Saudi Diyar
Consultants
Construction Supervision Department
Procedures Manual
Division 02 – Communications
PROCEDURE
for
SITE MEETINGS
Document No. CS-02-01 Revision H
Contents: 1. Purpose
2. Scope
3. Abbreviations & Definitions
4. Responsibilities
5. Flow Chart
6. Work Method
7. Verifying Method & Record Documents
8. References
9. Appendices
10. Document Status
Issued by Issue Date Document No.
1 PURPOSE
1.1 To describe how the various site meetings are conducted and the points
discussed are recorded and agreed by all parties.
1.2 To describe the agendas for each type of meeting.
1.3 To identify who chairs and who records the minutes of the various meetings.
2 SCOPE
4 RESPONSIBILITIES
4.1 The Head of Supervision Department (HSD) or the Area Manager (AM) is
responsible for the initiation of the Pre-Construction Meetings with the
Contractor and Resident Engineer.
4.2 The Resident Engineer and/or Site Engineers are responsible for
coordinating and conducting meetings with the Contractor at site and for
2 of 10
Issued by Issue Date Document No.
ensuring that all actions arising from the meeting are followed up. A matrix of
responsibilities is appended.
4.3 The Contractor is responsible for the preparation of all information and
documentation required for the Progress Meetings.
4.4 Generally, the site secretary is responsible for typing and distributing the
meeting minutes, and for maintaining the files. However, the Contract
Documents need to be consulted in situations where the Client’s or the
Project Manager’s secretaries have the responsibility for these actions.
3 of 10
Issued by Issue Date Document No.
Meeting
held
Notes in No
Engineer’s Are minutes
diary taken?
Yes
No
Site secretary makes Minutes
changes to minutes approved?
Yes
Site Secretary
distributes the
approved minutes
to all parties
Final
minutes
for record
Site
Document
Control Site secretary logs
and files minutes
Responsibility
of Site DC End
4 of 10
Issued by Issue Date Document No.
6 WORK METHOD
6.1.3 The minutes are taken by SDC and distributed to all parties, including
the HSD, by the site secretary.
6.1.4 The agenda for the meeting comprises, as a minimum, the following:-
i. Contractor’s mobilization plan, site preparation, temporary
installation and working hours
ii. General explanation of design concepts and quality
requirements
iii. Discussion on plans and specifications
iv. Special project conditions
v. Shop drawings and materials submittals
vi. Substitutions (materials)
vii. Project schedule
viii. Testing laboratory (third party)
ix. Payments
x. Contractor Reports
5 of 10
Issued by Issue Date Document No.
6.2.4 If it is SDC’s responsibility to take and distribute the minutes, then after
the meeting the site secretary types the minutes of meeting on form F-
CS01/A, which is signed by the attendees. All the important issues
raised during the meeting are to be included in the minutes of meeting.
6.2.5 Irrespective of which party takes the minutes, a copy of the minutes of
meeting is sent to all attendees and other interested parties, along with
a copy to HSD for necessary action and filing. The RE issues follow up
letters to ensure the actions have been taken.
6.2.6 It is important to have all parties agree to the minutes of the meeting
by making this the first item on the agenda at the next meeting. Any
items not agreed should be identified and the remainder agreed.
6.2.7 The site secretary logs the meeting minutes on Meeting Record Form
F-CS02/A for filing later.
6.3.2 The RE or discipline Site Engineer chairs the meeting if called by SDC
and the Contractor’s representative will chair the meeting if called by
the Contractor.
6.3.3 Notes should always be taken by attendees during the meeting for
record purposes and future reference, although it may not always be
necessary to distribute minutes.
6.3.4 If minutes are taken then the procedure for distribution and filing is to
be followed.
7 of 10
Issued by Issue Date Document No.
6.4.1 At the Pre-Construction and Site Progress Meetings the minutes are
taken by SDC site secretary or a designated staff member or the Client
representative’s secretary or Project Manager’s secretary, according to
the Contract Documents.
6.4.2 If the typed minutes are prepared by SDC staff, then these are passed
to the RE for review and the corrections made by the site secretary.
6.4.3 It is beneficial to send these minutes out to the Client and Contractor
for their comments prior to the next meeting. In this way there will be
no need to enter into protracted discussions during the meeting.
6.4.4 The agreed minutes, including any points of contention, are then
distributed to the attendees in time for the next meeting.
6.4.5 If the typed minutes are prepared by the Client representative’s
secretary or Project Manager’s secretary, then the RE and SDC
attendees review the minutes, comment as necessary prior to signing.
