38
Foundation Beams
Grid 1-1 1.00 9.75 0.25 0.25 0.61
Grid 2-2 1.00 9.75 0.25 0.25 0.61
Grid 3-3 1.00 3.25 0.25 0.25 0.21
Grid A-A 1.00 8.60 0.25 0.25 0.54
Grid B-B 1.00 8.60 0.25 0.25 0.54
Grid C-C 1.00 5.65 0.25 0.25 0.36
Grid D-D 1.00 5.65 0.25 0.25 0.36
Super-Structure
Columns
From plinth to FF 10.00 0.35 0.35 3.20 3.92
Floor Beams
First Floor Beams
Grid 1-1 1.00 9.75 0.25 0.25 0.61
Grid 2-2 1.00 9.75 0.25 0.25 0.61
Grid 3-3 1.00 3.25 0.25 0.25 0.21
Grid A-A 1.00 8.60 0.25 0.25 0.54
Grid B-B 1.00 8.60 0.25 0.25 0.54
Grid C-C 1.00 5.65 0.25 0.25 0.36
Grid D-D 1.00 5.65 0.25 0.25 0.36
area
Slab 1.00 122.85 1.00 0.13 15.36
Supplying & installing Aluminium Framed Casement Door one way/ two
ways openable with ventilator Natural Colour in the Section of 101x45 x1.5
mm including 9mm thick pre-laminated board or 5 mm thick Glass, silicon
sealant and accessories as per drawing, specification & instruction all
complete.
D1 1.00 1.20 2.10 2.52
D2 1.00 0.90 2.10 1.89
sum 4.41 Sqm #REF! #REF!
Formwork/ Centering & Shuttering with 18mm thick Plywood for all type of
concrete works necessary propping, scaffolding, staging, supporting inclusive
wedging and cutting holes for utilization work till the support is fully
unyielding as per instructions & specifications complete work .
Sub-Structure
Sub-Structure
Foundation Footings
F1 5.00 6.00 0.20 6.00
F2 5.00 7.20 0.20 7.20
Sub-Total
Foundation Beams
Grid 1-1 1.00 9.75 0.50 4.88
Grid 2-2 1.00 9.75 0.50 4.88
Grid 3-3 1.00 3.25 0.50 1.63
Grid A-A 1.00 8.60 0.50 4.30
Grid B-B 1.00 8.60 0.50 4.30
Grid C-C 1.00 5.65 0.50 2.83
Grid D-D 1.00 5.65 0.50 2.83
Plinth Beams
Grid 1-1 1.00 9.75 0.50 4.88
Grid 2-2 1.00 9.75 0.50 4.88
Grid 3-3 1.00 3.25 0.50 1.63
Grid A-A 1.00 8.60 0.50 4.30
Grid B-B 1.00 8.60 0.50 4.30
Grid C-C 1.00 5.65 0.50 2.83
Grid D-D 1.00 5.65 0.50 2.83
Super-Structure
Columns
From plinth to FF 10.00 1.40 3.20 44.80
Sill/lintel band
Ground floor
Grid 1-1 1.00 9.75 0.15 1.47
Grid 3-3 1.00 3.25 0.15 0.49
Grid A-A 1.00 8.60 0.15 1.29
Grid D-D 1.00 5.65 0.15 0.85
0.00
Deduct opening
D2 -1.00 0.90 0.08 -0.07
D1 -1.00 1.20 0.08 -0.09
12.5mm thick cement sand plaster (1:3) on ceiling of good finish including
cleaning, scrubing, wetting the surface before plaster work and curing the
same as per specifications & instructions all complete work
area
Ceiling area 1.00 122.85 1.00 122.85
deduct column -10.00 0.35 0.35 -1.23
250mm thick brick wall -1.00 27.25 0.23 -6.27
100 mm thick wall -1.00 3.25 0.10 -0.33
sum 115.02 Sqm #REF! #REF!
12.5 mm thick cement sand plaster (1:4) on Brick masonry walls
(inside/outside) of good finish including racking the joints, wetting the
surface & curing the work as per specifications & direction all complete.
Deduct opening
D2 -1.00 0.90 2.10 -1.89
D1 -1.00 1.20 2.40 -2.88
Deduct opening
D2 -1.00 0.90 2.10 -1.89
D1 -1.00 1.20 2.40 -2.88
3mm thick (1:1) Cement sand punning work on floor, walls etc including
mixing, laying, finishing to approved level, line and dimensions and curing as
per instruction & specification all complete work.
2 Coats Plastic emulsion Painting in inner part of building over one coat
primer or equivalent primer to give uniform colouring after rending the
surface clean & moist as per specification and instruction all complete work.
2 Coats weather guard 100% acrelic paint work over one coat primer on
( Epex Aultima or equivalent) Outer Part of building of filter and primer to
give uniform colouring after rending the surface clean & moist as per
specification and instruction complete work.
All around perimeter 1.00 41.60 0.45 18.72
Ground floor
Grid 1-1 1.00 9.75 3.20 31.20
Grid 3-3 1.00 3.25 3.20 10.40
Grid A-A 1.00 8.60 3.20 27.52
Grid D-D 1.00 5.65 3.20 18.08
Deduct opening
D2 -1.00 0.90 2.10 -1.89
D1 -1.00 1.20 2.40 -2.88
#REF! ;fx|f] k|sf/sf] Sn], g/d d'/d 9'+uf -#) ;]=dL=;Dd_ ld;]sf] df6f] ;a} lsl;dsf]
B1 vGg] sfd !) dL6/ af]sgL l8:kf]hn / !=% dL6/;Dd lnˆ6 ;d]t
b/ ljZn]if0fsf] nflu ! 3=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
>lds Hofld 0.80 hjfg 690.00 552.00 552.00
oflGqs
Hofldsf] Hofnfsf] #Ü n] 16.56
pks/0f
jf:tljs b//]6 568.56
!%Ü 7]s]bf/ cf]e/x]8 85.28
b/ k|lt 3=dL=sf] hDdf b/ /]6 653.84
?= 653.84 k}=
13s ;fdfGo df6f]n] k'g]{ sfd !%, !% ;]=dL= sf] txdf km}nfpg], kfgL 5g]{ /
B2 Hofldåf/f sDk}S6 ug]{ sfd ;d]t !) dL= b"/Laf6 9'jfgL ug]{ ;fy} l/Ë/f]8;Ddsf] df6f]sf] d"No ;d]t
b/ ljZn]if0fsf] nflu ! 3=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
>lds Hofld 0.50 hjfg 690.00 345.00 345.00
lgdf{0f ;fdu|L
kfgL 5.00 nL6/ 0.25 1.25 1.25
jf:tljs b//]6 346.25
