RISK ASSESSMENT

Contractor Name: Golden Falcon Technical Services


Project Name: Central Park PH1
Location: Masdar City
Client Name: Masdar
Description of Activity: Excavation and Backfilling work for solar system Isolator Installation
Sl. Task/ Process Hazards Identified Effects/ Impact Affected Existing Control Measures Initial Risk
No. Party
L C RR
1 Trial pits and collapce of the trench could Impact the Workers,pede Ensure to obtain the NOC if required.Obtain the internal work permit.Ensure identification underline services.Adequete 2 3 6
trench work cave in the people and strain proctection for the excavation cavethrough supports.Implement regular inspection
excavation. excavation property
(0.5m x 0.5m )

Shovling/ Phisical Injury could impact the Workers Wear proper protective clothing ,safety footware,gloves and coverall.Allow safe distance between the people if workinf with 6
Handtools people and other people
2 property 2 3

Adjecent works Phisical Injury could impact the Workers Only athorized persons is allowed in the working area.Harzards to be communicated to the work force. 6
people and
3 property 2 3

Working in Physical Injury,Heat Vehicle collition Workers 6


adverse weather stress,Heat stroke
4 Restricted working hours in accordance with ministry of labour requiremnets.Drinking Water facilities will be available in the 2 3
site.PPE is required handsleves,safety helmets or hard hats. All the work to be suspended during sandstrom where the
visibility is <5M .No countious working for more than 5hours without a 1 hour break
0
or Installation
Additional Control Measures Date Residual Risk Remarks
Completed L C RR
Supervision will be always available all time during the As and when 1 3 3
operation and adequete training to ensure all person in permit is
the excavation work aquire the understanding obtained

Ensure training of handtools and manula handling.sure As and when 3


the terrain where digging is undertaken is free of cables permit is
and pipes obtained 1 3

Supervision will be always available all time during the As and when 3
operation .communicate and cordinate with the team permit is
during the activity obtained 1 3

Work should be coordinated with security prior to arrival As and when 3


on working site.Ensuring use of dust filter or mask in dusty permit is
area.Arrange a rest area that is cooler than the work area. obtained 1 3