Professional Documents
Culture Documents
Phone No: +251928523627 Email: OCTOBER, 2022 Arba Minch, Ethiopia
Phone No: +251928523627 Email: OCTOBER, 2022 Arba Minch, Ethiopia
ON
TISHISHE SMALL SCALE IRRIGATION PROJECT
BY
UMAR ABDELLAH, G-4WRIE, SECTION-A, RAMIT/1194/11
SUBMITTED TO THE
FACULTY OF WATER RESOURCES AND IRRIGATION
ENGINEERING
ARBA MINCH WATER TECHNOLOGY INSTITUTE
ARBA MINCH UNIVERSITY
Email: Umarabdellah50@gmail.com
OCTOBER, 2022
____________________
Phone No:
Email:
ADVISOR APPROVAL PAGE
This is to certify that the internship report entitled ‘Tishishe Small Scale Irrigation Project’ is
prepared by Umar Abdellah under my guidance based on the regular reports that he had
submitted. I recommend this report to be submitted to the faculty of Water Resource and
Irrigation Engineering for evaluation.
Next my great thanks forwards to project supervisor engineer Tessfahun Dagamu, site
engineer worku and all staff as well as site workers; for assistance what and how I have to do
this internship project.
Finally, I would like to express my great thanks to my family those supporting me financially
and morally during my internship and all those contribute their own advice and helps for
fulfillment of this report.
i
ABBREVIATION/ACRONYMS
DB Division Box
D/S Downstream
FC Field Canal
MC Main Canal
SC Secondary Canal
U/S Upstream
ii
TABLE OF CONTENTS
ACKNOWLEDGMENT............................................................................................................i
ABBREVIATION/ACRONYMS.............................................................................................ii
LIST OF FIGURES...................................................................................................................v
LIST OF TABLES....................................................................................................................vi
EXECUTIVE SUMMARY.....................................................................................................vii
1 INTRODUCTION.............................................................................................................1
2.1 Materials......................................................................................................................6
2.2 Methodology...............................................................................................................7
iii
3.1.1.2 Purpose of diversion headwork....................................................................9
5.1 Conclusions...............................................................................................................20
5.2 Recommendations.....................................................................................................21
REFERENCES........................................................................................................................22
iv
LIST OF FIGURES
Figure 1.1 organizational flow chart.........................................................................................2
v
LIST OF TABLES
Table 3.1 Dimensions of Weir body.......................................................................................10
vi
EXECUTIVE SUMMARY
This internship report contains five main sections each section concludes many sub-sections
in detail.
The first section describes the introduction part, the historical backs ground of Tishishe small
scale project, project location, specific objective of project, organizational structure and area
of project location in the first chapter.
The second section deals with the material and methodology used.
The third section deals major activities of the project are construction of head work structure
main canals, secondary, divide wall, flume, culvert and foot path.
The fourth section deals with the assessment of the internship, work ethics related issues,
acquaintance acquired, Influences of Internship for Future Career, influences of internship
for future career and measures taken to overcome challenges of the project.
The last section deals with the conclusion, recommendation and reference
vii
1 INTRODUCTION
1.1 General Introduction about the Internship
This internship report has been written based on the internship conducted from July to
October 2022 which was taken at Sidama National Regional State Water and Irrigation
office. The report mainly addresses the knowledge that I have gained in terms of both
theoretical and practical experiences.
Sidama National Regional State Water and Irrigation bureau is one of the governmental
office which is located in the Government of National State of Sidama in Hawassa and
established public development enterprise in 2012. The office is mainly established in order
to promote clean water supply and irrigation of the Region. And the main customers of this
office are farmers and rural villages’ of the Region who had deficiency of water requirement
for their farm land and clean water for their drinks.
Sidama National Regional State Water and Irrigation bureau is governmental organization
and the objective is to solve the problem of water supply of the region and to promote the
productivity of the region by modernizing the irrigation system.
To expand the modern irrigation system, in order to increase the productivity in the
country.