b/ k|lt 3=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 51.93
?= 398.18 k}= hDdf b/ /]6 398.18
1 ;fdfGo df6f]n] k'g]{ sfd !%, !% ;]=dL= sf] txdf km}nfpg], kfgL 5g]{ /
B2 Hofldåf/f sDk}S6 ug]{ sfd ;d]t !) dL= b"/Laf6 9'jfgL ug]{ ;fy} l/Ë/f]8;Ddsf] df6f]sf] d"No ;d]t
b/ ljZn]if0fsf] nflu ! 3=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
>lds Hofld 0.50 hjfg 690.00 345.00 345.00
df6f] 1.50 3=dL= 80.00 120.00
lgdf{0f ;fdu|L
kfgL 5.00 nL6/ 0.25 1.25 121.25
jf:tljs b//]6 466.25
b/ k|lt 3=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 69.93
?= 536.18 k}= hDdf b/ /]6 536.18
1
D1 hu leQf kvf{ndf l;d]G6 s+lqm6 ug]{ sfd dfn;fdfg pknAw ug]{ #) dL6/;Dd 9'jfgL ;lxt
-lk=;L=;L= !M#M^_
b/ ljZn]if0fsf] nflu ! 3=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 1 hjfg 1000.00 1000.00
>lds
v_ HofdL 4 hjfg 690.00 2760.00 3760.00
l;d]G6 0.22 d]=6= 27210.00 5986.20
$) dL=dL=9'+uf -qm;\8_ /f]8f 0.65 3=dL= 2860.00 1859.00
lgdf{0f ;fdu|L @) dL=dL=9'+uf -qm;\8_ /f]8f 0.24 3=dL= 2960.00 710.40
v;|f] afn'jf vf]nfsf] 0.47 3=dL= 3080.00 1447.60
kfgL 120.00 nL6/ 0.25 30.00 10033.20
jf:tljs b//]6 13793.20
b/ k|lt 3=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 2068.98
?= 15862.18 k}= hDdf b/ /]6 15862.18
lgdf{0f ;fdu|L
@) dL=dL=9'+uf -qm;\8_ /f]8f 0.22 3=dL= 2960.00 651.20
lgdf{0f ;fdu|L
!') dL=dL=9'+uf -qm;\8_ /f]8f 0.11 3=dL= 2530.00 278.30
v;|f] afn'jf 0.445 3=dL= 3080.00 1370.60
kfgL 150.00 nL6/ 0.25 37.50 12532.00
jf:tljs b//]6 16292.00
b/ k|lt 3=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 2443.80
?= 18735.80 k}= hDdf b/ /]6 18735.80
1 $=% X @) dL=dL= kmnfd] lu|n agfO{ vfS;L nufO{ /]8cS;fO8 k]G6 ;d]t u/L hf]8\g]
M2 b/ ljZn]if0fsf] nflu !) j=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
$=% X @) dL=dL= kmnfd]
lgdf{0f ;fdu| lu|n agfO{ hf]8\g] 10.00 j=dL= 3145.00 31450.00
L fixing charge 21.50 kg 25.00 537.50
31987.50
jf:tljs b//]6 31987.50
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 4798.12
36785.62 Ö ?= 3678.56 k}= hDdf b/ /]6 36785.62
10
dL=dL=Aof;sf] :6]Gn];l:6ns} 7f8f] kf]i6 /fvL x\of08/]n / e"O+sf] aLrdf tLg tx t];f]{ @%
1
dL=dL=Aof;sf] :6]Gn];l:6nsf] d]Da/ /fvL @Ú–^Æ b]lv #Ú–)Æ ;Dd prfO{ ePsf] /]lnË
pknAw u/fO{ h8fg u/L /+u ;d]t nufpg] sfd .
b/ ljZn]if0fsf] nflu ! /=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
%) hDdf
lgdf{0f ;fdu| dL=dL=Aof;sf] :6]Gn];l:6ns
L f] kfO{ksf] Xof08/]n h8fg 1.00 /=dL= 4593.40 4593.40 4593.40
ug]{ sfo{
jf:tljs b//]6 4593.40
b/ k|lt /=ld=sf] !%Ü 7]s]bf/ cf]e/x]8 689.01
?= 5282.41 k}= hDdf b/ /]6 5282.41
1 Supplying and fitting Aluminium fixed panel window without Ventilation and without fly mesh shutter from
section (90 x 38 x 1.2 )mm and 5mm glass.
b/ ljZn]if0fsf] nflu ! Jf= dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
lgdf{0f ;fdu| hDdf
cfNd'lgodsf
L fixed panel window without Ventilation
-Hofnf ;lxt_ and without fly mesh shutter 1.00 j=dL= 4680.00 4680.00 4680.00
2 Supplying and fitting Aluminium fixed panel window with Ventilation but with fly mesh shutter from section
(90 x38.1x1.2)mm and 5mm glass.
b/ ljZn]if0fsf] nflu ! Jf= dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
lgdf{0f ;fdu| hDdf
cfNd'lgodsf
L fixed panel window with Ventilation but
-Hofnf ;lxt_ with fly mesh shutter 1.00 j=dL= 5111.00 5111.00 5111.00
jf:tljs b//]6 5111.00
b/ /]6 k|lt j= dL=sf] !%Ü 7]s]bf/ cf]e/x]8 766.65
?= 5877.65 k}= hDdf b/ /]6 5877.65
Supplying and fitting Aluminium casement door section of (101 x45 x1.3)mm sash 40x45x1.5mm & 5mm glass with
1 ventilator
1 Supplying and fitting Aluminium casement door section of (101 x45 x1.3)mm sash 40x45x1.5mm & 5mm glass
Supplying and fitting Aluminium partition with 5mm thick glass and 9mm thick laminated board of section (101 x40x1.3)
b/ ljZn]if0fsf] nflu ! Jf= dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
cfNd'lgodsf cfNd'lgodsf
lgdf{0f ;fdu| partition with 5mm thick glass
L
-Hofnf ;lxt_ and 9mm thick laminated board 1.00 j=dL= 5111.00 5111.00
sf ;/;fdfg 5111.00
Composite wall works with 8 mm thick cement board from both sides fixed to 75mm X 0.55mm thick C-
stud fixed to U-Track , central core filled with cement mortar with glass wool, including sealing joints
339 Item with fiber tapes and joint sealing compound, filling screw heads
source Analysis for 1 sqm
Type Quantity Unit Rate Amount Rs. Remarks
Material(with
labour & all
fittings) Composite wall 1.00 sqm 4000.00 4000.00
Actual Rate 4000.00
Overhead 15% 600.00
Rate per m2 4600.00
ljdsf] nflu !( dL=dL KnfO{sf] kmdf{ agfpg] sfd,dfn;fdfgsf] pknlAw, 5gf}6 ug]{, gS;f cg';f/ kmdf{ /fVg]
1 lsnf / cGt/ nufpg] kmdf{ lemSg], x6fpg] #) ld6/;Dd 9'jfgL ;lxt .
