Download as pdf or txt
Download as pdf or txt
You are on page 1of 43

HSVC-PP4 PROJECT DOC. NO..

YSE-PP4-HSE-002
eTEC REV. NO.. A
HSSE PLAN PAGE COVER

HEALTH, SAFETY, SECURITY AND ENVIRONMENT PLAN

PROJECT: HSVC-PP4
PACKAGE: MECHANICAL AND ISBL PIPING WORK
CONTRACTOR: eTEC E&C
SUBCONTRACTOR: YUSUNG E&C
SUB-SUBCONTRACTOR: PTSC

Issue for Approval

REV.
DATE DESCRIPTION PREP'N REVIEW APPROVAL APPROVAL
NO.

ETEC APPROVAL
REV. l'TSC PTSC
DISCIPLINE YUSUNG APPROVAL
NO. l'REl'ARATION REVIEW

A USE

p

/c
1.../

J. fAR!c
This DOCUMENT is the property of PTSC. Therefore, ii shall not he released to any third party without permission of
authori::ed personnel of PS/3
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

TABLE OF CONTENTS

1. SCOPE................................................................................................................................. 3
2. PURPOSE............................................................................................................................ 3
3. REFERENCES .................................................................................................................... 3
4. DEFINITIONS .................................................................................................................... 4
5. HSE ORGANIZATION ...................................................................................................... 5
6. HSE RESPONSIBILITIES ................................................................................................. 5
7. STARRT & TBM .............................................................................................................. 10
8. HSE TRAINING AND CERTIFICATION ...................................................................... 12
9. EQUIPMENT INSPECTION ............................................................................................ 15
10. RISK ASSESSMENT AND WORK EXECUTION PROCEDURES .............................. 16
11. WORKING PERMIT PLAN ............................................................................................. 27
12. ENVIRONMENTAL CONTROL PLAN ......................................................................... 28
13. ENVIRONMENTAL PROTECTION MEASURES ........................................................ 28
14. PERSONNEL PROTECTION EQUIPMENT .................................................................. 32
15. FIRE PREVENTION AND PROTECTION ..................................................................... 33
16. HEALTH MANAGEMENT PLAN .................................................................................. 34
17. ACCIDENT/INCIDENT INVESTIGATION AND REPORTING .................................. 38
18. MEDICAL SERVICES PLAN.......................................................................................... 41
19. HOUSEKEEPING PLAN ................................................................................................. 41
20. WORKING CLOTHES AND FACIAL HAIR ................................................................. 42
21. ALCOHOL AND DRUGS ................................................................................................ 42
22. SMOKING AND OPEN FIRES ....................................................................................... 42
23. HSE BULLETIN BOARDS .............................................................................................. 43

2|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

1. SCOPE
This document covers the health, safety, environment and security management programs
and procedures applied to the construction Site. For the Project details refer to the Project
Execution Plan.
The Site Manager and the HSE manager shall establish Site HSE programs to enhance
everyone HSE consciousness and improve their HSE culture.
This document applies to all staff, Suppliers, Vendors and Visitors of BIDDER.
2. PURPOSE
This Project HSE Program is developed to ensure that all construction activities conform
to safety regulations, legislation, contract provisions, codes and standards as well as the
stringent requirements of the Contractor's policy, Project and Owner requirements.
The management shall actively seek the support of all operatives engaged on the Project to
look after their own health and safety, as well as that of their colleagues, by working within
the spirit of this Program.
This HSE Program describes the objectives, implementing guidelines, control measures,
and the review of performance that will be utilized in the execution of onshore project
activities that includes but not limited to:
- HSE Policy
- HSE Organization
- Medical Fitness, Medical Services and Facilities
- Health Awareness Activities and Health Assurance Program
- Personnel Protection Program

3. REFERENCES
Government Decree No.06/CP dated 20/1/95 stipulating detailed provisions for a number
of articles of the Labour Code on Labour Safety and Sanitation.
Government Decree No.110/2002/ND-CP dated 27/12/02 amending and supplementing a
number of articles of Decree No.06/CP dated 20/1/95.
Decision No.205/2002/QD-BLDTBXH dated 21/2/02 supplementing and amending the list
of personal protection equipment and devices for laborers doing jobs involving dangerous
and/or hazardous factors.
Decree No.35/2003/ND-CP dated 04/4/2003 detailing the implementation of a number of
articles of the Law on fire Prevention and Fighting.

3|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Circular No.23/TT-BLDTBXH dated 3/11/2003 prescribing and guiding the procedures


for registration and expertise of assorted machinery, equipment, supplies and substances
subject to strict requirement on labour and sanitation safety.
Interministerial Circulation No 14/1998/TTLB-BLDTBXH-BYT-TLDLDVN dated
31/10/1998 of MoLISA, MoH and General Conference of Vietnam guiding the
organization for implementation of labour protection in business enterprises.
Circulation No 8/LDTBXH&TT dated 11/4/1995 of MoLISA instructing safety and
hygiene training works.
Circular No 12/2011/TT-BTNMT dated April 14th, 2011 Stipulating hazardous wastes
management.
Decree No 44/2016/ND-CP dated May 15th, 2016 of the Ministry of Labor Invalids and
Social affairs on providing for work safety and hygiene training
Circular No. 22/2010/TT-BXD dated December 3, 2010 of the Ministry of Construction
on labor safety in work construction.
4. DEFINITIONS
OWNER : Hyosung Vina Chemicals Co., Ltd.
CONTRACTOR : eTEC E&C
BIDDER : PTSC Supply Base
HSE Manager : Health Safety and Environment Manager
SITE : Location where the Plant is to be constructed.
HSE : Health Safety and Environment.
PPE : Personal Protective Equipment.
PSMC : Project Safety Management Committee.
ALARP : As Low as Reasonably Practicable
BBS : Behavioral Based Safety
JSA : Job Safety Analysis
LOTO : Lock-Out and Tag-Out
MSDS : Material Safety Data Sheet
NOC : Notification Of Construction
OEMP : Operations Environmental Management Plan
PTW : Permit to Work

4|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

START : Safety Task Analysis Risk Talk


SV : Supervisor/Foreman
SWMS : Safety Work Method Statement
TBM : Tool Box Meeting

5. HSE ORGANIZATION
Prior to the start of the construction work, the Site Manager should establish the Site HSE
organization
All HSE personnel have the authority to stop work in the event of a breach of safety rules
or when an unsafe act or unsafe condition is identified.
All personnel on site have the responsibility to report immediately to the HSE personnel
any breach of safety or environment rules, unsafe acts and unsafe conditions.
6. HSE RESPONSIBILITIES
6.1 PROJECT MANAGER
Has the authority and responsibility for implementation, monitoring and initiating any
improvements required in the project to ensure the system is effective.
- Ensure that there is an effective and cohesive Health Safety and Environment Policy,
Alcohols, Liquor and Stimulant Usage Policy across the project.
- Ensure that adequate resources are allocated for promoting & maintaining safety.
- Review safety reports.
- Manage the effectiveness of above-mentioned Policies and ensure all corrective action
and safety recommendation is being taken.
- Ensure that all employees fulfill their responsibilities in health, safety and environment
at work and no impediment exist to prevent fulfillment of this program.
- Chair all Project Safety Management Committee (PSMC) and to ensure all committee
members meets regularly and accomplishes its objectives effectively.
- Set a good example amongst project employees.
- Ensure that all proposed working methods comply with Vietnam regulations and close
liaison is mentioned with relevant authorities, either through or with the consent of the
Employers representative.
- Ensure that all incidents and dangerous occurrences are investigated, reported and that
appropriate remedial measures are taken to prevent a recurrence.

