Quality Control: Pre-Backfill Checklist
Quality Control: Pre-Backfill Checklist
Quality Control: Pre-Backfill Checklist
Rev. 03-03-16
System No:
System Description:
Pre-Backfill Checklist
Item Description QC Initials Date
1 All piping is installed in accordance with current rev. of drawings
3 Welds are all complete and NDE Testing is complete with no outstanding repairs.
Coating (including coatings over welds) is complete as specified with no visible
4
coating damage.
8 Staged backfill dirt is free of rocks, steel, wood and/or other debris.
Pre-Backfill Acceptance
The below signed confirm that the items initialed in the checklist section of this report are complete and acceptable for the identified piping
system or section.
Name Signature Date
SI Foreman/Supt.
SI QC:
CLIENT:
Comments:
1 of 1