Professional Documents
Culture Documents
Sunflo P-2000 PUMPS: June, 2010
Sunflo P-2000 PUMPS: June, 2010
P-2000 PUMPS
June, 2010
14845 W. 64th Avenue • Arvada, Colorado 80007 USA • +1-303-425-0800 • FAX: +1-303-425-0896 • www.sundyne.com
Sundyne Europe • Longvic Cedex • France • 33-3-80-383300 • FAX: 33-3-80-383371
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means,
electronic, mechanical, photocopying, recording or otherwise without the prior permission of Sundyne Corporation.
© 2007 Sundyne Corporation.
Warranty
Sundyne Corporation warrants to Buyer for a period of twelve (12) months from the date of being placed in service (but not to exceed eighteen
(18) months after the date of shipment) that the equipment at the time of shipment will be free from defects of design, material and workmanship.
If any defects or malperformance occur during the warranty period, Sundyne’s sole obligation shall be limited to alteration, repair or replacement
at Sundyne’s expense, F.O.B. Factory, of parts or equipment, which upon return to Sundyne and upon Sundyne’s examination prove to be
defective. Equipment and accessories not manufactured by Sundyne are warranted only to the extent of and by the original manufacturers’
warranty. Sundyne shall not be liable for damage or wear to equipment caused by abnormal conditions, vibration, or failure to properly prime or
to operate equipment without flow or caused by corrosives, abrasives or foreign objects. THE FOREGOING WARRANTY IS EXCLUSIVE
AND IN LIEU OF ALL OTHER WARRANTIES, WHETHER EXPRESSED OR IMPLIED INCLUDING ANY WARRANTY OF
MERCHANTABILITY OR FITNESS FOR ANY PARTICULAR PURPOSE. In no event shall Sundyne be liable for consequential or incidental
damages.
i
SA-07-11-61, Rev Orig Jun 2010
Contents
Verifying Auxiliaries ........................ 12
Contents.............................................. ii Seal Environmental Control System12
Piping Connections......................... 12
INTRODUCTION.................................. 1
Gearbox............................................. 13
Sunflo Centrifugal Pumps ................. 1
START UP ......................................... 14
Text Symbols...................................... 1
Start Up Checklist ............................ 14
Equipment and Safety Precautions .. 2
Wearing Personal Protective
Equipment ........................................ 2 OPERATION & CONTROL................ 16
Using Forklifts................................... 2
Ensuring Electrical Safety................. 2 Operation of Sunflo Pumps............. 16
Testing Equipment............................ 2
Using Chemicals............................... 3 Control of Sunflo Pumps ................. 18
Protection from Falling...................... 3 Guide to Basic Control Methods for
Preventative Machine Guards .......... 3 Sunflo Pumps ................................. 18
EXPLOSION/FIRE HAZARD ............ 3 System 1. Single Pump with Throttle
Valve............................................... 18
System 2. Single Pump with Throttle
INSTALLATION ................................... 4 Valve and Controlled Bypass.......... 19
System 3. Two or More Pumps in
Inspection ........................................... 4 Parallel. Equipped with Individual
Control Valves ................................ 19
Storing Your Pump Short-Term ........ 4
INTRODUCTION
Sunflo Centrifugal Pumps
Sunflo pumps provide high-energy performance This manual presents installation, servicing,
and competitive efficiencies in an industrial troubleshooting, maintenance and spare parts
quality, compact unit that is simple to maintain. information for the latest configuration of Sunflo
Sunflo pumps are single stage that employ an centrifugal pumps.
integral gearbox. Designed to increase the
pressure of a continuous flow of fluid by applying Note: Parenthetical numbers included in the
centrifugal action, Sunflo pumps are most text correspond to item numbers on the
commonly used in general industry applications. illustrated figures. The correct spare
Commonly applied in power generation, reverse part can be ordered for any generation
osmosis, and washdown services. Sunflo pumps pump by referencing the item and serial
are used in high-head, low-to-medium flow numbers.
processes.