E5 b/ ljZn]if0fsf] nflu !) j=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 2.67 hjfg 1000.00 2670.00
>lds
v_ HofdL 4.00 hjfg 690.00 2760.00 5430.00
lgdf{0f ;fdu|L KnfO{ af]8{ 1.65 j=dL= 1491.89 2461.61
sf7 nf]sn 0.039 3=dL= 60997.64 2378.90
kmnfd] k|k 0.4 ;+Vof 1694.00 677.60
lsnf 2.50 s]=hL= 104.50 261.25 5779.36
jf:tljs b//]6 11209.36
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 1681.40
=
12890.76 ?= 1289.07 k}= hDdf b/ /]6 12890.76
=
10
gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
0.02885/1.1/6x0.75=0.039
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
11.11/6x0.90=1.65
M kfO{k M !% k6s;Dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
8/15x0.75=0.40
sf7df kmdf{ agfpg] sfd, dfn;fdfgsf] pknlAw, 5gf}6 ug]{, gS;f cg';f/ kmdf{ /fVg]
1 lsnf / cGt/ nufpg] kmdf{ lemSg], x6fpg] #) ld6/;Dd 9'jfgL ;lxt
kmz{ / :n]j h:tf sfd
b/ ljZn]if0fsf] nflu !) j=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 1.72 hjfg 1000.00 1720.00
>lds
v_ HofdL 2.57 hjfg 690.00 1773.30 3493.30
:yfgLo s'–sf7 0.07 3=dL= 60997.64 4269.83
lgdf{0f ;fdu|L
lsnf 2.50 s]=hL= 104.50 261.25 4531.08
jf:tljs b//]6 8024.38
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 1203.65
=
9228.03 ?= 922.80 k}= hDdf b/ /]6 9228.03
10
gf]6 M ^ k6s;Dd k|of]u ug{ ;lsg] To; kl5 kmdf{sf] d"No @%Ü afFls /xg] lx;fj ul/Psf] -)=&% X )=%@^Ö)=)& 3=dL=_
Supplying and fixing double leaf solid corelead protected wooden flush door with solid wood frame
339 Item
including necessary handles , locks etc. of medium quality as per drawings.
source Analysis for 1 sqm
Type Quantity Unit Rate Amount Rs. Remarks
Material(with
labour & all
fittings) Door panel with frame 1.00 sqm 6500.00 6500.00
Actual Rate 6500.00
Overhead 15% 975.00
Rate per m2 7475.00
1 !@=% dL=dL= afSnf] l;d]G6 afn'jf Knfi6/ -!M#_ efudf l;lnËdf ug]{ .
I1 b/ ljZn]if0fsf] nflu !)) j=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 15.00 hjfg 1000.00 15000.00
>lds
v_ HofdL 20.00 hjfg 690.00 13800.00 28800.00
l;d]G6 0.625 d]=6= 24950.00 15593.75
lgdf{0f ;fdu|L
afn'jf vf]nfsf] 1.28 3=dL= 3080.00 3942.40 19536.15
100
125s kf]/l;lng gg-Un]H8 6fO{n(for flooring) !M$ l;d]G6 afn'jfdf 5fKg] sfd .
!!–& b/ ljZn]if0fsf] nflu !) j=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
H6
hDdf
s_ l;kfn' 13.00 hjfg 1000.00 13000.00
>lds
v_ HofdL 4.50 hjfg 690.00 3105.00 16105.00
l;d]G6 0.056 d]=6= 24950.00 1397.20
afn'jf vf]nfsf] 0.152 3=dL= 3080.00 468.16
lgdf{0f ;fdu|L
;]tf] l;d]G6 3.228 s]=hL= 24.27 78.33
kf]/l;lng gg-Un]H8 6fO{n 11.00 j=dL= 828.83 9117.10 11060.79
155 !# dL=dL= dfj{n !@=% dL=dL= afSnf] !M# efusf] l;d]G6 d;nfdf
s e¥ofÍ v'8\lsnf, :sl6{Ë, leQf, lkn/ cflbdf 5fkL 3f]6\g] / kflnz ;d]t ug]{ .
b/ ljZn]if0fsf] nflu !) j=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 14.00 hjfg 1000.00 14000.00
>lds
v_ HofdL 12.00 hjfg 690.00 8280.00 22280.00
l;d]G6 0.063 d]=6= 24950.00 1571.85
afn'jf vf]nfsf] 0.128 3=dL= 3080.00 394.24
!# dL=dL= dfj{n 11.00 j=dL= 1399.32 15392.52
lgdf{0f ;fdu|L cShflns Pl;8 0.37 s]=hL= 158.00 58.46
d}g kflnz 0.118 s]=hL= 524.00 61.83
tf/k]G6fOg 0.538 nL= 184.00 98.99
sfaf]{/08d 9'+uf cGbfhL – 120.00 17697.89
jf:tljs b//]6 39977.89
b/ k|lt j=dL=sf] = !%Ü 7]s]bf/ cf]e/x]8 5996.68
45974.57 Ö ?= 4597.45 k}= hDdf b/ /]6 45974.57
10
196s Ps sf]6 k|fO{d/ ;lxt b'O{ sf]6 j]b/sf]6 -Pk]S; jf ;f] ;/x_ k]G6 ug]{ sfd
J 26 b/ ljZn]if0fsf] nflu !)) j=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 5.80 hjfg 1000.00 5800.00
>lds
v_ HofdL 5.80 hjfg 690.00 4002.00 9802.00
c:t/ 8.0 nL= 455.00 3640.00
lgdf{0f ;fdu|L
j]b/sf]6 16.00 nL= 825.00 13200.00 16840.00
1 dfn;fdfg pknAw u/L 3 ld=ld=Plain kmfO{j/ Unf; kftfn] 5fgf 5fpg] sfd .
F14
b/ ljZn]if0fsf] nflu !) j=dL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
>lds l;kfn' 1.10 hjfg 1000.00 1100.00
HofdL 1.25 hjfg 690.00 862.50 1962.50
kmfOj/ Unf; sf]?u]6]8 3
dLdL= afSnf] 12.00 j=dL= 2200.00 26400.00
lgdf{0f ;fdu| * dLdL= g6 af]N6 30.00 uf]6f 13.50 405.00
h] x's 25.00 uf]6f 14.80 370.00
lj6'ldg jfz/ 55.00 uf]6f 3.00 165.00 27340.00
jf:tljs b//]6 29302.50
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 4395.37
33697.87 Ö ?= 3369.79 k}= hDdf b/ /]6 33697.87
10
339 Item Providing and cladding 8mm thick cement board in line and level as per drawings.
source Analysis for 1 sqm
Type Quantity Unit Rate Amount Rs. Remarks
Material(with
labour & all
fittings) Cladding wall 1.00 sqm 2200.00 2200.00
Actual Rate 2200.00
Overhead 15% 330.00
Rate per m2 2530.00
286
M 11 sfnf] kmnfd] kfO{ksf] 6«; agfO{ h8fg ug]{ sfd -k|fOd/ k]G6 ;lxt_
b/ ljZn]if0fsf] nflu !*=($ s]=hL= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
l;kfn' 0.687 ;+Vof 1000.00 687.00
>lds
HofdL 0.781 ;+Vof 690.00 538.89 1225.89
;j} k|sf/sf]
lgdf{0f ;fdu| sfnf] kfO{k
L jgfO{ hf]8\g] 18.94 s]=hL= 75.00 1420.50
k|fOd/ k]G6 cGbfhL – 110.00 1530.50
Supply and apply of water proofing with cementitious component over floor tile covering areas and 2ft
339 Item
wall tile covering areas as per specification and as directed by Engineer.
source Analysis for 1 sqm
Type Quantity Unit Rate Amount Rs. Remarks
Material(with
labour & all
fittings) Water proofing works 1.00 sqm 710.42 710.42
Actual Rate 710.42
Overhead 15% 106.56
Rate per m2 816.99
cement board in position for internal and external made with 10 mm thick cement board from both sides
339 Item fixed to 90mm X 0.55mm thick C-stud fixed to U-Track , central core filled with cement mortar with PE
source granules, including sealing joints with fiber tapesfor
Analysis and1 joint
sqm sealing compound, filling screw heads
Type Quantity Unit Rate Amount Rs. Remarks
Material(with
labour & all
fittings) Composite wall 1.00 sqm 4950.00 4950.00
Actual Rate 4950.00
Overhead 15% 742.50
Rate per m2 5692.50
dfn;fdfg pknAw u/L )=$% dL=dL=(light 24 Gauge) /+lug =hL=cfO{= zL6sf] w'/L agfO{
1 h8fg ug]{ sfd k'/f .
