Professional Documents
Culture Documents
Chapter 6
Chapter 6
BUILD UP RATE
METHOD
Introduction
a. Material cost
b. Labour cost
c. Plant and machineries cost
d. Management cost
e. Profit and overhead
Material Cost
b. Transportation cost
c. Storage cost
a. Skilled labour
c. Unskilled labour
Unskilled labour is needed for simple works such as cleaning the site,
transporting the materials and so on. Normally their wages can be RM
50.00 to RM 65.00 per day.
Plant and machinery cost
A contractor will use many plant and machineries for complete their works on construction site. It
is use for save time and energy. It will be divided on two categories which are:
Manually
It is a basic tool in carpentry work. Normally, owned by the contractor. Example - an example
no mechanical plant is ladders, carts, hand tools, baskets, buckets and so on.
Mechanical plant
To use the plant or mechanical equipment, contractor shall provide a capital to buy or rent.
Therefore the capital should be include in built up rate with all related price such as the rent or
buy the equipment include the workers who operate the equipment.
The types of mechanical equipment such as trucks, bulldozers, concrete mixer, concrete vibrator,
compactor and so on. Mechanical equipment whether leased or purchased by the contractor
depends on the financial position or needs-based contractor, either continuously or sporadically.
Schedule of Rates
Variation
Management Cost
Management cost is calculated as percent of the cost of materials, labour and plant of between
five to ten percent. Valuation per cent management cost is calculated by dividing the reversal of
money of the year by the total management cost.
Say, reversal money for a year is RM 1,000,000.00. The management cost is RM 50,000.00.
= RM 50,000.00 x 100%
RM 1,000,000.00
= 5%
18
Profit Rate
Profit rate calculated by percent from all material cost, labour and plant. Profit calculated is
gross profit ( gross profit ).
Gross profit consisting of:
Nett profit
Overhead
Overhead
Profit rate calculated by percent from all material cost, labour and
plant. Profit calculated is gross profit ( gross profit ).
Gross profit consisting of:
▪ Nett profit
▪ Overhead
Profit Rate
Using small equipment like hoe, spade and bucket. Suitable for small
quantity .
The matter that should be taken into consideration when build up rate concrete work are as
follows :
4m3 aggregate
2m3 sand
1m3 cement
Cont…
c. Concrete mixture also will be wastage when lift and pour to particular
place .
Example
1. Material cost
Calculation of concrete material mixture price (1:2:4-19mm aggregate)
To calculate the labour cost, thus need to know the labour constant for work.
a. Mixing concrete with hand, bring and lift if needed = 4.00 hour/m3
b. Filling the concrete into pad foundation at 50.0m distance = 1.31 hour/m3
c. Vibrate the concrete around reinforcement = 0.65 hour/m3
d. Levelling the concrete = 0.09 hour/m3
Labour cost can get by multiplying the labour constant with labour wage rate for one
hour.
Example of labour cost calculation
1. Material cost
2. Machinery cost
3. Labour Cost
Build up rate for concrete mixer machinery
Example
A. Capital cost
Cont…
Cont…
Cont…
a. Material
b. Labour wage
c. Profit and management
Material used to build a brick wall
a. Brick
▪ Standard size for brick is 213mm length x 102.5mm width and 65mm thick
▪ Brick price calculated according to unit or number.
▪ Total brick in a square metre depend on size and bond type.
cont….
Usually, brick bound using 10mm vertical and
horizontal mortar.
Length Thick
Height
Brick measure 215mm 65mm
225mm 75mm
Length
Cont….
b. Mortar
Cont..
