Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Enviro Infra Engineers Ltd

17.5 MLD STP, ZONE-4, Nava Raipur Atal Nagar


Completion Summary
% counting for balance work Since 20th march 2023
Date : 07-04-2023
Respective Quantity balance on Up to Target date of
Structure Up to date Today % achieved
20 March 2023 Yesterday completion
Shuttering (Sqm) 585.24 445.20 435.2 10.00 76.07%
Reinforcement (MT) 11.37 6.60 6.6 0.00 58.05% 15-04-2023
Concrete (Cum) 68.95 6.85 6.851 0.00 9.94%
SPS
Brickwork (cum) 315.00 0.00 0 0 0.00% 30-04-2023
Plaster (Sqm) 702.00 0.00 0 0 0.00% 12-05-2023
Flooring Stones 600.00 0.00 0 0 0.00% 22-05-2023
Shuttering (Sqm) 421.00 219.88 217 2.88 52.23%
Reinforcement (MT) 6.28 5.80 5.7 0.10 92.29% 02-05-2023
PTU
Concrete (Cum) 94.83 53.36 53 0.36 56.27%
Flooring Stones 0 20-05-2023
Shuttering (Sqm) 302.72 62.48 62.48 0 20.64%
Reinforcement (MT) 9.14 3.77 3.32 0.45 41.23%
Chlorine & Concrete (Cum) 47.13 3.80 3.796 0 8.05% 20-05-2023
Tonner Brickwork (cum) 44.90 0.00 0 0 0.00%
Building Plaster (Sqm) 387.20 0.00 0 0 0.00% 30-05-2023
Flooring tiles 0.00 0 0
Flooring Stones 0.00 0 0 10-06-2023

Shuttering (Sqm) 782.32 228.50 208.5 20 29.21%


Reinforcement (MT) 16.03 4.31 4.31 0 26.89%
Rapid Sand
Concrete (Cum) 100.05 0.00 0 0 0.00% 15-05-2023
Filter
Brickwork (cum)
Plaster (Sqm)
Shuttering (Sqm) 364.00 45.00 45 0 12.36%
Reinforcement (MT) 7.30 2.40 2.4 0 32.85%
SBR
Concrete (Cum) 47.85 0.00 0 0.00% 30-04-2023
Component
Brickwork (cum)
Plaster (Sqm)
Shuttering (Sqm) 1200.00 164.55 164.55 0 13.71%
Reinforcement (MT) 11.00 3.25 3.25 0 29.55%
Concrete (Cum) 85.00 6.00 6 0 7.06% 15-05-2023
Brickwork (cum) 0.00 0
TWRPH
Plaster (Sqm) 0.00 0
Flooring Stones 0.00 0
Door 0.00 0
Windows 0.00 0
Shuttering (Sqm) 0.00 0
Reinforcement (MT) 0.00 0
20-06-2023
Enviro Infra Engineers Ltd
17.5 MLD STP, ZONE-4, Nava Raipur Atal Nagar
Completion Summary
% counting for balance work Since 20th march 2023
Date : 07-04-2023
Respective Quantity balance on Up to Target date of
Structure Up to date Today % achieved
20 March 2023 Yesterday completion
Concrete (Cum) 0.00 0 20-06-2023
Dirty
Brickwork (cum) 0.00 0
Backwash
Plaster (Sqm) 0.00 0
Flooring tiles 0.00 0
Flooring Stones 0.00 0
Shuttering (Sqm) 0.00 0
Reinforcement (MT) 0.00 0
Concrete (Cum) 0.00 0
DWPE dosing
Brickwork (cum) 0.00 0
tank
Plaster (Sqm) 0.00 0
Flooring tiles 0.00 0
Flooring Stones 0.00 0
Brickwork (cum) 52.00 48.04 48.04 0 92.38%
Plaster (Sqm) 549.00 213.00 200 13 38.80% 22-04-2023
Blower Flooring tiles 0.00 0
Building Flooring Stones 0.00 0
Door 0.00 0
Windows 0.00 0
Flooring Stones 0.00 0
Admin Block Door 0.00 0
Windows 0.00 0 30-04-2023
Flooring tiles (Sqm) 697.67 0.00 0 0.00%
Wall tiles (Sqm) 204.65 59.88 39.87952 20 29.26%
Staff Quarters Granite (Sqm) 74.42 42.00 36 6 56.44%
Door 0.00 0
Windows 0.00 0 15-05-2023
Brickwork (cum) 18.00 18.00 18 100.00%
Plaster (Sqm) 145.00 145.00 145 100.00%
Toilet Block
Flooring tiles 0.00 0
Flooring Stones 0.00 0 30-04-2023
Campus Filling Compacted soil (Cum) 16000.00 4180.00 4024 156 26.13% 30-07-2023
Internal Road 30-05-2023

You might also like