F6 b/ ljZn]if0fsf] nflu !) /=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 2.00 hjfg 1000.00 2000.00
>lds
v_ HofdL 3.00 hjfg 690.00 2070.00 4070.00
)=$% /+lug zL6 12.00 dL6/ 319.00 3828.00
lgdf{0f ;fdu|L
cfjZos g6 jf]N6 cGbfhL – – 70.00 3898.00
1
F7 dfn;fdfg pknAw u/L 0.50mm Kn]g zL6sf] !%) ld=ld= rf}8fO{, $%) ld=ld= ;Ddsf]
u6/ agfO{ $)X# ld=ld= sf] kmnfd] a|fs]6, g6af]N6, jf;/ nufpg] ;d]t sfd k'/f .
b/ ljZn]if0fsf] nflu !) /=ld= lnOPsf]
k|To]s ;|
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ b/ k|lt PsfO{ /sd f]t ;fwgsf]
hDdf
s_ l;kfn' 1.75 hjfg 1000.00 1750.00
>lds
v_ HofdL 2.00 hjfg 690.00 1380.00 3130.00
;fbf 0.50mm sf] Kn]g l;6 13.5 dL6/ 230.00 3105.00
a|fs]6 32.0 ;+Vof 110.00 3520.00
lgdf{0f ;fdu|L
jf;/ 48.0 ;+Vof 2.00 96.09
af]N6 48.00 ;+Vof 27.50 1320.00 8041.09
b/ k|lt /=dL=sf]
=
jf:tljs b//]6 11171.09
12846.75 ?= 1284.67 k}= !%Ü 7]s]bf/ cf]e/x]8 1675.66
10.00 hDdf b/ /]6 12846.75
b/ k|lt j=dL=sf] =
12846.75 ?= 2141.12 k}=
6.00
->lds (–@ cg';f/ lnOPsf] o;df Kn]g l;6sf] rf}8fO{ )=^) dL= cGbfh ul/Psf] _
339 Item Supply and installation of interlocking floor tiles with stone dust all complete works.
source Analysis for 1 sqm
Type Quantity Unit Rate Amount Rs. Remarks
Material(with
labour & all
fittings) Interlocking Pavement 1.00 Sqm 970.91 970.91
Actual Rate 970.91
Overhead 15% 145.64
Rate per m2 1116.55
Labour Rate
Rate WITH 0%
Material Rate Rate TRANS.
Circuit Breakers
600x600 mm LED Ceiling Panel 36 watt, Ultima Ultra (LULTU1S036XC) Jaquar set 6400.00 6400.00
600x300 mm LED Ceiling Panel 24 watt, mento 2, (LES 4224-NW) Legero set 4560.00 4560.00
10 Watt 200X200 LED Ceiling Panel set 0.00 0.00
12 Watt LED Ceiling Panel Light, Cassini Square, (LCSN01S012XN) Jaquar set 1728.00 1728.00
6 watt LED Down Light, Cassini Round, (LCSN01R006XN) Jaquar set 1104.00 1104.00
18 Watt LED Ceiling Panel Light Cassini Square, (LCSN01S018XN) Jaquar set 2374.40 2374.40
12 Watt LED Ceiling Panel Light, Cassini Square, (LCSN01S012XN) Jaquar set 1728.00 1728.00
6 watt LED Down Light, Cassini Square, (LCSN01S006XN) Jaquar set 1104.00 1104.00
2X4 Watt LED Mirror Light set 8080.00 8080.00
48", 3 Blade ceiling fan with J Hook set 2318.00 2318.00
150 W, Highbay Luminaries set 23000.00 23000.00
18 Watt LED Garden Bollard set 16000.00 16000.00
10 Watt IP 67 Fountain Light set 8900.00 8900.00
PEL LED NM (SC), Prolite, Self Contained Rechargeable Emergency set 18600.00 18600.00
70 Watt Flood Light set 7000.00 7000.00
4 mtr 4" Metal pole with concrete base foundation set 3000.00 3000.00
8 Watt Garden Spike Light set 8000.00 8000.00
3 Watt Garden Spike Light set 6000.00 6000.00
Exit light set 6400.00 6400.00
Post top Light fixture set 678.00 678.00
15 W E27 LED Bulb set 780.00 780.00
2x3 Watt Up Down wall light, Lit ' Brite, (LWWL03x0203XW), Jaquar set 6080.00 6080.00
3 Watt LED Foot Light, Lytzon (LFLT01S105XW), Jaquar set 6480.00 6480.00
20 W LED Batten Tube Light, Kubik Ultra (LKBUO13022XN) Jaquar set 1076.80 1076.80
10 watt LED Bulk Head, (CWLLO1V109XX) , Jaquar set 2640.00 2640.00
4W LED Wall Light , (KCH-CHR-MB160275541A), Jaquar set 3198.40 3198.40
Earthing System
2core 1.5 sq. mm. FRLS Armoured pure copper cable in RED colour rm 110.00 110.00
2 loop addressable Fire Panel set 211,994.00 211994.00
12V 7Ah Backup batter required additional set 1,500.00 1500.00
CFP Standard 4 zone conventional Fire Panel of Key switch version with 2x12V
set 39,800.00 39800.00
3.3 A Hr VRLA battery pack
SITC of Intelligent Analog Addressable Type Manual Break Glass Call Point
having Surface or flush mounting Option fully complaint to EN54 having Rotary
set 7,168.00 7168.00
Decade Swicthes for Addressing and LED to indicate normal and alarm
condition. Duly Approved by EN54 and LPCB.
Surface Mounting IP 67 Outdoor use Crack glass fire call point set 2,130.00 2130.00
SITC of loop powered wall mount sounder strobe with red lens designed to alert
building occupants of an emergency using both visible and audible warning. The
sounder strobe should have at least 32 tone selecction and made of high quality
set 16,300.00 16300.00
UV stable robust material. The sounder should have maximum output of at least
75dB at 1metre and stobe flash rate of 1Hz. The sounder strobe has to be EN
and LPCB approved.