5|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Ensure that adequate supervision is always available at the workplace. This also
applies particularly to weekends and holiday periods.
6.2 SITE MANAGER
Site manager has primary responsibility for the HSE management and performance.
His major roles and responsibilities are to:
- Establish realistic HSE objectives and targets, and visibly demonstrate to the
organization that personal commitment to HSE is his number one priority.
- Ensure the setting up of HSE rules & regulations, programs, emergency response
procedures, work permit system, incentive award scheme.
- Chair the HSE Steering committee.
- Patrol the Site as frequently as possible to ascertain status of the work and compliance
with HSE requirements and to demonstrate an active and visible attitude toward HSE.
- Direct the construction manager, HSE Manager and other managers in carrying out
their roles and responsibilities.
- Establish and direct an Accident Investigation Team when an accident occurs.
- Evaluate HSE reports on HSE performance, HSE topics, and any accidents or near
misses prepared by the HSE manager, and report them to the Project Manager in a
regular and timely manner.
- Plan and coordinate the works to ensure that conflicts of interest between Bidders do
not occur.
- Guide discipline supervisors in ensuring their roles and responsibilities for HSE are
understood.
- Set up and chair weekly progress meetings, which should include HSE topics.
- Ensure that BIDDER analyze all routine and non-routine works and identify any
associated hazards.
- Determine at the work planning stage:
+ Sequence and method of work
+ Allocation of responsibilities
+ Identify hazards that could arise during work execution
+ Adequate lighting
+ Well fare and sanitation facilities

6|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

+ Fire precautions
- Ensure that work execution procedures, work method statements have been provided
for all works, and incorporate adequate provisions for HSE.
- Patrol the Site daily and ascertain the status of the work and compliance with HSE
requirements.
- Promote housekeeping and waste disposal at the highest standard.
- Accompany any official or statutory inspectors.
6.3 HSE MANAGER
The HSE manager shall assist the Site Manager with HSE matters in promoting the HSE
programs and to ensure that all HSE requirements are satisfied. The HSE manager is the
principal safety officer responsible for monitoring and administering a proactive overall
project HSE program designed to provide assistance in recognizing, evaluating, and
subsequently eliminating or controlling hazardous acts or conditions.
Prior to appointment the resume will be submitted to CONTRACTOR for review and
approval His major roles and responsibilities are to:
- Set up a Site HSE organization and assign Site HSE Supervisors and Officers and
define their roles and responsibilities.
- Set up Site HSE standards, procedures and inspection/ audit program.
- Advise on the legal and statutory requirements for safety, health and environment.
- Establish and maintain contact with government organizations for HSE issues.
- Set up the work permit system that will be used during the construction pre-
commissioning and commissioning periods.
- Organize fire prevention and firefighting activities.
- Organize and regularly test the emergency response program.
- Set up environment control measures to protect the environment and mitigate adverse
environment impact of the work on the marine and terrestrial environment; and ensure
compliance with all environmental rules and regulations.
- Advise the Construction Manager and Line supervisors on HSE requirements.
- Review JSA’s (Job Safety Analysis).
- Select and advise on topics for ToolBox Talks.

7|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Patrol the Site daily and audit activities, equipment and facilities to determine if they
are in compliance with HSE requirements.
- Lead the Accident Investigation Team and make recommendations to avoid
reoccurrence.
- Attend weekly HSE Meeting by Contractor.
- Report daily to the site manager on major HSE activities and topics, and prepare a
"Monthly HSE Report" for the Site Manager.
- Submit accident reports to the CONTRACTOR and Local Labor Office.
- Continuously evaluate project working conditions and safe work practices.
- Monitor the behavior of the people and provide coaching towards working safely.
6.4 SITE HSE SUPERVISORS AND INSPECTORS
The HSE supervisors and equipment/scaffold Inspectors are responsible for ensuring that
safe work practices and equipment standards are being implemented in the areas where
they have been assigned.
Their major roles and responsibilities are to:
- Assist the HSE Manager.
- Patrol the Site as frequently as possible, and inspect current activities and working
conditions.
- Advise the construction manager and discipline supervisors of any unsafe conditions
or violations and remedial action required.
- Report daily to the HSE Manager on any HSE issues.
6.5 DISCIPLINE SUPERVISORS
Their major roles and responsibilities for HSE activities are to:
- Coordinate with other discipline supervisors to ensure that all the activities are being
carried out in compliance with HSE requirements and standards.
- Ensure that the requirements of hazards identification, risk analysis and evaluation
(risk assessment) are implemented, and Work execution procedures are provided
incorporating risk control measures for all hazardous work.
- Ensure that to obtain any necessary Work Permits.
- Verify that to work is carried out strictly in accordance with the approved Work
Execution Procedures and associated Work Permit and/or JSA.

8|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Ensure that all tools, plant and equipment used meet minimum safety standards and
are adequately guarded and equipped with the required safety devices and where
necessary are tested in accordance with requirements.
- Verify that personnel properly wear and use personal protective equipment and safety
devices according to requirements and manufactures instruction.
- Ensure that housekeeping standards are maintained, and that a waste disposal program
for waste and scrap materials is set up and enforced.
- Regular take part in the Tool Box Meeting (TBM) and ensure all employees actively
participate and receive the necessary safety instructions.
- Report to the Construction Manager on anticipated HSE matters of concern.
- Establish and maintain a motivational environment that includes positive recognition
as well as enforcement.

6.6 RESPONSIBILITIES OF MANAGERS


- Submit their HSE organization and HSE management plan to CONTRACTOR for
review.
- Assign their own competent and experienced HSE Manager and Supervisors.
- Attend the HSE Committee Meetings and weekly HSE Meetings, and inform their
subordinates of all important matters deliberated in these meetings.
- Provide new or well-maintained tools/equipment and materials to be used for the work.
- Provide all necessary Personnel Protective Equipment (PPE) to their employees and
enforce them to wear and use it at all time during the work.
- Assign a sufficient number of competent supervisors, foremen and workers to the
works as per the requirements of the project execution procedure.
- Assign a sufficient number of safety officers to support the implementation of the HSE
programs.
- Prepare work execution procedures for hazardous or high risk work and submit them
to CONTRACTOR for review.
- Report any accident, property damage, environmental incidents and near misses to the
HSE Manager.

6.7 RESPONSIBILITIES OF FOREMEN AND WORKERS


Personnel including foremen and workers shall fulfill their roles and responsibilities
regarding HSE requirements according to their positions and work roles.
9|Page
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

6.8 RESPONSIBILITIES OF FOREMEN


The foremen and charge hands major roles and responsibilities are to:
- Incorporate safety instruction in routine orders.
- Prevent employees from taking unnecessary risks.
- Ensure that all new employees understand CONTRACTOR and OWNER HSE
regulations and standards for work.
- Reprimand those who fail to consider their own well being and that of others around
them.
- Report promptly to their Supervisor all defects in plant and equipment.
- Ensure that tasks are allocated to workers only in accordance with their capabilities
and qualifications.
- Ensure that all necessary work permits are at the work site.
- Conduct the STARRT (Safety Task Analysis Risk Reduction Talk) meetings with their
crew.
- Ensure strict compliance with PPE requirements.

6.9 RESPONSIBILITIES OF WORKERS


BIDDER personnel’s major roles and responsibilities are to:
- Be aware that HSE is everyone responsibility.
- Attend the HSE Induction training course prior to starting their field work, and any
specific training course according to project requirements.
- Strictly follow instructions and directions given by management, supervisors and
safety staff.
- Attend the STARRT meetings held every morning.
- Wear and use proper personal protective equipment, safety tools and devices, and keep
them in good condition
- Always keep their work location neat and tidy.
7. STARRT & TBM
7.1 SAFETY TASK ANALYSIS RISK REDUCTION TALK (STARRT)
The STARRT process is one of the most effective means of eliminating accidents/incidents
and enhancing the HSE awareness of all personnel. The STARRT is a short meeting by

10 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

individual work groups and is held in the close vicinity of the work location, prior to
starting the work of the day.
The group leader conducts the meeting and the whole crew shall actively participate in the
STARRT. Managers and supervisors should also attend some STARRT meetings as
frequently as possible.
Mainly, the working plan and procedures for the day are explained and confirmed including
the following:
- Briefing on topics raised in the weekly HSE meetings.
- Anticipated potential hazards and suitable counter measures (including fire
prevention).
- Safety instructions for equipment and tools to be used.
- Inspection of equipment, tools and facilities.
- Confirmation that any Work Permit required for the work has been obtained.
- Use of proper personnel protective equipment and safety devices.
- Information on the other work to be conducted in the vicinity of the working area.
- Visual check of the health condition and proper allocation of workers according to the
requirements.

