Professional Documents
Culture Documents
Dpe C11 401
Dpe C11 401
com
DPE-C11-401/N
NOV 2021
EDIT: 1, REVISION: 1
NETWORKS - LINES
AT and MT airlines
test protocol
Edition: 1
INDEX
7.1. Tests and verifications in the construction phase ..................................................... .................................................................. .....................6
7.1.1. Foundations ..................................................................... .................................................................. .................................................................. .............8
7.1.2. Supports ..................................................................... .................................................................. .................................................................. .....................8
7.1.3. Guard conductors and cables ................................................... .................................................................. .....................................8
7.1.4. Insulators and accessories .................................................................... .................................................................. ...............................................8
7.1.5. Ground circuits .................................................................. .................................................................. .................................................................. ....8
7.1.6. Specific tests for Optical Fibers ................................................ .................................................................. .......................8
7.1.7. Identification/authorization of owners ................................................... .................................................................. ..................8
1. INTRODUCTION
This document corresponds to the first revision of edition 1 of document DPE-C11-401. The most relevant
changes in this revision are:
⎯ Alteration of the criteria for defining tests on MV lines. In this review, the cable section was considered as
a criterion;
⎯ Alteration of the galvanizing quality verification process (separation between E-REDES, Electricity
Distribution, SA and Service Provider);
⎯ Elimination of the Table referring to the Insulation Coordination Guide regarding the number and type of
insulators, now referring to the Insulation Coordination Guide;
⎯ Alteration of the topographic verification map according to the new established criteria;
⎯ Elimination of the AT/MT Airline Verification Form annex, sending these verifications to those established
in the maintenance handover document.
2. OBJECT
This document is intended to define the tests, verifications and respective procedures, which must be carried out
whenever these are available in the management process of the service providers.
3. FIELD OF APPLICATION
This procedure applies to all new air circuits/sections, AT or MV, made up of cables whose characteristics are
defined in documents DMA-C34-110/N, DMA-C34-120/N, DMA-C34-125/ N, DMA-C34-127/N and DMA-C34-122/N.
This procedure must be carried out during the execution of the overhead line and when the said circuit/section
comes into service, immediately after its installation and before its connection to the network.
The stipulated voltage of the MT and AT materials that make up the test target circuits is given by the combination of the U
⎯ U0is the effective voltage value at power frequency between the conductor and earth;
In the case of MV and HV overhead lines used in the networks of E-REDES, Distribuição de Eletricidade, SA, the
stipulated voltage is shown in Table 1.
Table 1
10 6 10 12
15 8.7 15 17.5
30 18 30 36
60 36 60 72.5
In the case of installations that will be delivered to E-REDES, Distribuição de Eletricidade, SA for exploitation, the
tests and verifications defined in this document must be carried out by qualified technicians and/or in the
presence of an E-REDES, Distribuição de Eletricidade, SA
E-REDES, Distribuição de Eletricidade, SA reserves the right to only accept the circuit if it complies with the
provisions of this document.
This document was based on other documents listed below, indicating the respective edition dates.
DMA-C66-402/N Steel structures for overhead lines and devices for the protection of avifauna
Nesting and perching deterrent solutions for storks on overhead line supports
DRE-C65-310/N
Eurocode 2: Design of concrete structures - Part 1-1: General rules and rules for
EN 1992-1-1
buildings
For the purposes of this document, the definitions contained in the International Electrotechnical Vocabulary
(IEC) in the part referring to electrical conductors and cables (IEC 60050-461) apply.
6. ABBREVIATIONS
AT - High voltage
A.D - continuous voltage
During the construction process of an overhead line, monitoring and quality control will have to be carried out by
someone who supervises the activities in the various stages, with a view to preparing for the reception of the work.
The tests applicable to each type of circuit, based on its characteristics, are defined in Table 2.
Table 2
Tests and Checks
MT airlines AT airlines
Length Length
Section < 90 Section ≥ 90
Tests and Checks < 1000 m or ≥ 1000 m or
mmtwo mmtwo
no. of supports ≤ 2 no. of supports ≥ 2
1. Foundations
2. Poles
Support verticality X X X X
MT airlines AT airlines
Length Length
Section < 90 Section ≥ 90
Tests and Checks < 1000 m or ≥ 1000 m or
mmtwo mmtwo
no. of supports ≤ 2 no. of supports ≥ 2
mounting arrows X X X X
safety distances X X X X
5. Ground circuits
In order to ensure conformity and quality control in the construction of HV/MV overhead lines, guaranteeing the
conformity of the execution of the work with the respective project, it is necessary to carry out a set of tests and
verifications during its execution that prove the compliance with all good construction practices and the quality
of the materials installed, namely:
7.1.1. Foundations
⎯ topographic verification;
⎯ size of caboucos;
⎯ concrete identity tests.
