2023-02-18 Listed Event of SFBC (Chapter 13) by Joshua
2023-02-18 Listed Event of SFBC (Chapter 13) by Joshua
Natural Architect’s instruction NSC / NS Employer Gov department or Utility Company Other
(a)Force majeure: unexpected event such (f) ambiguity, discrepancy, divergence between (m) Delay caused by NSC / NS (s) The failure of the Employer to give (t) Delay to the work due to (d) Excepted risk ……
as war, crime, earthquake, etc …… clause the documents (因圖唔夾,要redo)…… clause which entitled to have EOT possession of the Site…… clause unreasonable foreseen of the approval or clause 25.1(3)
25.1(3) 2.4 under sub contract…… clause 23.1(2) consent from a Government
25.1(3)
department…… clause 25.1(3)
(b)Inclement weather: rainfall over (g) requiring the opening up for (n) Delay caused by contractor’s (v) prevention, a breach of contract (q) Delay caused by a statutory (u) special circumstance
20mm in 24 hours …… clause 25.1(3) valid objection of NS / NSC…… or other default by the Employer undertaker or utility company…… clause considered by
inspection of work covered up or the clause 29.2(6) (other delay) …… clause 25.1(3) 25.1(3)
the Architect (Time at
testing of materials, goods or work…… clause 8.2 last) …… clause 25.1(3)
(c) Tropical cyclone warning signal No. 8, (h) require variation…… clause 13.1 (o) Delay caused by the (p) Delay caused by a Specialist
black rainstorm warning…… clause replacement of NS / NSC …… Contractor (nominated by the
25.1(3) clause 29.13 employer) …… clause 25.1(3)
(e) Special peril: fire, (i) require variation that increase in the work to (r) The failure of the Employer to
be carried out of sufficient magnitude to cause supply or supply on time materials,
lightning, explosion, storm, tropical delay …… clause 13.2 goods, plant or equipment that
agreed to provide…… clause 25.1(3)
cyclone, flood, bursting or overflowing of
water tanks…… clause 25.1(3)
(j) call for postponement(possession/
commencement ) or suspension…… clause 23.3