Professional Documents
Culture Documents
On The Concept of "Risk Analysis-Driven Design": G. Russo, P. Grasso and L. P. Verzani A. Cabañas
On The Concept of "Risk Analysis-Driven Design": G. Russo, P. Grasso and L. P. Verzani A. Cabañas
ABSTRACT: In the current tunneling practice, the Risk Analysis and the structural Design are
frequently considered two separate and independent items. On the contrary, according to the Geodata
Engineering (GDE) approach they are integrated in one unique rational process, completely
developed by probabilistic method, structuring the so-called “Risk Analysis-driven Design (RAdD)”.
The key points of this innovative approach are presented, with general reference to one of the most
recent application, in particular related to the construction of the tunnels to the new productive level
of the El Teniente mine (Chile). El Teniente Mine, with more than 2400 kilometers of tunnels
excavated is the largest underground copper mine in the world. The tunnel works for the new mine
level, located at 1000 m depth, are actually under construction, permitting to complete the design
process and check the foreseen geological-geomechanical scenarios.
In the current tunneling practice, the Risk El Teniente Mine, located in the Libertador
Analysis and the structural Design are General Bernardo O'Higgins Region 80 km
frequently considered two separate and southeast of Chile’s capital Santiago, is the
independent items. On the contrary, according largest underground copper mine in the world,
to the Geodata Engineering (GDE) approach with more than 2400 kilometers of mine drifts
they are integrated in one unique rational and tunnels producing more than 400000 tons
process, structuring the so-called “Risk per year of fine copper recovered from the ore,
Analysis-driven Design (RAdD)”. either as refined ingots or as copper cathodes.
In the Figure 1, the basic flowchart is As a result of ore processing, nearly 5000
remarked, showing as well as it is combined tons of molybdenum are recovered as a by-
with the Italian Guidelines for Design (SIG, product.
1997) to guarantee a complete treatment of all The owner of the mine, Codelco
the fundamental items. (Corporación Nacional del Cobre de Chile,
Recently, some key concepts of RAdD have División El Teniente), is currently developing
been also shared in the AFTES the New Mine Level Project to ensure the
Recommendations (2012). continuity of the exploitation and the increase of
In the present paper, a short insight in the ore production.
RAdD approach is presented, with particular The New Mine Level (NML) project, located
reference to some more recent practical at 1000m depth, is being planned to extend the
applications, developed by the collaboration life of the mine by 60 years, entering production
with Ingeroc (Santiago), mainly involving the phase in 2017. New reserves of 2020 million
access tunnels to the new production level of the tons at present with 0.86% average copper grade
El Teniente mine. and 220 ppm of molybdenum, will maintain the
mine's production at its 137000 tons/day.
1
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
2
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
In Figure 8, a simple example of the expected upon excavation and then the most probable
distributions of the GSI index for the three hazard is performed for each RMU by
scenarios is reported, as resulting by the necessarily taking into account both stress and
performed additional study. geostructural analyses, as shown in the flow
chart of Figure 10.
4
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Hazard identification
Primary risk Mitigation measures*
CATEGORY
Sub-category *or cross-reference to
D&B TBM
TYPE Hazard geomechanical hazard [→]
Sub-type Probab.
Impact Risk Impact Risk
[P] D&B TBM
HAZARD [I] [R=PxI] [I] [R=PxI]
M01,M02,M23 M01,M22,M2
B1 ROCK BLOCK FALL ( OVERBREAKS) 5 2 10 1 5
,M24 ,M24
M01,M02,M03 M01,M08,M2
B2 CAVING (FACE / CAVITY COLLAPSE) 4 3 12 2 8 ,M06,M07,M0 ,M24,M25,M2
8,M24 7
M1,M2,M21,M M01,M22,M2
B3 ROCKBURST 2 3 6 2 4
23,M26,M27 ,M26
M01,M02,M05
M01,M22,M2
B4 SQUEEZING, FACE EXTRUSION 2 3 6 4 8 ,M07,M21,M2
,M27
4,M25,M27
M01,M02,M06
M01,M08,M2
B5 FLOWING GROUND 5 5 25 5 25 ,M07,M08,M2
,M25,M27
4
M01,M02,M06
M01,M08,M2
B6 WATER INRUSH 5 5 25 5 25 ,M07,M08,M2
,M25,M27
Figure 12: Example of the probabilistic results of the 4
Consequently, the probability of occurrence B8 VISCOUS LOADS (fault zone, poor ground) 4 4 16 4 16 M27
of the different hazards are derived for the B9 SWELLING LOADS (fault zone, poor ground) 3 3 9 3 9 M24,M27
(fault zone)
..... .........