Text Symbols
The following symbols may be found in the text
RECOMMENDED: Text accompanied by
of this manual.
this symbol indicates recommended
They have the following meanings: usage.
WARNING: Text accompanied by this
symbol indicates that failure to follow
directions could result in bodily harm or REMINDER: Text accompanied by this
death. symbol indicates a reminder to perform
an action.
1
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
INSTALLATION
Inspection
Immediately inspect your Sunflo product upon shipment. Notify the carrier and Sundyne
receipt of the equipment. Check for any immediately if damage is evident.
damage, which may have occurred during
5
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
6
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
There are three seal arrangements available for Tandem Seal Liquid Buffer System
the P2000 pump; single seal, double seal, and
tandem seal. A liquid buffer system is used with tandem seal
arrangement to cool and lubricate the outboard
seal and to contain process fluid leakage from
Single Seal Flush System the inboard seal. The buffer fluid must be cool,
A seal flush system is available for use with the clean, and compatible with the process fluid and
single seal arrangement when the process fluid pump materials of construction. The buffer
is contaminated with solid particles or if the liquid is introduced into the “buffer in” port of the
pump fluid temperature dictates the need to seal housing at atmospheric pressure and must
flush. A clean, cool fluid from an external source maintain a flow of 0.5 to 3.0 gpm / 0.10 to
is introduced into the seal flush port at 15 0.70 m3/hr through the buffer cavity to properly
psi/103.4 kPa above seal cavity pressure and at lubricate and cool the outboard (secondary)
a controlled flow of 0.5 to 2.0 gpm / 0.11 to seal.
0.45 m3/hr. This allows only clean fluid at the
seal face minimizing seal deterioration.
Gearbox and Process Seal Drain
Note: Seal flush port must be plugged if not in
use. As a standard, the seal drain chamber has three
oblong openings. If optional configuration with
NPT drain ports is used, ensure all shipping
Double Seal Liquid Buffer System plugs have been removed.
A liquid buffer system is used with double liquid
seals to prevent process liquid leakage out of Seal Cavity Pressure Rise
the pump. The buffer must be cool, clean and
Whenever a single seal with an external flush,
compatible with the process fluid and pump
double seal, or tandem seal arrangement is
metallurgy. The buffer is introduced into the
used, the seal cavity pressure rise must be
“buffer in” port at a pressure 15 psi /103.4 kPa
known to determine the seal flush pressure or
higher than the seal cavity pressure. A buffer
buffer pressure. The area behind the impeller,
flow of 0.5 to 3.0 gpm / 0.11 to 0.68 m3/hr must
near the seal, is referred to as the seal cavity.
be maintained through the buffer cavity. The
Suction pressure plus the seal cavity pressure
flow should be regulated by a valve or orifice on
rise plus a safety margin of 15 psi/103.4 kPa
the “buffer out” port.
equals the required double seal buffer pressure
or the single seal flush pressure. For tandem
Note: The buffer system must be in operation seals, the buffer pressure should be 1.3 psi/8.96
prior to flooding the pump casing. kPa minimum or a maximum of 30 psi/206.8 kPa
below seal cavity pressure.
The required seal flush/buffer pressure may be determined for your pump by using the appropriate values
in the Seal Cavity Pressure Rise Tables and the method provided below:
1. Find the pump model which is applicable to your pump.
2. Determine the seal cavity pressure rise (based on water with a specific gravity of 1.0).
3. Multiply the seal cavity pressure rise by the specific gravity of the process fluid.
4. Specify the seal flush/buffer pressure to equal the sum of the suction pressure, the specific gravity
corrected seal cavity pressure rise determined in Step 3 above and the safety margin of
15 psi.
5. Seal cavity pressure rise values shown in Table 1 are for minimum flow (first value) followed by
B.E.P. flow (second value).