Diesel Generator
40 KVA, 415 Volt, 3 Phase, 50 Hz silet type with canopy standby Diesel
set 989,700.00 989,700.00
Generator set - Deutz Engine, Stamford Alternetor, PaiKane
Battery and its Charger set 20,000.00 20,000.00
Exhaust pipe with Arrangements set 45,000.00 45,000.00
500A TPN 4 Pole manual changeover switch set 69,500.00 69,500.00
200A TPN 4 Pole manual changeover switch set 36,500.00 36,500.00
100A TPN 4 Pole manual changeover switch set 17,800.00 17,800.00
Accessories
Lighting protection with 14.2x1000mm dai multiple point cu. solid rod Lighting tip
with 100mm dia 20 ft long GI pole with Base foundation, 3 nos of stay set
complete, 75 sq. mm cu strip bar with solid weld from lighting tip to Earthing set 47,090.00 47090.00
station (without joint in middle of span) with required mounting arrangements
(Cost should include separate cu. plate Earthing station)
Supply and installation of 25*3 mm Copper Strip from lightening arrestor to
Earthing station as Lightening protection and bonding of metal roof to the Kg 1,587.50 1587.50
Earthing system
4 Way Splitter set 3260.00 3260.00
Splitter outer Box set 1200.00 1200.00
95 sq.mm cable shoe pc 143.00 143.00
16 sq.mm cable shoe pc 64.00 64.00
PVC Tape pc 15.00 15.00
Item Description Unit Qty Rate Amount
No:
C. 16 A AC outlet point
A. Material cost
2.5 sq. mm copper wire mtr 10 26.90 269.00
4.0 sq. mm copper wire mtr 20 43.48 869.60
20 mm Dia PVC conduit mtr 10 46.00 460.00
Pipe nail, Banding wire LS 1 3.00 3.00
Cement/Sand Mortar for redoing the chiselled area LS 1 25.00 25.00
PVC Tape, Insulating Materials LS 1 5.00 5.00
A. Total 1631.60
B. Labour Costs
Skilled prn 0.25 1000.00 250.00
Semi-Skilled prn 0.25 730.00 182.50
B. Total 432.50
C. Total (A+B) 2064.10
D. Overhead & Profit 15% of C 309.615
E. Total (C+D) 2373.72 /point
2 Light Fixture
A. 32 W LED fixture with diffuser of 48" SM270C
A. Material cost
LED Fixture set 1 11000.00 11000.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 11000.00
B. Labour Costs
Skilled prn 0.1 1000.00 100.00
Semi-Skilled prn 0.1 730.00 73.00
B. Total 173.00
C. Total (A+B) 11173.00
D. Overhead & Profit 15% of C 1675.95
E. Total (C+D) 12848.95 /set
Q. 5 W, foot light
A. Material cost
Light fixture set 1 4000.00 4000.00
Hanging chain LS 0 100.00 0.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 4011.00
B. Labour Costs
Skilled prn 0.1 1000.00 100.00
Semi-Skilled prn 0.1 730.00 73.00
B. Total 173.00
C. Total (A+B) 4184.00
D. Overhead & Profit 15% of C 627.6
E. Total (C+D) 4811.60 /set
S. Exit Light
A. Material cost
Light fixture set 1 6400.00 6400.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 6411.00
B. Labour Costs
Skilled prn 0.1 1000.00 100.00
Semi-Skilled prn 0.1 730.00 73.00
B. Total 173.00
C. Total (A+B) 6584.00
D. Overhead & Profit 15% of C 987.6
E. Total (C+D) 7571.60 /set
w. 15 Watt Post top Light with 4 mtr long 4" metal pole
A. Material cost
4 mtr 4" Metal pole set 1 3000.00 3000.00
Post top Light fixture set 1 678.00 678.00
15 W E27 LED Bulb set 1 780.00 780.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 4469.00
B. Labour Costs
Skilled prn 0.1 1000.00 100.00
Semi-Skilled prn 0.1 730.00 73.00
B. Total 173.00
C. Total (A+B) 4642.00
D. Overhead & Profit 15% of C 696.3
E. Total (C+D) 5338.30 /set
3 Fan Fixture
A. 220 v, 50 Hz, Exhaust fan
A. Material cost
DX 5 Blade (200mm) Exhaust Fan set 1 2700.00 2700.00
4" PVC duct with housing/hanging canopy set 1 345.00 345.00
Nail, Grips etc. LS 1 33.00 33.00
A. Total 3078.00
B. Labour Costs
Skilled prn 0.5 1000.00 500.00
Semi-Skilled prn 0.5 730.00 365.00
B. Total 865.00
C. Total (A+B) 3943.00
D. Overhead & Profit 15% of C 591.45
E. Total (C+D) 4534.45 /set
B. 280-370 Exhaust fan
A. Material cost
150mm dia 280-370 m3/h, 1770-2290 RPM Exhaust fan set 1 3068.26 3068.26
4" PVC duct with housing/hanging canopy set 1 345.00 345.00
Nail, Grips etc. LS 1 25.00 25.00
A. Total 3438.26
B. Labour Costs
Skilled prn 0.2 1000.00 200.00
Semi-Skilled prn 0.1 730.00 73.00
B. Total 273.00
C. Total (A+B) 3711.26
D. Overhead & Profit 15% of C 556.689
E. Total (C+D) 4267.95 /set
F. 32 Amp DP switch
A. Material cost
Switch set 1 Err:509 Err:509
18 SWG Metal Box nos 1 35.00 35.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total Err:509
B. Labour Costs
Skilled prn 0.1 1000.00 100.00
Semi-Skilled prn 0.2 730.00 146.00
B. Total 246.00
C. Total (A+B) Err:509
Err:509
D. Overhead & Profit 15% of C Err:509
E. Total (C+D) Err:509 /set
5. Power Cable
D. 4x6+1x4copper cable
A. Material cost
4Cx6sq. mm copper cable r mt 100 350.00 35000.00
16 mm Dia PVC conduit r mt 0 36.00 0.00
4 sq. mm copper wire r mt 100 43.48 4348.00
Cable tie, fixing materilas r mt 100 50.00 5000.00
A. Total 44348.00
B. Labour Costs
Skilled prn 1 1000.00 1000.00
Semi-Skilled prn 2 730.00 1460.00
un-Skilled prn 3 690.00 2070.00
B. Total 4530.00
C. Total (A+B) 48878.00
C. Total 48878.00
D. Overhead & Profit 15% of C Total 7331.7
E. Total (C+D) 56209.70
562.10 /m
D. FFDB
A. Material cost
60/75/100 AMP, 9"×36"×48" size Panel Board -1 set set 1 21414.00 21414.00
Cement/Sand Mortar for Installation lot 1 2000.00 2000.00
40 A TP MCCB pcs 1 5665.00 5665.00
50 A TP MCB pcs 0 2637.00 0.00
6 A SP MCB pc 9 206.00 1854.00
16 A DP RCCB pc 5 2000.00 10000.00
16 A SP MCB pc 22 206.00 4532.00
45465.00
B. Labour Costs
Skilled prn 1 1000.00 1000.00
Semi-Skilled prn 2 730.00 1460.00
B. Total 2460.00
C. Total (A+B) 47925.00
C+D Total 47925.00
E. Overhead & Profit 15% of C+D Total 7188.75
F. Total (C+D+E) 55113.75 /set
1.40 B. RG 6 TV socket
A. Material cost
socket set 1 290.00 290.00
18 SWG Metal Box nos 1 35.00 35.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 336.00
B. Labour Costs
Skilled prn 0.05 1000.00 50.00
Semi-Skilled prn 0.1 730.00 73.00
B. Total 123.00
C. Total (A+B) 459.00
C. Total 459.00
D. Overhead & Profit 15% of C Total 68.85
E. Total (C+D) 527.85 /set
R. RJ 45 LAN socket
A. Material cost
socket set 1 557.00 557.00
18 SWG Metal Box nos 1 35.00 35.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 603.00
B. Labour Costs
Skilled prn 0.14 1000.00 140.00
Semi-Skilled prn 0.2 730.00 146.00
B. Total 286.00
2core 1.5 sq. mm. FRLS Armoured pure copper cable in RED colour mtr 10 110.00 1100.00
16 mm Dia frls grade conduit mtr 10 60.00 600.00
Circular Box PVC 4 way no. 1 8.00 8.00
Pipe nail, Banding wire LS 1 3.00 3.00
Cement/Sand Mortar for redoing the chiselled area LS 1 25.00 25.00
A. Total 1736.00
B. Labour cost
Skilled prn 0.25 1000.00 250.00
Un-Skilled prn 0.25 730.00 182.50
B. Total 432.50
3 CCTV System:
3.10 Color CCTV Bullet camera
A. Material cost
2MP 2.8-12mm @F1.4 varifocal IP Outdoor Bulle set 1 17016.00 17016.00
Screw, Grips etc. ls 1 11.00 11.00
Material Total 17027.00
A. Total 17027.00