7.1 All record documents will be processed in accordance the Procedure for
Document Control on Site.
8 REFERENCES
8 of 10
Issued by Issue Date Document No.
9 APPENDICES
10 DOCUMENT STATUS
H 6 Dec 11 D. Oxley
Revision Revision Name
Sign Name Sign
No. Date
Document Status Originator Approver
9 of 10
Issued by Issue Date Document No.
10 of 10
Minutes of Meetings
Project Title Date:
Time:
Project Number Page No.
Subject
Attendees : Distribution:
Prepared by:
Item Action to be taken
Description of Agenda
No. By Date
F-CS01/A
Page 1
Page No.
F-CS01/A
Page 2
Page No.
F-CS01/A
Page 3
التاريخ اسم المشزوع
رقم المشزوع
صفحة الموضوع
نسخة : الحاضزون
بتاريخ
F-CS01/A
صفحة رقم
أخذ قزار ومتابعة البيان المسلسل
تاريخ بواسطة
F-CS01/A
Meetings Record Form
PROJECT NAME : Project No.:
RESIDENT ENGINEER :
PARTIES
No. Date Type Distributed To Remarks
for
Contents: 1. Purpose
2. Scope
3. Abbreviations & Definitions
4. Responsibilities
5. Flow Chart
6. Work Method
7. Verifying Method & Record Documents
8. References
9. Appendices
10. Document Status
Issued by Issue Date Document No.
1 PURPOSE
1.1 To describe how work progress on site is effectively recorded for project
control and reported to the Client and SDC Main Office, in accordance with
the Contract requirements.
2 SCOPE
2.1 Applies to all progress reports issued from site to the Main Office and the
Client, i. e.
o Weekly to Main Office
o Monthly to Main Office
o Monthly to the Client
4 RESPONSIBILITIES
4.1 The individual engineers are responsible to complete their daily reports to be
used in the compilation of the weekly and monthly reports.
4.2 The REs are responsible for the coordination of the preparation, in
conjunction with the Senior Engineers, and issue of Weekly and Monthly
Reports to the Head of Supervision Department (HSD).
4.3 HSD and/or Area Manager are responsible to review and approve the
Monthly report to the Client (Arabic).
4.4 The Chairman or Managing Principal approves and signs the Monthly Report
(Arabic) to particular Clients.
4.5 The Main Office or site secretaries are responsible for the typing and
recording of the Monthly Report to the Client (Arabic).
2 of 7
Issued by Issue Date Document No.
Required
by
Contract
Daily Report
Site Engineer
F-CS13/A
writes Daily
Reports
No
RE
Site
requests
Engineer
reports?
files
Yes
Yes
HSD/CM reviews; Arabic
secretary types; final Client?
review by HSD/CM
President No
signs report
Document
Control
Send to Client Monthly
Report in
Arabic
Responsibility End
of DC
3 of 7
Issued by Issue Date Document No.
6 WORK METHOD
6.1 General:
6.1.1 All Site Engineers must keep daily notes of work progress and
problems encountered during the day and have available for
inspection by the HSD or RE, if requested. The report is to include the
activities performed together with any discrepancies/observations that
have taken place on the day. These details are to be recorded on Daily
Report Form F-CS13/A.
6.1.2 The Weekly Report (F-CS11/A) shall cover the activities of the
previous week, and shall be prepared by the RE in conjunction with the
Senior Engineers on site and submitted to the HSD for information and
necessary action.
6.1.3 The Monthly Report (F-CS12/A) shall cover the activities up to the end
of the previous month, and shall be prepared by the RE. The report
shall include all required assistance or follow up from the Main Office
and recommendation to increase the progress on site.
6.1.4 Project Data sheets (F-CS17-1/A), Site Immediate Design
Requirements (F-CS17-2/A) and Summary of Site Progress (F-CS17-
3/A) reports are prepared by the RE and/or Site Engineer and
submitted to HSD every two weeks.
4 of 7
Issued by Issue Date Document No.
7.1 All record documents will be processed in accordance the Procedure for
Document Control on Site.
8 REFERENCES
9 APPENDICES
10 DOCUMENT STATUS
G 7 Dec 11 D. Oxley
Revision Revision Name
Sign Name Sign
No. Date
Document Status Originator Approver
6 of 7
Issued by Issue Date Document No.