EXAMPLE
8
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
P2-AJN 12/5 P2-BJN 35/28 P2-CJN 41/20 P2-DJN 32/16 P2-EJN 38/15 P2-FJN 58/18 P2-GJN 120/70
P2-AHP 12/5 P2-BHP 35/28 P2-CHP 41/20 P2-DHP 32/16 P2-EHP 38/15 P2-FHP 58/18 P2-GHP 120/70
P2-AFQ 12/5 P2-BFQ 35/28 P2-CFQ 41/20 P2-DFQ 32/16 P2-EFQ 38/15 P2-FFQ 58/18 P2-GFQ 120/70
P2-AER 12/5 P2-BER 35/28 P2-CER 41/20 P2-DER 32/16 P2-EER 38/15 P2-FER 58/18 P2-GER 120/70
P2-ABS 12/5 P2-BBS 35/28 P2-CBS 41/20 P2-DBS 32/16 P2-EBS 38/15 P2-FBS 58/18 P2-GBS 120/70
P2-AAT 12/5 P2-BAT 35/28 P2-CAT 41/20 P2-DAT 32/16 P2-EAT 38/15 P2-FAT 58/18 P2-GAT 120/70
P2-AAU 14/10 P2-BAU 40/30 P2-CAU 24/15 P2-DAU 35/20 P2-EAU 42/18 P2-FAU 64/22 P2-GAU 125/75
Table 1
9
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Mounting
During pump installation, ensure that adequate Grout should be of a consistency to flow out
surrounding space is available for inspection, under the bedplate against the wood dam.
operation, and maintenance requirements. Grout should be puddled continuously as it
is poured to expel air and to completely fill
The pump and driver for both the close-coupled
the space under the bedplate. Fill to the
and the frame mounted units should be bolted to
level of the grout hole.
a concrete foundation or an adequately
supported structure substantial enough to 9. Allow the grout to harden for at least 48
absorb any vibration and to form a rigid support. hours. Tighten the anchor bolts.
If the pump and driver are mounted on a
bedplate, the bedplate should be mounted on a Note: Piping must not be connected to the
concrete foundation and grouted. pump until after pump hold-down bolts
have been tightened.
1. Choose a solid ground location and build the
foundation form 3 inches larger overall than
the bedplate. Figure 2. Bedplate Installation
2. Use bedplate anchor bolts of the same size
specified in the outline drawing. Provide
pipe sleeves with an I.D. 2.5 to 3.0 times the
bolt diameter. Provide flat washers between
the bolt head and pipe sleeve to keep the
bolt from slipping through the pipe sleeve.
See Figure 2.
3. Bolts should be of sufficient length so that
they will project at least one-fourth inch
above the nuts after allowing for bedplate,
shim and nut thickness. Locate the bolts
accurately according to the outline drawing. Frame Mount Drive Unit Installation
4. Pour concrete and tamp or vibrate during Pumps supplied from the factory with a driver,
the pouring process to ensure no hollow base, and coupling are rough aligned prior to
spots form. This is especially important shipment. However, stresses caused by lifting
around the anchor bolts. Do not allow any and shipment may cause minor distortion which
concrete to fall inside the pipe sleeves. will alter the factory alignment. Check the
5. Level off the concrete surface. Leave a coupling alignment after the baseplate has been
rough finish to provide a good base for leveled and prior to grouting.
grout. Allow the foundation to cure for one If the coupling alignment has been disturbed by
week before installing equipment. improper leveling of the baseplate, correct prior
6. Hoist the bedplate above the foundation and to grouting. After the base has been grouted
lower into position over the anchor bolts. and the piping connected, make a final pre-
Anchor bolts can be moved laterally in the startup alignment check. Additionally, a hot
hollow of pipe sleeve for ease of alignment alignment check should be made once the pump
with the holes in the bedplate. has reached normal operating temperature.
7. Using a precision level across the bedplate Coupling alignment should be verified only after
(front to rear and side to side), insert steel the suction and discharge piping has been
shims as required next to each bolt until the connected.
bedplate is level in all directions. Secure the Note: If a coupling is being used that was not
anchor bolt nuts finger tight only. supplied by Sundyne, it must be a
8. Provide a wood dam around the base flexible type, vibration damping
perimeter of the bedplate and thoroughly coupling. Refer to the coupling
wet the top surface of the foundation. The manufacturer’s recommendations for
use of non-shrink grout is recommended. installation and alignment.