Bil Work Description Bricklayer Labour Mortar Num of
(hour) (hour) (m3) Brick
1 230mm thick brick wall 2 2/5 1 1/5 0.05 118
Example of Labour constant and material used for 1 meter square brick wall
45
Example Question
Answer
1. Material cost
a. Brick
60 brick @ RM 0.18 = RM 10.80
b. Mortar
0.03 m3 @ RM140.45 = RM 4.21
Total material cost = RM 15.01
48
Cont…
2. Labour cost
Bricklayer = 1 ½ hour @ RM 4.00 = RM 6.00
Labour = 9/10 hour@RM 2.75 = RM 2.48
RM 8.48
Cost of Brick Work = Material cost + Labour cost
= RM 15.01 + RM 8.48
= RM 23.49
49
Cont…
Exercise Question
Cont…
Data Given: 230mm thick brickwall Data Given: 115mm thick brickwall
Number of brick =118 Number of brick =60
Brick price = RM 0.25 Brick price = RM 0.25
Mortar = 0.05m3 Mortar = 0.03m3
Mortar price = RM140/m3 Mortar price = RM 140/m3
Labour constant Labour constant
Bricklayer = 2 2/5 hour Bricklayer = 1 ½ hour
Labour = 1 1/5 hour Labour = 9/10 hour
Wages Wages
Bricklayer wage = RM 10.00/hour Bricklayer wage = RM 10.00/hour
Labour wage = RM 5.00/hour Labour wage = RM 5.00/hour
Profit & management = 15% Profit & management = 15%
52
Answer
1. 230mm thick brick wall area Profit & management (15%)
2.438m x 1.219m = 2.97m2 15/100 x RM 66.50 = RM 9.98
3.048m x 1.219m = 3.72m2 Cost 1m2 = RM 76.48
2(2.896m x 1.219m) = 7.06m2
= 13.75m2
Construction cost for 230mm thick
2. 115mm thick brick wall area
brick wall = 13.75m2 x RM 76.48
0.762m2 x 1.219m = 0.93m2
= RM 1,051.60
3. Cost for 1m2 230mm brick work
Material: Brick=118 x RM 0.25 = RM 29.50
Mortar= 0.05 x RM140.00 = RM 7.00
Labour: Craftmen = 2 2/5 x RM 10.00= RM24.00
Labour = 1 1/5 x RM 5.00 = RM 6.00
RM 66.50
53
Cont…
4. Cost for 1m2 115mm brick work Profit & management (15%)
Material: Brick=60 x RM 0.25 = RM 15.00 15/100 x RM 38.70 = RM 5.81
Mortar= 0.03 x RM140.00 = RM 4.20 Cost 1m2 = RM 44.51
Labour: Craftmen = 1 1/2 x RM 10.00= RM15.00
Labour = 9/10 x RM 5.00 = RM 4.50 Construction cost for 230mm thick brick
RM 38.70 wall = 0.93m2 x RM 44.51
= RM 41.39
Bil Reinforcement diameter Wall, floor & roof Beam, column Foundation
Table: Labour constant for cutting, bending and place the reinforcement for each 50kg
56
Cont…
b. Material cost
▪ Material cost depend on types and reinforcement size used.
▪ There are two common types of reinforcement namely mild steel reinforcement
and high steel tensile. Usually mild steel used as a link while high steel tensile
used as a main reinforcement.
▪ Reinforcement used will be cut according to length and specification
requirement. and deduction. This deduction called wastage. Therefore, need to
be added a five percent as wastage factor when calculating material cost.
57
10mm diameter steel a. Cost 1 tonne (1000 kg) steel 10mm= RM1850.00
b. Labour wage/day (skilled labour) =RM 40.00
in building foundation c. Labour wage (common labour) = RM 25.00
including cutting, d. Labour constant for cutting and
Answer
Cont…
Tutorial Question
Estimated totaled 35 kg 12mm diameter steel size used in column stump construction.
Calculate the steel cost for this column if there are eight column that want to be built.
Assuming the price for 1 tone steel 12mm diameter size is RM 1250.00 including
transportation.
Data Given:
Price for 1 tone (1000 kg) = RM 1250.00
Labour constant cutting & bending = 3 hour
Labour constant lift and placing = 2 ½ hour
Wastage = 5%
Skilled labour wage/day = RM 120.00
Labour wage /day =RM 80.00
Profit & management = 5%
61
End….