Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
METHOD STATEMENT
CUTTING TREES
TWJO-MST-0002-revC PAGE 1 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
Table of Contents
1. GENERAL ............................................................................................................. 4
2. MATERIAL ............................................................................................................ 5
2.1. Temporary Hoarding ................................................................................... 5
3. SURVEY ............................................................................................................... 5
4. TYPICAL CONSTRUCTION SEQUENCE ............................................................. 5
4.1. General of Cutting Tree .............................................................................. 5
4.2. Removal of Existing Trees (Type A) construction sequence ....................... 6
4.3. Removal of Existing Trees (Type B & D) construction sequence ................ 8
4.4. Removal of Existing Trees (Type C) construction sequence ..................... 10
4.5. General of Site Clearing............................................................................ 10
5. PLANTS AND EQUIPMENTS ............................................................................. 11
6. TYPICAL DRAWING AND TRAFFIC CONTROLLER ......................................... 12
TWJO-MST-0002-revC PAGE 3 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
1. GENERAL
A brief description for removal of existing tree & site clearing is documented below which
explaining construction procedures, materials, equipment and tolerances applicable.
The working time for the tree relocation work for the walkway and greenbelt (Ciputat Raya
and Kartini street) will be from 23:00 to 05:00. In the Depot Area relocation work may be
carried out anytime since the area is closed from public transportation.
Work Procedure
• For Small Tree Relocation Work
1. Install safety sign and caution tape for tree relocation work.
2. Removal and uprooting of tree can be done on the daytime and stock on the
beside sidewalk whichever the location of tree relocation.
3. Schedule to collect uprooted tree will be on midninght because we need to
utilize public transportation for loading of tree for relocation.
4. Traffic signs, traffic warning, barricades, etc will be on standby during loading
work on the road.
5. Clear spillage on the road and housekeeping before moving out of area.
TWJO-MST-0002-revC PAGE 4 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
2. MATERIAL
Temporary Hoarding
Temporary hoarding shall be installed before site clearing works start. Height, type and
color of temporary hoarding shall be discussed in order to suit to site condition and
local culture / regulations.
3. SURVEY
Temporary bench marks / control points shall be installed on ground nearby the
construction site. Surveyor shall in routine check the reference coordinates of control
points frequently.
Surveyor will set out the area of Construction site. The marking of temporary hoarding
alignments shall be joint-inspected by JV and Engineer before work starts.
Only after getting approval from the Head of Landscape and Cemetery (Dinas
Pertamanan) DKI Province and relevant authorities regarding the existing trees, the
trimming or felling work shall start and be carried out.
The typical construction sequence of the removal of existing trees is described below.
1) Obtain approved layout plan of existing tree removal from the Engineer.
2) Co-ordinate with local authorities regarding the trees to be fell.
3) Joint-inspection at construction site with representatives from local authorities for the
trees to be fell.
4) Install marking on the trees which need to be removed during the site inspection.
5) The marking on trees shall be quite rigid so that it will not be removed or changed
easily.
6) Prepare shop drawings of removal of existing tree and submit to the Engineer and
local authorities for approval.
7) After getting approval from local authorities, temporary barricade the surrounding of
the trees to be fell.
8) Area to be barricaded shall be considered properly so that trees will not fell outside
the barricaded area and cause injury.
TWJO-MST-0002-revC PAGE 5 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
9) During the tree falling, only experience workers shall present and cut the trees with
proper tools.
10) Warning signs shall be installed at certain areas and signalman shall also present to
give warning to the public.
11) After removal of existing tree, debris shall be collected and disposed off-site.
12) The team of workers shall be shifted to other area where trees need to be remove
and same procedure to be repeated as above.
13) After removal of existing trees, joint-inspection shall be carried with the Engineer and
local authorities to confirm the cutting.