1
To increase employment opportunity.
To construct water related infrastructures like: - canals, bridges, dams and others.
The organization flow chart of the section is in to two divisions (Irrigation and Water
supply).
2
Project study and design.
Using Tishishe River the local farmers practice traditional irrigation along the River at large
scale at different places. In Sidama Region shebedino wereda, Ramada Kebele, farmers are
one of the users of Tishishe River by traditional irrigation method for a long period of time.
Upgrading and increasing the efficiency of traditional irrigation system through modern and
well-designed system provision is the main objective of this modern small scale irrigation
project.
The project is located in Sidama regional state, Leku district in Ramada Kebele at about
27km from Hawassa town (Region capital) and 3km from woreda capital leku. It is at about
307 Km from Addis Ababa out of which 304 Km is asphalt road, 4Km gravel road to
headwork.The area is elevated to 1920m a.s.l and can be categorized under temperate or
“Woyna Dega” climate. Farm lands dominate the land use of the area and have fair
vegetation cover. The area has good water resource potential mainly springs emerging at
various points. The soil of the area is dark brown silt clay in texture. It is deep, non-
expansive, firm and with low infiltration rate and high water holding capacity. There are
good attempts made by local community to practice traditional irrigations around the project
area. The area has good opportunity for diversification of crop production through modern
irrigation. Currently the farmers mainly grow Inset, coffee, cabbage and maize
3
Figure 1.1 Location map of Tishishe Irrigation Project
Students in the university are expected to be well equipped both in theoretical concept
and practically in the field. Especially in science field, it is difficult to incubate
competent graduates at national and international level unless creating situations to
practice in the field for what they have been learning theoretically in the class. An
internship offers the chance to learn by doing in a setting where students are supervised
by work place professionals and have the opportunity to achieve their own learning goals
without the responsibility of being a permanent employee.
An internship also offers students to the opportunity to work with someone who can
become a mentor not only in the internship but throughout our career.
Until recent years most of students were graduated from universities without doing
internship practices which causes lack of good performances when they are employed
and become responsible to do tasks in the actual field work.
4
1.4.1 Importance and requirements of the internship
Internship plays very important role in site to apply theoretical knowledge what I have
learned in class. There are many reasons to pursue an internship: opportunity for “hands-on”
experience: while students may gather a great deal of information in their courses, there is no
substitute for direct experience in a professional environment. Internship allow students to
gain direct experience.
Site visit
Data collection by interviewing the site Engineer and workers.
Read available TSSIP design data documents.
5
2 MATERIALS AND METHODOLOGY
2.1 Materials
During my internship period, there were different materials and equipment’s in both site and
office works which are necessary to understand the project and also to write this report.
6
On office work: some secondary data’s that gave good information about the project.
Such as :-
AutoCAD and civil 3D files of the structures like headwork, canals, etc.…
Detailed design data documents and also several monthly reports of the project.
2.2 Methodology
Some methodologies in this internship program that followed to get more knowledge:-
Filed visit at the project site and collecting relevant data’s (like topographic condition of
the site, types of crop in that area...)
By making group discussion with my friends on what we see and what we done at the site
and at the office, respectively as a team work.
By asking questions which were not clear for us to the site engineer and to our supervisor.
By referring previous studies and design data documents about TSSIP for further
information.
7
3 GENERAL OVERVIEW OF THE ACTIVITIES
During this internship period, I were done my work in two interrelated ways; by supervision
and collecting different data’s from the site and the other is organizing the collected data and
group discussion with our engineer and also writing daily and weekly activities at the office.
In this internship duration, there are several irrigation structures with their appurtenant works
at the site work which are listed below;
Diversion weir was designed and constructed to raise the level of water in the river
sufficiently to the desired height for diverting the water in part through regulator into the
main supply canal for the development of irrigated agriculture.
TSSIP mainly comprises of diversion weir on Tishishe River, which is a perennial type of
river with relatively good base flow, for the diversion of flow of river Tishishe and network
of canal system for conveyance and distribution of the diverted irrigation water to the target
command area.