7.2 TOOLBOX MEETING (TBM)


A TBM is one of the most effective means of enhancing the HSE awareness of all
personnel. The TBM is short meeting held at least on a weekly basis and covering specific
safety issues decided by the site HSE team based on previous incidents or observations.
Weekly toolbox meeting shall be held every Monday morning at each Project involvement
all Supervisors, Safety officer & workers/ contractors, this meeting will last for
approximately fifteen (15) minutes. The meeting will be led by Construction Manager with
assistance from HSE team and Construction team. The purpose of the safety toolbox
meeting is to stimulate interest in accident prevention amongst employees; Enable
supervisors to stress how safety fits into every job. Establish action required with respect
to new or hazardous conditions. Provide an opportunity for individual expression of ideas
for improving, maintaining or promoting safety.
Before each shift, Team leader/foreman will be held pre-shift toolbox talk with
involvement all working team. The team leader/foreman to assign tasks and highlight all
relevant safety requirements for all their employees.
The attendant of Toolbox meeting as follows:

11 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

1. Supervisor
2. Site safety officer
3. Foreman
4. Team leader
5. Employees directly working on the site.

8. HSE TRAINING AND CERTIFICATION


HSE Training will be implemented on site:
- HSE Induction training for new entrants.
- HSE Training for Manager and Supervisors.
- HSE Training for Specific hazardous Work.
- STARRT (safety task analysis risk reduction talk).
- Fire, Evacuation and first aid training.
- Pre-commissioning/Commissioning training.
The HSE Manager and his team set up the HSE training programs and materials and
conduct the various courses with the support of CONTRACTORS HSE managers and
officers.
The language used by instructors shall be English and Vietnamese.
Training records shall be retained at the HSE office throughout the entire construction
period.
8.1. HSE INDUCTION FOR NEW ENTRANTS
It is mandatory for all managers and employees of BIDDER to attend the HSE Induction
Training course prior to start any field work. Without attending this training course, they
will not receive their ID card necessary to enter the construction Site.
Prior to the HSE Induction Training, all personnel shall submit their "Personal Information"
using the designated form (name, age, gender, profession, physical status, experience,
license or certificate, etc.).
The Induction includes, but is not limited to the following:
8.1.1 GENERAL ORIENTATION
Stresses the importance of HSE and each individual responsibility.
Orientation on the site layout and the workplace, using maps/drawings.

12 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Working rules (duty hours; over time; holiday, transportation; prohibition of smoking,
gambling drugs and alcohol, etc.).
Participation in the TBM and the STARRT program.
Security rules, including Gate control, traffic rules and regulations.
Actions to be taken in case of emergencies, (outline of the Emergency Response
Procedure).
Awareness of the dangers and safety requirements for the use of radioactive materials.
Work Permit System.
Use of personnel protective equipment.
Anticipated environmental programs and their countermeasures.
Stresses the importance of housekeeping.
8.1.2 INSTRUCTION FOR INDIVIDUAL WORK CATEGORIES
Individual instruction shall be given to workers according to their work categories, as
described below:
- Working at heights (prevention of falls), safe working platform, handrails, protection
around openings, scaffolds, use of safety harnesses (safety belts are prohibited), etc.
- Hot work (prevention of fire and accidental burns): Gas cutting and welding work,
electric -arc welding, storage and handling of acetylene and oxygen cylinders, use of
fire extinguishers, etc.
- Crane operation and lifting work: Crane certificates, operator’s license, safe operating
manner, use of outriggers, inspection and maintenance of equipment, signals, rigging
work, sling work, safety devices.
- Operating vehicles and construction equipment: safe operating practices including the
use of a Banksman, operator’s license, maintenance and inspection, speed limit, etc.
- Electrical work: safe work practices, electrical insulation, grounding, circuit breakers,
electrical-arc welding, safe tools and use of insulated personal protective equipment,
etc.
- Work in confined space: Work Permit System, pre-job inspection, oxygen/gas
measurement equipment, entry control, ventilation, respiratory apparatus and its use,
evacuation system, etc.
- Handling of hazardous substances: Material Safety Data Sheets (MSDS), specific PPE,
waste management process, etc.

13 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

8.2. HSE INSTRUCTION FOR SPECIFIC HAZARDOUS WORK


Specific training shall be given by competent and qualified persons to any personnel
involved in hazardous or harmful work as:
- Handling and storage of hazardous substances.
- Work under, over or on water.
- Deep excavation and trenching.
- Work in confined areas or narrow spaces.
- Rigging, lifting and crane operation.
- Erection and dismantling of scaffolding.
- Electrical safety (license electrical workers, explosive powered tools operators, etc.).
- Radiography.
8.3. STARRT INSTRUCTION
The STARRT (Safety Task Analysis Risk Reduction Talk) program is designed to instruct
supervisors and foremen in analyzing the tasks to be performed, identifying and eliminating
hazards and communicating with their crews on how to do the jobs safely. They will be
trained in STARRT within three months of the project kick-off.
8.4. FIRE EVACUATION AND FIRST AID INSTRUCTION
Basic Firefighting and First aid Training will be given to all supervisors and safety
personnel, by qualified professionals, as well as to any volunteers that will then form the
Project Emergency Response Team.
Emergency drills on any potential emergencies will be conducted periodically in order to
assess the reactivity of all employees as well as those of the Emergency Response Team.
Refer also to Section 14, Fire Prevention and Protection.
8.5. PRE-COMMISSIONING/ COMMISSIONING TRAINING
Specific Pre-commissioning/Commissioning Training will be given to all personnel
remaining on site at the start of Pre-commissioning activities. This training will cover all
rules that will be changed or modified due to the introduction of new risks on site. (Work
Permits, restricted access, etc.).
8.6. VISITORS HSE INDUCTION
Visitors should have a dedicated HSE induction identifying specific rules for visitors while
visiting. Visitors shall be made responsible for their safety by understanding site rules and
signing a declaration of understanding.

14 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

9. EQUIPMENT INSPECTION
9.1. INSPECTION
Construction equipment and tools shall be inspected and tested by competent mechanics or
electricians on arrival at the construction Site and periodically according to the applicable
procedure and in compliance with the national and/or local regulations, to confirm they are
in a safe operating condition.
Certification tags (with validity and expiration date) or color code shall be displayed on
accepted equipment, and details of certification registered in a log kept and undated in the
HSE office.
The user or operator shall carry out daily inspections supported by checklists as detailed in
the "Audits and Inspection Procedure before the construction equipment or tools are used".
Instructions on the use of the daily inspection checklists shall be given to the user or
operators before they start their work.
The HSE Manager shall prepare a standard form for each type of equipment to record the
inspection results, any substandard conditions, and maintenance or repairs completed.
Where the national and/or the local laws and regulations specifies the inspection of major
equipment, the supplier of the equipment shall arrange a formal inspection by an authorized
thirdparty inspection company, according to the type/or capacity.
A copy of the certificate issued by the inspector shall be submitted to the HSE office for
review and recording.

9.2. NOTICES OF UNSAFE ACTS AND CONDITIONS


When an unsafe act, unsafe condition or substandard equipment/facility is detected, the
finder must not overlook nor ignore the situation. The finder should immediately take
proper action to make the directly responsible supervisors/foremen or workers rectify the
situation. He should then record the action using a dedicated form.
Where an immediate threat to personnel or property is recognized, all related work shall be
stopped and use of the facilities or equipment shall be prohibited until the defect is
remedied or controlled.
The safety/security directives and reports of remedial actions shall be recorded and retained
in HSE office, during the entire construction period.
Unsafe or substandard situations shall be disclosed and deliberated at the HSE meetings by
all personnel concerned to prevent a reoccurrence of the defect.
The major observations found during an HSE inspection shall be used to develop, modify
or improve the work execution plans and procedures and/ or the HSE procedures or
requirements and shall be reported in the HSE monthly report.
15 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

9.3. SAFETY TAG SYSTEM


The HSE Manager shall establish a safety tag system for specific equipment and facilities,
such as scaffolds, lifting equipment and lifting gear, electrical equipment and tools, so that
permission is obtained before use.
The inspections will be carried out by HSE Inspectors who are required to be suitably
qualified and experienced.
After the nominated inspection, the inspector shall issue a "green safety tag" for the
equipment of facility, if acceptable.
The validity date for use, the date of inspection, the signature of the inspector, and any
other important information shall be entered into the equipment Logbook, kept by the HSE
Office and as much as possible mentioned on the tag itself.
When any defect occurs in equipment or facilities, or a device malfunctions during the
inspection, a red tag shall be attached to the defective equipment or facilities indicating use
is prohibited and the reason why nobody may use the defective equipment or facilities
unless it has a "green safety tag".
Safety tag system will be detailed in the following procedures:
- Scaffolding procedure
- Lifting and rigging procedure
- Electrical equipment & tools

10. RISK ASSESSMENT AND WORK EXECUTION PROCEDURES


10.1. IDENTIFICATION OF HAZARDS AND RISK ASSESSMENT
The identification and analysis of potential loss (Risk Assessment) and the establishment
of measures to prevent accidents/incidents and/or property damage are essential for
executing the work properly and safely. All work activities shall be systematically analyzed
by competent personnel to identify serious loss potential anticipated during the execution
of the work.
The work analysis and identification of hazards will be used to support the development of
effective and safe work execution procedures and included to:
- Examine how work is to be performed and write down the work steps and procedures.
- Identify potential risks for each work step.
- Analyze and evaluate risks according to severity and probability, and whether risk
control or risk education measures are required.