Executive Summary
Schedule Update
QA/QC Report
Correspondence Logs
Safety Report
Progress Photographs
Progress Charts
7 of 7
Weekly Report Supervision Department
3. State overall actual progress in comparison to the latest revised work program:
Delay - Behind program by: Days Advanced - Ahead of program by: Days
4. List submittals and important correspondence received from the Contractor this week:
(Indicate response or still under consideration).
5. List of drawings, instructions and any other relevant materials issued to the Contractor this week:
(Indicate here if any may constitute a variation).
Should any of the space allowed becomes insufficient for your data, please attach a page/s to the report titled: Continue from: Report titles, no. & date.
Page 1 of 2 F-CS11/A
6. Urgent requirements from the Main Office (indicating letter date and name addressed to ):
8. General:
a - State your opinion in regard to the Contractors general performance (specially quality).
(stating average manpower, staff, machinery, working hours and their adequacy to perform).
b - Identify and list potential future risk areas in respect to duration, cost & quality:
c - List items or works which were rejected this week and detail actions taken by Contractor to rectify:
d - Recommendations & any important issues or complaints you may like to draw the management's attention to:
e - Briefly insert here info. in respect to: any important visitors, any special incidents, abnormal weather conditions.
Signed: Name:
Page 2 of 2 F-CS11/A
Monthly Report Supervision Department
A. Contractors Performance:
1. Progress of Works:(attach a clear copy of the Contractor's Summary Work Program, where actual progress
i s marked by you with red lines above the bar representing each activity).
a. Overall Delay: Days (list and define critical items and or activities).
b. Reasons of Delay:
c. Issues with potential to cause delays in the future unless addressed immediately:
d. Actions to be taken by the relevant parties (state hereunder) to speed up the work and make up the delays:
2. Cash Flow: (compare value of approved payment applications to estimated cash flow)
Total Applications Value Up Todate:
Total Cash Flow Forecast for same period:
3. Quality:
Page 1 F-CS12/A
SD2 Page 2 Monthly Report / Project: Dated:
Should any of the space allowed becomes in-sufficient for your data, please attach a page/s to the report titled: Continue from:Report titles,no. & date.
4. Issues of Dispute:
B. Financial Issues:
1. Variations: Does, in your opinion, any of the drawings and/or instructions issued last month constitutes a
Variation Order? If "yes", list hereunder.
2. List hereunder information, queries, drawings and any decisions requested from the Main Office, but not
answered / received yet. (Please state request date and department/person concerned).
D. Any other matters, recommendations, problems and/or issues you like to add or to draw the management attention to:
Signed: Name:
Page 2 F-CS12/A
Daily Site Report
Project Title and No.
Contractor
Materials Delivery:
Important Remarks:
Building /Area
Performance
Completion
Bldg / Area
Contractor
Expected
Site Progress/
Item Project No. Project Title
Construction Stage
Date
F-CS17-3/A
#
Date :
Proj. #
Project Title
Date of
Schematic
Design approval
Client's
Required Date
of completion
Construction
Starting Date
Construction
Date of
Completion
Page 1
% age time
elapsed
% age work
done till last
payment
Project Data Sheet
Contractor's
current
performance on
site
Any Additional
work
Any approved
extension of
time
SDC Estimated
Date of
Construction
Completion
General Remarks
F-CS17-1/A
Site Immediate Design Requirements
F-CS17-2/A
PROCEDURE
for
Contents: 1. Purpose
2. Scope
3. Abbreviations & Definitions
4. Responsibilities
5. Flow Chart
6. Work Method
7. Verifying Method & Record Documents
8. References
9. Appendices
10. Document Status
Issued by Issue Date Document No.
1. PURPOSE
1.1. To ensure that all incoming and outgoing correspondence is properly controlled on
site.
1.2. To ensure that only the latest revision of documents are in circulation on site to
prevent inadvertent use of superseded documents and drawings on site.
1.3. To describe how documents in current usage are filed to facilitate retrieval and how
documents will be archived for future reference.
2. SCOPE
2.1. Applies to all correspondence and documents received by and issued from the
SDC project site office.
2.2. The Document Control Categories are divided as follows:-
2.2.1. General Documents
2.2.2. Project Document
2.2.3. Design Working Drawings
2.2.4. Submittals
2.2.5. Project Files
2.2.6. PHO/FHO Documents
2 of 13
Issued by Issue Date Document No.
4. RESPONSIBILITIES
4.1. The RE is responsible for ensuring that all records, logs and files are maintained
up-to-date and are accurate.
4.2. The RE is also responsible for sending the logs each month to the Technical
Manager for analysis of service performance.