10
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
11
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Pre-Commission Checklist
Driver
Ensure all installation and starting
instructions provided by the driver
manufacturer have been followed. (This
information is included in the final data
package.)
If the driver is coupled, un-couple; then
verify that the direction of the driver
rotates in the same direction as the
arrow stamped or cast on the gearbox.
Verifying Auxiliaries
Before start up, verify that the following
auxiliaries are met:
Check the utility connections
Verify that the auxiliary piping conforms
to Sundyne standards, as indicated in
the detailed specifications
Verify all switch and instrument
connections
Verify that all switch and instrument
settings are set to normal operating
standards
Calibrate all measurement equipment,
such as flow meters, ampere meters,
and pressure meters, etc.
12
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Gearbox
Any oil used in Sunflo gearboxes must meet the Remove the fill/vent plug (P2-8) and fill the
lube oil specifications in table 6. gearbox until fluid reaches the designated level
on the sight glass. Replace gearbox fill plug.
In general, ISO VG 32 turbine oils and ISO VG
32 synthetic oils will meet the specifications in Oil Capacity:
table 6. The properties of the oil should be 2 quarts / 1.9 liters for aluminum gearbox
verified with the oil manufacturer prior to use. 2.2 quarts / 2.1 liters for steel gearbox
The following lubricants (or equivalent
lubricants) are recommended for use in Sunflo Note: Overfilling the gearbox will cause seal
gearboxes: leakage, excess foaming and excessive
use of horsepower.
Mobil SHC 624 or Mobil DTE Oil Light
Note: Dextron III type ATF is not recommended Make up oil can be added through the fill/vent
for use in Sunflo gearboxes. Problems port during operation if required.
with foaming may occur and the
additional additives could compromise the Note: The oil in the gearbox should be
mechanical integrity and reliability of your changed every six months or 4000
Sunflo pump. hours.
13
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
START UP
Start Up Checklist
Perform the following steps to start the Sunflo direction as the arrow on the gearbox
pump: housing marked “PUMP ROTATION”.
Review pump specification sheet noting Note: Three-phase motor rotation may be
design parameters and possible seal reversed by interchanging any two
system requirements. motor leads. Motor and pump rotate in
Check to ensure that the driver has been opposite directions due to the single
serviced per instructions provided by the step gear arrangement.
driver manufacturer.
Check to ensure temporary suction screen Note: Reverse rotation may cause damage to
has been installed on inlet side for initial the pump.
start-up (35-40 mesh recommended). On startup or after gearbox assembly, the
Double Seal Configurations: If buffer motor should be jogged once or twice and
fluid or external seal flush is required, this oil circulation should be seen in the sight
system should be pressurized prior to glass.
admitting process fluid into the pump
Note: During startup, pay close attention to
casing. If the buffer fluid is not pressurized,
the discharge pressure gauge. The
process fluid will contaminate the buffer
pressure should rise quickly and remain
fluid. If the seal flush is not pressurized,
steady. If the pressure rise is sluggish
contaminants may cause seal face
and drops back to a lower level, stop
damage.
the pump. The erratic pressure
Check oil level in gearbox. behavior is a sign that air and/or vapors
are being purged from the pump.
Open suction and discharge block valves
fully. If there is a check valve in the Start the driver. Adjust the control valve to
discharge piping, ensure that the space the desired flow and check the head, flow,
between the pump and check valve is and motor horsepower against the
vented. anticipated conditions.
Note: Never start or run the pump against a
closed discharge valve. Note: Do not overload the pump or motor (an
Purge or vent all high points in the suction ammeter is recommended to determine
and discharge lines. motor load).