16 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Examine and establish risk control or risk reduction measures (Elimination of hazards
or reduction of risk).
The risk control or reduction measures shall be practicable, efficient and cost effective.
10.2. WORK EXECUTION PROCEDURE
The results of the work analysis and risk assessment will be recorded and used to establish
Work Execution Plans, incorporating risk control or risk reduction measures.
For specific hazardous work, the Construction Manager and the Discipline
Managers/Supervisors are responsible for preparing a comprehensive list of hazardous
works, prepare and submit work execution procedures for such hazardous work.
Competent and experienced personnel designated by the Construction Manager will review
the Work Execution Plans submitted.
The following construction/erection activities, without limitation, are generally considered
as hazardous work and are covered by a dedicated procedure:
- Installation and dismantling of scaffoldings
- Electrical work
- Work inside confined spaces
- Heavy lifting operation work
- Handling and storing of hazardous substances
- Deep excavation for foundation and trenching
- Blasting activities
- Pneumatic Testing Air Blowing and chemical cleaning,
- Grating installation and removal
- Use of man cages
- Other work designated by the Construction Manager.
The work execution procedures including a dedicated Job Safety Analysis (JSA) are
examined by competent and experienced personnel designated by Construction Manager.
Those responsible personnel shall explain the contents of the work execution procedures
to the personnel concerned with the work, prior to commencement of the work and at the
daily STARRT meeting.
Accidents/incidents may occur during minor work or routine work, therefore, responsible
personnel concerned with the work shall also examine such minor or routine work other

17 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

than the work listed above, regarding potential hazards and measures to prevent potential
losses.
10.3. JOB SAFETY ANALYSIS
Work shall not be conducted without a Job Safety Analysis (JSA) or pre-job risk
assessment discussion (STARRT) appropriate for the level of risk, in accordance with the
Job Safety Analysis procedure.
For hazardous activities shall perform a detailed JSA that will be attached with their work
execution procedure.
For any other jobs, Supervisors/Foremen will perform a JSA with their crew to identify the
potential hazards that the group may encounter, and eliminate the hazards or implement the
necessary controls.
For that purpose, they will use the STARRT cards that will be signed by all employees at
least on a daily basis.
At shift changes, Supervisors/Foremen shall review active JSA or STARRT cards and
inform their employees of any changes. Supervisors are responsible for ensuring all
workers are familiar with applicable JSA or STARRT cards prior to commencing work.
10.4. SAFETY TASK ANALYSIS RISK REDUCTION TALK (STARRT)
The STARRT (Safety Task Analysis Risk Reduction Talk) process is held before beginning
work each workday; when starting any new tasks during the day, or when a safety problem
has been identified in a crew involving more than one individual.
The basic steps of the STARRT process are to:
- Assemble the work team (ensure all people participating in the task are involved in
this process).
- Ensure all persons are trained and competent in the work they conduct.
- Define the task or scope of work.
- Clearly define individual sequential steps to be done.
- List of workers and equipment to be used in the job.
- Identify and list potential job hazards and employees exposure for each step of the
work.
10.5. PRE-COMMISSIONING/COMMISSIONING
10.5.1 SIMULTANEOUS OPERATIONS (SIMOPS)

18 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

For ensuring that all hazards are controlled, CONTRACTOR will apply the following
safety management system for simultaneous operations of pre-commissioning,
commissioning and construction activities (SIMOPS):
a) Pre-start up HSE
BIDDER will prepare a Commissioning Safety Rules document that will be issued to all
parties on site. This will include samples of a Erection Completion Certificate (to confirm
system is ready to commission), and a Safety Rules Clearance Certificate (to confirm the
system complies with all Commissioning Safety Rules).
Prior to commencement for pre-commissioning and commissioning activities, pre-start up
HSE review will be carried out to check the readiness. The review includes the following:
- All recommendations raised during previous HSE reviews are implemented in the
installations.
- Completion of operation test of safety systems, fire protection system and
environmental protection system (refer to Environmental Plan) and they are ready for
operation.
- All documents related to safety and operations (such as safety manuals, operation
manuals, procedures, emergency response plan, etc) are available.
- Training is conducted for all personnel, who will engage in pre-commissioning,
commissioning focused on potential risk, precaution for eliminating the risks, use of
personnel protection equipment, measures in case of accident/emergency and rules to
be observed.
b) Custody transfer of system
When all required inspections/tests of components included in the SYSTEM are completed
and documented the custody of SYSTEM is transferred to a commissioning team. The
extent of the SYSTEM is to be clearly defined on P&ID’s with component lists included
in the SYSTEM.
Upon transfer of the custody, the physical area of the SYSTEM shall be identified with
signs and barrier tapes by the commissioning team. The access and/or entry to the area is
restricted to essential personnel who have been trained for commissioning and hold a
project specific <COMMISSIONING> badge.
c) Control risks and permit to work
Any construction activity inside the area of commissioning teams custody shall be
performed under strict (permit to work) system. This permit to work system will be
identified by a detailed procedure.

19 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Construction supervisors will issue an application of a “permit to work” to commissioning


team describing the details of work (method statement) including precautions/measures to
be taken.
The construction supervisor, commissioning supervisor and HSE supervisor shall review
the application and:
- Identify hazard/risk involved in the work.
- Assess if the precaution/ measures are adequate against the identified hazards/risks and
prepare additional precautions/measures as required.
Before the start of the work, construction supervisor and commissioning supervisor will
jointly check and confirm that the precautions/measures are provided and observed per the
(permit to work). During the check, special attention shall be paid that energized
equipment, valve positions (open/close), and isolation blinds are set correctly with warning
signs and lockout devices for isolating live systems/lines as the (permit to work).
During the execution of the work, the construction supervisor shall watch if the work is
performed in compliance with the conditions of (permit to work) as well as other safety
rules. Upon completion of the work and cleanup of the area, the construction supervisor
and commissioning supervisor will jointly confirm the completion of the work.
d) Communication and coordination
For facilitating communication and co-ordination between construction and
commissioning teams, co-ordination meetings shall be held. In the meeting the following
is to be discussed.
- Review of activities performed, and prepare/update a resolution/improvement plan if
any problems are detected.
- Planned activities for next week by both construction and commissioning teams.
- Commissioning team to inform all parties of the schedule and location of construction
activities such as blowing/flushing, machinery run-in test and introduction of feed
stocks/utilities into systems and/or piping.
- Construction team to inform all parties of the schedule and location of construction
activities within/nearby any SYSTEM under commissioning.
- Co-ordination of the progress and interfaces of each activity so as to be able to use the
working areas most safety and effectively and to eliminate conflicts of interest among
teams.
In addition to above, weekly co-ordination meeting, and a tool box meeting will be held
every morning to confirm activities and the last situations of the day.

20 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

The weekly and daily activities of pre-commissioning and commissioning as well as the
information of live systems/lines will be distributed to all parties of construction office
including BIDDERS, and the same will be displayed on HSE notice board.
10.5.2 RISK ASSESSMENT FOR HAZARDOUS WORKS
a) Testing activities
The following testing activities are generally considered as specific hazardous work:

Activities Hazardous Controls


JSA and permit to be
raised Pre-pressure test
inspection of the lines and
Hydro testing of tanks, lines The equipment may fail
fittings Exclusion zones to
and columns/vessels which can cause injuries
be calculated and set
Test methodology to have
hold points identified

The chemical may leak due MSDS to be provided


to equipment failure or Emergency equipment to
could be spilled due to be kept on site including
failure of fittings and causes eye wash and wash down
burns to the skin on contact facilities
Chemical cleaning of lines
and injury to the eyes or PPE to be suitable for the
and equipment.
contaminate the material
environment. If water that used
is contaminated with Plan to be prepared on how
chemicals is drunk, it may to remove contaminated
result in illness or death. material.
Pressure testing procedure
to be developed and
approved (by whom).
Pneumatic testing of line Area clearance to be
and equipment incurs the established, fixed and
Equipment or fittings may
greatest level of risk and protective barriers to be
fail and cause injuries.
will be subject to strict erected when necessary
controls Fittings and outlets to be
checked - ensure pressure
rating is compatible with
test pressures.