B. Labor Costs
Skilled prn 1 1000.00 1000.00
Semi-Skilled prn 2 730.00 1460.00
Un-Skilled prn 2 690.00 1380.00
B. Total 3840.00
4. Generator
4.10
A. Material cost
Fully Enclosed type 200KVA, 415 Volt, 3 Phase, 50 Hz standby
Diesel Generator set 1 2845840.06 2845840.06
Exhaust pipe with Arrangements set 1 20000.00 20000.00
Battery and its Charger set 1 45000.00 45000.00
A. Total 2910840.06
B. Labour Costs
Skilled prn 2 1000.00 2000.00
System Engineer for Entire Testing prn 1 5000.00 5000.00
Semi-Skilled prn 2 730.00 1460.00
un-Skilled prn 4 690.00 2760.00
B. Total 11220.00
RG 6 TV socket
A. Material cost
socket set 1 226.00 226.00
18 SWG Metal Box nos 1 35.00 35.00
Screw, Grips etc. LS 1 11.00 11.00
A. Total 272.00
B. Labour Costs
Skilled prn 0.1 1000.00 100.00
Semi-Skilled prn 0.2 730.00 146.00
B. Total 246.00
C. Total (A+B) 518.00
C. Total 518.00
D. Overhead & Profit 15% of C Total 77.7
E. Total (C+D) 595.70 /set
FDB-LOWER FLOOR
A. Material cost
60/75/100 AMP, 9"×36"×48" size Panel Board set 1 21414.00 21414.00
Cement/Sand Mortar for Installation lot 1 2000.00 2000.00
40 A TP MCCB pc 1 5665.00 5665.00
6 A SP MCB pc 8 206.00 1648.00
16 A DP RCCB pc 4 2000.00 8000.00
16 A SP MCB pc 27 206.00 5562.00
44289.00
B. Labour Costs
Skilled prn 1 1000.00 1000.00
Semi-Skilled prn 2 730.00 1460.00
B. Total 2460.00
C. Total (A+B) 46749.00
C. Total 46749.00
D. Overhead & Profit 15% of C Total 7012.35
E. Total (C+D) 53761.35 /set
3 CCTV System:
3.10 Color CCTV camera
A. Material cost
2MP 2.8-12mm @F1.4 varifocal IP Eyeball (Dome set 1 16243.00 16243.00
Screw, Grips etc. ls 1 11.00 11.00
Material Total 16254.00
A. Total 16254.00
B. Labor Costs
Skilled prn 1 1000.00 1000.00
Semi-Skilled prn 2 730.00 1460.00
Un-Skilled prn 2 690.00 1380.00
B. Total 3840.00
E. IP PBX 24 Extension
A. Material cost
IP PBX 24 Extension, Main unit (Built in 6-CO + 16SLT + 2DPT)
(Make: Panasonic or equivalent) set 1 60000.00 60000.00
Installation materials, Bracket, Anchoring set 4 11.00 44.00
A. Total 60044.00
B. Labour Costs
Skilled prn 1 1000.00 1000.00
Semi-Skilled prn 1 730.00 730.00
B. Total 1730.00
C. Total (A+B) 61774.00
61774.00
C. Total 61774.00
D. Overhead & Profit 15% of C Total 9266.10
E. Total (C+D) 71040.10 /set
4. ONLINE UPS
4.10
A. Material cost
15 kVA online UPS, 400 Volt, 3 Phase, 50 Hz set 1 227200.00 227200.00
100 Ahr UPS battery set 30 17280.00 518400.00
Battery rack set 1 15000.00 15000.00
A. Total 760600.00
B. Labour Costs
Skilled prn 1 1000.00 1000.00
System Engineer for Entire Testing prn 1 5000.00 5000.00
Semi-Skilled prn 2 730.00 1460.00
un-Skilled prn 4 690.00 2760.00
B. Total 10220.00
skilled 1000
unskilled 690
(63x50)cm Porcelain clay white glazed O- counter Wash basin with mixer Complete set. (Duravit, Grohe, American Standard,
Thai or equivalent)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 2 nos 690.00 1,380.00 3,380.00
a. 63x50cm Porcelain clay O- counter white glaze
4,950.00 4,950.00
materials Wash basin (large) 1 nos
b. 32 mm pvc bottle trap including 32mm CP waste 523.60 523.60
coupling with CP chain and rubber plug etc. 1 nos
d. 1.5x45Cm (½"x18") pipe connector 2 nos 157.30 314.60
e. screw etc Ls 40.00 5,828.20
Actual rate 9,208.20
15% contractor overhead 1,381.23
Rate per set Rs. 10589.43 Total (Rs.) 10,589.43
(50x40)cm Porcelain clay white glaze Wash basin regular complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 2 nos 690.00 1,380.00 3,380.00
a. 50x40cm Porcelain clay white glaze Wash basin
1 nos 782.10 782.10
regular
b. 32 mm pvc bottle trap including 32mm CP waste
coupling with CP chain and rubber plug etc. 1 nos 523.60 523.60
materials
c. 15 mm CP basin mixer 1 nos 4,662.90 4,662.90
d. 1.5x45Cm (½"x18") pipe connector 2 nos 157.30 314.60
f. screw etc Ls 40.00 6,323.20
Actual rate 9,703.20
15% contractor overhead 1,455.48
Total (Rs.) 11,158.68
(50x40)cm Porcelain clay white glaze Wash basin with pedestal and mixture complete set. (with pillar cock)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 2 nos 690.00 1,380.00 3,380.00
a. 50x40cm Porcelain clay white glaze Wash basin
1 nos 1,650.00 1,650.00
regular
white glazed pedestal for wash basin 1 nos 3,300.00 3,300.00
b. 32 mm pvc bottle trap including 32mm CP waste
coupling with CP chain and rubber plug etc. 1 nos 523.60 523.60
materials
c. 15 mm CP pillar cock 1 nos 892.10 892.10
d. 1.5x45Cm (½"x18") pipe connector 1 nos 157.30 157.30
-
f. screw etc Ls 40.00 6,563.00
Actual rate 9,943.00
15% contractor overhead 1,491.45
Total (Rs.) 11,434.45
Porcelain clay white glaze Wash basin for disable with Pillar cock and grab bar all complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 2 nos 690.00 1,380.00 3,380.00
a. Porcelain clay white glaze Wash basin for disable
20,549.00 20,549.00
with grab bar all complete 1 nos
b. 15mm swan neck type cp pillar cock 1 nos 1,361.00 1,361.00
c. 1.5x45cm (½"x18") pipe connector 1 nos 157.30 157.30
d. screw etc Ls 40.00 22,107.30
Actual rate 25,487.30
15% contractor overhead 3,823.09
Total (Rs.) 29,310.39
29310.39
Porcelain clay White glazed Indian Pattern Comode with low level glazed cistern with complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 1,000.00 3,000.00
un skilled 3 nos 690.00 2,070.00 5,070.00
a. Porcelain clay White glazed Indian Pattern Comode
7,022.40 7,022.40
materials with all complete set . 1 nos
b.10.0 ltr.porcelain clay low level flushing cistern
4,486.90 4,486.90
complete accessories( Internal PVC fittings) 1 nos
c. 1.5x45 CM (½" x18") PVC pipe connector 1 nos 157.30 157.30
d. screw, etc. Ls 40.00 11,706.60
Actual rate 16,776.60
15% contractor overhead 2,516.49
Rate per set Rs. 19293.09 Total (Rs.) 19,293.09
580 mm size Porcelain clay white glazed Orissa pan with low level glazed cistern complete set
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 1,000.00 3,000.00
un skilled 3 nos 690.00 2,070.00 5,070.00
a. 580 mm Porcelain clay white glaze Orissa Pan 1 nos 909.70 909.70
b.10.0 ltr.porcelain clay low level flushing cistern
4,486.90 4,486.90
materials complete accessories (Internal PVC fittings) 1 nos
c 32mmx60cm size flushing CP pipe 1 nos 330.00 330.00
d.1.5x45 Cm (½" x18") PVC pipe connector 1 nos 157.30 157.30 5,883.90
Actual rate 10,953.90
15% contractor overhead 1,643.08
Rate per set Rs. 12596.98 Total (Rs.) 12,596.98
1
Small Flat back White glazed urinal (46.5x35.5x26.5)cm all complete set
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 1 nos 690.00 690.00 2,690.00
a. 46.5x35.5x26.5 cm White glaze flat back Urinal
materials (Hindware, Parryware,cera or eqv.) 1 nos 921.80 921.80
15mm C.P.Urinal Auto closing Valve with built in
control cock 1 nos 2530.00 2,530.00
1
Kitchen Sink Stainless Steel 37" long 8" deep with sink cock all complete set.