5
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
6
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
.... ....
.... ....
.... ....
Figure 18: Extract of definition of the support Section
R3) Other advancement related problems
Type according the logic remarked in Figure 16 (above)
R30 Low advancement rate
and resulting probability of occurrence for the different
scenarios (below). R31 TBM driving difficulty
.... ....
As remarked in the flowchart of Figure 1, an R4) General construction problems (not analysed)
7
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
grs,26.09.09
RMi rock supported chart for discontinuous ground* ros, 06.10.09
IG
N) fib
re
1x
1 .2
5x
1 .2
5
Numerical methods are used to verify the
re
ES
IA
LD 0m
m
inf
or
ce .5
final lining, as well as all the cases in which
Size ratio [Sr = (Dt/Vb1/3)*(Co/Nj)]
C 20 m
en x1
PE 1 .5
(S
15
0m
m t
1.5 anysotropy does not allow for the descrrbed
100
10
0m
m
2
2x
2
simplification intrinsic to the analythical
3x
3
method. In the case, the Point Estimated
Sh
m 3
0 m
Method (PEM, Rosenblueth, 1975) is used
ot
0 -2 5 60
cr
15 m
50m
e te
0 40m m
for probabilistic analysis.
th
0 -1 5
ic k
10 10
ONLY ROCK BOLT
00
ne
-1
70
ss
0
-7
50 50
(m
- 1.5
40
m)
.5
x1
1 .5 2 G
2 IN
Rock bolting 2x LT
BO
3 T
spacing (m) x3 S PO
1 3
0.60
0.40
ur [m]
0.20
0.00
0.0 4.0 8.0 12.0 16.0 20.0
pi/p0 [%]
8
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
4 Probabilistic time & cost progress and GDE provides with a specific team
estimation on site collaboration and technical support to
Codelco. This is evidently fundamental to
On the basis of the expected distribution of control and manage all the construction aspects
Section Types along the tunnels, the and check the effective advantages of the
probabilistic estimation of the construction time proposed approach.
and cost is finally developed, incorporating also Also in this challenging phase, the same
the estimated probability and impact of the basic concepts described in the previous
residual risk. sections are implemented.
In particular, the calculation involves the For example, the main hazards for the
probabilistic assessment of excavation are systematically checked during
the advancements of the tunnels, by very
the unitary cost of the Section Types; detailled face mapping and the concurrent
the relative advance rate; application of the “GDE Multiple graph”
the time & cost estimation of the residual risk (Russo, 2008, 2013).
(“accidents” in Figure 23) The GDE multiple graph is composed by 4
sectors (Figure 24), each of them finalized to a
user-friendly quantification of the following
engineering equations (proceeding clockwise
from the bottom-right quadrant to the top-right):
“wedge instability-rockfall” are in the case the Hoek E., Brown E.T. 1997. Practical estimates of rock
main type of hazards. mass strength. Submitted for publication to the Int. J.
Rock Mechanics & Mining Sciences.
Hoffmann J.S., Hammonds F.O. and Bartell S.M. 1994
An Introductory Guide to Uncertainty Analysis in
Environmental and Health Risk Assessment -Prepared
6 Conclusion for OAK RIDGE NATIONAL LABORATORY
Tennessee 37831-6285.
