TMF Weekly Coordination

Week 1 - June
Period : June 2 nd – June 8st 2022
TMFE – Construction
Geotechnical Monitoring

MNG 10 & 11 Movement Rate, 52-74 mm/day


TMFE – Construction
Geotechnical Monitoring

CM-15 movement 79 mm/day


TMFE – Construction
Production review

• Weekly Total volume PP-C Excavation (Productive) : 169 Bcm


• Production Loss by Idle : 425 Bcm • Total Excavation Volume PPC MTD June (Productive) : 195 Bcm
• Production Loss by STB : 5314 Bcm • Weekly Total volume Non Productive : 1092 BCm
• RainFall weekly : 17.5 mm, and Duration at Day Shift : 4.25 Hours
• Rainfall MTD :5.63 mm, and Duration Rain & Slippery : 0 Hours
TMFE – Construction
Polishing Pond B Water Elevation Monitoring

TMF Polishing Pond B


164.00 90.0

80.0
163.00
70.0

162.00 60.0
Pond Elevation (m)

Rainfall (mm)
50.0
161.00
160.77 40.0

160.37
160.00 30.0

20.0
159.00
10.0

158.00 0.0
1/6/22 2/6/22 3/6/22 4/6/22 5/6/22 6/6/22 7/6/22 8/6/22 9/6/22 10/6/22 11/6/22 12/6/22 13/6/22 14/6/22 15/6/22

Rainfall Polishing Pond B (mm) Elevasi Pond B


Plan Next Week

Pioneer Road
 Continue Regrade & Patching Pioneer Road.

No Aktivitas Alat CN Plan/Actual 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun

P
Pembentukan drainase & tanggul jalan Pioneer sesuai standar
A
Loading material Clay untuk meninggikan jalan pioneer area P
1 20 T EX 9184
CH 0+350 & CH 0+500 – CH 0+700 (regrade) A
Loading boulder untuk patching jalan pioneer CH 0+700 – CH P
0+950 A
Rock Breaker Boulder di Spillway PP B & Boulder diarea P
2 Stockpile PP B untuk Patching Jalan Pioner CH 0+700 – CH 30 T EX 9162RB
0+950 A
Support Dozing & Spreading aktivitas Regrade Jl Pioneer CH P
0+500 - CH 0+750 (19 – 20%)
A
3 D6R DZ 9213
P
Support Dozing Pelebaran Jalan CH 0+750 – CH 0+950
A
RO9712 & P
4 Compacting access PPC dan pioneer road Compactor
RO9700 A
P
5 Vessel sampling ADT
A
SURVEY PLAN
TMFE – Design
Survey Schedule
PIONEER ROAD
TMFE – Design
Pioneer Road

 Update Pioneer Road ( STA 0+000 – STA 1+428 )


• Length Road : 1.428 km
• Update Progress : STA 0+000 – STA 0+950

LEGEND
NCD AREA

PIONEER ROAD

RIVER
TMFE – Design
Pioneer Road

STA 1+000

STA 0+800

STA 0+600
ACTIVITY STA 540 - STA950

STA 0+400

LEGEND
7 MAY 2022

11 MAY 2022

STA 0+200

STA 0+000
UNDERDRAINAGE
TMF - Design
Underdrainage
Update Topographic Survey
As of 7 June 2022
TMF
TMF WEST EAST

Remain
UNDERAINAGE
survey area SURVEY UPDATE
LEGEND
TOPO LIDAR
River 1 TOPO ACTUAL
Remain TYPICAL SECTION
survey area UNDERDRAINAGE

Segment 3

River 2
Bdy TMF East
Segment 2

Segment 1 Bdy Stage 1A

Underdrain
Channel
Terimakasih