After the suction is flooded, adjust the Continually check the pressure drop
control valve to approximately 25% open. across the suction strainer. Never allow
This is necessary to prevent overloading of the suction pressure to drop below the
the driver and to prevent the pump from minimum design pressure that would
operating off the end of the curve at ensure adequate NPSHr. This minimum
startup. suction pressure should be established
before commissioning. A 35-40 mesh
Insure that the motor shaft rotation is in the strainer is recommended to be installed in
same direction as the arrow on the gearbox a new piping system to collect any debris
marked “MOTOR ROTATION”. To that could damage the pump or
determine shaft rotation, observe the motor mechanical seals.
shaft or fan while “jogging” the motor in
short, one-second intervals. Rotation of the
high-speed shaft must be in the same
14
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
When the pressure drop across the to clog up. If no new debris shows up for
strainer increases, the temporary screen is a reasonable period of time the temporary
becoming clogged with particles and must strainer and pressure gauge can be
be cleaned out. The pump should be removed.
shutdown and the discharge and suction
If the temporary strainer keeps clogging
valves blocked in to isolate the pump and
up at a relatively steady pace and the
screen. After the strainer has been
clogging material is process oriented
cleaned and reinstalled, the pump must be
particles, such as undissolved crystals,
primed just as during the initial start up.
“high boiler” compounds or other entrained
Examine the debris and/or particles particles which are expected to continue
removed from the strainer each time it is forming in the pumpage at about the same
cleaned. Hopefully, the strainer contents constant rate, some permanent
will be matter foreign to the process and it modification in the pumping system may
will take longer and longer for the strainer be required.
15
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
D. As the pump is operated closer to BEP, the have exactly the same performance, the
Sunflo pump performance curve provides a curves in Figure 5 show that pump A
more responsive change in flow for a given produces slightly more head than pump B.
change in pressure. Either pressure or flow The pumps arranged with a manifold having
control of the Sunflo pump is suitable in this a common control valve are as shown in
area. However, flow control is still Figure 6.
recommended because of the problems
With the manifold pressure set at P1, the
associated with pressure control that were
flow through pump A is indicated as A1 and
discussed in the previous paragraph.
the flow through pump B is indicated as B1.
E. In the portion of the performance curve If the throttle valve is closed to set the
beyond BEP, the Sunflo pump performance manifold pressure at P2, the flow through
curve shape provides for small changes in pumps A and B are A2 and B2 respectively.
flow for large changes in pressure. If the control valve were closed even further,
Operation in this portion of the performance then pump B would cease to flow entirely
curve is discouraged because of control resulting in damage for deadheading the
problems and the potential to exceed the unit. This situation can be avoided through
driver capabilities and to exceed the NPSH the proper selection of the control system.
requirements.
Figure 6
F. If the user requires that the pump is
operated on pressure control, contact Sunflo
or your local sales representative. It is
possible to modify the pump to steepen the
pump performance curve with a discharge
orifice so that pressure control is more
practical.
Parallel Operation
G. When centrifugal pumps are operated in
parallel, their control becomes more critical
because one pump may tend to “overpower”
the other pump in terms of head at total
H. The best way of ensuring that one of the
lower flows. If pumps are connected
pumps in a parallel pump system is not
together at discharge by a simple,
deadheaded is to provide a separate control
unrestricted manifold, the discharge head of
valve for each pump as shown in Figure 7.
one pump is upon another; all pumps see
Sunflo also recommends that individual
the same discharge head at any given
minimum flow lines be installed for each
moment in time. This situation is shown in
pump operated in parallel.
Figure 5.
Figure 7
Figure 5
Series Operation
Figure 5 shows the characteristic curves of I. Series pump operation is not suggested due
two duplicated pumps designated as pump to possible high suction pressure on the
A and pump B. Since no two pumps will second pump.
17
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Guide to Basic Control Methods for Note: Because of the flat performance curve,
Sunflo Pumps do not use a pressure relief valve to
control the pump flow and pressure.
This portion of the manual covers the most
common control systems for Sunflo pumps.
Consult the factory for advice on unusual
systems not covered.