4.3. The RE has the responsibility of assigning the distribution of the received
documents to the concerned persons for both their information and action, as
necessary.
4.4. The site secretary is responsible for stamping the received documents with the date
received and distribution stamps.
4.5. The site secretary is responsible for distributing the received documents to the SDC
staff and for sending the outgoing correspondence to the correct recipients.
4.6. The site secretary is responsible for maintaining the document records, their
distribution and filing.
3 of 13
Issued by Issue Date Document No.
Sent by
Contractor
or other
Site secretary
checks, logs,
stamps &
distributes to
RE
RE assesses
action and
allocates
person to act
Site
Document
Yes No No Control
Is it a
Is it a
submittal?
letter?
Procedure
CS-04-04 Yes
Response
required?
Yes
Assigned Engineer
formulates Response letter
response
Response to
Contractor or other
End
4 of 13
Issued by Issue Date Document No.
6. WORK METHOD
6.1. General:
Incoming Letters
i. Secretary receives from messenger and reviews for accuracy:
Date of correspondence
Addressee
Any attachments
Outgoing Letters
i. Secretary receives from originator a draft of letter/memo/fax, assigns a
serial number, logs, types and prints onto plain paper. Spell and
grammar checks have to be used.
ii. The letter reference format is shown in Appendix 9.2.
iii. Secretary returns the typed draft and original draft to the author for
review and any amendments.
iv. The author reviews the letter and releases for final printing
v. Secretary prints and gives, along with all attachments and previous
drafts, to author for final check and initialing, then to RE for signing.
5 of 13
Issued by Issue Date Document No.
vi. A copy of the signed letter is given to the author for record after
received stamp.
vii. Letter original and a copy are delivered by hand to the addressee, who
then stamps and signs the copy. Similarly, with recipients of a copy of
the letter.
viii. The stamped copy of the letter is filed in the master file.
6.3. Filing:
6.3.1. All incoming and outgoing letters, faxes, memos, circulars, drawings,
submittals, reports, manuals, etc. are to be filed separately with the
identification reference title on each file.
6.3.2. The list of file types and subdivisions are listed in Appendix 9.5.
6.3.3. It is imperative that up-to-date and comprehensive files be maintained on the
site for use on a day-to-day basis and for future resolution of claims and
counter-claims.
6.3.4. The files are accessible to all as and when required, but they must be
returned in tact after finishing with them.
6.3.5. It is preferable to keep them in the master File Room, read and take copies
as needed, rather than remove.
6 of 13
Issued by Issue Date Document No.
6.4. Administration:
6.4.1. Document Revision Management: The site Document Controller or
secretary reviews the date of issue and the revision of the incoming
document transmittal and attached documents. The incoming transmittal
revision is checked against the current log to ensure that the next revision is
chosen and that there are no gaps in the sequence. Any discrepancies are
immediately notified. Changes to drawings are identified by clouding and
revision lettering; changes to text documents by striking through and
highlighting.
6.4.2. File Safekeeping and Storage: All documents are to be stored and archived
safely on site and this is the responsibility of the site secretary or Document
Controller.
6.4.3. Handling Confidential Files: Care is to be taken by the site secretary or
Document Controller when handling confidential files. Only authorized
personnel are allowed access to both the hard copies and e-files.
Confidential documents shall be stored safely and are not allowed to have
copies made without permission of the Client.
6.4.4. File Archiving: The Document Controller archives the Design drawings and
final As-Built drawings. If electronic files of drawings are also required for
future reference use and they shall be stored on CDs.
6.4.5. File Disposition: The Document Controller is in charge of the disposition of
all old files that are no longer needed and are inactive. Files are to be burned
and not thrown out as garbage.
7.1. All record documents will be processed in accordance the Procedure for Document
Control on Site.
7 of 13
Issued by Issue Date Document No.
8. REFERENCES
9. APPENDICES
8 of 13
Issued by Issue Date Document No.
9.0 Appendices
001 A 101
Drawing sheet No.
Building No.
A Architectural
S Structural
M Mechanical
E Electrical
CV Civil
9 of 13
Issued by Issue Date Document No.
CM-O/JE-YY00/000-X
CM : Letter originator
O : Secretary/typist Code
JE – Jeddah
KH – Al Khobar
MD – Madinah
MO - Morocco
MK – Makkah
RY – Riyadh
TA - Taif
10 of 13
Issued by Issue Date Document No.
TR/0000/JE-YY00
TR : Transmittal
TR/CS/JE-YY00
11 of 13
Issued by Issue Date Document No.