7.1.2. Supports
⎯ verification of the placement of the bases;
⎯ support verticality;
⎯ Integrity of reinforced concrete supports;
The conclusions of the tests and verifications carried out in the construction phases must be recorded in the respective
reports, which will form an integral part of the technical compilation prepared at the end of the work and the
commissioning of the HV or MV line asset.
It will be based on the conclusions of the tests and verifications carried out that the commissioning act will be carried out without
⎯ verification of compliance with aeronautical buoyancy according to Aeronautical Circular 10/03, of May 6, of the
National Institute of Civil Aviation;
⎯ verification of the register of owners and the authorization of the owners (applicable only in case of
works delivered by third parties);
⎯ verification of the Loss Reports (RP) (applicable only in the case of works delivered by third parties);
⎯ verification of bidirectional attenuation test reports (only for lines that include cables
fiber optic);
⎯verification of optical power measurement test reports (only for lines that include cables
fiber optic).
8.1. generalities
The works associated with the construction of an overhead line, as well as all the tasks to be carried out for an
efficient compliance and quality control, will have to be carried out in compliance with all the processes,
procedures and operating methods defined by the specifications, by the installation manuals by equipment
manufacturers, by tool use manuals, by safety and health data sheets, by national and international standards
and by established good practices.
In the absence of the supervisory body, it is up to the PSE to carry out the measurements and records indicated throughout this
document.
Note: The documentation produced within the scope of this document must be placed in the Work Order in JUMP
and, before the commissioning phase, it must be verified that all the information has been correctly entered.
8.2.1. Foundations
It will be essential to ensure that the foundations are executed in accordance with what is defined in your project
(dimensions according to the type of terrain), and also that the materials applied in their execution are adequate.
Therefore, it is essential to carry out a series of tests and verifications, in all phases of the execution of the
support foundation, in order to carry out its conformity and quality control.
This topographic verification (simplified or complete) must be recorded, according to the criteria established in
Table 2, on a topographic verification map, according to the models found in Annex A.
Check the dimensions of the gullies, the verticality of the walls and that the bottom of the gullies is in the state of
natural terrain, perfectly regularized and horizontal.
⎯ Terrain type;
When there are alterations to the foundations, previously validated by E-REDES, Distribuição de Eletricidade, SA,
they must be registered in the map of foundations, according to the model in Annex B.
These characteristic values relate to laboratory tests on standard test specimens, sampled, cured and tested in
accordance with EN 12350-1, EN 12390-2 and EN12390-3.
The evaluation of the quality of the concrete, from its application on the construction site, can be carried out by
measuring the compressive strength“in situ”characteristic, which is defined as the value below which 5% of all possible
determinations of the resistance of the considered volume of concrete are expected to fall.
The compressive strength ratio“in situ”characteristic with compressive strength class is given by the following
Table 3 (NP EN 13791):
Table 3
Ratio of the characteristic “in situ” compressive strength to the compressive strength class
Depending on the number of samples per batch of concrete, the identity criteria in Table 4 may be considered.
Table 4
ID criteriaconcrete quality by quantity and sample
Number “n” of test results for the Criterion 1 Criterion 2
compressive strength of the volume of
concrete in question
Average of “n” results (fcm) Any single result (fci)
N/mm² N/mm²
being fckthe characteristic compressive strength, fcmthe compressive strength of the average of tests of the same
volume of concrete efcithe individual compressive strength of each test.
Proof of the quality of the concrete applied on site must be obtained through:
⎯ Proof of the supplied concrete manufacturer;
⎯ Compression tests on samples in specimens (identity tests).
The specimen must be filled with concrete used in concreting the foundations of the supports, recommending a
quantity of 4 specimens per support.
Once filled, the test piece must be stored immersed in water at a temperature between 18 and 22 ºC, during the
first 7 days of age, and stored in the air, with relative humidity between 50 and 70% and temperature between 15
and 22 °C for 21 days.
The compression test must be carried out at 7 and 28 days of age of the specimen
The results of the concrete identity tests at 7 and 28 days must be recorded on the foundation map, according to
the model in Annex B, which will form part of the technical compilation that, at the end of the work, must be
organized.