18
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
System 2. Single Pump with Throttle Valve System 3. Two or More Pumps in Parallel.
and Controlled Bypass Equipped with Individual Control Valves
This system should be used if a lower minimum
flow than can be reached with System 1 is This arrangement is a multiple pump version of
required, or where the pump must start against a the Control System 1. A separate throttle valve
high back pressure. The bypass will maintain is installed at each pump discharge to allow
minimum flow until the pump can establish flow each pump to be throttled to approximately the
through the system. Refer to Figure 9. same flow rate. This must be done to prevent
one pump from taking the entire load and
(1) The throttle control valve must be “deadheading” the other. Refer to Figure 10.
adjusted to keep the total pump flow
above the minimum value as per Pump loads can be balanced by monitoring
System 1, thereby realizing less system current drag to each motor or by individual pump
flow. flow measurements.
(2) A heat exchanger may be required for Because of the relatively small change in
return to supply tank or suction pressure at different flow rates, balancing by
depending on the pipeline distance, size pressure readings is not recommended.
of the tank, allowable rise, temperature,
Figure 10. System 3
etc.
Figure 9. System 2
19
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
MAINTENANCE
Disassembly of the Sunflo P-2000
STEP 1 STEP 3
Disconnect all electrical power and insure Pull out the high-speed shaft assembly
pump casing and piping have been (P2-9).
depressurized. Remove suction and
discharge piping.
20
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
STEP 7
Using a gear puller, remove drive gear (P2-3).
STEP 5
Lift out gearbox shroud. (P2-16).
STEP 8
STEP 6 Remove the drive key (P2-5). Use a puller to
Remove driver gearbox bolt (P2-62) and remove the baffle sleeve (P2-45).
washer (P2-63), using a 9/16” socket wrench.
STEP 9
Remove gearbox baffle (P2-44).
21
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Step 10 to 14 – For Frame Mounts Only STEP 12
STEP 13
STEP 11 Using snap ring pliers, remove the shaft
Using a gear puller, remove the drive gear retaining ring (P2-114).
(P2-3).
STEP 14
Note: Do not allow puller to bear directly on Using a soft mallet, gently tap on the driver
gear teeth. end of the shaft and remove the shaft and
bearing assembly from the frame mount
Note: To install the drive gear, heat to 250°F (P2-100).
(121°C), not over 300°F (149°C) in an
enclosed oven for approximately 1
hour. Be sure to wear suitable heat
insulated gloves for hand protection.
22
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
23
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
STEP 1 STEP 3
Remove the impeller nut (P2-69) or inducer Remove the inboard seal rotating face
(P2-57). (P2-25).
STEP 2
Remove the impeller (P2-33), diffuser plate
(P2-31), impeller key (P2-65), impeller stud
(P2-102), and o-ring (P2-20).
24
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
STEP 5 STEP 7
Remove the o-ring (P2-117) and shaft sleeve To remove the mechanical seal (P2-77,
(P2-22) from the high-speed shaft. P2-30), tap the seal retainer lightly using a
drift punch and light hammer.
STEP 6
Remove the gearbox seal rotating face
(P2-25) from the high-speed shaft.
25
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
TROUBLESHOOTING
Gearbox and Pump Diagnostics
Several system factors may affect the These factors as well as internal problems must
performance of the pump. These factors are: be considered when analyzing pump system
performance. The following table gives
• Temperature diagnostic information that can be useful when
• Specific gravity analyzing gearbox and pump performance
problems.
• Suction pressure
• Driver speed
• Flow rate and control characteristic
26
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
27
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
28
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
29
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
30
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
31
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
SPECIFICATIONS
Torque Values
ft – lbs N-m
Note: When using PTFE o-rings, allow 15 minutes between repeated torquing for the PTFE to cold
flow. Repeat until there is no change in torque value.
32
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
EP Additive....................................................................................................................................................... Present
33
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
DRAWINGS
Figure 12. Servicing Checkpoints
34
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Note: Recommendation - Entire high-speed shaft assembly P2-9 is available. To avoid costly
downtime, keep a spare assembly in your stock.
Table 7. Pump and Gearbox
Item Part Name Qty. Item Part Name Qty.
No. No.