21 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Activities Hazardous Controls


Water can cause “water
hammers” if not properly
drained after hydro testing
and result in lines jumping
Air blowing of lines off racks or bursting open
and cause injuries. Flying
particles at open ends may
result in eyes injuries. High
noise levels often result.
Steam will heat up the lines
and equipment, which can
cause burns. Steam blowing
Steam blowing of line
is also associated with high
levels of noise, which may
harm the ears.
Valves or isolation blinds
Nitrogen drying and
may fail and create a lack of
inserting of lines or vessels
oxygen in confined spaces.
If the line is under pressure
“BREAKING” of
with product or substance it
pipes/flanges to replace
will escape and cause
studs/ bolts/gasket/ “swing”
burns, eye injuries, or other
blind/ insert or remove
types of serious injuries,
spades etc.
fires, gas leak/clouds etc.
There is always a danger of
electrical shock and/or
unguarded moving parts
Rotating equipment and
that may cause injuries.
other electrical testing
Furthermore there is also
the possibility that the
equipment may fail.
Failure of equipment or
fittings/tubes which could
Hydraulic testing of
lead to eye injuries and
instrument system.
environmental
contamination

22 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Other aspects which, if not given adequate attention, may contribute to existing
hazards/dangers and requiring continuous consideration are as follows:
- Many people simultaneously doing different job in the same small area.
- Persons who have conflicting interests working on the same equipment/activity.
- Too much pressure applied to finish work quickly resulting in “short cuts” being taken.
- Ignoring/by passing safety aspects because “they cause delays” retard progress.
- Using incorrect sub-standard tools/equipment or faulty tools/equipment,
- People not being trained and familiarized with dangers associated with hazardous
products /substances/gases.
- Ignoring permit conditions or working without an authorized work permit.
- No banner and warning signs for restricted area access control.
- No barricades erected to create a restricted access area.
- Tampering with equipment, temporary installation (e.g. scaffolds), etc.
- Highlighted items will result in the removal from site of the offenders.
b) Live lines
After the lines have been cleaned, pressure tested and dried to the proper dew point, they
are commissioned. This is when they are charged/loaded/filled with the products they were
designed to carry during the facility’s operation i.e.: hydrocarbons, nitrogen, gases, potable
water, etc.
They will then be marked with stickers on which “Live Line” is written.
Some of these gases are poisonous and others can kill because they displace the air which
people need to breathe to stay alive. Some of the chemicals are poisonous and others can
literally eat or burn away skin or muscles. Some of the gases are explosive when mixed
with air and many of the liquids are flammable.
When the pressure and temperature of a dangerous chemical or gas is increased, then the
product’s hazardous properties are further magnified by pressure or temporary increase.
Some products, which may normally be only flammable, may be so hot in the process that
they will also ignite automatically when exposed to the air.
These aspects make it very important to not interfere with commissioned pipe lines or
equipment.

23 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Furthermore: NO WORK IS ALLOWED ON A LIVE LINE WITHOUT OWNER


AUTHORISED WORK PERMIT.
10.5.3 SAFETY CONTROLS
Start-up has the potential to be hazardous and safe working procedures and systems of work
shall be implemented to provide the level of controls required in an effort to prevent
injuries, loss of life, and damage to equipment or environmental contamination during
“start-up” and commissioning activities.
a) Safety action plan
BIDDER shall develop a Commissioning Safety Rules and submit it to eTEC for review
and approval. BIDDER shall also submit associated procedures to OWNER for review and
approval prior to the start of any pre-commissioning and or start-up work.
b) Permit to work
ALL WORK IN THE “START -UP” AND RESTRICTED AREA’S WILL ONLY BE
CARRIED OUT ON AN AUTHORISED PERMIT.
BIDDER shall submit to eTEC the Permit to Work System for an operating facility for
OWNER approval/authorization before the start of the work.
All proposed personnel to be Permit Applicants and/or Permit Holders will have undergone
Permit to Work training and be identified in a list of ‘authorized’ personnel.
The system and procedures constitutes the most methodical means of ensuring that safe
work practices are followed and that the work environment is safe. The objective is for an
experienced and trained authorized person, (who will ultimately sign the permit to work),
to pre-assess (with all the necessary technical assistance) the hazardous circumstances
involved and prescribe:
- The work to be carried out and the hazards involved.
- All precautions required.
- Who may perform the work?
- The limits of the permit area and equipment.
- LOTO (Lock-out Tag-out) requirements.
In particular, the permit will assist the authorized person in prescribing all the necessary
precautions. Each permit should detail the specific precautions to cope with, for example,
confined spaces, excavations, pressure tests, hydro static tests, radiographic tests, spading,
mechanical and electrical lock-out etc. The permit is designed to ensure that all parties
involved are aware of:
- The nature of the work to be performed
24 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- The place the work has to be carried out


- The equipment or plant involved
- Details of all mechanical and electrical isolations
- The period of time in which the work may be carried out
- The hazards which are, or might be, present; i.e. live plant and systems in the area.
- The test and checks which have to be made and the precautions to be taken before
starting the work.
- The equipment to be used or to be made available on a standby basis
- The personal protective equipment to be used by those involved in the work.
- The requirement, if any, for further periodic tests and checks
- Personnel permitted to do the work
- The emergency/rescue procedure and other arrangements for the evacuation of
personnel.
No work shall be allowed during the pre-commissioning and or start-up phase without an
authorized permit. The supervisor in charge must make sure that he and his crew fully
understands all the permit conditions and will be able to comply.
Therefore the supervisor in charge must personally check all the system isolations, tools
and equipment to be used, the work environment, PPE and explain the work and the permit
conditions to his crew before the work commences.
A work permit therefore authorizes entry into “start-up” area’s/process units/restricted
areas. BIDDER supervisor shall always ensure that the following requirements are carried
out:
- Sparks must be contained with fire resistant material (i.e. fire blanket, etc.)
- All sewers/drains within 10 meters must be covered.
- A fire extinguisher(s) must be available at the work point.
- A metal container to deposit welding rod stubs, never deposit welding stubs anywhere
else than in such metal container.
c) Barricades/Fences
Barricades and fences are there to prevent people from going into hazardous/dangerous
areas. All barriers shall be solid; tape is not acceptable.

25 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

This should not be taken lightly and everyone should comply. In general barricades are
required around excavations holes, openings in floor or roof areas, edges of roof, elevated
platforms, around certain types of overhead work, around areas where radioactive tests are
performed, where steam, chemicals or air blow -outs are possible because of pressure tests,
where equipment could be hot, etc.
All areas where hazardous pre-commissioning and or start-up work is being performed
shall be properly barricaded and access into the area controlled. CONTRACTOR shall keep
a sign in/out log of all authorized people entering/ exiting the retracted area.
d) Banners and signs
Banners and sign are displayed on SITE to warn or inform people of hazardous zones, or
to prescribe the use of certain personal protective equipment or to prohibit certain activities.
BIDDER shall display banners and signs to warn people against the possible hazards and
dangers. The following are examples and is not a limited list:
- Prohibited smoking zones
- Prohibited items in live system/plant areas
- In noise zones to wear ear protection
- Touching hot pipes, valves, equipment.
- Chemical cleaning of pipes, valves, and equipment
- Chemical, oil spillage
- Possible blasting particle during air blowing activities,
- Electrical hazards
- Hazardous work overhead
- Permit areas.
- Various pressure tests and associated hazards/dangers.
10.5.4 HAZARDOUS MATERIALS/SUBSTANCES
Hazardous materials are substances capable of posing a risk to personal health and safety.
Many of the pipelines and vessels will contain such hazardous substances.
The best way to protect your health and safety is to know about each of the chemicals being
handled or worked with and comply with the conditions of use described in the relevant
Material Date Sheet (MSDS).
Hazardous material/substances are generally be classified as follows:

26 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Toxic Materials A toxic material is one which adversely affects the body and organs.
Carcinogenic Materials, which have the potential to cause cancer, are known as
Material carcinogens.
Radioactive Radiation has serious effects on skin tissue, skin cell structure and
Materials body organs and in high doses can lead to death.

Chemicals that cause visible destruction or changes in living tissues


Corrosive
by chemical action upon contact.
An irritant is a non-corrosive chemical that causes a reversible
Irritants
inflammatory effect on living tissue by chemical action on contact.
Chemicals/gases which can cause suffocation by restricting the
Asphyxiates uptake of oxygen or by respiratory paralysis or by diluting/displace
oxygen below levels needed by the body.
Flammable &
Liquid that gives off enough vapors to form an ignitable mixture
and Combustible
with air produce a flame when a source of ignition is present.
Liquids

10.5.5 TRAINING
BIDDER shall ensure all employees involved in pre-commissioning and start-up work are
trained in their task and associated hazards and dangers of their work.
Only people who have received this orientation training and are authorized on a Permit to
Work will be allowed to perform work inside restricted areas.
11. WORKING PERMIT PLAN
Every item of work to be done must be evaluated to determine whether specific work permit
is required or not.
The following work is generally subject to the Work Permit System:
- Hot work in designated locations.
- Cold work in designated locations.
- Entry in a confined space.
- Deep excavations and trenching.
- Pressure testing (hydrostatic, pneumatic).
- Entering or operation of mobile cranes, vehicles or other construction equipment at
designated locations.