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 1 nos 690.00 690.00 2,690.00
a. Stainless steel sink Bowl with ordinary drain board
materials
37" long and 8" deep size. 1 sets 1.15 1.14
b. 32 mm pvc bottle trap including 32mm CP waste 523.60
coupling with CP chain and rubber plug etc. 1 nos 523.60
c. 15mm cp sink cock 1 nos 2,420.00 2,420.00
d. 1.5x45cm (½"x18") pipe connector 1 nos 157.30 157.30
e. Zink Oxide screw etc. LS 40.00 3,142.04
Actual rate 5,832.04
15% contractor overhead 874.80
6706.84 Total (Rs.) 6,706.84
2
Kitchen Sink Stainless steel double Bowl 62" long 8" deep with sink cock all complete set.
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 3 nos 1,000.00 3,000.00
un skilled 2 nos 690.00 1,380.00 4,380.00
a. Stainless steel sink double bowl with single drain
materials
ordinary board 62" x 8" size 1 sets 1.16 1.15
b. 32 mm pvc bottle trap including 32mm CP waste 476.00 476.00
coupling with CP chain and rubber plug etc. 1 nos
c. 15mm cp sink cock 1 nos 2,420.00 2,420.00
d. 1.5x45cm (½"x18") pipe connector 1 nos 157.30 157.30
e. Zink Oxide screw etc. LS 40.00 3,094.45
Actual rate 7,474.45
15% contractor overhead 1,121.16
8595.61 Total (Rs.) 8,595.61
1033
300 ltr with 3 panel solar water heater with electric booster all complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3.00 nos 1,000.00 3,000.00
un skilled 3.00 nos 690.00 2,070.00 5,070.00
materials a. 300 ltr with 3 panel solar water heater 1 nos 55,000.00 55,000.00
b.Zink oxide screw etc. Ls 40.00 55,040.00
Actual rate 60,110.00
15% contractor overhead 9,016.50
69126.50 Total (Rs.) 69,126.50
1038
2000 Ltr PVC\HDPE Water Tank
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 1,000.00 3,000.00
un skilled 4 nos 690.00 2,760.00 5,760.00
a. 2000 ltr PVC water tank with Inlet, outlet, over flow,
materials cleanout hole etc. 1 nos 26,400.00 26,400.00
b.Tanki nipples with wash out plug etc. Ls 188.00 26,588.00
Actual rate 32,348.00
15% contractor overhead 4,852.20
37200.2 Total (Rs.) 37,200.20
1049
2 H.P. Electrical motor water pump Multi stage coupled pump (Crompton)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 1,000.00 4,000.00
un skilled 3 nos 690.00 2,070.00 6,070.00
a.2 H P Electricmotor pump with base plate nuts, bolts
materials etc.set Multi stage, coupled pump (Crompton) 1 nos 54,574.30 54,574.30
b.Zink oxide screws etc. Ls 40.00 54,614.30
Actual rate 60,684.30
15% contractor overhead 9,102.64
69786.94 Total (Rs.) 69,786.94
1144
50 mm dia PVC Pipe 6 kg/cm2.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/18) 0.06 nos 1,000.00 60.00
un skilled(1/10) 0.10 nos 690.00 69.00 129.00
materials a.50 mm dia. PVC pipe 6 kg/cm2. 1 RM 145.20 145.20
b. Jointing materialsetc. Ls 25.00 170.20
Actual rate 299.20
15% contractor overhead 44.88
344.08 Total (Rs.) 344.08
1145
75 mm dia PVC Pipe 6 kg/cm2.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1,000.00 110.00
un skilled 0.11 nos 690.00 75.90 185.90
materials a.75 mm dia. PVC pipe 6 kg/cm2. 1 Rm 327.80 327.80
b. Jointing materialsetc. Ls 25.00 352.80
Actual rate 538.70
15% contractor overhead 80.80
619.50 Total (Rs.) 619.50
1146
110 mm dia PVC Pipe 6 kg/cm2.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.17 nos 1,000.00 170.00
un skilled 0.20 nos 690.00 138.00 308.00
materials a.110 mm dia. PVC pipe 6 kg/cm2. 1 Rm 689.70 689.70
b. Jointing material setc. Ls 25.00 714.70
Actual rate 1,022.70
15% contractor overhead 153.40
1176.10 Total (Rs.) 1,176.10
1165
CI Cover 22" X 22" (22 kg) Heavy Duty
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.33 nos 1,000.00 330.00 330.00
materials CI Cover 22" X 22" (22 kg) Heavy Duty 1 nos 5,776.10 5,776.10 5,776.10
Actual rate 6,106.10
15% contractor overhead 915.91
7022.01 Total (Rs.) 7,022.01
1179
200mm dia. HDP Pipe (4 Kg/cm2)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 1,000.00 250.00
un skilled 0.33 nos 690.00 227.70 477.70
materials a.200mm dia.HDP Pipe (4 Kg/cm2) 1.0 RM 1,581.80 1,581.80 1,581.80
Actual rate 2,059.50
15% contractor overhead 308.92
2368.42 Total (Rs.) 2,368.42
1185
15 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 1,000.00 10.00
un skilled 0.01 nos 690.00 6.90 16.90
materials a. 15 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm2 1 Rm 155.10 155.10
b. Cpvc fittings Ls 100.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 285.10
Actual rate 302.00
15% contractor overhead 45.30
347.30 Total (Rs.) 347.30
1186
20 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 1,000.00 10.00
un skilled 0.01 nos 690.00 6.90 16.90
materials a. 20 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm2 1 Rm 237.60 237.60
b. Cpvc fittings Ls 100.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 367.60
Actual rate 384.50
15% contractor overhead 57.67
442.17 Total (Rs.) 442.17
1187
25 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 1,000.00 11.00
un skilled 0.019 nos 690.00 13.11 24.11
materials a. 25 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm2 1 Rm 353.10 353.10
b. Cpvc fittings Ls 120.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 503.10
Actual rate 527.21
15% contractor overhead 79.08
606.29 Total (Rs.) 606.29
1188
32 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 1,000.00 11.00
un skilled 0.019 nos 690.00 13.11 24.11
materials a. 32 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm2 1 Rm 522.50 522.50
b. Cpvc fittings Ls 120.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 672.50
Actual rate 696.61