8
3.1.1.1 Headwork site selection criteria
The diversion headwork site selection was mainly done based on the following criteria’s:
i. The site which is closed to the command area of the off taking canal was selected.
ii. The site which gave most economical arrangement for the diversion headwork and
distributions works (canals) were selected.
iii. The site which have constant (smooth) flow with minimum slope and also the location
with narrow and well-defined river x-section were selected.
iv. The site which have suitable geological condition for the foundation according to
minimize the cost and in erodible soil type for the river banks were selected.
v. The site which is easily accessible to road were selected. And soon…
Weirs are differ in type and shape, but designed and constructed to serve the same purposes.
By taking into account the following points and other factors, Broad crested masonry weir
with 1:0.5 slope of d/s face and 1:10 slope of u/s face is selected and constructed for this
specific site. Based on:
9
Figure 3.2 =TSSIP Diversion Weir
Weir height 3m
Retaining wall
Retaining wall at the proposed weir site was provided for the following reasons:
10
Figure 3.3 Retaining wall of TSSIP
bottom width 2m
11
foundation depth 1.0m
Under sluice
Under Sluices are gate controlled openings in the weir with crest at low level. They are
located on the same side of off-taking canal. Its main functions are:
To preserve a clear and defined river channel approaching the canal regulator.
To scour silt deposited in front of canal regulator and to control silt entry in to
the canal.
To lower the highest flood level.
Only one under sluice is provided in this specific site at the left end of diversion weir from
where canal off take near head regulators. The crest level of the under sluice was kept at an
average river bed (i.e. at 1858 m). The width of waterway is 1m. The under sluice was
provided with opening of 1.2m width by 1.2m height. The discharge passing through the
under sluice is 2.79 m3/s.
Irrigation network of Tishishe Project has been planned for commanding the entire existing
area under traditional irrigation with the available head and irrigation water for the critical
crop–water periods. The main objective of the irrigation system is to provide the river to the
field units with efficient method. The irrigation system proposed consists of an open main
canal (MC) serving one secondary and sub secondary canals.
Main Canal
The MC of Tishishe project is the largest size of the canal network capable of conveying the
flow of the system under favorable hydraulic conditions of flow velocity with minimum
losses. It has a rectangular shape and it is aligned along the exiting traditional main canal
route. It takes off from the head regulator located at the intake to the tail end where the last
field canal [FC-15] off takes. The designs discharge of the main canals at 12hrs irrigation
time is 0.121m3/s and has a total length of 1002m. The longitudinal slopes of the main canal
adopted is to follow existing canal bed level with minor cut and fill depending on existing
12
canal bed level of the selected traditional main canal. This (Main canal) is lined with
masonry.
FB 0.3m
Off-take
The entire command area is divided into several segments by field canals, which get
irrigation water from off-takes through furrows. There are about 43 off-takes (i.e. 21 off
taking from MC and 7 off taking from SC). The locations of the FCs are mainly based on the
existing off take location.
13
Figure 3.5 off-take
Culverts are canal crossing structures used to facilitate easy access within the project site. As
we can see the main canal were crossed several roads and foot paths. At the location of major
road crossings a rectangular box culvert (6m length) were constructed and at the location of
foot path 2m and 4m 150mm precast RCC slab over the lined part of the canals is planed to
construct.[right now not constructed]
Division Boxes
Division box is provided in the system to control and quantify the volume of water supplied
to the various canal networks in accordance with their respective discharge required as per
the schedule. At different points of the main canal division boxes are provided.
There are about 20 division box (DB) along the main canal and 23 DB along Secondary
canal(as a plan) (SC), total 43 division boxes are diverting the irrigation water to the
respective off taking canals.
14
Figure 3.7 division box
Flume
It is the structure which provided on a canal where an artificial canal crosses a natural
drainage channels like rivers, springs, and small streams.