27 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Radiation work.
- Any work on energized equipment.
- Other work or locations designated by CONTRACTOR.
12. ENVIRONMENTAL CONTROL PLAN
CONTRACTOR fully recognizes that management of environmental matters during
construction and commissioning work is very important. Those responsibilities include the
proper handling of waste materials and environmental protection.
Each SUB-CONTRACTOR working on the construction site will appoint an HSE Manager
that will be responsible for the environmental aspects of the SUB-CONTRACTOR
activities. He will co-ordinate closely with the CONTRACTOR HSE Manager.
13. ENVIRONMENTAL PROTECTION MEASURES
The following environmental aspects are important at construction sites and the mitigation
measures described below will be implemented to minimize environmental impact and
prevent environmental incidents:
13.1 WASTE MANAGEMENT
The objectives of waste management activities will be:
- To reduce waste generation and to recycle or reuse them as much as possible.
- To ensure a collection of all construction wastes in a timely manner to avoid any
temporary waste disposal around the site or on lay down areas.
- To ensure the responsible and safe disposal of wastes, as defined by the environmental
requirements.
- To ensure safe, ultimate disposal of hazardous waste (if any) while retaining control
for future treatment.
Flammable waste, non-flammable waste, hazardous waste, perishable waste will be stored
separately in proper containers or bins.
All SUB-CONTRACTORS will be responsible for removing their own waste from the site
to the designated disposal locations.
HSE Manager will establish the on-site waste disposal policy and procedure of the manifest
control of waste transportation, disposal or treatment in line with the statutory
requirements.
Before the disposal of waste, the HSE Manager will contact the waste transporters and the
waste treatment contractor licensed by the local authority.
a) Non-hazardous waste

28 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

BIDDER are responsible for the cleanup and disposal of waste, debris, and surplus
materials that they generate during the work.
Blasted Rock and Debris from Underground Work
Rocks and debris generated by underground of piping and cable trench, soil excavation
work will be used for road construction and excavation back-filling, if applicable. Excess
rocks will be used for landfill at the designated place.
b) Hazardous waste
BIDDER will contract a licensed waste transporter and the waste disposal or treatment
facilities designated by the local authority to handle all construction site hazardous waste.
Waste collection facilities will be provided throughout the construction areas and facilities.
Before disposal of substances which are categorized as hazardous in accordance with
statutory regulation, they will notify the Site Manager with documentation describing the
chemical property, category, and quantity of waste involved.
The Site Manager will issue the document to eTEC or local authorities, as appropriate, to
obtain approval prior to disposal.
c) Pest control
No person will place, leave, dump or allow to accumulate any garbage, refuse or litter in
any building or any premises or open site in a manner that will provide food and nutrients
for insects, rodents, or wild animals.
Vector borne diseases will be controlled through the application of management controls
advised by the environmental specialist
Where necessary ‘fogging’ will be carried out to control mosquito.
13.2 LIQUIDS & EFFLUENTS MANAGEMENT
a) Rainning water from non-contaminated areas
Site drains and permanent base for site roads shall be installed prior to work commencing.
Raining water will be collected through a temporary drainage system and will be
discharged into clarifier basins to settle sediments. After settling of sediments, the top clear
water will be discharged to the river after confirmation of the water quality, and sediments
will be removed to the designated location approved by the local authority.
b) Sewage
BIDDER will provide sanitation facilities and systems in offices and camps.
c) Sanitary waste
Embedded tanks will be approved. Waste will be collected by licensed companies for
treatment and disposal.

29 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

d) Wasted water
All water pumped out from the underground works will be discharged into clarifier basins
to settle sediments.
e) Contaminated effluents
Oils, grease, fuels, lubricants, paints, solvents, acids and alkalis, and contaminated wasted
water will not be allowed to migrate into the plant ditch system or discharged to the ground.
Washing and maintenance of vehicles may only be done in specifically designated
contained areas.
All storage into tanks and loading/unloading of chemicals, fuels and similar bulk materials
must be in curbed or died areas.
Cleaning, washing and hydro-blasting of process equipment which has been exposed to
chemicals, oils, acids or other contaminant must be performed in runoff containment areas
approved for this type work.
Note: Any spill of petroleum products, chemicals and other materials will be immediately
reported to the CONTRACTOR HSE office and containment and clean up started
immediately. Spills larger than 180 liters will be recorded as incidents and will be reported
to the OWNER.
13.3 MITIGATION MEASURES TO REDUE NOISE AND DUST
a) Noise
The following noise and vibration control measures mainly concern employees on the work
site:
- Provide proper silencers/mufflers for mobile and engine driven equipment.
- Replace or repair defective equipment/parts with abnormal noise and /or vibration.
- Minimize high noise operations like pile driving at night.
- Use proper ear protection.
- Controlled blasting: underground blasting will be conducted using relayed and
controlled blasting techniques.
- Traffic in the residence area will be limited at night.
b) Dust (Blasting/Grit blasting/Grouting)
Grit blasting requires a Method Statement, risk assessment and job safety analysis.
Grit blasting shall be carried out in an enclosed designated area, leveled, and with sufficient
safe access, both to the area, and around the work pieces.

30 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

The grit blasting area shall be used. Under no circumstances shall products containing free
silica be used.
Personnel involved in the actual blasting of material shall be protected by a blast hood that
meets approved standards and providing both respiratory and eye protection.
The nozzle shall be fitted with a properly functioning dead man’s handle, and a standby
man shall stand by the blast pot. Nozzle and hose must be earthed.
Standby man shall be provided with suitable respiratory and eye protection.
Spent grit shall be collected and properly disposed of.
13.4 MITIGATION MEASURES TO MINIMIZE IMPACT OF CHEMICAL
a) Handling
The use of any toxic hazardous materials or chemicals, must be approved by BIDDER HSE
Office.
Material Safety Data Sheet (MSDS) shall be supplied for chemical and other harmful
materials used or stocked at the site. A copy of MSDS shall be submitted to BIDDER HSE
Office.
Hazardous materials such as radioisotopes, chemicals, etc, shall be kept in suitable and
approved containers which are properly labeled identifying the substance, nature of
hazards, precautions in handling, etc.
Areas where hazardous materials are used or stocked and hazardous conditions exist shall
be identified and properly isolated with enclosures or barricades.
Written handling procedures of substances shall be established and displayed near the
handling and storage location, which include: Substance Name, Nature of the Hazards,
Precaution for Handling, Emergency Treatment of Exposure, and Spill Clean-up, Disposal.
The inventory of hazardous substances should be recorded and updated periodically
including the names of substance, the volume brought in and the volume consumed and
any incident reports, etc.
Handling of chemicals.
Warning sign boards are displayed at conspicuous locations near storage and handling
places with the name, property, handling method, and actions required in an emergency.
A chemical handling procedure shall be established for using, storing and disposing of
chemicals, including identification of potential hazards, occupational exposure limits
necessary personal protective equipment (PPE), fire prevention and first- aid requirements.

