MONITORING REMAINING WORKS

DAY TO DAY MONITORING


Team Normal Over Time
NO REMAINING WORKS Finish Remarks % DAYS COMULATIVE COMPLETION ( % )
07.00 AM - 04.00 AM 04.00 AM- 09.00 PM 9-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 1-Nov 2-Nov 3-Nov 4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov

89 Mechanical mounting 5-Nov-21 85.38


90 Area: Pellet unloading 1 15 September 99.71429
91 Main equipment
92 Steel structure 100
93 Hopper 100
94 Hoist 100
95 Blender 100
96 Combistations 100
97 Scissor lift 100
98 Small equipment OS Blind flanges 98
99 Area: Extruder 89.38462
100 Main equipment
101 Steel structure (hoisting) 100
102 Hoppers (with separators) and frame 100
103 Movable combistations, secondary filters Positioning / still waiting leveling 70
104 Docking station (containers) 100
105 Collecting screw shim leveling 98
106 Exhausters shim leveling 98
107 Feeders shim leveling 98
108 Extruder and accessories shim leveling 98
109 Pelletizer and accessories 100
110 Classifier 100
111 Fluidized bed 100
112 Small equipment 100
113 Chutes Still waiting shim leveling 0
114 Area: Finished product 99.66667
115 Main equipment
116 Steel structure 100
117 Silos 100
118 Bag filling station 100
119 Big bag filling station 100
120 Small equipment still install flexible 98
121 Chutes 100
122 Area: Dedusting (outside) 93.33333
123 Main equipment
124 Steel structure 100
125 Filters (vacuum, dedusting, cyclone) 100
126 Small equipment OS install sensor 80
127 Piping 79
128 Pneumatic conveying pellet unloading 100
129 Air piping pellet unloading 100
130 Pneumatic conveying finished product 100
131 Air piping finished product Clash with hydrant pipe 90
132 Vacuumcleaning Clash with hydrant pipe 90
133 Water piping (pelletizer) Still extruder shim leveling 0
134 Water piping (cleaning silos) 100
135 Dry air piping (cleaning silos) 100
136 Dedusting Clash with Wall Fan & Ducting temporary 10
137 Dedusting fluidized bed 100
138 Electrical mounting 51.20
139 MCC room 68.33
140 Installation of cabinets 100
141 Cable trays fr distribution to nordson & Jtech Panel 70
142 Cabinet connections Still Waiting Cable 35
143 Area: Pellet unloading 49.33
144 Cable trays clash with vaccum pipe 98
145 Cabling Still Waiting Cable 4 pulling, 50
146 Field connections 0
147 Area: Extruder 15.00
148 Cable trays 30
149 Cabling extruder to drive panel blind wiring, 0
missing cable 2 type, driver to main steer type
0
150 Field connections cable & conection??
151 Area: Finished product 30.00
still waiting bridge silos to el. 6000 (other LYB
90
152 Cable trays contractors)
still waiting bridge silos to el. 6000 (other LYB
0
153 Cabling contractors), RFQ not scope by???
still waiting bridge silos to el. 6000 (other LYB
0
154 Field connections contractors), RFQ not scope by???
155 Area: Dedusting (outside) 93.3
156 Cable trays 100
157 Cabling 100
158 Field connections still waiting MDS 6 pull connection 80
159 Commissioning and start-up
160 Quarantine I/O testing
161 I/O testing
162 I/O testing
163 Dry testing
164 Wet testing