P2-1 Flat Washer 4 P2-45 Baffle Sleeve 1
P2-2 Hex Nut 4 P2-46 Lock Washer 4
P2-3 Drive Gear 1 P2-50 Gearbox Housing Assembly 1
P2-4 Motor Shaft 1 P2-8 • Fill and Vent Fitting 1
P2-5 Drive Gear Key 1 P2-10 • Sight Glass 1
P2-7 Oil Shroud Gasket 1 P2-11 • Sight Glass Gasket 2
P2-9 High Speed Shaft Assembly 1* P2-12 • Sight Glass Retainer 1
(Refer to Figures 14, 16, and 18) P2-13 • Self Tapping Screw 2
P2-16 Gearbox Oil Shroud 1 P2-14 • Square Head Pipe Plug 1
P2-17 Hex Head Cap Screw 4 P2-15 • Gearbox Housing 1
P2-32 Pump Casing 1 P2-62 Hex Head Screw 1
P2-42 Hex Head Cap Screw 4 P2-63 Lock Washer 1
P2-43 Lock Washer 4 P2-64 Flat Washer 1
P2-44 Gearbox Baffle 1 P2-121 Gearbox Gasket 1*
35
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
*Recommended spare parts per unit
36
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
37
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
38
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
39
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Table 12. High-Speed Shaft Assembly, Tandem Seal with Gearbox Lip Seal
Item Part Name Qty. Item Part Name Qty.
No. No.
P2-18 O-ring, Impeller 1 P2-53 Seal Housing Assembly 1
P2-20 O-ring, Seal Housing./Pump Case 1 P2-36 • Seal Housing 1
P2-23 Ball Bearing (Outboard) 1 P2-54 • Retaining Ring 1
P2-25 Seal Rotating Face 3 P2-55 • Flat Washer 1
P2-28 O-ring/Seal Housing 3 P2-56 • Wavy Washer 1
P2-29 Pipe Plug 2 P2-57 Inducer 1
P2-30 Gearbox Mechanical Seal 1 P2-58 O-ring, Inducer 1
P2-31 Diffuser Plate 1 P2-65 Impeller Key 1
P2-33 Impeller 1 P2-77 Pump Mechanical Seal 2
P2-34 Shaft Sleeve 1 P2-89 Retaining Ring 2
P2-36 Seal Housing 1 P2-102 Stud 1
P2-37 Ball Bearing (Inboard) 1 P2-117 O-ring, Sleeve 3
P2-38 Pinion Shaft 1 P2-148 O-ring, Seal Housing/Gearbox 1
P2-40 Shaft Sleeve 1
40
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
41
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
Note: Recommendation: The shaft and bearings are available as an assembly (P2-97). To minimize
downtime, keep a spare assembly in your stock.
Table 14. Frame Mount Assembly
Item No. Part Name Qty.
P2-95 Ball Bearings 2*
P2-96 Input Shaft 1
P2-97 Shaft and Bearing Assembly 1*
P2-99 Key 1*
P2-100 Mounting Frame 1
P2-114 Retaining Ring 1
P2-116 Slinger
P2-127 Drive Gear Key
*Recommended spare parts per unit.
42
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
43
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
SPARE PARTS
When ordering replacement parts, provide the
pump serial number, and list each part required Exchange High Speed Shaft
by item number and part name along with Assemblies
quantities desired. When requesting information
concerning your Sunflo Pump, always refer to • Easier to perform routine seal and
the pump model number and pump serial bearing maintenance
number as they appear on the nameplate. • Normal delivery is two weeks
All Sunflo products are available on an • Same quality construction, testing and
expedited basis. The factory should be warranty as new shaft assemblies
contacted prior to order placement to ensure
part availability. Stock spare parts requiring no • Can ship on an expedited three-day
machining will be shipped 24 hours after receipt basis when needed. Old shaft assembly
of order at the factory and parts requiring can be returned for credit within 60
additional machining will be shipped within 96 days.
hours after receipt of order at the factory.