31 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

All personnel involved in the handling and use of these chemical and those supervising
these jobs are to receive a pre-job training which shall also emphasize the hazard of static
electricity when transferring flammable liquids from one container to another.
MSDS and Chemical Handling Procedure shall be submitted to HSE Manager and relevant
personnel. Chemicals shall be stored in their original or approved containers and labeled
accordingly.
b) Storage
All containers shall be labeled with the chemical’s name, ingredients, and cautions for
storage and handling.
Flammable liquid shall be stored in the safety cabinet.
Flammable chemicals shall be used in a safe can
Chemicals shall be stored in a non-combustible warehouse with adequate ventilation, an
impermeable floor, washing and drain facilities, shower and/or eye shower, and air
conditioning, as required.
The warehouse shall be equipped with warning signs and locked to avoid unauthorized
entry.
The name of the responsible person shall be posted at the warehouse.
c) Transportation
Persons handling hazardous chemical wastes shall wear appropriate protective gear and
take all precautions to ensure that the potential for spills and accidents is minimized.
Employees shall be trained in emergency response procedures in the event of a spill or an
accident.
Information on the safety precautions necessary to ensure the protection of health and the
environment shall be maintained. This information shall be made available to all employees
Training in the handling of hazardous chemical wastes shall be provided.
14. PERSONNEL PROTECTION EQUIPMENT
- The HSE Manager will specify the PPE requirements for each category of work.
- BIDDER shall provide their employees with necessary and well- maintained or new PPE
free of charge.
- All employees concerned with construction work shall wear safety helmets, safety shoes
and safety glasses at all times when on the construction site.
- All PPE shall be regularly maintained and kept in good condition.
- Worn-out or damaged PPE shall be returned for repair, or disposal and replacement.
32 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Additional PPE according to the work execution plan and related risk assessment, will be
worn.
Training will be given to the users of PPE either when required by regulations or when a
specific skill is required to use the PPE.
Training for use of ordinary PPE is given during the Induction Training for new entrants,
and specific PPE training, such as for using respirators, is given by BIDDER and
Contractor.
HSE Manager or competent HSE supervisors or by other persons nominated by the HSE
Manager.
15. FIRE PREVENTION AND PROTECTION
15.1 GENERAL
Emphasis is place on pre-planning, hot work permit controls, flammable gas, liquid, and
material control; the control of smoking; training and use of warning signs, proper electrical
wiring, and proper waste storage and removal.
15.2 HOT WORK
Fire hazardous areas requiring to be defined as hot work permit areas are designated by the
HSE Manager after consulting with the Construction Manager responsible personnel, and
the work is carried out in accordance with the hot work permit procedure.
All flammable materials and debris near and/or under any hot work, such as welding, gas
cutting, etc., shall be removed or covered with noncombustible materials. Fire
extinguishers shall be supplied near and/or under the hot work locations. Gas cutting at
high elevations shall require a fire blanket.
An experienced person shall be assigned the responsibility for hot work and his/her name
shall be displayed in a prominent location at the workplace. The person responsible shall
always inspect and validate the workplace and conditions. Such inspection includes checks
on whether there are any fire hazards possible during the work and that no sources of fire
after the arks as well as the proper containment of sparks during cutting, grinding and
welding activities.
15.3 FIRE EXTINGUISHERS
Fire extinguishers shall be provided where the use of fire is permitted, such as in offices,
smoking sheds and hot work areas, and near electrical equipment or diesel/gasoline engine
equipment. The fire extinguishers shall be appropriate for the type of hazard present.
The type, capacity, and number of fire extinguishers shall be subject to the HSE Manager’s
approval. The locations and condition of the fire extinguishers shall be inspected
periodically by HSE Supervisors according to a predetermined schedule and checklist.

33 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

As part of the general site induction, all personnel will be trained for the use of fire
extinguishers.
16. HEALTH MANAGEMENT PLAN
16.1 RESPONSIBILITIES
The overall responsibilities of health control on the construction site shall be borne by the
Site Manager, and secondly for construction work by the Construction Manager. However,
the requirements of the Health Management Plan and the CONTRACTOR requirements
shall be observed by every personnel involved in the Project, including the BIDDER. The
HSE Manager shall assist them to fulfill the requirements of health control.
The SITE Manager and the HSE Manager shall establish an Occupational Health Program
and the On-Site Health Rules for the creation of a safe and healthy work environment for
all employees concerned with construction work, referring to this document and the Legal
and the CONTRACTOR requirements.
The Site Manager shall assign medical staff who shall take proper care of injured persons
or patients, and advise the HSE Manager with general health promotion programs on the
site.
If they find any unsatisfactory or substandard conditions that may affect personnel’s health
condition, they shall report it to the HSE manager. The HSE manager shall take necessary
measures to prevent its detrimental influence on people’s health, after consulting the Site
Manager and the persons concerned.
16.2 HEALTH RISK CONTROL
For effective control of health risks associated with the work the following proactive
process is essential.
This process shall be carried out at an examination meeting involving engineers or
specialists but also supervisors or foremen with experience and knowledge of the work.
a) Health hazard identification
Identify and make an inventory of the potential health hazards associated with the work
and the work environment.
All activities, material and environmental conditions associated with the work shall be
carefully and systematically examined to identify potential health hazards appropriately:
observation, sampling, inspection, measurement, interviews with people involved in the
work, etc.
This will provide the necessary data to allow for the provision of any specialized equipment
and medications to deal with any potential health or injury situation.

34 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

A survey shall be conducted to identify and evaluate the following potential occupational
health hazards:
- Toxic substances
- Physical hazards
- Psychological hazards
- Ergonomic hazards manual lifting of loads
- High noise and vibration hazards
- Other health hazards, if any.
b) Health risk assessment
Evaluate the risk anticipated from identified health hazards, and establish appropriate risk
control measures. The assessment requires suitable systematic evaluation techniques in
order to quantify the severity of the risk and the frequency and the time exposed to the
hazards.
c) Health hazard control measures
Health hazard control measures should be established during the planning phase of the
project execution and engineering phase of plant/facilities, and improved when necessary
during construction.
The principles of health control are:
- Elimination of hazards.
- Substitution with safe substance and/or devices.
- Engineering control, such as improvement of operation, providing safeguards,
ventilation, etc...
- Administrative control, such as providing proper work procedures, educational
training, observation of compliance with the established hazard control measures, HSE
requirements and rules, etc.
d) Health surveillance
Health surveillance aims at:
- Assessing the health of the individuals BIDDER’s employees and workers.
- Assisting in checking the effectiveness of control measures.
- The collection of data for the detection and evaluation of health hazards.

35 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- The checking of radiographer film badges will be identified in the NDT (Non
Destructive Testing) BIDDER’s Safety Plan.
Health surveillance may include physical monitoring and medical examination. The
contents and frequency of health surveillance should be determined according to the risk
evaluation results including pre-employment/pre-placement medical examination reports.
e) Record keeping
Health surveillance records and the records of exposure to identified health hazards shall
be kept in HSE Office to monitor individual’s health trends and occupational health
problems arising from the work and work environment, to fulfill legal requirements and to
safeguard the CONTRACTOR against unjustified compensation claims.
Personal medical records are confidential and must be treated accordingly.
16.3 HEALTH HAZARDS
TOXIC SUBSTANCES
Any toxic substances, for which possession or use is prohibited by law and regulation, such
as asbestos or asbestos containing product, PCBs, etc… shall not be used on this project.
For other toxic substances, such as chemicals, including solvents, catalyst, etc, the supplier
shall submit Materials Safe Data Sheet (MSDS) to HSE Manager for information.
Material Safe Date Sheet shall be used for risk assessment and establishing risk control
measure; which shall cover how the substances are stored, used and disposal of while they
are on the site
The assessments shall state the precautions to be taken by personnel who use or come in
contact with the substances on the work site
Hazard assessment shall be carried out to clarify:
- The expected duration and frequency of exposure,
- The type of exposure i.e. vapor, dust, or liquid, inhalation or absorption by skin
contact,
- Means of reducing potential risk to tolerable level i.e. keeping in tightly sealed
containers, isolating the operator from the material (by personal protective equipment,
or barriers, etc.) or modifying or improving the operation methods,
- Whether hazardous materials, such as radioisotopes, chemicals, etc are kept in suitable
containers, as accepted by HSE Manager. The containers shall be properly labeled to
identify the contents, nature of hazard, handling, precautions, etc.
Ares where hazardous materials are used or stored and areas where hazardous conditions
exist shall be identified and properly isolated with enclosures or barricades.
36 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

Exposure to X-ray and lasers shall be strictly controlled. All radiographers shall be trained
personnel, and all radioactive sources shall be controlled under the Permit to work system.
Areas in which radiography is taking place shall be roped off to restrict the access of
unauthorized personnel.
Written instruction for handling of hazardous substances shall be established and displayed
near the handling and storage location. The instructions shall indicate:
- Substance name
- Nature of the hazards
- Handling precautions
- Emergency treatment after exposure to the substance
- Spill clean-up
- Disposal
The inventory of hazardous substances should be recorded and updated, periodically
including the names of substances, the volume brought in and the volume consumed and
any incident reports, etc.
Special HSE training shall be given to employees with a risk of being exposed to hazardous
substances.
Personnel exposed to or handling specific toxic chemicals or substances or radioactive
substances shall receive periodic medical examinations in accordance with Industrial
Safety and Health Laws and Regulations.
16.4 GENERAL HEALTH PROMOTION
a) General
General health promotion aims at preventing health risks associated with the living
environment and life style such as infectious disease (by immunization and prophylaxis),
inadequate nutrition (by information), use of tobacco, alcohol and other drugs (by
employee assistance program), and lack of absenteeism and employee turnover.
The following activities are essential for an effective health promotion program:
- Assessment and prevention of health risk associated with the living environment.
- Assessment of life style associated with health risk in so far as they relate to work
performance.
- Employee information and assistance programs to prevent these health risks.
- Record keeping monitoring progress in controlling these health risks.