15% contractor overhead 104.49
801.10 Total (Rs.) 801.10
1190
40 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 1,000.00 11.00
un skilled 0.019 nos 690.00 13.11 24.11
materials a. 40 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm2 1 Rm 724.90 724.90
b. Cpvc fittings Ls 175.00
c. Jointing materials (flow guard adesive soln) Ls 50.00 949.90
Actual rate 974.01
15% contractor overhead 146.10
1120.11 Total (Rs.) 1,120.11
20 mm CPVC Ball Valve, CTS sockets
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 1,000.00 110.00
materials a. 20 mm CPVC ball valve, CTS sockets, 1 set 534.60 534.60 644.60
Actual rate 644.60
15% contractor overhead 96.69
741.29 Total (Rs.) 741.29
1
C P towel rod 1.5x60cm (½"x 18") size
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(2/9) 0.22 nos 1,000.00 220.00 220.00
materials a .C P Towel rod 1.5x60cm (½"x 18") 1 nos 418.00 418.00
b. Screws Ls 40.00 458.00
Actual rate 678.00
15% contractor overhead 101.70
Rate per nos Rs. 779.70 Total (Rs.) 779.70
2
C.P. Grab bar European pattern 600-900mm long bend type Grohe, Essel or Eqv.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/9) 0.22 nos 1,000.00 220.00 220.00
a. C.P. Grab bar European pattern 600-900mm long
materials bend type Grohe, Essel or equivalent 1 nos 7,906.80 7,906.80
b. Zink oxide screw etc. Ls 40.00 7,946.80
Actual rate 8,166.80
15% contractor overhead 1,225.02
Rate per nos Rs. 9391.82 Total (Rs.) 9,391.82
1
73 mm Ms Seamless Pipes SCH 40
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2.7 nos 1,000.00 2,700.00
un skilled 3.2 nos 690.00 2,208.00 4,908.00
materials a 73 mm OD Ms Seamless pipes SCH 40, 5.16 mm thick 1 Set 1,895.00 1,895.00
b. Jointing materials and painting Ls 250.00 2,145.00
Actual rate 7,053.00
15% contractor overhead 1,057.95
Rate per set Rs. 8110.95 Total (Rs.) 8,110.95
1
101.6 mm Ms Seamless Pipes SCH 40
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2.7 nos 1,000.00 2,700.00
un skilled 3.2 nos 690.00 2,208.00 4,908.00
materials a 101.6 mm Ms Seamless pipes SCH 40 ,5.74mm thickness 1 Set 3,205.00 3,205.00
b. Jointing materials and painting Ls 200.00 3,405.00
Actual rate 8,313.00
15% contractor overhead 1,246.95
Rate per set Rs. 9559.95 Total (Rs.) 9,559.95
Fire Pump 20 HP Electric Motor Pump-2 set with control pannel, pressure gauge and acessories (kiloskar or eqv.)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 6 nos 1,000.00 6,000.00
un skilled 4 nos 690.00 2,760.00 8,760.00
Fire Pump 20 HP Electric Motor Pump-2 set with control pannel,
materials 550,000.00 550,000.00
pressure gauge and acessories (kiloskar or eqv.) 1 Set
550,000.00
Actual rate 558,760.00
15% contractor overhead 83,814.00
Rate per set Rs. 642574 Total (Rs.) 642,574.00
Fire post with landing valve, hose reel or box with complete set
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 5 nos 1,000.00 5,000.00
un skilled 2 nos 690.00 1,380.00 6,380.00
a. Landinng valve ISI marked is : 5290, Hose box 18 gauge mild
steel, 75x60x25cm (30"x24"x10") to accommodate two hose length
of 15 meters each and one branch pipes with locking arrangement, 2
29,935.40 29,935.40
lengths Jayashree RRL hose (ISI is : 636 in 15 meter length with
male and female coupling dully binded with wires, Branch pipe
materials short GM.)( minimax) 1 Set
29,935.40
Actual rate 36,315.40
15% contractor overhead 5,447.31
Rate per set Rs. 41762.71 Total (Rs.) 41,762.71
1
1.5 H.P. Electrical motor water pump, Monoblock type
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 1,000.00 4,000.00
un skilled 2 nos 690.00 1,380.00 5,380.00
a.1.5 H P Electric motor pump with base plate
19,250.00 19,250.00
materials nuts,bolts,etc.set 1 nos
b.Zink oxide screws etc. Ls 40.00 19,290.00
Actual rate 24,670.00
15% contractor overhead 3,700.50
Rate per set Rs. 28370.5 Total (Rs.) 28,370.50
Kitchen Sink Stainless Steel 37" long 8" deep with sink cock all complete set.
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 1 nos 690.00 690.00 2,690.00
a. Stainless steel sink Bowl with ordinary drain board
materials
37" long and 8" deep size. 1 sets 5,209.60 5,209.60
b. 32 mm pvc bottle trap including 32mm CP waste 523.60 523.60
coupling with CP chain and rubber plug etc. 1 nos
c. 15mm cp sink cock 1 nos 2,420.00 2,420.00
d. 1.5x45cm (½"x18") pipe connector 1 nos 157.30 157.30
e. Zink Oxide screw etc. LS 40.00 8,350.50
Actual rate 11,040.50
15% contractor overhead 1,656.07
Rate per set Rs. 12696.57 Total (Rs.) 12,696.57
300 ltr with 3 panel solar water heater with electric booster all complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3.00 nos 1,000.00 3,000.00
un skilled 3.00 nos 690.00 2,070.00 5,070.00
materials a. 300 ltr with 3 panel solar water heater 1 nos 54,313.60 54,313.60
b.Zink oxide screw etc. Ls 40.00 54,353.60
Actual rate 59,423.60
15% contractor overhead 8,913.54
Rate per set Rs. 68337.14 Total (Rs.) 68,337.14
(40x40)cm Porcelain clay white glaze corner Wash basin regular complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 1,000.00 2,000.00
un skilled 2 nos 690.00 1,380.00 3,380.00
a. 50x40cm Porcelain clay white glaze Wash basin
1 nos 691.90 691.90
regular
b. 32 mm pvc bottle trap including 32mm CP waste
coupling with CP chain and rubber plug etc. 1 nos 523.60 523.60
materials
c. 15 mm CP basin mixer 1 nos 4,662.90 4,662.90
d. 1.5x45Cm (½"x18") pipe connector 2 nos 157.30 314.60
0 0 nos -
f. screw etc Ls 40.00 6,233.00
Actual rate 9,613.00
15% contractor overhead 1,441.95
Total (Rs.) 11,054.95