Regardless of whether specimens are collected from all supports, additionally, and by sampling, testing of the
concrete masses may be required, by core drilling, to verify the quality of the concrete applied on site, in the
supports to be indicated by the supervisory entity.
Lower results than those required in the tests carried out on specimens collected during concreting will not be
admissible.
8.2.2. Supports
⎯ alignment -The offset from alignment (dalin), that is, the distance between the axis of the support and the actual
alignment (for either side), must be smaller, in centimeters, than: dalin ≤ D/500[cm], with a tolerance of 5 cm,
being D the distance, in meters, from the axis of the support to the nearest angle;
⎯ support orientation (metallic) -the distances from the vertices of the bases to the alignment axis (for an
alignment support) or to the angle bisector (for an angle support) must not differ from each other by more than 5
mm per meter;
⎯ horizontally (metallic) -the vertices of the bases must be located in the same horizontal plane, with a
maximum tolerance of 5 mm.
The distance from the verticality of the supports, after their assembly, must not exceed 50 mm, whatever their
height.
The quality of the galvanization must be evaluated before the installation of a metallic post/frame, through two
processes, depending on the supply:
⎯visual verification of the appearance, adhesion, continuity and uniformity of the galvanized surface.
⎯ visual verification of the appearance, adhesion, continuity and uniformity of the galvanized surface.
Indeed, for the line to perform well throughout its life, the integrity of the cable must be guaranteed during the
entire process – unwinding, stretching, adjustment and placement in the clamps.
No less important will be to ensure correct regulation of the cables as defined in the project, guaranteeing the
correct mechanical performance of both the cables and the supports, as well as the safety distances from all
obstacles.
This torsion may have an even more appreciable effect on cables incorporating optical fibers, one of the most harmful
effects being the compression of the fibers inside their guide tubes.
As a preventive measure, it is recommended that the number of turns that a cable makes on itself during the
unwinding process does not exceed 10 turns per 100 meters of length, recommending that its average value be
around 5 turns per every 100 meters in length.
During unrolling, the executing entity must carry out a verification test consisting of the following process:
⎯ placement of a plumb line, with adequate length, in the cable, at the exit of the pulley of an extreme support of
a span;
⎯ continuation of unwinding until the plumb line is seen next to the pulley of the other extreme support of
the span;
⎯ count of the number of turns that the plumb line “won” along the span by winding the cable.
If the number of turns is greater than the recommended value, immediately act as follows:
⎯ in the swivels placed in the connection between the guide and the cable to be uncoiled, replacing them
or increasing their number by coupling elements in series;
⎯ on the pulleys, checking and adjusting their positioning at the vertices of the layout in order to ensure that the cable
In the case of cables incorporating optical fibers, torsions can be even more harmful so, in addition to the
previous process, an additional control of the winding ratio (pitch/diameter) of the cable during unwinding must
be carried out, as follows:
⎯ the operator must, before starting the unwinding work, check the values provided by the cable
manufacturer in relation to the cable pitch and the outer diameter of the cable, measuring them before
entering the brake;
⎯ the same measurement should also be taken at the exit of the brake, at the entrance and exit of the first support and,
eventually, at other points of the route to be indicated by the supervisory body, namely at the entrance and exit of
The relationship between the diameter and pitch must be maintained, during unwinding, with a tolerance of 10% in relation to
Tendentially, the external diameter should decrease and the cable pitch increase, although these variations are
marginal and stable throughout the unwinding. It is required to record these checks in a table, according to the
model found in Annex C.
If there is a significant or abnormal change in the values found, the work must be stopped and the causes
analyzed.
registration of the assembly arrows must be carried out, for validation according to the project.
The accuracy of adjusting the arrows will be ± 3% in relation to the theoretical design value and the regulatory
distances must always be checked.
The measurement method may be on the posts, applying rulers at a distance of the length of the assembly
arrow in relation to the fixing points on the supports.
For greater convenience, the assembly arrow can be checked from the ground, using topography equipment.
A topographical method consists of fixing a measuring device under the point of attachment of the cable to one of the
extreme posts of the test span, according to the example in Figure 1.
The viewing angle, φ, has the following relationship with the arrow f, at mid-span:
h − 4 ∗ f + 4 ∗ √(f ∗ D)
ϕ = arctan( )
The
where:
⎯ h (m) – difference in level measured between fixation points, considered positive when the fixation height on the downstream
support is greater than the fixation height on the support where the device is located and negative when the fixation height on the
downstream support is greater lower than the height of fixation on the support where the device is located;
⎯ D (m) – distance between the measuring device and the point of attachment of the cable to the pole, measured vertically;
In Annex D, the main distances to be covered and the most important indications mentioned in the RSLEAT are
presented.
