FiberHome Antenna&Filter Technical Manual V1.0
FiberHome Antenna&Filter Technical Manual V1.0
FiberHome Antenna&Filter Technical Manual V1.0
Label Radome
Package List
No. Item Qty. Unit
1 Antenna 1 pcs
2 Technical Manual 1 set
Low installation Bottom platform 3 RET Operating Manual 1 set
Bracket cover
4 Quality Certificate 1 pcs
Dimension:2100×448×200mm Radome material : Fiberglass 5 Antenna Bracket 1 set
Weight:40kg Radome Color : Light grey
RET Introduction
RET Features and Appearance RET Concatenation
Precise angle control;
AISG V2.0 protocol;
Small volume, light
weight, easy installation;
Reliable lightning AISG IN AISG OUT AISG IN AISG OUT AISG IN
protection design;
Daisy chain connection.
From RRU
Note:
It is suggested that AISG cable and RCU joint be wrapped with
waterproof tape.
It can be tightened only by hand, wrenches and other tools can’t be
used.
FDD Filter Introduction
Filter Appearance view Package List
8
5 2
9
7
4 Bottom Unit
<RF:Din‐F;CAL:NF>
SN1 HXTR12X22HHHH161
1 PCS Dual Band 12 Port Antenna 1 Antenna
7065T2C
2300M 850M HXCAB-RCU-5- 5m AISG Cable from Antenna
2 PCS 5m AISG Cable (8Pin to DB15) 1
DB15P RET to FDD RRU RET
RF RF RF RF Cal RF RF RF RF RF RF RF RF 5m jumper from Antenna CAL
ZTE-8A: 3 N-J/N-J-1/2"-5M PCS 5m jumper with Protection Rubber(NM-NM) 1
to TDD RRU CAL
FDD+TDD Beam 5m jumper with Protection Rubber (DINM- 5m jumper from Antenna RF to
Forming 12 Port 4 DIN-J/N-J-1/2"-5M PCS 8
NM) TDD RRU RF
Antenna 2PCS 5m jumper from Antenna
(w/ R8998G & 5m jumper with Protection Rubber (DINM- RF to Filter;
SN5 R8862a) 5 DIN-J/DIN-J-1/2"-5M PCS 4
SN3 SN2 DINM) 2PCS 5m jumper from Antenna
RF to FDD RRU RF
SN6 6 HXFLT847-33UD-2 PCS Filter 2 in 2out DINF-DINF 1 Filter
5m jumper with Protection Rubber (DINM- 5m jumper from Filter to FDD
7 DIN-J/DIN-J-1/2"-5M PCS 2
SN4 DINM) RRU RF
SN7
SN5
DB15
BBU
Antenna&Filter Installation & Handling
Connect the
Jumper and RET
Waterproof
Material Return Site Clean QC check
treatment
Tools Kit
Base Station Antenna Deploy
Install Bracket Install antenna on the pole
Step1:Indetify and assemble mounting bracket Step 1:Tilt to 0° and tighten nut A
secure the U clamp with M8 bolts(18Nm) Step 2:Fasten antenna vertically to pole with M10*150 bolts
Step2:Attach mounting brackets to antenna secure it (25Nm)
with M8 bolts
Filter installation
Step1:Take out the filter and throat clamps from Step3:Pass the hoop through the mounting
the package and prepare a flat screwdriver bracket of the filter
Step2:Loosen the hoop Step4:Put the hoop through the pole and fasten
the screw
Base Station Antenna Deploy
System Connectivity diagram Connect relation table
Filter Port Antenna
RRU TYPE RRU Port name Remark
name Port name
ANT1(TX/RX) BTS ANT 1 +45
ANT2(RX) / / 2 -45
FDD RRU ANT3(RX) / / 4 -45
ANT4(TX/RX) BTS ANT 3 +45
AISG/MON / / AISG IN /
ANT1 / / 9 -45
ANT2 / / 10 -45
ANT3 / / 11 -45
ANT4 / / 12 -45
TDD RRU ANT5 / / 5 +45
ANT6 / / 6 +45
ANT7 / / 7 +45
ANT8 / / 8 +45
CAL / / CAL /
Filter was accessed transmit port of RRU , each filter connect different array of antenna.