Submittals Files
1. Shop Drawings
2. Material Submittals
3. Sample Submittals
4. As-Built Drawings
5. O&M Manuals
12 of 13
Issued by Issue Date Document No.
Project Files
1. Contractor Incoming Correspondence
2. Outgoing Correspondence
3. Memos
4. Site Instructions
5. Inspection Requests
6. Site Surveys
7. QA & QC Reports
8. Non Conformance Reports
9. Reports (Daily, Weekly & Monthly)
10. Monthly Attendance Record Sheets
PHO/FHO Documents
1. Project Snags and Photos
2. Testing and Commissioning Data
3. PHO and FHO Certificates
4. Final As-Built Drawings
5. O&M Manuals
6. Test Certificates
7. Warranty Certificates
8. Spare Parts List
13 of 13
PROCEDURE
for
ARCHIVING
Document No. CS-02-34 Revision A
Contents: 1. Purpose
2. Scope
3. Abbreviations & Definitions
4. Responsibilities
5. Flow Chart
6. Work Method
7. Verifying Method & Record Documents
8. References
9. Appendices
10. Document Status
Issued by Issue Date Document No.
1. PURPOSE
1.1. To describe how project documents from a site, which are no longer in current
usage, are retained in secure and safe storage conditions and in an efficient
manner to ensure the safe-keeping of project records and to facilitate retrieval at a
later date.
2. SCOPE
2.1. Applies to all correspondence and documents received by and issued from the
SDC project site office.
2.2. The Document Control Categories are divided as follows:-
i. General Documents
ii. Project Document
iii. Design Working Drawings
iv. Submittals
v. Project Files
vi. PHO/FHO Documents
vii. Test Records
viii. Warranty Certificates
ix. As-Built Drawings
x. O & M Manuals
2 of 11
Issued by Issue Date Document No.
4. RESPONSIBILITIES
4.1. The RE is responsible for ensuring that all appraised records, logs and files (hard
and soft copies) are maintained up-to-date.
4.2. The site secretary is responsible for preparing the document files for archiving by
making out lists of the contents of the individual files and maintaining a log thereof.
4.3. The site secretary is responsible for packing the files in boxes and making out lists
of files within the boxes, i.e. labeling items with necessary identifying information,
and attaching the contents list to the boxes.
4.4. The site secretary is responsible for the log of all documents, files and boxes sent
to storage for archiving.
None applicable
3 of 11
Issued by Issue Date Document No.
6. WORK METHOD
6.1. General:
6.1.1. The papers in lever arch and/or box files are filed in reverse chronological
order. No matter when the papers became available they are filed in the date
on which they were written.
6.1.2. Attachments or enclosures to documents are filed immediately below the
document to which they relate. Drawings or bulky items such as catalogues
are put in a pouch with the contents recorded on the front of the pouch.
These are stored separately.
6.1.3. Electronic are filed along with the paper files. The title of the diskette being
written on it.
6.1.4. Logs of the files and their contents are maintained.
6.3. Storage:
6.3.1. All the boxes pertaining to a site are taken to a dry and secure storage in the
nearest SDC office in either Jeddah or Riyadh by the secretary of HSD.
4 of 11
Issued by Issue Date Document No.
Documents in storage that are beyond the retention period are reviewed annually to
determine whether they, in whole or part, should be retained longer or destroyed.
If the decision is taken to retain whole or part then a new retention period is
assigned.
If the decision is to destroy whole or part then the documents are destroyed by
incineration.
7.1. All record documents will be processed in accordance the Procedure for Document
Control on Site.
5 of 11
Issued by Issue Date Document No.
8. REFERENCES
9. APPENDICES
6 of 11
Issued by Issue Date Document No.
9.0 Appendices
001 A 101
Drawing sheet No.
Building No.
A Architectural
S Structural
M Mechanical
E Electrical
CV Civil
7 of 11
Issued by Issue Date Document No.
CM-O/JE-YY00/000-X
CM : Letter originator
O : Secretary/typist Code
JE – Jeddah
KH – Al Khobar
MD – Madinah
MO - Morocco
MK – Makkah
RY – Riyadh
TA - Taif
8 of 11
Issued by Issue Date Document No.
TR/0000/JE-YY00
TR : Transmittal
TR/CS/JE-YY00
9 of 11
Issued by Issue Date Document No.
Submittals Files
1. Shop Drawings
2. Material Submittals
3. Sample Submittals
4. As-Built Drawings
5. O&M Manuals
10 of 11
Issued by Issue Date Document No.