8.2.4.2. Verification of type and number of insulators and string orientation (up or down)
A check must be made to ensure that the insulator chains, with regard to the number and type of insulators, are
in accordance with the definition in the Insulation Coordination Guide.
When the chains applied are different from those defined in the project, a record must be made in a separate file,
according to Annex H.
To this end, during the execution of the compressions, a set of measurements of the thickness of the compression
should be carried out, both for steel and aluminum, and these values recorded in the registration forms of
conformity of compressions of unions and clamps for conductors and guard cable, which are in Annex E.
In addition to the three measures of the thickness of the hexagon, the reference of the accessories and applied matrices must
The measurement of the thickness of the hexagon must be done before and after the clamp is placed in mechanical traction.
⎯ after concreting, filling the foundations and connecting the elements, including guard cables, to the earth
circuit.
The values obtained in the measurements carried out must be registered in a list, according to the model presented in Annex
At supports up to 1 km away from the line output substation, earth resistance must not exceed 30 ohm.
Cumulatively, in public and frequented areas and in supports equipped with cutting devices and/or aerial/
underground transitions, the earth resistance must be less than 20 ohm. Specific tests for Fiber Optic cables.
The execution of these tests consists of carrying out measurements in both directions in order to characterize:
⎯ Unidirectional and average attenuation values per joint, splitter fusion and total bond, at wavelengths
1310 nm, 1550 nm and 1625 nm;
⎯Distances from the melting points (joints, splitters) to the ends of the connection.
The registration, according to the FO Connection commissioning form found in Annex G, of all measurements carried
out with the OTDR must be made available to the person in charge of E-REDES, Distribuição de Eletricidade, SA
immediately after the completion of the tests (IT support of the " traces” of OTDR).
When carrying out reception tests, PSEs must be equipped with two pairs of equipment for testing the total
attenuation of the connection (optical sources and receivers) or, alternatively, a pair of equipment in which each
of them has integrated source functionalities and receiver, and prepared for operation at wavelengths of 1310,
1550 and 1625nm, so that the bidirectional total attenuation test can be carried out without the need to change
positions of the two team members.
After performing the fusion splicing of the fibers, attenuation tests should be carried out, using the equipment
described above.
In these tests, for the calculation of total attenuation, the following procedures must be respected:
The Total Attenuation ( ) will be obtained through the following expression:
The maximum attenuation value must comply with the criteria defined in the ITU-T G.652 standard (Section 6.1)
shown in Table 5.
Table 5
Attenuation coefficients - Maximum admissible values
Attenuation Coefficients
Length of Maximum value
wave admissible
1310nm 0.40 dB/km
1550nm 0.30 dB/km
1625nm 0.40 dB/km
In addition to the presentation in a table, the reports of these tests must be provided in digital format, and must
include the necessary software to read the respective traces.
Note: The degree of cleanliness of the optical connectors is a factor with great influence on the measurement results,
so the following procedures must be ensured:
⎯ Placement of a protective cover whenever they are not connected (whether those of the optical splitter, those
of the measuring equipment, or those of the cords);
⎯ Cleaning the connectors before each test, for this purpose, use a lens cleaning paper or pen, clean the
fiber termination and the outer part of the connector.
DIT – Innovation and Technological Development Department page 18/32
DPE-C11-401/N
NOV 2021
EDIT: 1, REVISION: 1
It is also mandatory to register the contact made and the respective authorization to carry out the work with the owner,
filling in the model indicated in the ECTs of the Tender Specifications for the Continuous Network Employment.
The contact forms must be part of the technical compilation of the work, so that they can be consulted whenever
a complaint appears.
The Damage Reports must be part of the technical compilation of the work, so that they can be consulted
whenever a complaint appears.
Note: Once the installation is in conditions to be commissioned, due follow-up must be given to the
commissioning of the corresponding JUMP work, as well as the placement of the corresponding DM work in the
“Pending Connection” status, so that the installation can be placed in exploration.
Before putting the installation into operation, the phase concordance test must be carried out, for which we can
use two types of equipment:
⎯ kilo Voltmeter - measures, through a physical connection, the voltage between the phases to be checked;
⎯ Radiofrequency (RF) checker - consisting of 2 modules (transmitter and receiver) that communicate via
radiofrequency, emitting a sound/light signal whenever the equipment is in concordant phases.