Note: A highly recommended option to normal
The kits shown below simplify maintenance and pump maintenance is the purchase of a
inventory control. They are available through spare high-speed shaft assembly which
your Sunflo distributor. can be replaced quickly and easily as a
complete unit.
O-Ring Repair Kits
• Packages all o-rings in one kit Ordering Replacement Parts
Order parts through your Sunflo distributor. For
• Color coded o-ring material
information or assistance contact:
• Easy-to-read instructions describe exact
location of each o-ring
Sundyne Corporation
14845 W. 64th Avenue
Seal Repair Kits Arvada, Colorado 80007
• Custom tailored for the specific pump Telephone: 303-425-0800
and seal type Fax: 303-425-0896
• Single and double seal options Attention: Parts Order Coordinator
www.sundyne.com
• Easy-to-read instructions prevent
installation mistakes
or
• Eliminates misplacement of parts and
simplifies inventory control Sundyne Europe
13-15 Blvd. Eiffel
Zone Industrielle de Dijon SUD (21600)
BP30
21600 Longvic Cedex, France
Telephone: 011-33-3-80-383300
Fax: 011-33-3-80-383371
44
SA-07-11-61, Rev Orig Jun 2010
Instruction and Operation Manual
INDEX
Assembly of the Sunflo P-2000, 23 Operation of Sunflo Pumps, 16
Auxiliaries, 12 Ordering Replacement Parts, 44
Chemical Use, 3 O-Ring Repair Kits, 44
Control of Sunflo Pumps, 18 Personal Protective Equipment, 2
Disassembly of the High-Speed Shaft, 24 Piping Connections, 12
Disassembly of the Sunflo P-2000, 20 Pre-Commission Checklist, 12
Double Seal Cross Section, 39 Preventative Machine Guards, 3
Double Seal Liquid Buffer System, 7 Pump and Gearbox, 35
DRAWINGS, 34 Pump Mechanical Seal Diagnostics, 30
Driver, 12 Seal Cavity Pressure Rise, 7
Electrical Safety, 2 Seal Environmental Control System, 12
Equipment and Safety Precautions, 2 Seal Environmental Control System, 6
Exchange High Speed Shaft Assemblies, 44 Seal Repair Kits, 44
Explosion/Fire Hazard, 3 Servicing Checkpoints, 34
Fall Protection, 3 Single Pump with Throttle Valve, 18
Final Alignment, 11 Single Pump with Throttle Valve and
Flange and Hardware, 43 Controlled Bypass, 19
Frame Mount Assembly, 42 Single Seal Cross Section, 37
Frame Mount Drive Unit Installation, 10 Single Seal Flush System, 7
Gearbox, 13 SPARE PARTS, 44
Gearbox and Process Seal Drain, 7 SPECIFICATIONS, 32
Gearbox and Pump Diagnostics, 26 START UP, 14
Gearbox Lube Oil Specifications, 33 Start Up Checklist, 14
Guide to Basic Control Methods for Sunflo Storing Your Pump Long-Term, 4
Pumps, 18 Storing Your Pump Short-Term, 4
High-Speed Shaft Assembly, Double Seal, Suction and Discharge Piping, 5
38 Sunflo Centrifugal Pumps, 1
High-Speed Shaft Assembly, Single Seal, 36 Tandem Seal Liquid Buffer System, 7
Inspection, 4 Testing Equipment, 2
INSTALLATION, 4 Text Symbols, 1
INTRODUCTION, 1 Torque Values, 32
ISO 9001, 2 TROUBLESHOOTING, 26
Machine Familiarization, 12 Two or More Pumps in Parallel. Equipped
MAINTENANCE, 20 with Individual Control Valves, 19
Mounting, 10 Using Forklifts, 2
OPERATION & CONTROL, 16
45
SA-07-11-61, Rev Orig Jun 2010
SUNFLO
14845 W. 64th Avenue • Arvada, Colorado 80007 USA • +1-303-425-0800 • FAX: +1-303-425-0896 • www.sundyne.com
Sundyne Europe • Longvic Cedex • France • 011-33-3-80-383300 • FAX: 011-33-3-80-383371