The main features of the Risk Analysis-driven ITA/AITES. 2004. Guidelines for tunnelling risk
management. International Tunnelling Association,
Design (RAdD) developed by Geodata Working Group No. 2. (Søren Degn Eskesen, Per
Engineering have been described. Tengborg, Jørgen Kampmann, Trine Holst Veicherts).
The key concept of RAdD is that the Design Tunnel. Underground Space Technol n. 19.
and the Risk Analysis are not two separate item, Kontrec P., Constandinidis V. 2013. Engineering
but a unique and fully probabilistic integrated geological characterization of the rock mass in the
Adit P4600, Project El Teniente, Chile, ITA
process. symposium Croatia, 7-8 May.
In each phase of the study, uncertainty and Palmström A. 2000. Recent developments in rock support
variability are adequately taken into account and estimates by the RMi. Journal of Rock Mechanics and
reliability analysis are consequently performed Tunnelling Tecnology, vol. 6.
to check the support system and lining. Rosenblueth E. 1975. Point Estimates for Probability
A practical application has been presented, Moments. Proceedings, Nat. Acad. Sci. USA 72 (10):
3812-3814.
with specific reference to the design and RussoG., Kalamaras G.S., Xu S, Grasso P. 1999.
construction of the tunnels to the new "Reliability analysis of tunnel support systems". Proc.
productive level of the El Teniente mine of the 9th ISRM Congress. Paris.
(Chile). Russo G. 2008. A simplified rational approach for the
preliminary assessment of the excavation behaviour in
rock tunneling. Tunnels et Ouvrages Souterrains n.
207.
REFERENCES Russo G. 2009. A new rational method for calculating the
GSI. Tunnelling an Underground Space Technology
AFTES 2012: Recommandation sur la caractérisation des n.24.
incertitudes et des risques géologiques, Russo G., Grasso P. 2007. On the classification of the
hydrogéologiques et géotechniques. Tunnels et Espace rock mass excavation behaviour tunneling.
Souterrain - n°232. Proceedings of the 11th Congress of International
Bieniawski Z. T. 1989. Engineering Rock Mass Society of Rock Mechanics, Lisbon, 9-13 July 2007.
Classification. John Wiley and Son. Russo G. 2013 (in press). An update of the “multiple
Carranza-Torres, C. 2004. Elasto-plastic solution of graph” approach for the preliminary assessment of the
tunnel problems using the generalized form of the excavation behaviour in rock tunneling. Tunnelling an
Hoek-Brown failure criterion. Int J Rock Mech Min Underground Space Technology n.41 (to be published
Sci. 4: supplement 1, 629-639. March 2014).
Decman A., Stella F., Verzani L. P. 2013. Geomechanical SIG 1997. Italian National Project for Design and
follow-up of El Teniente new mine level access Construction Standards in Underground Works,
tunnels, ITA symposium Croatia, 7-8 May. "Guidelines for Design, Tendering and Construction
Diederichs M. S. 2005: Design methodology for spalling of Underground Works". Gallerie e grandi Opere
failure and rockburst hazards. Summary of meeting Sotterranee, n.51.
with GEODATA SPA. Torino.
Diederichs M. S. 2007. Mechanistic interpretation and
practical application of damage and spalling
prediction criteria for deep tunnelling. Can. Geotech.
J., 44, 1082-1116.
Grasso P., Mahtab M. A., Kalamaras G., Einstein H.H.
2002. On the development of a Risk Management Plan
for Tunnelling. Proc. World Tunnel Congress.
Sydney.
Grasso P, Xu S., Pescara M, Russo G. and Repetto L.
2006. A methodology for the geotechnical design of
long high-speed rail tunnels under the conditions of
uncertainty ITA-sponsored 2006 China International
Symposium on High-Speed Railway Tunnels &
Exhibition 20-21 November 2006, Beijing, China.
Hoek E., Brown E. T. 1980. Underground excavations in
Rock. The Institution of Mining and Metallurgy,
London.
10