TWJO-MST-0002-revC PAGE 6 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
TWJO-MST-0002-revC PAGE 7 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
TWJO-MST-0002-revC PAGE 8 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
TWJO-MST-0002-revC PAGE 9 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
1) Prior to the commencement of site clearance, the following shall be carried out either
independently or jointly with the Employer's Representative.
a) The boundary of work site shall be surveyed and set out according to the
coordinates stated in the drawings.
b) Photographs shall be taken of structures, landscaping trees and shrubs, fences,
telephone and electrical poles and etc.
c) Access roads to the site shall be constructed if required to enable vehicles,
equipment and plants to be brought into the site.
d) Solid waste dumps sites shall be predetermined within or outside the site for the
dumping of the site clearing materials. The Employer’s Representatives or
relevant authorities shall approve these dumping sites.
2) The site clearance shall then proceed to clear the trees, vegetation, undergrowth,
bushes and minor structures by hydraulic excavators and/or dozers.
3) All unwanted materials shall be piled up and disposed off-site in a safe tidy manner at
the designated dumping areas.
5) Install permanent site hoarding, construct Engineer & Contractor office, temporary
drainage and other buildings according to Engineer’s approved Site Utilization Plan.
TWJO-MST-0002-revC PAGE 10 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
The plant and equipment planned to be used for Backfilling and Landscaping works is
shown in Table 2-2.
Table 2-2 List of Equipment for the Backfilling and Landscaping Works
TWJO-MST-0002-revC PAGE 11 / 12
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101 & CP102 Method Statement Cutting Trees
Typical drawing layout cutting trees is shown in Appendix 1. This layout for cutting trees
shows path of areas consist of Area A (Kartini Street), Area B (Depot Area), and Area C
(Ciputat Raya Street).
For Depot Area (Area B), the cutting and relocation work may be carried out anytime
since the area is closed from public transportation and the method of work will follow the
C work procedure as described above. The method for Area A and Area C is shown in
Appendix 2. For layout cutting trees sign shown in Appendix 3.
TWJO-MST-0002-revC PAGE 12 / 12
MATCHLINE STA 3+600
0+600
MATCHLINE STA
CP101
CP102
C
C
Fence(Type1)
Shop in Track Gate House C TO
LL
JO
RR
C TO
LL
JO
RR
(Gantry Crane)
EX
IT
TO
LL
(Stock Yard) 8 JO
RR
JL
. KA
RT
Back Gate IN
I
Domestic Wastewater Treatment Shed
Car Parking
Motorbike Parking2 (Space for future)
Fence(Type1)
Workshop Main Building
Fence(Type1)
1K
Workshop
Emergency Exit Office
Building
Site Administration Car Garage1 Fuel Tank
Office
Car Parking Car Parking
1
CON
CRE
TE
CONCR
ETE
CONCRETE
7
8
9 2K 2
CONCRETE 1
CONCRETE CONCRETE
CONCRETE
NOTE:
CONTENTS SHOWN IN THIS DRAWING
REFLECT THE AVAILABLE SCHEME AT
INCEPTION DESIGN STAGE. THEY ARE
SUBJECT TO CHANGES AND/OR
REFINEMENT DURING TECHNICAL
DESIGN STAGE.
TOKYU-WIKA Joint Operation
EX
I T
TO
LL
8 JO
JL RR
.K
AR
TI
NI
NOTE:
CONTENTS SHOWN IN THIS DRAWING
REFLECT THE AVAILABLE SCHEME AT
INCEPTION DESIGN STAGE. THEY ARE
SUBJECT TO CHANGES AND/OR
REFINEMENT DURING TECHNICAL
DESIGN STAGE.
TOKYU-WIKA Joint Operation
NOTE:
CONTENTS SHOWN IN THIS DRAWING
REFLECT THE AVAILABLE SCHEME AT
INCEPTION DESIGN STAGE. THEY ARE
SUBJECT TO CHANGES AND/OR
REFINEMENT DURING TECHNICAL
DESIGN STAGE.
TOKYU-WIKA Joint Operation