Project Files
1. Contractor Incoming Correspondence
2. Outgoing Correspondence
3. Memos
4. Site Instructions
5. Inspection Requests
6. Site Surveys
7. QA & QC Reports
8. Non Conformance Reports
9. Reports (Daily, Weekly & Monthly)
10. Monthly Attendance Record Sheets
PHO/FHO Documents
1. Project Snags and Photos
2. Testing and Commissioning Data
3. PHO and FHO Certificates
4. Final As-Built Drawings
5. O&M Manuals
6. Test Certificates
7. Warranty Certificates
8. Spare Parts List
11 of 11
PROCEDURE
for
CUSTOMER SATISFACTION
Document No. CS-02-35 Revision A
Contents: 1. Purpose
2. Scope
3. Abbreviations & Definitions
4. Responsibilities
5. Flow Chart
6. Work Method
7. Verifying Method & Record Documents
8. References
9. Appendices
10. Document Status
Issued by Issue Date Document No.
1. PURPOSE
1.1. To describe the methods for measuring, monitoring and interpreting customer
perception information to determine whether SDC Construction Supervision
Department is meeting customer requirements.
1.2. To act as one of the measurements of the performance of the quality management
system to ensure the goals and targets of customer requirements and expectations
are met.
2. SCOPE
2.1. The scope of this procedure is to assess the level of customer satisfaction by
obtaining input from various sources defined later, and to increase the effectiveness
of activities and processes to provide added beneficial change in quality
performance to SDC and its customers.
2.2. Trends and key indicators of satisfaction will be identified and benchmarked
2 of 8
Issued by Issue Date Document No.
4. RESPONSIBILITIES
4.1. The SDC management is responsible for determining the appropriate measures,
methods and use for monitoring and measuring of customer satisfaction, for the
future vision of SDC organization.
4.2. The QMR is responsible for collecting and analyzing the data from the various sites
and reporting to the Top management of SDC. The records will be kept with the
QMR
4.3. The REs are responsible for reporting back to the Main Office (HOD & QMR) all
complaints raised by the Customer even if the complaints are verbal.
3 of 8
Issued by Issue Date Document No.
Required by
ISO 9001
No
Is
Customer
satisfied?
Yes No
Does this
satisfy the
customer?
Company
records
End
4 of 8
Issued by Issue Date Document No.
6. WORK METHOD
6.1. General:
Customer satisfaction measurement has a critical role in informing service
improvement.
Results focused – we establish goals, measure our performance and report our
success in achieving those goals
Innovative and creative – we learn from experience and results, and seek out new
and efficient ways to solve problems and serve, which help in furthering SDC’s
objectives
5 of 8
Issued by Issue Date Document No.
6 of 8
Issued by Issue Date Document No.
8. REFERENCES
8.1. Procedure CS-02-07: Site Document Control
8.2. Procedure CS-02-34: Archiving
8.3. QM-00-01: SDC Quality System Manual
8.4. Customer satisfaction survey
9. APPENDICES
9.1. F-CS55/A: Customer Satisfaction Survey
9.2. F-CS56/A: Customer Complaint log
9.3. F-CS64/A: Customer Verbal Complaint
7 of 8
Issued by Issue Date Document No.
8 of 8
Customer Satisfaction Survey - Supervision Department
Saudi Diyar Construction Supervision Department is committed to quality and customer satisfaction. We would like to know your opinion of our supervision
service, therefore please indicate your level of satisfaction with and the importance to you of each of the following aspects of our service.
On a scale of 1 to 5, circle the appropriate number that indicates how satisfied you are with each of the following items.
A score of 1 being very dissatisfied (VD) and 5 being very satisfied (VS).
On a scale of 1 to 5, circle the appropriate number that indicates the importance to you of each of the following items.
A score of 1 being very unimportant (VU) and 5 being very important (VI).
In the comments section after each question, please include reasons for your satisfaction or dissatisfaction with this item including specific examples where
possible.
Satisfaction Importance
Project Name: VD VS VU VI
Technical knowledge of SDC site staff 1 2 3 4 5 1 2 3 4 5
Comments:
Overall how satisfied are you with SDC Construction Supervision's performance 1 2 3 4 5
Comments:
Customer
Date Action By Close out
Complaint
Received Site Affected Customer Complaint Details Date
Reference
Rec'd Ret'd
F-CS 56/A
CUSTOMER VERBAL COMPLAINT
Details of Complaint:
By: Date:
Management Follow-up:
F-CS64/A