37 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

b) Sanitation facilities
BIDDER shall ensure the provision of adequate sanitation including sufficient toilets,
urinals and washing facilities for all personnel. All facilities will be kept clean and
hygienic. Urination or defecation in no-designated areas shall be cause for immediate
dismissal.
When men and women are working together in offices, canteens, workshops, etc…
separate wash rooms and toilets shall be supplied. Washrooms and toilets shall be kept tidy,
clean and hygienic.
Sanitary water shall be treated or disposed of in accordance with local regulations and the
OWNER requirements.
c) Potable water
Potable water shall be periodically tested and certified by an authorized laboratory. The
quality of potable water shall satisfy the local regulations and the CONTRACTOR
requirements.
d) Infectious disease
If a patient is suspected of having an infectious disease as designated by the local
regulations, the HSE Manager shall report it immediately to the Site Manager and the local
health officer, with the name of the disease and the name, age, position and address of the
patient. He/she shall be sent to an appropriate hospital.
e) Local disease
The HSE Manager shall investigate any local disease which are specific to the district, prior
to the commencement of the construction work. The information is then made public
regarding the disease, specific symptoms, prevention measures, etc.
16.5 AUDIT OF HEALTH MANAGEMENT
Using an assigned assessment team, BIDDER management will periodically assess the
health management performance on the Site. These assessments will include the health
management plan and the overall performance.
The management leadership is essential for health management on the site.
The audit team assigned by Site Manager will periodically audit the project health
management performance and issue a formal report to the Management and
CONTRACTOR.
The Project Manager’s monthly progress report is available for review by the audit team.
17. ACCIDENT/INCIDENT INVESTIGATION AND REPORTING
The Site Manager shall take the initiative in conducting accident/incident investigations.

38 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

The requirement shall be: accident investigation, reporting and follow-up of accidents, and
occupational illnesses using the standard report forms. The following is a summary of the
requirements.
17.1 ACCIDENT/INCIDENT INVESTIGATION
If an accident occurs resulting in personnel injury, death, or property damage, the Site
Manger will immediately report the essential details of the accident to all concerned parties
according to the emergency communication network, and organize an accident
investigation team on the site.
The accident investigation team, directed by the Site Manager, will consist of the HSE
Manager, Engineer and Supervisors directly responsible for the work. The BIDDER HSE
Manager, The BIDDER manager personnel, and supervisors and foremen directly
concerned with the accident, and if possible, any injured personnel will also be involved in
the investigation team.
17.2 EXTENT OF ACCIDENT INVESTIGATION
The following items will be included in the scope of the investigation:
- Any fatalities.
- All non-disabling injuries and occupational illnesses.
- All disabling injuries and occupational illnesses.
- Traffic accidents.
- Fires and explosions.
- Equipment failures.
- Failure of facilities.
- Discharges of any hazardous substances and related accident and incidents (near-
miss).
- Near-miss with the potential for a major accident.
17.3 INVESTIGATION PROCEDURE
The following procedure will be applied when investigating an accident:
- Sealing-off of the vicinity of the accident, if possible.
- Securing the site of the accident, preserving any physical evidence and taking
photographs to record the situation.
- Collection of information from personnel present at the time of the accident.

39 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Analyzing the causes of the accident using a root cause analysis process
- Establishing countermeasures to prevent recurrence accidents.
17.4 ACCIDENT REPORT
All accidents/incidents shall be immediately reported to the Project Manger and HSE
Management Office, to the CONTRACTOR and other concerned parties or authorities,
according to the emergency communication network.
The interim and the final investigation reports shall be completed without delay, and in
accordance with the accident/incident investigation and reporting procedure.
The Site Manager will be responsible for finalizing and signing all accidents/incident
reports, and subsequent reporting.
17.5 FOLLOW-UP ACTIONS
After receiving permission from the CONTRACTOR and/or other parties, such as the
insurance, CONTRACTOR, local authorities, police, etc the follow-up activities for
remedial action and restarting of construction operations will commence according to the
Site Manager’s and/or Construction Manager’s instructions.
The progress of the remedial and follow-up action shall be recorded in the appropriate form
and the completed form retained for record during management meetings and managerial
reviews, progress reports, evaluation of the results, and communications to employees.
The results of each accident investigation, especially the outline, basic and direct causes of
the accident and measures taken to prevent reoccurrence of similar accidents, shall be
announced by electronic messaging to all CONTRACTOR management and employees to
be utilized for HSE training.
17.6 PROCEDURE FOR DISSEMINATION LEARNING POINTS
a) Accident data analysis
Full use shall be made of all accident information:
- Root cause analysis shall be used to identify the organizational latent failures leading
to serious incidents.
- A monthly summary of incidents will be made and widely distributed across the
project.
- An analysis of lost workday cases and the lost workday case rate by craft will be used
to highlight problem areas.
- Cumulative statistics, including first-aid incidents will be used to show trends over the
life of the project.

40 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

b) Project monthly HSE report


Significant HSE Activities shall include a concise review of HSE problems that occurred
during the month and the corrective actions taken to resolve them. HSE inspections by
CONTRACTOR or third parties should also be recorded here.
Unsolved HSE Issues will be described in sufficient detail to enable HSE Management
Office (home office) to assist in resolving the problem.
Anticipated HSE Issue, which is expected to arise within the next few months, shall be
listed here. Awareness of potential problems will enable SE Management Office to give
better assistance to the field.
The HSE Manager will submit this report together with the monthly HSE Performance and
Statistics report to the Project Manager, HSE Management office (Head office) and
CONTRACTOR.
c) Lessons learned program
Key information and lessons learned from the investigation and analysis of any incidents
will be appropriately disseminated in scheduled or special safety meetings and via the other
communication tools within the HSE Program.
18. MEDICAL SERVICES PLAN
The CONTRACTOR will provide medical facilities on site such that medical assistance
can be rendered to workers in the event of an incident arising.
Trained first aid personnel and suitable first aid facilities shall be supplied at the site and
the camp, and a doctor and a nurse shall be assigned at those locations. A project ambulance
will also be provided with full equipment.
Each work site shall maintain close communication with and have access to occupational
Medical Service (Hospital or clinic).
A list with details of the nearest hospital, including its locations and phone numbers, shall
be posted in all the Site Offices, including the camp offices.
19. HOUSEKEEPING PLAN
All employees are responsible for keeping the Site, Camps, and other facilities clean and
orderly at all times.
The major objectives of housekeeping are to:
- Eliminate the causes of accidents and fires by removing obstacles and flammable
hazards which might interfere with activities and passage of personnel and vehicles,
and become a source of fire.

41 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

- Effectively utilize area and equipment by providing comfortable and safe working
conditions
- Create and maintain hygienic and safe working conditions.
All employees shall be encouraged to maintain their areas to the highest standards of
housekeeping.
After each day’s work, all work crews should spend 15 minutes to clear their work locations
and arrange the materials and equipment in order.
Every Monday morning & Saturday afternoon, BIDDER shall organize an overall site
cleaning by employees, lasting at least 30 minutes.
20. WORKING CLOTHES AND FACIAL HAIR
The working cloths are task specific and not offend the cultural sensibilities.
The wearing of short pants /skirts and of sleeveless shirts shall not be allowed even for
office activities.
As well, loose or torn clothing and sandals or sports shoes are prohibited.
Facial hair must be worn short so as not to hinder the wearing of PPE The above restrictions
shall be applied to all personnel.
21. ALCOHOL AND DRUGS
Entry to the site while under the influence of, as well as possession of, use or sale of drugs,
is strictly prohibited and is cause for dismissal.
However, in the Camp, licensed hotels and the like, the moderate drinking of alcohol may
be permitted during off-duty hours, unless restricted by local regulation, and provided that
it does not annoy others or affect the following day’s work.
Substance abuse (for example the use of drugs or immoderate consumption of alcohol)
impairs performance at work and gives a serious threat to HSE and productivity.
22. SMOKING AND OPEN FIRES
Smoking and possession of matches or lighters shall be strictly forbidden, except
designated areas where permitted by Site Manager:
- Smoking is allowed only at the area designated by Site Manager and under controlled
conditions.
- Smoking in vehicles is always prohibited at the site.
- Open Fires are strictly forbidden on the site, except where permitted.

42 | P a g e
HSVC PP4 - HSSE PLAN
PACKAGE: MECHANICAL & ISBL PIPING WORK

23. HSE BULLETIN BOARDS


HSE bulletin boards are provided at designated entrances to the construction site and other
conspicuous locations. The accident-free-man-hours figures for each Bidder, total
accident-free man-hour figures, monthly HSE objectives/targets and Safety slogans, etc...
Are displayed on the boards.
Information Boards: information and notification regarding HSE subjects, etc... Are posted
at prominent locations in the offices, canteens and camps.
HSE Posters and Signboards: HSE posters and signboards are displayed at prominent
locations on the construction site to enhance HSE consciousness and provide warnings
against hazards and unsafe acts.

43 | P a g e

You might also like