In Tishishe project there are 3 flumes (above drainage) structures are constructed at the main
canal.
Camping
A camping station for the construction crew such as the contractor and supervisor on the
project site is indispensable for efficient implementation of the project. During construction
15
and after construction stage, it can be serve as living room, store, engineer’s office, guard
house and also for toilet.
Foot Bridge
These are structures constructed on main canals at foot path crossing sites to allow easy
movement of inhabitants in the project area. There are 14 structures (6 & 8 along MC& SC,
respectively) of this type and are designed and constructed of reinforced concrete.
16
4 ASSESSMENT OF THE INTERNSHIP
4.1 Overall Benefits of the Internship
During my internship period, I have been able to gain a lot of knowledge about general work
function and it helps me to improve and apply my theoretical knowledge to the practical one.
In my duration, I could learn how to communicate with workers; in turn I could improve my
interpersonal communication skills. Besides, I was able to understand work ethics related
issues such as punctuality, team work, finishing a given work on time, etc.… on top of this I
learned how to come with a solution when challenges are facing during work time and I also
improve my team playing and leadership skills. I assure that the skills I gained in the
internship will actually help me to be efficient when I get into work after graduation because
I was already familiar with skills which are essential in working environment. In addition to
that, used to perceive things deeply and also to develop the ability to competence in the
construction of diversion weir and canal construction.
The major benefits that I got form the internship are listed and stated as below briefly:
During my internship period in TSSIP, I have tried to improve my practical skills by doing
different activities like supervision works in the site to control the work activity and report to
our supervisor in daily and weekly report form, understanding construction steps (specially
canal) from site clearance up to plastering.
17
4.1.3 Communication and Social interaction skill
In terms of understanding about work ethics I could also learn to be punctual on work time
and not to be late. I also learned group norm, discipline and the value of hard working.
During my internship period I have tried to learn the following ethical issues flawlessly:
18
4.1.5 Team working skill
I had also understood that team working increases self-confidence, moral and loyalty of
individuals. Team collaboration, self-development, continuous learning and access to
information is a few benefit of team playing skill.
Generally, team working skill can make individuals confident, effective in work, role model
for the others and sociable.
My contribution to the company of Sidama National Regional State Water and Irrigation
Bureau was to control (supervision) the sit work and different kinds of work that done by
each labor with together the site engineer. In addition to these control the speed of their work
and reporting to our supervisor engineer in daily and weekly report form.
On the first time I am afraid to approach and communicate easily with the company
supervisor engineer, site engineer and regular workers to acquire the knowledge
where I got from them.
The environmental condition was difficult for some health problems.
Transportation problems especially the location of headwork is far from the main
road
It is my nature and I were fix it after about some days and after that I made most of
the workers like my friends by approaching them to ask different question concerning
about the project thus afraid have broken, all (site engineer, supervisor and also daily
workers) are willing full to share their knowledge.
I took medical supports and after some days I were back to my work.
Most of the time me and my friends choose to went by foot to the headwork location.
19
5 CONCLUSIONS AND RECOMMENDATIONS
5.1 Conclusions
Depend on my internship on the TSSIP, I can conclude that small scale irrigation projects are
becoming highly favored b/c of:
They takes a short period of construction time as compared to large scaled ones.
They brings about house hold food security.
They reduces dependency on food aid economic growth.
They reduces the dependence on rain fed agriculture.
They also help farmers to get crop productions more than one per year.
20
5.2 Recommendations
Every end user around the Tishishe irrigation project should develop the
construction of catch drain which helps them in protecting the main canal
from damage due to the incoming flood from catchment area.
Proper management, maintenance when happen some problems of the project
should be given due consideration in order to make the scheme to operate
efficiently throughout its life period.
Irrigation water should be applied to growing crops. In the proper time
&depth.
21
REFERENCES
Fact Consulting Engineers, P. (2019). Final Feasibility & Detailed Design Report of
headwork and irrigation infrastructure design on Tishishe SSIP. Addis Ababa.
22