When putting the installation into operation, whenever possible, it should only be maintained at electrical
voltage, at the nominal voltage foreseen for its operation, maintaining this state for an experimental period,
which is recommended to be 24 hours. After the experimental period, the line can be placed on load, that is, in
normal operation.
On MV lines with branches, this type of test is often impracticable and can be dispensed with whenever the
quality of service of the installation is in question.
ANNEX A
N – Support number; T
– Type of Support;
F – Type of fixation;
Ang. – Support angle (grads); V –
Span (m);
DO – Distance to the origin (m); C –
Dimension of the support (m);
D – Gap between supports in the span (m);
M – Geographic Coordinate;
P – Geographic Coordinate;
* Automatic filling.
ANNEX B
N – Support number; T
– Type of Support; TT –
Type of terrain;
DA – Dimension of face A of the excavation (m);
DB – Dimension of face B of the excavation (m);
VE - Excavation volume (m3);
VB – Volume of concrete (m3);
DB – Concreting date;
7 days – Value obtained in the compression test of the concrete specimens at 7 days (N/mm²); 28 days –
Value obtained in the compression test of the concrete specimens at 28 days (N/mm²).
ANNEX C
⎯ Wiring pitch: Axial length of a complete turn of the helix formed by an individual strand of a
stranded conductor.
⎯ Winding ratio = pitch/diameter
ANNEX D
NOV 2021
ISSUE 1, REV. 1
In the previous table the distances are presented in meters and referring to bare conductors, in the conditions of maximum
deflection.
twoAlong the lines, a 5m wide service strip must be established, divided in half by the axis of the line, in which the
necessary trees will be cut and cleared to make its assembly and conservation possible (RSLEAT, Art. 28.º .4). In
order to guarantee the safe operation of the lines, the protection zone will have a maximum width of 15m for
LMT at 15kV and 25m for LAT at 60kV (RSLEAT, Art. 28.º .3). In the protection zone, trees will be cut or cut if this is
sufficient to guarantee the minimum distance, as well as trees that, due to falling, do not guarantee in relation to
the conductors, in the event of a maximum arrow without wind overload, the minimum distance of 1.5m (RSLEAT,
Art. 28.º .4).
NOV 2021
ISSUE 1, REV. 1
ATTACHMENT IS
Conformity Record Forms for Compressions of Unions and Clamps for Conductors and Cable
Guard – part 1
Contract: Line
Date:
NOV 2021
ISSUE 1, REV. 1
Conformity Record Forms for Compressions of Unions and Clamps for Conductors and Cable
Guard – part 2
Contract: Line
Date:
NOV 2021
ISSUE 1, REV. 1
ANNEX F
Airline:
Post Kind of Kind of Kind of earth mesh before the cable after cable
zone land (2) occupation on guard guard
No. Type (1) from soil R (Ω) Date R (Ω) Date
Initial_________________
Date: __________________
ANNEX G
Cable Type:
Optical connection identification:
MT/AT Line Name:
Local Name A:
Joint 1 (support number, distance from A)
ODF Position 1
Joint 2 (No. support, distance from A)
ODF Position 2
Joint 3 (No. support, distance from A)
ODF Position 3
Joint 4 (No. support, distance from A)
ODF Position 4
Joint 5 (support number, distance from A)
B Location Name:
Joint 6 (support number, distance from A)
ODF Position 1
Joint 7 (support number, distance from A)
ODF Position 2
Joint 8 (support number, distance from A)
ODF Position 3
Joint 9 (support number, distance from A)
ODF Position 4
Joint 10 (support number, distance from A)
Name Place C:
Joint 11 (support number, distance from A)
ODF Position 1
Joint 12 (support number, distance from A)
ODF Position 2
Joint 13 (support number, distance from A)
ODF Position 3
Joint 14 (support number, distance from A)
ODF Position 4
Joint 15 (support number, distance from A)
Entity responsible for the intervention:
Joint 16 (support number, distance from A)
Responsible Person (name and number)
2- Procedures to be Followed
Performer
No.:
Entity:
Signature:
Date:
ANNEX H
Insulator Chains
Support
Project Installed
Fixation Fixation
Kind of # rods Guidance Kind of # rods Guidance
# Type drivers drivers
insulator insulators [Y/N] [Up/Down] insulator insulators [Y/N] [Up/Down]
[Love/Susp] [Love/Susp]