Antenna P5~8 were +45°polarization, antenna P9~12 were -45°polarization, Antennas and TDD RRU
should be connected with the same polarization.
Base Station Antenna Deploy
How to avoid Jumper cross? Antenna RF and Cal connect cross
Step1:Use the Jumper connect with RRU; First of all ,it’s hard because of the connector type
Step2:Make a label like label table; is different . If connect cross on RRU side , there two
Step3:According to RRU and Jumper connect kinds of impact:
relation ,pasted the label on the Jumper; Cross-connection will lead to abnormal calibration,
Step4:According to the label ,connect antenna and the pattern probable deformed, seriously
and Jumper affecting the signal coverage of the coverage area.
RRU CAL port just receive signal, if connector cross,
the crossed Antenna port will be no input power;
Label Content Remark
TX/RX1-BTS1 FDD RRU ANT1 to Bottom Filter BTS port
ANT1-1 Bottom Filter ANT port to Antenna P1
RX2-2 FDD RRU ANT2 to Antenna P2 There is a damage risk for antenna CAL port if long
RX3-4 FDD RRU ANT3 to Antenna P4
TX/RX4-BTS2 FDD RRU ANT4 to Top Filter BTS port time work.
ANT2-3 Top Filter ANT port to Antenna P3
AISG FDD RRU MON to Antenna AISG IN
ANT1-9
ANT2-10
TDD ANT1 port to Antenna P9
TDD ANT2 port to Antenna P10
Bracket reduce from 3 to 2
ANT3-11
ANT4-12
TDD ANT3 port to Antenna P11
TDD ANT4 port to Antenna P12
The bracket design needs to consider the wind
ANT5-5
ANT6-6
TDD ANT5 port to Antenna P5
TDD ANT6 port to Antenna P6
load and the weight of the antenna. The wind load is
ANT7-7
ANT8-8
TDD ANT7 port to Antenna P7
TDD ANT8 port to Antenna P8
calculated based on the size of the antenna;
CAL-CAL TDD Cal port to Antenna Cal Current bracket meets the theoretical design and
the wind load test.
Base Station Antenna Deploy
Connector waterproof
Step 1:wrap the 3M tape Step 2:Push rubber sleeve
Use 3M tape wrap 3 times after connect Jumper , the first Push the Rubber sleeve up, it
time from bottom to top ,the second time from top to could cover whole connector.
bottom ,the last time from bottom to top.
Base Station Antenna Deploy
QC check list
Quality control mainly includes antenna installation, jumper connection and waterproof treatment, etc.
NO Content Pass Fail
1 Antenna/Filter installation position conforms to the design. ■ □
2 There are no object blocking at the front of the antenna ■ □
3 The antenna within lightning rod protection range of the 45°. ■ □
4 Antenna systems should have safety grounding, grounding resistance <5Ω. ■ □
5 Antenna azimuth angle error ≤±5° ■ □
6 Antenna mechanical tilts error ≤±1° ■ □
7 Antenna/Filter installation is reliable and firm, the screws are fastened ■ □
8 The pole which installed antenna is firm and the verticality ≤±1° ■ □
9 Jumper connector waterproof seal treatment ■ □
10 Appearance of Jumper is good , no obvious damage ■ □
11 The jumper wires should be arranged neatly, and bend radius ■ □
>20 times the jumper diameter
12 The excess part of the jumper is coiled in a standard manner and bound with cable ties ■ □
13 The relationship between the jumper and the antenna is correct, and there is no cross ■ □
connection
Base Station Antenna Deploy
Site clean
clean all of the things related about our material ,rubbish and unused things.
Take Photo-Report after implementation included tower elements according to Beeline’s requirement before leave
the site as the Photo Report standard.
Base Station Antenna Deploy
Material return
Cover the port , repackage Cover the port ,record type and
QTY on the label Fix goods by rope ,cover by plastic
Notes: Prepare the SRN (site return note) before inbound warehouse
Antenna packing and storage
Antenna package Antenna storage
Note:
1 Antenna connector must be protect by plastic foam(like the photo No 1)
2 After antenna dismantled from site, the bracket must disassemble, and package
it independent, include screw nuts and bolts.
