ESTMATES Beam – 2

FOUNDATION (F1) Size: 0.35 x 0.50 x 115.50

Size: 2.10 x 2.10 x 0.30 Total volume = 20.21 cu.m

Total No. = 12 #bags – 182 bags

Total Volume: 15.88 cu.m Sand = 10.20

No. of Cement – 143 bags Gravel = 20.30 cu.m

Sand – 8 cu.m Beam- 3

Gravel – 15.90 cu.m Size: 0.25 x 0.40 x 2

C2F1 Total Vol. =0.20 cu.m

Size: 0.50 x 0.50 #bags =2 bags

Total no. =12 Sand = 0.10 cu.m

Total volume = 21.6 cu.m Gravel = 0.20 cu.m

# bags = 195 bags Roof beam

Sand = 10.8 cu.m Size: 0.20 x 0.40 x 53.5

Gravel = 21.6 cu.m Total volume = 4.28 cu.m

C1F1 #bags =39 bags

Size: 0.40 x 0.40 x 3.80 Sand =2 cu.m

Total No. = 12 Gravel = 4.30 cu.m

Total Volume = 7.30 cu.m

#bags = 66 bags OVERALL TOTAL (Footing, Columns, Beams)

Sand = 3.70 cu.m VOLUME = 78.83 CU.M

Gravel = 7.30 cu.m NO. OF BAGS = 712 BAGS (40kg)

SAND = 39.5 CU.M

Tie beam GRAVEL = 79 CU. M

Size: 0.35 x 0.50 x 53.50

Total Vol. = 9.36

#bags = 85 bags

Sand = 4.70 cu.m

Gravel = 9.40 cu. m


REBARS

FOUNDATION

4-20mmx6m @ 200mm hook both sides / F1

20MM dia. x 6m = 48 pcs for 12 units footing

Column

C1F1 & C2F1

8-20mm x 6m

@12.8 m height , 800mm development legth,


1m splicing - 12.8/6m = 2.13 pcs x 8 bars =
17.06pcs per column

Total Column = 12 units

Total bars = 205pcs – 20mm x 6m