Filter packing and storage
Filter package Filter storage
Step1:Check Filter appearance whether damaged Storage temperature :5-45 ℃
Step2: Put the product into a plastic bag and put it in a foam box Relative humidity :≤ 95%
Step3: After covering the foam cover, place the 2PCS hoop in Plate storage
the groove of the foam cover,close the box and put them on the 1 plate totally 70pcs(7 layers, each
plate. layer 10 pcs)
The package needs to be
wrapped by membrane ,reduce
the contact with the air
All connector need take
cover ,avoid dust going inside
lead to IMD degraded.
Dismantle product need
repackage by box ,record
condition/time/reason on label etc.
Dismantle product quality check
Visual inspection
Step 1: Appearance inspection , It wasn’t obvious damage
Step 2: Connector clean ,there wasn't visible dust , the outer conductor and inner core of the connector are not
deformed
VSWR measure
Use the Sitemaster measure VSWR, if the VSWR Satisfy the requirement of specification ,so the dismantle product can
reuse.
Note:
1 Measure instrument and accessories condition need confirm before test
2 Antenna test area should horizontal put on the platform without metal material,
the height of the platform ≥80cm
3 The radiation surface of the antenna should be turned over during the test. And
there is no obstruction in the radiation range
4 The test tool should be placed in front or behind the antenna under test, not on
the side, and keep a certain distance from the antenna under test.
Commissioning and Troubleshooting
C
Antenna commissioning
Adjust Electronical Tilt in OMC
RET serial
number
Note:
1 HXS06-R1-2210000001 and HXS06-R2-2210000001 for FDD Technical , if antenna connect
2*2T2R, they can controlled independently
2 HXS06-Y1-2210000001 is for TDD Technical
3 It is recommended that take a photo of the antenna label and record the SN after installed
antenna
Antenna commissioning
Adjust Electronical Tilt by Handheld Terminal
Step1:Connect Antenna and terminal Step2:Turn on switch and click ” Step3:Scan successful , show
Enter ” Antenna RET SN, click ” Enter ”
AISG IN
AISG cable
FH 12P TDD
Broadcast Weight
Troubleshooting and maintenance
RET Module replace in the field
Step1: Insert the RET module
The RET is inserted into the antenna
slot ,the antenna is placed as picture
and the side of the RCU tag must be
upwards ,if reverse, it would fail to insert.
Step4: Waterproof
Use the 3M and Waterproof wrap the
connector position.
Troubleshooting and maintenance
VSWR Fault UL Interference
Fault description: RRU VSWR alarm Fault description: UL noise floor higher , Throughput
Fault analysis: abnormal
Project quality problem (feeder and joint Fault analysis:
standing wave height) project quality problem
The RRU is abnormally External interference (such as improper repeater
RRU VSWR threshold setting settings)
There is a block in front of the antenna Base station equipment is working abnormally
The antenna VSWR fault Base station parameter setting problem
Troubleshooting step: frequency planning
Check the quality of the project mobile terminal problem
Check RRU parameter settings The antenna IMD3 fault
Adjust the antenna coverage angle and Troubleshooting step:
position Check the engineering quality
Measure Antenna VSWR Find external sources of interference
Check base station equipment and base station
parameter settings
Replan frequency
Analyze the usage of mobile phone users
Measuring antenna IMD3
Troubleshooting and maintenance
Coverage area issue RET scan failure
Fault description: Fault description:
weak coverage. Whole site cannot be scanned.
Overlay coverage Only individual scan failure
Failure cause analysis Failure cause analysis
weak coverage. Whole site cannot be scanned.
RRU output power or configuration fault; The voltage output from RRU to the RCU ESC is
Jumper fault; abnormal
Antenna Azimuth/ET/MT configuration fault; The voltage parameter configuration of OMC is abnormal,
Antenna fault(VSWR higher) and the voltage switch is not turned on.
Overlay coverage Only individual scan failure
RRU parameter fault AISG Cable fault
Antenna Azimuth/ET/MT configuration fault RET module fault
Antenna Gain too high, Horizontal beam too width Trouble shooting step:
Trouble shooting step: Check the OMC configuration
Check RRU parameter configure; Check the voltage of AISG cable PIN6 and PIN7 by
Check subsystem VSWR power meter, it whether around 22V;
Adjust the downtilt and azimuth of the antenna Replace AISG cable or RET
Check Antenna specification ,it is whether
available .